Installation of PV Panels Risk Assessment
Installation of PV Panels Risk Assessment
1
Minimum Fixed Guarding: The height of the upper guard rail must meet WAHR 2005 and the BS EN 13374: 2004 requirements. The overriding requirement is that the guard rail should be
suitable and sufficient to prevent a person or object falling, so far as is reasonably practicable. As a guide, aim for the top guard rail height of 950- 1000mm and a maximum gap of around 470 - 500mm, in
normal circumstances this would be seen as sufficient by HSE inspectors. For construction activity the top guardrail must be at least 950mm, this is in line with the requirements of the European Temporary
Working at Height Directive which stipulates guardrail height in construction as 1000mm + or – 50mm. Therefore the requirements of the WAHR and the BS EN are not inconsistent but set out the requirements
in a slightly different way. The standard can be set at a particular height, but the Regulations must reflect the margins recognized throughout Europe.
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 1 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
Operators use closed blade (safety) knife to cut strapping and remove shrink
wrap from box
Internal packing removed and placed inside the box and within waste bags
strategically placed around the site
PV panel removed and inspected for damage
All packaging is segregated and placed within the correct waste stream
Manually handling of loads to be avoided where possible by using machinery
PV Panels Manual particularly for distribution of the panels.
Handled from Box
(L Where unavoidable, no-one is to carry anything more than they are comfortable (VL
WRULD’s 1 3
and Packaging and 2 3 with and never more than 20kg. Panels are to be lifted by 2 persons onto mounting )3
fixed to mounting
Cuts, Grazes and Bruises )6 frame.
frame Mechanical means available (Bobcat) to move heavy and multiple loads
Kinetic lifting techniques adopted, the load must be minimal (max one steel at a
time)
Using impact drivers the operators hold the panel and fixe the panel to the frame.
The operator ensures PV panel cable is free close to the string cable, when PV
panel is fixed correctly to the mounting frame the Panel cable is plugged
into the correct string cable
Sprains or strains due to handling of Manually handling of loads to be avoided where possible by using machinery
Steel uprights, Pearling’s, framework, particularly for distribution of the panels.
string boxes, cable reels, Solar panels Where unavoidable, no-one is to carry anything more than they are comfortable
Manual Handling of
and other associated loads. with and never more than 20kg. Panels lifted by 2 persons.
Steel (VL
Operators preparing steel for fixing to (L Mechanical means available (Bobcat) to move heavy and multiple loads 1 3
framework/fixtures 2 3 )3
Piles )6 Kinetic lifting techniques adopted, the load must be minimal (max one steel at a
and fittings
Hand injuries due to handling of time)
panels. Operators share the task of collecting steel upright prior to ramming to reduce the
repetitive task Gloves to be worn when handling panels.
Operators involved in noisy operations issued with correct PPE (EN352)
Operators exposed to excessive noise Ear plugs (EN352-2) supplied to peripheral workers who may be affected by the
from impact tools and metal to metal noisy operations (VL
(M 1 4
Noise and Vibration contact 3 4 All impact hand tools will be checked to ensure the ELV is 2.5 m/s-2 or more for an )4
Operators exposed to excessive ) 8 hour day
vibration from impact tools 12 Operators affected by noise and vibration are subject to Occupational
Health Monitoring
Moving Operators hit by vehicle (VL
(L All operators must be fully trained/experienced to operate 1 3
Pallet/Boxed PV Pallet falls from vehicle 3 3 )3
Panels Box is damaged during transit over )9 bobcats/telehandlers (CPCS, NPORS etc)
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 2 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
site Bobcat/telehandler tested and inspected in line with LOLER and PUWER
documentation checked and available on site
Where restrictions are apparent banksmen will be used.
Bobcat/Telehandler place the palleted box of PV panels at the end of each row to
assist in reducing he distance operators unpacking and carrying PV panels for
installation
Telehandler transport palleted box of PV panels to Unimat to assist in reducing
he distance operators unpacking PV panels for installation by the Panel installers
using the Unimat platform
Machine tipping or over turning C30R Yanmar machine to be positioned downhill of working position
Using C30R
during operation Where ground is on excessive camber, excavator will assist in removing soil to (VL
Yanmar Machine on (M 1 4
Running over feet when moving 3 4 allow for machine to be true within position before using C30R Yanmar )4
Sloping or uneven )
machine commences.
ground 12
Crushing operators Stability of the C30R Yanmar machine will be checked prior to each use
Where unavoidable, no-one is to carry anything more than they are comfortable with
Manual Handling of and never more than 20kg. Panels are to be lifted by 2 persons.
