Professional Documents
Culture Documents
4.1 GENERAL
In order to incorporate typical Nepali conditions in the guidelines, the Consultant studied
six operational and one under-construction run-of-river hydropower projects in Nepal to
comprehend their planning, design, construction, operation and maintenance. The
findings of the study are summarized in this chapter.
HEP
From Table 4-2, it can be observed that the simple run-of-river plants, viz. Andhi Khola
and Modi Khola have ungated weirs to divert the river water towards their intakes. Gated
side undersluices are provided in these headworks to control the water level at the intake
and to flush out the bed load downstream to have unobstructed passage for the intake.
Gated concrete weirs are provided in the four pondage run-of-river projects (Kali
Gandaki “A”, Marsyangdi, Middle Marsyangdi and Sun Koshi HEPs). These weirs work
as spillways during the flood season, store water behind the structures for diurnal
pondage and divert water towards the intake structure.
Different types of desanding, with differing degrees of sophistication, are provided in the
projects. Both intermittent and continuous flushing arrangements are present.
4.3.2 Principal Design Parameters
For Nepali projects, the design flood, the level of seismic resistance and the desander
trapping efficiency are design parameters that primarily govern the hydraulic and
structural adequacy of headworks. These parameters for the seven projects are listed in
Table 4-3.
Table 4-3: Principal design parameters
S.N Project Diversion structure Desander
.
Design flood Seismic coeff. Trapping efficiency
1. Kali Gandaki “A” 1,000 year 0.3g 100% particles > 0.2 mm,
HEP 95% particles > 0.15 mm
2. Modi Khola HEP 100 year 0.1g 95% particles > 0.2 mm
3. Marsyangdi HEP 1,000 year Not known 100% particles> 0.125
mm, 80% particles > 0.05
mm
4. Upper Bhote 10,000 year 0.2g 99% particles > 0.5 mm,
Koshi HEP 95% particles > 0.3 mm
5. Sun Koshi HEP2 2,150 m3/s 8 grade 100% particles > 0.25 mm
6. Andhi Khola HEP 100 year - 100% particles > 0.3 mm
7. Middle 10,000 year 0.2g 95 % particles > 0.2 mm
Marsyangdi HEP
The design parameters show considerable variation and inconsistency. The design flood,
for example, varies from the 100 year flood to the 10,000 year flood. Although the
selection of flood is very site specific, the choice of very different floods for projects on
the same river and/or with similar consequences of failure is difficult to explain.
The seismic design coefficients also vary considerably. Except in the case of the Kali
Gandaki “A” HEP, the selection of the design seismic coefficients appears to have been
made without sufficient analyses. Considering the fact that Nepal lies in a seismically
active zone, the correctness and variation of the coefficients is a matter of concern.
The trapping efficiency specified for the desander depends primarily on the
characteristics of the sediments in the river. Nevertheless, the frequent wear and tear of
turbines clearly indicates at the insufficiency of these trapping efficiencies at most
projects.
4.3.3 Major Issues in Construction
The main issues related to headworks construction are river diversion during
construction, quality control, instrumentation and monitoring and environmental
2
Equivalent values in terms of return period and percentage of acceleration due to gravity (g) not available.
monitoring and control. Of these, the first two issues seem to have been appropriately
taken care of in each project. However, the other two issues, namely instrumentation and
monitoring and environmental monitoring and control, have been introduced to different
extents in most of the recent projects.
4.3.4 Major Issues in Operation and Maintenance
The headworks of six projects studied by the Consultant have been in operation for
varying periods of time. During these periods, some of these headworks have followed
good practices aimed at ensuring proper functioning of the projects. However, these
practices are outweighed by the operational problems and structural damage faced by
these headworks.
The good practices followed at the headworks that were studied are listed in Table 4-4.
The major problems at these headworks are enumerated in Table 4-5.
Photo 4-1: Repaired ogee surface of diversion dam spillway at Kali Gandaki “A” HEP
Photo 4-2: Missing steel lining (left) and exposed reinforcement (right) in flushing sluice at
Modi Khola HEP
Photo 4-3: Damage to trash rack from logs at intake of Sun Koshi HEP
load
Water levels Normal water level: El. 808.4 m
Flood water level: El. 811.3 m
Diversion barrage 70.55 m long concrete barrage
Four gated overflow spillways and two gated scouring sluices
Stilling basin with downstream cut-off wall, with steel lining in
sluicing portion
Steel-lined flushing channel with sand guiding sills
Six radial gates and maintenance gates
Two operating decks and a vehicular bridge
Intake Canal intake with four openings
Slide gates and trash racks in each opening
Intake canal Open canal between intake and desanding basin
Lateral sand trapping channel discharging in sand sluicing gallery
Bypass canal Open canal between intake and end of desander
Desanding basin Single chamber surface desander
Flow straightening walls in divergent section
Continuous flushing through sand-trapping channels and sand
flushing galleries