Table 1.

Calendar of Activities

ACTIVITIES SCHEDULES
Preparation of Business Plan January 15 to April 14, 2024
Project Appraisal April 15 to April 22, 2024
Acquisition of Capital April 23 to April 30, 2024
Registration of Business May 6 to May 7, 2024
Procurement of Raw Materials May 10 to May 15, 2024
and Supplies
Procurement of Tools and Mary 16 to May 21, 2024
Equipment
Hiring of Caretaker, May 22 to May 25, 2024
Laborer and other staffs
Construction of Bahay Kubo May 26 to June 9, 2024
Construction of Fences June 10 to June 30, 2024
Construction of Poultry House July 1 to July 10, 2024
Construction of Barn House July 11 to July 20, 2024
Making of Fish Pond July 21 to August 11, 2024
Land Preparation August 12 to August 20, 2024
Hole Digging August 21 to August 26, 2024
Planting of Mango Trees August 27 to August 31, 2024
Planting of Guyabano September 1 to September 5, 2024
Planting of Avocado September 6 to September 10, 2024
Planting of Dragon Fruit September 11 to September 15, 2024
Planting of Calamansi September 16 to September 20, 2024
Maintenance and Care August 2024 to December 2028
Mulching and weeding August 2024, November 2024, February 2025, May 2025,
August 2025, November 2025, February 2026, May 2026,
August 2026, November 2026, February 2027, May 2027,
August 2027, November 2027, February 2028, May 2028
Watering August 2024-December 2028
Pruning October 2024, April 2025, October 2025, April 2026, October
2026, April 2027, October 2027, April 2028 October 2028
Cleaning May 2024 - December 2028
Application of organic fertilizer August 2024, November 2024, February 2025, May 2025,
August 2025, November 2025, February 2026, May 2026,
August 2026, November 2026, February 2027, May 2027,
August 2027, November 2027, February 2028, May 2028
Procurement of livestock September 2024 to December 2028
Feeding September 2024 to December 2028
Harvesting September 2024 to December 2028
Cleaning and Sorting September 2024 to December 2028
Weighing September 2024 to December 2028
Marketing of Products September 2024 to December 2028
Construction of Function Hall August 2025
Construction of Swimming August 2025
pools
Construction of Rooms August 2025
Construction of Court August 2026
Recording April 23, 2024 to December 31, 2028