Sprains or strains due to handling of (VL
Panels from C30R (L Kinetic lifting techniques adopted, to be minimal (max one steel at a time) 1 3
Solar panels and other associated loads. 2 3 )3
Yanmar platform )6 Workers share the task of man handling Panels to reduce the repetitive task Gloves
to be worn when handling panels.
Damage to materials during Suitable size machine will be used to carry loads.
Movement and movement or poor storage. Machine Loads will be distributed along the line to reduce the need for excessive
storage of other turning over or dropping loads due (L movement. (VL
3 3 1 3
construction to excessive weight / )9 Materials to be stored in specific areas as agreed with Site Manager. )3
materials overloading/undermining Storage areas to be fenced off using double clipped Heras fencing.
excavations Movement of materials around the site to be carried out by telehandler.
Only competent persons are to operate any items of mobile plant.
Machinery must only be operated in accordance with safety procedures.
Contact with other machinery, No-one is to approach any machine until they have made the driver aware of
structures or people your presence and you get a clear signal to approach.
Other Plant Overturning of Mobile Equipment
Always be alert to moving plant/equipment and take the view that the driver
movements- Unauthorised start up and
hasn’t seen you. (VL
Telehandler & Bob movement (M) 1 4
3 4 Seat belts to be worn at all times. )4
cats Parking of operator/visitor’s cars 12
(Traffic and vehicles All machines to have amber flashing lights operating unless otherwise
Management) Fuel spillages specified by your supervisor.
Hydraulic oil leaks and spillages All persons on foot to wear high visibility clothing.
Machinery not left unattended , key removed and machine secured.
Parking of private cars and contractors vehicles will take place in designated areas.
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 3 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
Refuelling will only be undertaken within a designated refuelling point within the
staging area – in accordance with Principal Contractor CPP
Spillkits will be in place and maintained at the designated refuelling point
Refuelling elsewhere on site can only take place with the express
Refuelling Pollution due to spillage.
permission of the Principal Contractor Site Manager (VL
operations of (L 1 3
Health problems due to contact with 2 3 A double skinned fuel tank will be used and placed in an area as designated by the )3
Excavator/Dumper/ )6
diesel. Site Manager.
Water pumps
Drip trays will be used during refuelling operations.
A suitable sized spill kit will be kept adjacent to fuel tank during refuelling.
The fuel tank is to be kept locked at all times when not in use.
A CoSHH assessment is to be carried out for the diesel.
All Employees/Contractors briefed on Lone working procedures, including:
o No high risk working when working alone (VL
Lone Working Injury or illness without support (M 1 4
3 4 o Constant communication with Security/SB Project Team )4
) HSE Guidance INDG 73(v3) http://www.hse.gov.uk/pubns/indg73.pdf
12 No visitors/sub-contractors work on site alone
Programed hazardous work to take place during daylight hours
Access lighting provided by Principal Contractor, task lighting provided by
Injury due to tripping, hidden voids, (VL
Working in hours of (M Sustainable Bright. 1 4
misjudgement etc. 3 4 )4
darkness
End of summertime hours ) Head torches to be worn by all operatives as required by Principal Contractor site
12 rules.
Site housekeeping maintained at high level at all times
Tool registers must be maintained up to date by Principal Contractor Site
Cuts, grazes and bruising to hands Manager (VL
(L 1 3
Use of Hand tools Failure of damaged tools 2 3 Contractors must inspect tools prior to use discard or dispose of damaged or broken )3
Use of incorrect tools )6 tools
Correct tools for the correct job every time
Ladders must be EN131 classification (Old Class II) or Class I classification
To gain access/egress into All ladders must be on the site ladder register
Use of Ladders/Step excavations (L Scafftag fitted to ladder in accordance with Principal Contractor CPP
(VL
3 3 1 3
ladders Gain access to high parts of )9 Three point contact with step ladders adopted, including knee and body – )3
mounting structure o http://www.hse.gov.uk/pubns/indg455.pdf
o http://www.hse.gov.uk/work-at-height/myths.htm
Ladders to be positioned stable ground, Stability of ladders will be checked prior
Machine tipping or over turning
to each use
during operation (VL
Working on Sloping (M Where ground is on excessive camber, excavator will assist in removing soil to 1 4
Running over feet when moving 3 4 )4
or uneven ground ) allow for machines to be operating true before work commences
machine
12 Pedestrians have right of way to machines, operators must observe the correct
Crushing operators
crossing points on site for pedestrians.
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 4 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
No person to enter any excavations until an assessment has been carried out by a
competent person to establish the stability of the sides and determine whether
support is needed for the sides.
