Professional Documents
Culture Documents
Summary. This case history de- Introduction ect management, engineering, field super-
scribes relief-well planning and exe- In Dec. 1988, Saga Petroleum A/S set vision, rig mobilization, and blowout and
244.5-mm casing at 4437 m on Well 2/4-14 relief-well specialists.
cution for a deep, underground blow-
in the Ekofisk area of the North Sea. Saga
out. Key achievements include an was drilling from a semisubmersible in 68 Choosing the Kill Method
innovative relief-well strategy, locat- m of water to evaluate the Jurassic hydrocar- The flowing reservoir consists of fine- to
ing and tracking the target casing bon potential 300 m deeper. This explora- coarse-grained sandstone with an estimated
tory well was the first drilled to such a depth 100-md permeability. The fluid was light oil
with electromagnetic ranging and
in the prospect. or gas condensate with a high GOR and a
conventional surveying techniques, Drilling continued through the Cretaceous reservoir pressure estimated at 98 MPa. Bot-
and integrating kill pumping units with 215.9-mm bits and water-based mud. tornhole static temperature (BHST) was
and associated equipment on a semi- A sharp transition occurred and formation 167°C.
pore pressure increased from an estimated From data before the pipe was sheared,
submersible. This was the first known 1.65- to 2. 11-g/cm 3 equivalent mud weight the team decided that the annulus around the
instance of relief-well intersection and (EMW) near the reservoir top. Formation BHA probably was sealed (by cement or set-
kill without a plug back and redrill after integrity at the casing shoe was 2.18-g/cm 3 tled barite) and that flow was passing
EMW. The hole penetrated several poten- through the bit and up the drill string to the
ranging. The techniques and equip-
tially weak formations above the objective, wellhead. The annulus contained 2.09-g1
ment, plus good teamwork, provided and while drilling near-balanced, narrow cm 3 mud. The introduction of 70.3 MPa
the necessary ingredients to place a margins between influx and lost circulation on the surface might have fractured the for-
bit into a 215.9-mm open hole 5 km were encountered. mation at the casing shoe. There was no sig-
On Jan. 11, 1989,the crew observed a nificant wellhead pressure drop (during the
away and to regain well control suc- 1-m drilling break at 4733 m. The well be- 16 hours from shearing the pipe to leaving
cessfully. This work also summarizes gan to flow immediately. The upper annular the location) that would indicate a casing
a parallel kill effort with a snubbing blowout preventer (BOP) was closed arid at- rupture and underground blowout. How-
tempts were made to establish circulation
unit for surface intervention. ever, because a similar blowout in 1984 held
with the driller's method and to bullhead,
at 82.7 MPa for 6 days before rupturing its
but without success. After fighting simul-
casings, a rupture was anticipated. 1
taneous loss and influx for several days, the
Operators facing a blowout must choose
bottornhole assembly (BHA) was cemented
how many relief wells to start and how to
at 4700 m, and a backoff and sidetrack
use them (Table 1). Two simultaneous,
planned. The drillstring, however, became
redundant, intervention projects historically
plugged, requiring a coiled-tubing operation
prove sufficient. The team decided that a
to remove the obstructions. Well control was
single relief well, designed for a worst-case
lost on Jan. 20, making it necessary to shear
the 127-mm drillpipe with 4482 m of coiled scenario, would act as a backup to surface
tubing inside. Wellhead pressure increased intervention. The team designed two extra
to a maximum of 70.3 MPa. relief-well geometries.
An attempt was made to bullhead down
the kill line but the flex hose burst at the slip Surface Intervention. The task force, as-
joint. The well flowed for approximately 1 sisted by Boots & Coots Inc., adopted a sur-
minute before being shut in by the fail-safe face intervention plan. The operation would
valves. The crew disconnected the riser and use the existing subsea BOP, combined with
moved the rig offlocation (Fig. 1). The sub- a custom-built stack and high-pressure riser
sea stack was vertical. No hydrocarbons system designed for a snubbing unit. This
were discharging into the sea. stack and riser maintained pressure integrity
Saga, with cooperation from partners from the seabed to the jackup, Nedrill
Statoil A/S, Amerada Hess Corp., and Elf Trigon.
Aquitaine, immediately formed an internal The surface team intended to latch on to
task force to manage the operations and to the severed drillpipe with a custom-made
regain control. This task force studied proj- packoff overshot and to fish out the coiled
tubing. Afterward, they could examine
Copyright t 992 Society of Petroleum Engineers several kill alternatives.
