You are on page 1of 32

31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.

UK

GOV.UK
Home Housing, local and community Planning and building
Building regulation
Building Safety Remediation: monthly data release - November 2023

Department for
Levelling Up,
Housing &
Communities

Research and analysis


Building Safety Remediation:
monthly data release -
November 2023
Published 21 December 2023

Applies to England

Contents
Headlines
Introduction
Enquiries
Building Safety overview
Overall remediation progress
ACM Remediation
Building Safety Fund
Cladding Safety Scheme
Developer remediation
Social Housing Sector

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 1/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Enforcement
Accompanying tables
Related Statistics

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 2/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

© Crown copyright 2023

This publication is licensed under the terms of the Open Government Licence v3.0 except where
otherwise stated. To view this licence, visit nationalarchives.gov.uk/doc/open-government-
licence/version/3 or write to the Information Policy Team, The National Archives, Kew, London TW9
4DU, or email: psi@nationalarchives.gov.uk.

Where we have identified any third party copyright information you will need to obtain permission
from the copyright holders concerned.

This publication is available at https://www.gov.uk/government/publications/building-safety-


remediation-monthly-data-release-november-2023/building-safety-remediation-monthly-data-
release-november-2023

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 3/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Date of next publication: 9.30am on Thursday 18 January 2024

From October 2023 onwards the Building Safety Remediation data release
includes data on buildings in the Building Safety Fund, Cladding Safety
Scheme, developer remediation contract and reported by registered providers
of social housing, as well as high-rise buildings with ACM cladding systems.
Previous versions of the data release have only included data on high-rise
buildings with ACM cladding systems unlikely to meet Building Regulations,
with data on buildings in the Building Safety Fund published separately.

Headlines

Overall remediation
At the end of November 2023, there are 3,824 residential buildings 11 metres
and over in height identified with unsafe cladding whose remediation
progression is being reported on in this release, an increase of 27 since the end
of October 2023.

At the end of last year, DLUHC was monitoring the remediation progress of
high-rise buildings with ACM cladding systems unlikely to meet Building
Regulations and buildings progressing in the Building Safety Fund. Throughout
2023, DLUHC has started monitoring the remediation progress of buildings in
the Cladding Safety Scheme, developer remediation contract and reported by
registered providers of social housing. This change in scope has largely driven
the reporting of an additional 2,222 buildings with unsafe cladding since the end
of December 2022.

Overall, 1,603 buildings (42%) have either started or completed remediation


works. Of these, 777 buildings (20%) have completed remediation works. The
total number of buildings reported to have started or completed has remediation
works has doubled since the end of December 2022.

Figure 1: Of the 3,824 buildings identified with unsafe cladding, 1,603


(42%) have started or completed remediation works, of which 777 (20%)
have completed remediation works. This includes remediation progress
on buildings mid-rise (11-18m) in height, as well as further identified high-
rise (18m+) buildings.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 4/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Note: Up to October 2023 combined remediation progress in the Building


Safety Fund (BSF) and ACM programme is shown. Between June 2023 and
September 2023 there was a decrease in the number of buildings due to
buildings transferring from the BSF to being remediated by developers. From
October 2023 onwards combined remediation progress is shown across the
BSF, ACM programme, Cladding Safety Scheme, developer remediation
contract and as reported by registered providers of social housing. The total
number of buildings does not sum to the total number of buildings reported in
each respective section of the data release due to crossover between schemes.

The majority of the increase in completions shown between October and


November 2023 is due to a change in methodology when assigning remediation
statuses for buildings that crossover between multiple schemes.

ACM remediation – monthly update (as at end November)


since previous publication
As at 30 November 2023, of the 496 high-rise (18 metres and over in height)
residential and publicly owned buildings with ACM cladding systems, unlikely to
meet Building Regulations, 476 (96%) have either started or completed
remediation works, an increase of three since the end of October.

