The route, Agric – Isawo – Konu – Arepo was selected after the route selection process of various route corridors. The
selected route is in line with the Strategic Transport Master Plan (STMP) jointly carried out by ALG Consultants and
Advanced Engineering Consultants (AEC). The project when completed will enhance free movement of the people
and goods from adjacent communities to the mainstream of Lagos via Mile 12 Ikorodu road and Lagos - Ibadan
Express way.
The project is expected to enhance community policing within the area and improve infrastructure within the
environment from Ikorodu area through to Lagos Ibadan Express way. The present project is the completion of Agric -
Isawo – Konu – Arepo Road (CH. 0+000 – 0+400)/Upgrading of Ogolonto, Agric and Aruna junctions will provide the
following:
i. Construction of 400m dual carriage with dedicated U-turns
ii. Construction of 100m slip road
iii. Provision of 80mm thick paving stone on the Carriageway as surfacing
iv. 40mm thick sharp sand bedding
v. 150mm thick crushed stone base course (≥80% CBR)
vi. 200mm Soil – Cement stabilized subbase (5% Cement)
vii. Shape and compact
viii. Provision of pedestrian walkways
ix. Construction of reinforced concrete drains/culverts
x. Provision of Street Lighting Including Generators and Transformers
xi. Provision of Service Ducts (Longitudinal and Transverse)
xii. Provision of Traffic System Management
The scope of consultancy services :
1.0) Engineering Design and Reviews
2.0)Construction Supervision and Management
COST:NIL