You are on page 1of 14

This has reference to unit’s application dated 21.08.

2018 for reduction of


contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.

This has reference to unit’s application dated 21.08.2018 for reduction of


contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p a proval and signature.


This has reference to unit’s application dated 21.08.2018 for reduction of contract demand
by 100 KVA. In this regard, in reference to our letter dated 25.06.2018 in reply to
unit’s request for reconnection na d adjustment of outstanding amount with unit. Unit may
be again informed that their connection at present is under temporary disconnection na d
load not under operational condition. Under the circumstance, demand cannot be
reduced and to establish reconnection they have to apply for reduction of demand
accordingly hence they have to clear all the Outstanding Dues before reconnection of
electric supply is established.

Fair copy of letter to unit submitted for p a proval and signature.


This has reference to unit’s application dated 21.08.2018 for reduction of
contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.
This has reference to unit’s application dated 21.08.2018 for reduction of
contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.
This has reference to unit’s application dated 21.08.2018 for reduction of
contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.
This has reference to unit’s application dated 21.08.2018 for reduction of
contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.
Sub : Submisis on of documents/ bill received from PGCIL for the month of ………….

Dear Sir,

In reference to above please find attached copy of the documents/bill


received from PGCIL for the month of …………… for verification and necesars y
action pleaes .

Yours faithfully,
Encl : As above.
Manager (SEZ)
NO. AKVN/IND/SEZ POWER/13/ DT.

To,

Addl. CE (Operation)
O/o Managing Director
MPPKVVCL
Pologround, Indore
Email : aooperation@gmail.com

Sub : Submisis on of documents received from …………………………………………


……………………………………………….

Dear Sir,

In reference to above pleaes find attached copy of the documents received from
……………………………………………………………………..…………… vide No…………………………………………..dated ………………… for necesars y action
pleaes .
Yours faithfully,
Encl : As ba ove.
Manager (SEZ)
NO. AKVN/IND/SEZ POWER/13/ DT.

To,

Addl. CE (Operation)
O/o Managing Director
MPPKVVCL
Pologround, Indore
Email : aooperation@gmail.com

Sub : Submisis on of documents/ bill received from MP Power Tranm


s isis on Co. Ltd., Jabalpur –
Revised UI charges bill for the month of Jun 13.

Dear Sir,

In reference to above pleaes find attached copy of the documents/ bill received from MP
Power Transmisis on Co. Ltd., Jabalpur vide letter No. 2447 dated 14-8-13 for necesars y action
pleaes .
Yours faithfully,
Encl : As ba ove.
Manager (SEZ)
NO. AKVN/IND/SEZ POWER/13/ DT.

To,

Shri G.K. Sharma


Addl. CE (Operation)
O/o SE (Operation & Maintenance)
MPPKVVCL
Pologround, Indore
Email : se.operation@gmail.com

Sub : Verification of the weekly power bill received from MP POWER MANAGEMENT CO. LTD.,
Jabalpur for the period ……………..

Dear Sir,

In reference to above pleaes find attached copy of the Invoice received from MP
POWER MANAGEMENT CO. LTD, Jabalpur for the period …………………. for Rs. ……………………. The due dt. is
………………...
Pleaes send us the verification at the earliest so that payment can be made before the
due date.
Yours faithfully,
Encl : As ba ove.
Manager (SEZ)
NO. AKVN/IND/SEZ POWER/13/ DT.

To,

Shri G.K. Sharma


Addl. CE (Operation)
O/o SE (Operation & Maintenance)
MPPKVVCL
Pologround, Indore
Email : se.operation@gmail.com

Sub : Verification of the weekly power bill received from NTPC Ltd., Mumbai for the month
of …………………………..

Dear Sir,

In reference to above pleaes find attached copy of the Invoice received from NTPC
Ltd., Mumbai for the month of …………………. for Rs. ……………………. The due dt. is ………………...
Pleaes send us the verification at the earliest so that rebate can be a vailed for early
payment.
Yours faithfully,
Encl : As ba ove.
Manager (SEZ)
NO. AKVN/IND/SEZ POWER/13/ DT.

To,

Shri G.K. Sharma


Addl. CE (Operation)
O/o SE (Operation & Maintenance)
MPPKVVCL
Pologround, Indore
Email : se.operation@gmail.com

Sub : Verification of the weekly power bill received from PGCIL, Nagpur for the month of
…………………………..

Dear Sir,

In reference to above pleaes find attached copy of the Invoice received from PGCIL,
Nagpur for the month of …………………. for Rs. ……………………. The due dt. is ………………...
Pleaes send us the verification at the earliest so that rebate can be availed for early
payment.
Yours faithfully,
Encl : As ba ove.
Manager (SEZ)
This has reference to unit’s application dated 21.08.2018 for reduction of
contract demand by 100 KVA. In this regard, in reference to our letter
dated 25.06.2018 in reply to unit’s request for reconnection and
adjustment of outstanding amount with unit. Unit may be again informed that
their connection at present is under temporary disconnection and load
not under operational condition. Under the circumstance, demand
cannot be reduced and to establish reconnection they have to apply for
reduction of demand accordingly hence they have to clear all the
Outstanding Dues before reconnection of electric supply is established.

Fair copy of letter to unit submitted for p


a proval and signature.

You might also like