Of these, 422 buildings (85%) have completed ACM remediation, including


those awaiting building control sign-off, no change since the end of October.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 5/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

There are 20 buildings yet to start ACM remediation (4% of all buildings), a
decrease of two buildings since the end of October. Two buildings are vacant
and so do not pose a risk to resident safety, 14 buildings have forecast start
dates and three without a start forecast have had local authority enforcement
action taken against them.

Building Safety Fund (BSF) – monthly update (as at end


November) since previous publication
As at 30 November 2023, of the 974 high-rise (18 metres and over in height)
residential buildings proceeding with an application for funding through the
Building Safety Fund, 268 buildings (28%) have started remediation works and
212 buildings (22%) have completed remediation on unsafe non-ACM cladding,
including those awaiting building control sign-off.

Overall, 480 high-rise buildings (49%) in the BSF have either started or
completed remediation works on non-ACM cladding, an increase of 21 since
the end of October. Of these, 212 buildings (22% of buildings) have completed
remediation works, an increase of 13 since the end of October.

Cladding Safety Scheme (CSS) – monthly update (as at


end November) since previous publication
As at 30 November, 522 buildings 11 metres and over in height have live
applications with the Cladding Safety Scheme, which launched fully in July
2023, and are progressing at pace through the eligibility checks.

A further 75 buildings have already been assessed as eligible for the


programme, an increase of 27 since the end of October. All have either signed
grant funding agreements or are in the process of doing so, and the most
advanced 17 applications have reached the stage of assembling a works
package.

This is in addition to over 1,400 buildings in the pipeline that are being
investigated, and where within programme parameters, are being brought into
the application process, including 447 buildings in the pre-application stage.

Developer remediation – data remains at end October


(the same as previous publication) with minor revisions
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 6/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

and updates
As at 31 October 2023, 1,345 buildings 11 metres and over in height have been
identified as having life-critical fire safety risks which developers have
committed to remediate or pay to remediate, including cladding and non-
cladding defects.

Of these, developers reported that 473 (35%) have either started or completed
remediation works, including 262 (19% of buildings) which have completed
remediation works.

When excluding buildings reported with only non-cladding defects, there are
1,273 buildings which developers have reported as having unsafe cladding, of
which 445 (35%) are reported to have started or completed remediation,
including 245 (19% of buildings) which are reported to have completed
remediation.

Social housing sector – latest data remains at end


August (the same as previous publication)
As at 31 August 2023, a survey of registered providers of social housing’s
building stock has identified 1,608 buildings 11 metres and over in height as
having unsafe cladding. Of these, providers have reported that 500 (31%) have
either started or completed remediation works, including 106 (7% of buildings)
which have completed remediation.

Enforcement - monthly update (as at end November)


since previous publication
As at 30 November 2023, local authority enforcement action has been, or is
being, taken under the Housing Act 2004 against 277 high-rise buildings with
unsafe cladding.

Introduction
This Data Release provides data on:

Remediation progress across DLUHC’s Building Safety Remediation


portfolio, covering buildings in the ACM programme, Building Safety Fund,
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 7/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Cladding Safety Scheme, developer remediation contract and reported by


registered providers of social housing
Progress with remediation of high-rise (18 metres and over in height)
residential buildings (including student accommodation and hotels) and
publicly owned buildings with ACM cladding systems unlikely to meet
Building Regulations in the ACM programme
Progress with remediation of high-rise residential buildings with non-ACM
cladding systems assessed as eligible for funding from the Building Safety
Fund
Progress with the applications for and remediation of medium-rise (11 – 18
metres in height) residential buildings in England and high-rise residential
buildings outside of London with non-ACM cladding systems in the Cladding
Safety Scheme
Progress of remediation of residential buildings 11 metres and over in height
with life-critical fire safety risks under the developer remediation contract
Progress of remediation of residential buildings 11 metres and over in height
with unsafe cladding reported by registered providers of social housing
Enforcement action taken by local authorities against high-rise residential
buildings with unsafe cladding under the Housing Act 2004.

