NOVEMBER 1, 2022 - WORK SCHEDULE

START OF CONSTRUCTION o
N vember 1, o
20-N vember 1, 204

2022 2023 2024


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
NAME OF WORKS nov dec jan feb mar apr may yune yule aug sep oct nov dec jan feb mar apr may yune yule aug sep oct

1 Demolition of existing dilapidated housing


2 Perimeter pile driving
3 Foundation pit processing
4 Pouring the foundation slab
5 End of the bearing monolithic part of the project
6 Perimeter walls and partitions
7 Roof hydro and thermal insulation
8 Installation of windows and stained-glass windows
9 Ventilated facade
10 Installation of elevators
11 Finishing of common areas NOVEMBER 1, 2024 -
COMPLETION OF WORKS
12 Gasification of the complex
13 Installation of all communication systems
14 Installation of entrance doors
15 Connection of all communications
16 Beautification of the surrounding area
17 Handing over keys to residence owners