JULI AGUSTUS

Jenis/Spesifikasi/ PERSENTASE
No. Deskripsi Komponen Jumlah Unit Proses M2 M3 M4 M1 M2 M3 M4
Material PROGRESS
1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7
Permintaan Percepatan PLTU 9 UP PAITON
1. Protecting Sleeve A No. 44 1 - PROSES PENGADAAN 100%
2. Sleeve for Diffuser Vane No. 33 2 - PEMBUATAN PATTERN 0%
3. First Wearing Ring No. 28 2 - POURING 0%
A ASTM A536 buah
4. Next Stage Wearing Ring No. 29 6 - GRINDING 0%
5. Protecting Sleeve (30) 1 - MACHINING 0%
- FINISHING 0%
6. Shaft Sleeve for Bearing D (15) 1 100%
- PENGADAAN MATERIAL
7. Block Sleeve (20) 2 0%
8. Shaft Sleeve for Bearing C (14) 1 0%
B 9. Shaft Sleeve for Bearing Up (37) SUS 316 L 1 buah - MACHINIING 0%
10. Seal Sleeve (42) 1 0%
11. Shaft Sleeve A (43) 1 0%
- FINISHING
12. Separate Sleeve (10) 1 0%
13. Bearing Upper No.39 1 - PENGADAAN MATERIAL 100.0%
C 14. Bearing C No.26 Thordon SXL 1 buah - MACHINING 0%
15. Bearing C No.27 1 - FINISHING 0%
Sesuai Batas Penugasan PLN Pusharlis 0%
16. Shaft Sleve for Bearing Down (13) 1 - PENGADAAN MATERIAL 100%
D 17. Shaft Sleeve (21) SUS 316 L buah - MACHINING 0%
1
- FINISHING 0%
TOTAL PERSENTASE PROGRESS 20%