From October 2023 onwards the Building Safety Remediation data release
includes data on buildings in the Building Safety Fund, Cladding Safety
Scheme, developer remediation contract and reported by registered providers
of social housing, as well as high-rise buildings with ACM cladding systems.
Previous versions of the data release have only included data on high-rise
buildings with ACM cladding systems unlikely to meet Building Regulations,
with data on buildings in the Building Safety Fund published separately.

Since April 2023, the management information tables published alongside the
data release have included a table on combined remediation progress in the
ACM programme and BSF, accounting for buildings that are eligible for both
programmes.

In Figure 1 in this data release, up to October 2023 the data includes the
combined remediation progress in the ACM programme and BSF. From
October 2023 onwards, the data in Figure 1 and the overall remediation
progress section of the data release, shows the combined remediation progress
across DLUHC’s Building Safety Remediation portfolio, covering buildings and
accounting for crossover in the ACM programme, Building Safety Fund,
Cladding Safety Scheme, developer remediation contract and reported by
registered providers of social housing.

The figures in this publication are correct as at the specified dates. Remediation
progress on the ACM programme, BSF and CSS will be updated monthly, and
remediation progress on the developer remediation contract and registered
providers of social housing will be updated quarterly.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 8/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Enquiries
Contact: BuildingSafetyData2@levellingup.gov.uk

Media enquiries: 0303 444 1209

NewsDesk@levellingup.gov.uk

User engagement
We are committed to improving and broadening this data release further in the
months ahead and would welcome feedback both on the revised content of this
data release and what could be further done in the future. Please contact
BuildingSafetyData2@levellingup.gov.uk

Building Safety overview


The government has made ground-breaking reforms to building and fire safety
legislation and is making good progress in dealing with the legacy of unsafe
cladding in England to make homes safe. All residential buildings above 11
metres in England have a pathway to fix unsafe cladding, either through a
taxpayer-funded scheme or through a developer-funded scheme, protecting
leaseholders from these costs.

Building owners and the industry that constructed and profited from the
defective buildings have a responsibility to make sure these buildings are safe.
51 developers have taken responsibility for fixing life-critical fire safety defects
arising from design or construction by signing the developer remediation
contract, committing to fix or pay to fix residential buildings in England at an
estimated cost to themselves of £2.7 billion. The Responsible Actors Scheme
has been established to monitor the progress made by responsible developers
in identifying and remediating buildings. 41 developers have already joined the
Scheme and any eligible developer who fails to comply with the terms of the
developer remediation contract will be subject to significant prohibitions.

The government has committed £5.1 billion to address unsafe cladding on


residential buildings where developers or building owners are not currently
doing so. The government is prioritising the highest-risk buildings – high-rise
buildings with unsafe, ‘Grenfell-style’ Aluminium Composite Material cladding –
and has almost finished the ACM programme. Relevant high-rise residential
buildings with other forms of unsafe cladding are remediated through the
Building Safety Fund. After a pilot in autumn 2022, the full opening of the
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mont… 9/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Cladding Safety Scheme in July 2023 marked the culmination of extensive work
to ensure that medium-rise buildings have a pathway towards remediation. The
Scheme is also open to new applications for 18m+ buildings outside of London.
All eligible applications to the Building Safety Fund received before 9 May 2023
will continue through the Fund.

Registered providers of social housing are responsible for making sure their
buildings are made safe in a proportionate and timely way. The Social Sector
ACM Cladding Remediation Fund has funded the remediation of ACM cladding
on social housing buildings. The BSF and CSS for 11m+ buildings with other
forms of unsafe cladding is open to registered providers to provide funding
equivalent to the amount which the registered provider would otherwise be
entitled to pass on to leaseholders; or where remediation would render the
owner financially unviable. A number of social housing buildings are also
expected to be remediated by the original developers under the terms of
developer remediation contracts.