266 March 1992 • JPT
Relief-Well Strategy
Table I gives the kill objectives and design Sheared Drill Pipe
Treasure Saga 15,000 psi
and Coiled Tubing
steps. The chosen method called for hydrau- Blind/Shear Rams Closed
655 Bar on Wellhead
lic kill through a relief well into the blowout and BOP Stack Vertical
near the reservoir. Novel methods have been
studied or tried. 5-\3 We considered dynam-
No Hydrocarbon Discarge
ic kill with seawater followed by mud, com- to the Sea Sea depth 68 m
munication with seawater followed by mud,
brine followed by mud, and mud as the only
kill fluid.
Unknown if There
Establishing Kill Point. The team consid- is Flow Down Annulus
ered three kill points: one at the shoe with
direct intersection, another in the reservoir 30"
within 10 m, and a third within 1 m of open 4432 m of 1 112"Coiled Tubing 214.5 m
hole between the bit and the reservoir. Table inside Drill Pipe
1 gives the key elements considered. The
team chose the last option as promising the
greatest chance for success under all 20"
scenarios. We would refine placement after 901 m
setting casing. Unknown if casing
The relief well had to stay at least 20 m is Ruptured
away from the blowout until passing its shoe
and potential weak zones above 4560 m.
Then a liner would be set and pointed at the Top of Cement 133/8"
target, a minimum of 6 m from the open hole Behind 9 5/8" Casing 2509m
of Well 2/4-14. This restriction aimed to 3050m
avoid premature communication before set-
ting the kill string.
supervisor controlled the 16 pumps from a The team ordered a special two-outlet kill the surface coordinates or the azimuth refer-
control house adjacent to the catwalk. A spool that slips between the upper annular ence system,15 we ran redundant surveys
computerized monitor on a skid tracked and top blind shear ram on the subsea BOP between the wellheads using different tech-
pressures and flow rates within the pump- stack. Two additional high-pressure flex niques. Land surveying and the global po-
ing system. hoses hung over the side ofthe rig, connect- sitioning system (GPS) worked better than
Mud transfer tests showed that we could ing the spool to the surface system. These other methods and achieved a relative posi-
move only 0.7 m 3 /min of kill fluid from afforded the primary flow path, with choke tion uncertainty of about 1 m. We used land.
the supply boats to the rig deck. We con- and kill lines acting as backup. coordinates until the casing triangulation
tracted a stimulation vessel to provide a We used conventional casing design af- bypass. A true north azimuth reference
pumping capacity of 5595 kWand additional ter evaluating burst and collapse forces and helped eliminate any remote grid errors.
storage. This vessel also could act as an in- special conditions. The design gave adequate A borehole surveying specialist investigat-
dependent kill platform for either the relief diameter to pump at the required rate ed models and offset data, while the serv-
well or the surface operation, and it carried without excessive pressure, allowed an ex- ice company calibrated instruments. 16-18
318 m 3 of 2.75-g/cm 3 hematite mud and tra string, and met environmental consider- Measurement-while-drilling (MWD) pro-
238 m 3 of2.3-g/cm 3 ZnBr2. We soon dis- ations such as H 2S. Fig. 3 shows the final vided blowout well surveys to 4722 m. The
covered that hematite could not be main- plan. well basically is vertical, with inclinations
tained in suspension for long, and it had to The mud program followed offset wells under 20. MWD instruments tested within
be removed. (including the blowout). We evaluated su- specifications.
The vessel was loaded with a 400-m 3 percharging or drawdown, hole stability, Experience has shown that near-vertical
tank of 2.25-g/cm 3 barite-weighted kill fluid effects on electromagnetic ranging, and MWD surveys primarily exhibit systematic
mud. A cementing pump transferred the lost-circulation procedures. errors. Errors become randomly distributed
fluid at rates up to 4.1 m 3 /min. This boat from station to station. This results in
served the Nedrill Trigon but could quickly Position Uncertainty. Because more than smaller position uncertainty than from a
move to the relief well. one well has missed its target after muffing purely systematic model. By combining the
V
Tangent Inclination, 30 0
First ranging Point
Executing the 3829 m was the depth of closest approach. way it would be used offshore) for a high-
Blowout Intervention Plan No magnetic poles were observed during the pressure-function test 2 weeks before the
Relief Well. The relief well spudded Jan. bypass. The coordinate shift was only 5 m 244-rrun casing was set. The equipment was
31, 1989, 11 days after disconnecting from from the surveyed location at this depth. mobilized and reassembled on the rig after
Well 2/4-14. The 508-rrun casing was set Drilling continued with pendulum assem- casing was set_ The offshore kill team and
at 900 m on Feb. 6, without detecting shal- blies to the casing point at 4249 m, 4505 m equipment remained on standby during drill-
low gas, Treasure Saga's BOP stack re- measured depth (MD). On June 16, the well ing of the 215.9-rrun hole to guard against
was vertical and 22 m away at 165 ° azimuth. uncontrolled corrununication. Detailed plans
mained on the Well 2/4-14 wellhead, so the
A fifth ranging survey back past the cross- for circulation loss included contingencies
rig moved to Lyngdal, Norway, for a
point helped calibrate intensity values to the for complete losses (>1.3 m3/min) with
replacement.