Contractors/trespassers falling into (L Physical barriers to be placed where excavations are left open on both sides of the (VL
Open excavations 3 3 1 3
excavations )9 excavation (to prevent accidental falls from Contractors, trespassers and vehicles) )3
Site Manager to agree period of inspections to be undertaken by whom and when
based on stability?
Desk top UXO ordinance Survey carried out June 2016 by Fellowes (No known
hazards identified, however contingency plans are in place should a
discovery of an unknown object be apparent)
Hidden UXO/UXB Explosion o Preliminary UXO risk assessment Ref: 6 Alpha Project No P5094 available (VL
(M 1 4
discovered during Damage to Site Plant 4 4 via dropbox )4
surveying Major Injury/Death ) Contingency procedures communicated to all Contractors during Induction by
16 Principal Contractor Site Manager and Principal Contractor Project Manager of
actions to take if unidentified objects are discovered during
excavations
Employees and Contractors made aware of the possible insects, reptiles and wild
animals within UK that could be found on site
Bites & Stings
Interaction with (L Employees and Contractors briefed to be aware of the risks of Leptospirosis (VL
Leptospirosis Bleeding 2 4 1 3
insects, reptiles and )6 (Wields Disease) and the symptoms )3
and cuts Infection and
wild animals
Reaction
Full mandatory PPE worn at all times (Minimum Hard Hat, Hi Vis waistcoat
and Safety Boots)
First Aid Provisions available on site
Harming or disturbing roaming Principal Contractor and Sustainable Bright Site Manager ensure clear details
Interaction with reptiles or amphibians of no go and exclusion areas are clearly marked on site.
reptiles or Contaminating the land or water (H) All Contractors and sub-contractors are instructed during induction of no go and (VL
4 4 1 4
amphibians courses 16 exclusion zones )4
(Planning Consent) Disturbing feeding or breeding No Go and exclusion zones are checked daily by either Principal Contractor and
areas Sustainable Bright Site Manager ensure controls are maintained
Contractors briefed as to the requirements of correct clothing as weather moves
Contractors suffering for effects of
from summer to winter
coldness
Hypothermia or (L Drying room facilities provided & First Aid arrangements available (VL
Contractors and sub-contractors 3 3 Contractors briefed as to the requirements of correct clothing as weather moves 1 3
Hyperthermia )9 )3
suffering for effects of heat from Spring to Summer
exposure Potable water provided & First Aid arrangements available
Correct clothing must be worn
Dog and cat faeces Toxocariasis (H Full mandatory PPE worn 1 4
4 4 (VL)
(Toxocara canis) Loss of sight, ) Full site induction Toxocariasis risks are communicated
16
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 5 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
(Toxocara cati) ill health o Be aware strict PPE protocols must be adhered to. 4
o Wash hands thoroughly before eating, smoking etc
o Employees and Contractors reporting of any ill health to First Aid and
Sustainable Bright Project Team
Contractors under tight deadlines to Deadlines are clear and Contractors allowed adequate time to prepare in line
complete the works with program
(L Project managers ensure the correct work equipment/information is (VL
Stress Poor or incorrect communication 3 3 available to undertake the task 1 3
and instruction )9 )3
Work supervised effectively in a professional manner
Wrong tools for the job Adequate breaks are provided
Workers/Contractors briefed correctly on all tasks
OVERALL Risk Involved with NO Control Measures in Place RR OVERALL Risk Involved with FULL Control Measures in Place RR
Likelihood (L) Severity (S) (H) (L)
1 2 3 4 5 1 2 3 4 5 16 1 2 3 4 5 1 2 3 4 5 8
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 6 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 7 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
Risk Rating
Very Low Low Medium High Very High
1-4 5 -9 10 - 15 16 - 20 20 - 25
Risk Rating = Severity (S) x Likelihood (L)
The risk assessment matrix below (TABLE 1) should be used to calculate the risk level (Likelihood x Severity). Consideration may also be given to property damage or business risk; this can be added to
the severity section as appropriate. Once the risk has been calculated the priority for action can be set from TABLE 2.
Likelihood = L TABLE 2:
Risk Action
TABLE 1: Very May Unlikely Score
Certain (5) Likely (3) Rating
Likely (4) happen (2) (1)
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 8 of 9
Sustainable Bright – Risk Assessment
Reference RA08-SB-PV Solar Park – V1
Site /Work Location:
Assessment For:
PV Solar Park – (North Yorkshire)
Installation of PV Panels and connecting to Strings Cables EXAMPLE
Who is at Risk: Sustainable Bright Employees and Sub-Contractors
© Sustainable Bright & Absolute Health and Safety Solutions Ltd Page 9 of 9