This data release publishes data across all the above remediation activities to
give an overview of the progress made to remediate unsafe cladding on
residential buildings over 11m in England. Developers send the department
regular updates on the progress of remediation on those buildings. This data
release also includes data on how each developer is performing against their
contractual commitments.

Overall remediation progress


Figure 2: 1,603 residential buildings have started or completed
remediation on unsafe cladding, of which 777 (20%) have completed
remediation works.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 10/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Number Percentage

In programme 2221 58% 2221 58%

Remediation 826 22% 3047 80%


underway

Remediation 777 20% 3824 100%


complete

Total 3824 100% 3824 100%

Table 1: Remediation progress for buildings monitored by DLUHC in the ACM


programme, Building Safety Fund, the CSS, the developer remediation
contract, and social housing surveys, England, 30 November 2023

Overall remediation: key statistics


Of the 3,824 residential buildings 11 metres and over in height with unsafe
cladding DLUHC are monitoring, as at 30 November 2023:

777 buildings (20%) have completed remediation, including those awaiting


building control sign off
826 building (22%) have started remediation
2,221 buildings (58%) have not started remediation

Since the end of December 2022:

DLUHC is monitoring the remediation progress of 2,222 more buildings,


largely due to the opening of new programmes and new data reporting on the
CSS, developer-led remediation, and from social housing registered
providers.
854 more buildings are known to have started or completed remediation, of
which 329 more buildings are known to have completed remediation.

There are an estimated 224,000 dwellings in the occupied private and social
sector 11m+ residential buildings with unsafe cladding that DLUHC are
monitoring. Of these an estimated 53,000 dwellings are in buildings that have
completed remediation, and an estimated 51,000 additional dwellings are in
buildings that have started remediation.

Figure 3: Remediation progress differs across the programmes due to the


differing maturity of the schemes.
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 11/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Overall remediation by height


Figure 4: 50% of the 18m+ buildings DLUHC is monitoring the remediation
progress of have started or completed remediation on unsafe cladding,
compared to 28% of 11-18m buildings

Overall remediation by location


Figure 5: Most buildings that DLUHC are monitoring the cladding
remediation of are concentrated around urbanised areas in England,
particularly the urban areas of Greater London, Greater Manchester, West
Yorkshire and the North East
England, 30 November 2023

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 12/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

See London
insert

London

Local authorities with 10 or fewer 11m+ buildings monitored with unsafe


cladding are excluded from this map as their inclusion could lead to the
identification of buildings with unsafe cladding.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 13/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

ACM Remediation
Information in this section is correct as at 30 November 2023 and shows a
monthly update from the previous publication.

Figure 6: 96% of the 496 identified ACM clad high-rise buildings have
started or completed remediation, with 93% having had their ACM
cladding removed and 85% having completed remediation.

ACM Remediation: key statistics

Remediation Number of Percentage Cumulative Cumulative


Stage buildings number Percentage

Remediation 388 78% 388 78%


Complete

Remediation 34 7% 422 85%


Complete awaiting
building control
sign off

Remediation 39 8% 461 93%


started – cladding
removed

Remediation 15 3% 476 96%


started

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 14/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Remediation Number of Percentage Cumulative Cumulative


Stage buildings number Percentage

Remediation plans 14 3% 490 99%


in place

Intent to remediate 1 0% 491 99%

Remediation plan 5 1% 496 100%


unclear

Total 496 100% 496 100%

Table 2: Remediation status of buildings with ACM cladding systems unlikely to


meet Building Regulations, 30 November 2023

As at 30 November 2023, DLUHC has identified 496 high-rise residential and


publicly owned buildings identified with ACM cladding systems unlikely to meet
Building Regulations, an increase of one since the end of October.

422 buildings (85% of all buildings) have completed ACM remediation - no


change since the end of October. Of these, 388 buildings (78% of all
buildings) have received building control sign off – an increase of 19 since
the end of October.
476 buildings (96% of all buildings) have started or completed ACM
remediation - an increase of three since the end of October. Of these, 461
buildings (93% of all buildings) have removed ACM cladding - an increase of
one since the end of October.