triangulated fix (Fig. 5). a two-fluid (calcium chloride and Econo-
On Feb. 21, the 444.5-rrun hole section
lite™) flow-check process followed by a
was started with steerable motors and a KCl
Top Kill. The surface intervention team barite plug.
polymer mud system. This section had sta-
reattached the riser to the Well 2/4-14 well- Team concern focused on six areas in this
bility problems and required three side-
head on May 1. Wellhead pressure had section. The first zone was adjacent to the
tracks. Shallow seismic indicated that the
dropped from 65.5 to 19.3 MPa, indicating Well 2/4-14 casing shoe. The other five
relief well paralleled a possible fault through were thin, weak formations that might pro-
a change in the blowout circumstances. Fish-
the weak section. The 339.7-rrun casing was ing for coiled tubing commenced. On June vide a 'flowpath to the blowout. To facili-
set April 23 at 2500 m, with 26.7° inclina- 8, a production logging tool (PLT) revealed tate pumping lost-circulation materials, we
tion and 1 ° azimuth. The inertial gyro sur- flow rates of 2900 m 3 /d, indicating a leak decided that these sections would be rotary
vey in casing shifted the bottomhole location in the overshot and an underground blowout drilled without MWD or bit nozzles, Mo-
4.5 m east from that computed from MWD. to an unknown zone. As a result of uncer- tor work would take place only between
The 311-rrun hole was drilled with steer- tainty and an early team decision to perform these weak sections, making each tool run
able motors down to the initial ranging point only one critical operation at a time, the critical for alignment purposes,
at 3559 m without problems. The blowout relief well went on temporary standby. Drilling resumed Aug. 12. The 215.9-rrun
casing appeared in the predicted area, and On June 30, the leaking overshot was re- hole was rotary drilled from the shoe to 4557
drilling continued through the second and placed and the drillpipe bullheaded. Pres- m, 3 m below the first two weak zones. The
third ranging depths. The relative position sure response indicated flow up the annulus hole passed the blowout casing shoe 21 m
of the blowout casing changed from 24 m or through holes in the drillpipe below 3350 away _ Next, a motor run was made to start
at 18° azimuth at Fix 2 to 13 m at 45° m. A PLT and noise log indicated a hole in the nudge toward the kill point. The motor
azimuth on Fix 3 _This showed that the pro- the casing at 1372 m_ Flow probably entered was pulled 3 m above the next weak zone
jected well path would cross the blowout a large Pliocene sand at 840 to 890 m, Fish- and this zone was rotary drilled, No major
casing between 6 and 10 m west. Drilling ing for the coiled tubing continued to a depth problems were encountered,
continued past Well 2/4-14, with MWD of 3623 m when the decision was made to A ranging survey showed that the Well
used as a pendulum and earth field data mon- continue the relief well to the liner depth, 2/4-14 BHA (now adjacent to 165-rrun drill
itored for interference. The Run 4 triangu- collars) was at a relative azimuth of 187°
lation survey fixed the relative location at Relief Well Resumes. All surface pumping (±5°), The survey proximity was 16,3 m
6.3 m ±0.7 m at 93.5° azimuth. Hence, equipment was assembled in Holland (in the (±1.6 m) at 177° (±6°). This azimuth
t
Horizontal Vtew
6 112" Drill Collars
Zone 1
Zone 3
Surveyed Position of Casing
at 3829 m. 3.5m E &3.2 mN
of Triangulation Fix 4 ~--,:::=':::"::~-:::-;::=-:-:'f----ir- Fix. 6
-
107 m@ 189 0
Rotary Drill @ 4642 m TVD
Fix'8
Crossing
Blowout Casing • •••••••
Zone 5
CasingPoint4673mTVD
9.10inci.&1910Azimuth ~
n 7.1m@192.00
@4668mTVD
-
Fix 119
-
Fig. 5-Electromagnetic triangulation of Well 2/4-14 casing. Fig. 6-Well 2/4-15S' 8.5-in. hole section.
