Acid Cleaning

Project Name : Sulfindo VCM Project

1. BOQ

Equipment Data Total System


S/N Item / Package Description ITEM NO. / PKG NO. Volume m3 Remark
Piping size Net Volume ID Height Net Volume (Piping + Equip)
LINE NO. Length Material Item No. Description Qty
(OD) Inch (M3) (M) (M) (M3)

i 3-H01-11210316-BG55CQL 3 0.5 0.002 0.0 0.00

1.5-H01-11210316-BG55CQL 1.5 24.5 0.03 0.0 0.03

1-H01-11210316-BG55CQL 1 0.5 0.0003 0.0 0.00

10-H-10011011-BG55CQL 10 95 4.81 0.0 4.81

1121U300
1 Hydrogen Compressor 2-H-10011011-BG55CQL 2 2 0.004 0.0 0.00
VG5521

8-H-10011101-BG55CQL 8 2 0.06 0.0 0.06

2-H-10011014-BG55CPL 2 11 0.02 0.0 0.02

1.5-H-10011014-BG55CPL 1.5 3 0.00 0.0 0.00

1-H-10011014-BG55CPL 1 19 0.01 0.0 0.01


Acid Cleaning
Project Name : Sulfindo VCM Project

1. BOQ

Equipment Data Total System


S/N Item / Package Description ITEM NO. / PKG NO. Volume m3 Remark
Piping size Net Volume ID Height Net Volume (Piping + Equip)
LINE NO. Length Material Item No. Description Qty
(OD) Inch (M3) (M) (M) (M3)

14-GPR10-11210835-BG55CPL 14 21.5 2.14 0.0 2.14

12-GPR10-11210832-BG55CPL 12 7 0.51 0.0 0.51

6-GPR10-11210832-BG55CPL 6 0.5 0.01 0.0 0.01


1121U200
2 Recycle Gas Compressor
VG5513
24-GPR10-11210835-BG55CPL 24 6 1.75 0.0 1.75

14-GPR10-11210835-BG55CPL 14 23.5 2.33 0.0 2.33

3-GPR10-11210835-BG55CPL 3 0.2 0.001 0.0 0.00

4-GWD08-11211601-BG55CPL 4 34.5 0.28 0.0 0.28

6-GWD08-11211616-BG55CPL 6 8 0.15 0.0 0.15

4-GWD08-11211616-BG55CPL 4 10.5 0.09 0.0 0.09

1221U700
5 Vent Gas Compressor 3-GWD08-11211616-BG55CPL 3 3 0.01 0.0 0.01
VG5512

6-GWD12-10011212-BG55CPL 6 122 2.23 0.0 2.23

6-GWD12-10011212-BG55CPL 6 33 0.60 0.0 0.60

1-GWD12-10011212-BG55CPL 1 1 0.00 0.0 0.00

1121E001
6-OXY03-11210216-EG57CBO 6 21.5 0.39 Oxygen Feed Heater 1 0.36 2.60 0.3 0.65
VH5511

4-OXY03-11210216-EG57CBO 4 1.5 0.01 0.0 0.01

3-OXY03-11210216-EG57CBO 3 0.5 0.00 0.0 0.00

1-OXY03-11210216-EG57CBO 1 0.5 0.00 0.0 0.00


6 Oxygen Line
4-OXY-12410101-EG55CBO 4 100 0.81 0.0 0.81

4-OXY-12410101-EG55CBO 4 34 0.28 0.0 0.28

3-OXY-12410101-EG55CBO 3 2 0.01 0.0 0.01

6-OXY03-11210216-EG57CBO 6 9.5 0.17 0.0 0.17

ACID Cleaning 16.7 0.3 17.0

TOTAL (M3) 16.7 0.3 17.0


Acid Cleaning
Project Name : Sulfindo VCM Project

1. BOQ

Equipment Data Total System


S/N Item / Package Description ITEM NO. / PKG NO. Volume m3 Remark
Piping size Net Volume ID Height Net Volume (Piping + Equip)
LINE NO. Length Material Item No. Description Qty
(OD) Inch (M3) (M) (M) (M3)

Note.
1. Chemical cleaning volume is calculated as per Marked Up P&ID and piping BOM.