There are an estimated 25,000 – 28,400 dwellings in private and social sector
buildings that have completed remediation, and a further 6,000 – 6,400
dwellings in occupied private and social sector buildings that have yet to be
remediated.

Driving ACM remediation forward


There are 20 buildings yet to start ACM remediation (4% of all buildings) – a
decrease of two buildings since the end of October. Two buildings are vacant
and so do not pose a risk to resident safety.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 15/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Remediation All Of which:


Stage occupied
buildings
yet to start
remediation

Enforcement Enforcement Forecast Foreca


action action start to start
supported available the end
by Joint Decem
Inspection 2023
Team

Total 18 13 8 14 0

Table 3: Enforcement action and forecast start dates for occupied high-rise
buildings yet to start ACM remediation, 30 November 2023

Of the 20 high-rise occupied buildings yet to start ACM remediation:

Twelve buildings are forecast to start works by the end of March 2024.
A further two buildings are forecast to start works by the end of December
2024.
A further three buildings without a start forecast have had local authority
enforcement action taken against them.
One building was newly in scope of the ACM monitoring programme in
November 2023

These forecast estimates are based on information provided by building owners


and agents and are expected to change as further information is received.
These estimates can also change as a result of buildings being newly identified.
The Department continues to engage with building owners to start remediation
works on site as soon as possible, and will continue to support local authorities
and fire and rescue services in the use of their enforcement powers.

Figure 7: 96% of buildings are forecast to have started or completed ACM


remediation works by the end of December 2023, with 94% estimated to
be de-risked and 88% estimated to have completed remediation

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 16/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

600 Figures a er 30 November


2023 are projected based on
planned start and completion
500 dates

400 67
135
3 216
289
101 354
300 388
54 436
123 468
33
200
64
255 269 168
100 192 53
96 34
56 54 40
45 32 24 14 22
0 20 6 6
10 JAN 2018 31 DEC 31 DEC 31 DEC 31 DEC 31 DEC 30 NOV 31 DEC 31 DEC
2018 2019 2020 2021 2022 2023 2023 2024
Unknown forecast Not started remediation works
Started remediation works Works complete awaiting building control sign off
Remediation completed

ACM remediation progress by year of identification


Figure 8: 98% of buildings identified at 31 December 2021 have started or
completed remediation compared to 96% of all buildings in the
programme.

All buildings 78% 7% 8% 3% 4%

Buildings identified
80% 7% 8% 3% 2%
at 31 Dec 2021

Buildings identified
82% 7% 7% 3%1%
at 31 Dec 2020

Buildings identified
84% 6% 7% 2%1%
at 31 Dec 2019

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Remediation completed Works complete awaiting building control signoff


Remediation started - cladding removed Remediation started
Remediation not started

Since 31 December 2021, 15 further high-rise residential buildings have been


identified with ACM cladding systems unlikely to meet Building Regulations and
have moved into scope of the Building Safety Programme. Of these, six
buildings were identified in 2022, and nine so far this year – an increase of one
since the end of October.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 17/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

ACM remediation by sector


Figure 9: 100% of the 161 social sector residential buildings in the ACM
programme have started remediation, compared to 93% the 238 private
sector residential buildings.

Building Safety Fund


Information in this section is correct as at 30 November 2023 and shows a
monthly update from the previous publication.

Figure 10: 49% of buildings proceeding with an application for funding in


the BSF have started or completed remediation, with 22% having
completed remediation.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 18/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Number Percentage

Remediation 135 14% 135 14%


Complete

Remediation 77 8% 212 22%


Complete awaiting
building control
sign off

Remediation 268 28% 480 49%


started

Remediation plans 191 20% 671 69%


in place

Intent to remediate 303 31% 974 100%

Total 974 100%* 974 100%

Table 4: Remediation status of buildings within the Building Safety Fund, 30


November 2023. Note that individual percentages do not sum to 100% due to
rounding.