swing was greater than anticipated but still 7.1 m (±1.7 m, 3-m worst-case scenario) two fish in the hole. Four days later there
within the estimated uncertainty values. 0
at 188.5 (±4°) relative azimuth at 4668 m. were indications (later verified) that casing
Drilling continued with a bent sub and The 178-mm liner was set without problems had parted. A PLT indicated flow through
motor to 21 m above the fourth weak zone. on Sept. 17. Inclination was 9. 1 with a 0 multiple parts in the casing between 850 and
A hard tum put the well over to align to the 191 0 azimuth. 869 m.
latest ranging fix. If drilling continued as The target was at 4711 m, a 39-m drill- The mechanical condition of the blowout
originally planned, there would be too little ing distance. The projected proximity to the well steadily deteriorated after this, making
vertical depth to correct direction without Well 2/4-14 open hole at the kill point was further attempts to fish impractical. On Nov.
a plugback. The team decided to survey at 30 cm (Fig. 6). The relief well was put on 28, the relief well became the primary kill
this important depth with different tools. standby to wait for progress from the sur- vehicle. The surface kill team would snub
Tools agreed, Well 2/4-14 coordinates were face operation. The target could be reached 89-mm tubing to 1469 m. A wireline PLT
shifted, and the relief-well geometry was within 48 hours if required. tool would be set just out of the tubing to
replanned accordingly. During this run, we monitor pressure, temperature, density, and
observed electromagnetic intensity readings Top Kill Unsuccessful. When the relief- flow rate during the kill (Fig. 7).
that were lower than predicted. Lower in- well liner was set, coiled tubing had been
tensity may have resulted from parted drill- fished to 41 ()() m and no further progress Relief Well. Extensive rock-mechanics
pipe or from oil around the pipe causing could be made. A noise log run in the relief analysis gave the most desirable kill point
electrical insulation. well indicated a hole in the blowout drill- as an impermeable claystone at 4705 m. This
At 40 m above the liner setting depth, the pipe at 4110 m. The surface team decided location, 4 m above the lower weak zone,
motor was changed for a rotary assembly to cut the drillpipe at 4062 m and snub it should minimize fluid loss during kill. The
to ream the new section and to run a north- out. The team proposed to set a special pack- study also suggested breakthrough was like-
seeking gyro and EMS in drillpipe. During er above the cut drillpipe and snub 60-mm ly if the wellbore centers were within 1 m
this run, we noted a lO-m difference be- tubing inside the 127-mm string to tie back because of pressure drawdown and proba-
tween wireline and driller's depth. Most of to the surface. Flow now would go through ble enlargement in the blowout. 19 Updated
the difference could be attributed to drill- the packer and up the tubing to the surface. hydraulic simulations indicated that seawater
string stretch and temperature expansion. The well then could be bullheaded or the could kill the well dynamically and that
Because the MWD log correlated with the tubing used as a choke for a combination kill 2.25-g/cm 3 mud would ensure static kill.
depths from Well 2/4-14, we decided to with the relief well. The basic plan was to drill a 149-mm hole
match wireline and EMS depths to the Drillpipe recovered from the blowing well with 1.95-g/cm 3 mud to 4705 m, a distance
driller's depth. This small point prevented showed scale buildup that thickened with of 32 m. The proximity at this depth was
a depth mismatch and misalignment to the increasing depth. This prompted a decision estimated to be 0.5 m (-2.5- and +3.5-m
target. to run a taper mill to the packer setting worst-case scenario). The uncertainty in dis-
Rotary drilling continued below the fifth depth. The assembly stuck at 3816 m on tance meant communication might be
weak zone, and then motor drilling con- Oct. 20, and while attempting to pull free, achieved any time after 4700 m (Fig. 8). If
tinued to 4673 m (4930 m MD), the 178-mm the pipe parted. The well flowed up the drill- breakthrough did not occur by the planned
liner setting depth. The final ranging sur- pipe. Attempts to stab a safety valve failed depth, we would attempt to fracture at less
vey indicated the Well 2/4-14 casing to be and the shear rams were activated. This left than the liner test pressure. If communica-
20"
Bottom part of
outsider cutter
Hole in 9 5/S" csg. at 1372 m
4062 m-----\7.lthu
9 5/S" 4437 m
Bit at 4700 m
4734 m TVD
1910 ....
