You are on page 1of 1

TENANT TESTING & COMMISSIONING CHECKLIST FORM NO.

: PRV-RDD-E-019

Project: Date: Click or tap to enter a date.


Unit Name Click or tap here to enter text. Unit Number Click or tap here to enter text.

TESTING AND COMMISSIONING CHECKLIST

The below testing and commissioning reports are to be submitted by the Tenants Fit-out Contractor.

1 Firefighting pipe pressure test Complete Not Required

2 All HVAC equipment installed, commissioned, tested and balanced Complete Not Required

3 FCU/AHU/FAHU air balancing Complete Not Required

4 Chilled water pipe pressure test and flushing report Complete Not Required

5 Chilled water flow balancing Complete Not Required

6 Megger test and calibration certificate Complete Not Required

7 Water supply chlorination certificate and pipe pressure test Complete Not Required

8 Waterproofing tank test Complete Not Required

9 Drainage gravity test Complete Not Required

10 Live test certificate Complete Not Required

11 Kitchen extract hood/ fan/ ecology unit commissioning (F&B) Complete Not Required

12 Kitchen ventilation balancing report Complete Not Required

13 Smoke extract alarm & fan startup simulation (anchor) Complete Not Required

14 S/NG system third party inspection & ADNOC NOC Complete Not Required

15 LPG third party inspection certificate Complete Not Required

16 Fire alarm testing and commissioning report

16.1 LPG panel is interfaced with fire alarm/suppression system Complete Not Required

16.2 Electrical equipment below hood interfaced is interfaced with FACP Complete Not Required

16.3 HVAC is interfaced with FACP Complete Not Required

16.4 Access control maglock de-energization(if applicable) Complete Not Required

16.5 Pa/audio system mutes in the event of alarm Complete Not Required

16.6 Fire protection supervisory valve is interfaced with FACP Complete Not Required

16.7 Kitchen hood fire suppression system is interfaced with FACP & commissioning Complete Not Required

16.8 Tenant FACP interacting report with mall main fire alarm system Complete Not Required

17 Annual Maintenance Contract for firefighting fire alarm and LPG if available Complete Not Required

Note: The tenant’s main contractor is to ensure the correct certification is attached.

Tenant contractor Click or tap here to enter text.

Signature:

ACKNOWLEDGMENT

Retail Delivery: Click or tap here to enter text.

Date: Click or tap to enter a date.


Signature:

Facility Manager: Click or tap here to enter text.

Date: Click or tap to enter a date.


Signature:

You might also like