TO at 4734 m _ _ _.L.--fr:---.L.._ _ _ _ _ __
Vertical Section
Fig. 7-Condition of Well 2/4-14 at kill time. Fig. a-Projection of Well 2/4-15S from liner to kill pOint.
tion still could not be obtained, drilling Communication and procedure drills were pumped continuously down the blowout an-
,-,'ould continue into the Intra Mandal sand- held. Nedrill Trigon (Well 2/4-14), Treas- nulus at 0.3 m 3 /min during this operation.
stone at 4711 m. If communication failed ure Saga (Well 2/4-15S), Big Orange 18 The relief annulus pressure indicated that the
there, additional contingencies included acid (stimulation vessel), and the Far Scotsman BHP was above the reservoir pressure, and
squeeze and a sidetrack as a last resort. (kill mud supply vessel) were prepared for PLT data indicated that the kill mud had suc-
simultaneous operations. The command cessfully V-tubed up the blowout. The Well
.Kill Procedure. After communication, we center on Safe Britannia coordinated work . 2/4-14 blowout was statically dead.
planned to pull the bit back inside the liner On Dec. 12,1989, the 178-mm shoe was A 16-m 3 , 2.25-g/cm 3 temperature unsta-
and open the fail-safe valves on the injec- tested to 2.25-g/cm 3 EMW. The kill team ble pill pumped into Well 2/4-14 and under-
tion spool. A cementing tree would replace and equipment went on hot standby while displaced by 4 m 3 formed a solid barite
the kelly. If losses exceeded 1.6 m 3 /min, drilling to intersection.' At exactly 4705 m plug from the top of the drillpipe fish, fill-
the HT -400 pumps would inject seawater (4962 m MD), complete loss of returns was ing the BHA and open hole. PLT monitoring
through the kill spool. With the annular experienced and the drill string fell 1 m. during this operation was sensitive enough
preventer closed, the drill string would be There was an immediate pressure and spin- to detect 1-m movements of the Treasure
displaced with seawater. The seawater in- ner response on the PLT, indicating direct Saga drillstring and thus determined when
jection rate would be increased to the dy- communication. The bit was pulled back to the plug settled. After 35 hours, pipe move-
namic kill rate, but not over the shoe-test the liner shoe and the cementing test tree ment no longer could be detected. At 72
pressure of less than 2 MPa. connected as planned. The annulus was kept hours, an integrity test reached the 2.25-g1
PLT data from the blowout would help to full of 1.95-g/cm 3 drilling fluid with the cm 3 EMW. A noise log run in the relief
estimate the downhole fluid losses, the time riser booster pump. The initial loss rate was well showed previous anomalies were gone.
when oil and gas cleared the fish, and when 1.6 m 3 /min. After 10 minutes, the loss rate A balanced cement plug then was set in Well
the well was dynamically dead. Then, had fallen to 1.1 m 3 Imin, and after 3 hours 2/4-15S, and the well was abandoned tem-
pumping the static kill mud would start. The to 0.5 m 3 /min, for a total loss of 215 m 3 . porarily with two bridge plugs.
drillpipe simultaneously would be filled with PLT pressure response indicated that mud
1.95-g/cm 3 mud (to limit differential pres- was filling the blowout with little or no loss Remarks and Conclusions
sure) to monitor BHP during the static kill to the formation. The low flow rate implied Relief-well planning strategy proved a com-
pumping. When the PLT showed that Well a choking effect by the old BHA and bit. plete success. Despite the minor stability
2/4-14 was statically dead, the 2.25-g/cm 3 With these positive results, the team aban- problems in the top hole, the relief-well plan
mud in the relief-well annulus would be dis- doned the dynamic kill approach and chose was executed flawlessly. The 119 days on
placed with 1.95-g/cm 3 mud. A 2.25-g1 to pump the 2.25-g/cm 3 kill mud down the standby, while disappointing, were justified
cm 3 temperature-unstable mud would then drillpipe. The bag preventer was closed and to avoid unnecessary risk.
be pumped through the drillpipe into the the annular pressure was used to monitor This was the first time a relief well was
blowout and allowed to set. Plug and aban- BHP. The initial injection rate was 1 designed to cross a blowout casing for locat-
donment would follow. m 3 /min, slowing to <0.15 m 3 /min after ing purposes and then to drill to the kill point
160 m 3 . Injection continued at this low rate without plugging back. This approach avoid-
Well Intersection. All kill and safety equip- . through the next day, circulating out trapped ed losing the accuracy gained in the trian-
ment was tested for pressure and function. hydrocarbons. Treated seawater was gulation bypass and was dictated by the