BSF remediation: key statistics


As at 30 November 2023, 974 buildings were assessed as eligible and are
proceeding with an application for funding from the Building Safety Fund. The
remaining 2,660 buildings registered with the fund are either ineligible (1,093),
withdrawn which includes those transferred to developers (1,500), in review or
have given insufficient evidence (67).

Of the 974 buildings proceeding with an application for funding in the Building
Safety Fund:

167 buildings (17%) are remaining in the fund with developers set to
reimburse the cost of remediation,
31 buildings (3%) are anticipated to be transferred to developers for their
remediation.

Of the 974 buildings proceeding with an application for funding, 480 buildings
(49%) have either started or completed remediation works – an increase of 21
since the end of October.
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 19/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Of the 480 buildings that have started or completed remediation as at 30


November 2023:

268 buildings (28%) have started remediation.


212 buildings (22%) have completed remediation – an increase of 13 since
the end of October. Of these, 135 buildings (14%) have received building
control sign off.

There are 494 eligible buildings that have not started remediation, of which:

303 have reported an intent to remediate


191 have remediation plans in place.

There are an estimated 86,000 dwellings in buildings that are proceeding with
an application for funding in the BSF.

BSF remediation progress over time


Figure 11: 137 more buildings proceeding with an application for funding
in the BSF have started or completed remediation since the end of 2022.

BSF remediation by tenure


https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 20/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Figure 12: 64% of social sector buildings in the BSF have started or
completed remediation compared to 46% of private sector buildings.

Cladding Safety Scheme


Information in this section is correct as at 30 November 2023 and shows a
monthly update from the previous publication.

Figure 13: There are over 1,000 buildings at different stages of the
Cladding Safety Scheme, including 522 buildings with live applications.

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Number Percentage

Remediation 0 0% 0 0%
Complete

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 21/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Number Percentage

Works started 0 0% 0 0%

In Programme 75 100% 75 100%

Total 75 100% 75 100%

Table 5: Remediation status for buildings within the Cladding Safety Scheme,
30 November 2023

Cladding Safety Scheme: Key statistics


As at the end of November 2023, there were over 1,000 buildings in the
different stages of the Cladding Safety Scheme. Of the pre-eligible buildings:

447 buildings are in the pre-application stage.


522 buildings have a live application and are progressing at pace through the
eligibility stages.

There are 75 eligible buildings in programme as at the end of November 2023,


an increase of 27 since the end of October. Of the 75 eligible buildings:

All 75 buildings have been issued or have signed Grant Funding Agreements
(GFA) - an increase of 16 since the end of October - with those eligible
receiving pre tender support.
17 buildings are assembling or preparing to assemble a works package to
complete the remediation works required, having signed a GFA – an increase
of 11 since the end of October.

In total, 43 buildings (57% of eligible buildings) have signed a Grant Funding


Agreement and 31 buildings (41% of eligible buildings) have received a pre-
tender support payment.

A further 1,000 buildings are being investigated to establish whether they can
start the pre-application process.

Height breakdown

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 22/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Figure 14: Of the 75 eligible buildings in the CSS, 64 are 11-18m and 11
are 18m+.

Tenure breakdown
Figure 15: Of the 75 eligible buildings in the CSS, 66 are private sector
buildings and 9 are social sector buildings.

Developer remediation
Information in this section is correct as at 31 October 2023. Some information
has been received and processed since the date of the previous publication,
and so will show minor amendments and updates.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 23/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

The estimates in this section include some buildings which are also included in
other sections of this data release e.g., those reported under the following
sections: ‘ACM Remediation’, ‘Building Safety Fund’, ‘Cladding Safety Scheme’
and ‘Social Housing Sector’.

Figure 16: 35% of buildings in the developer remediation contract have


either started or completed remediation works on life-critical fire safety
risks, with 19% having completed remediation works.

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Number Percentage

Remediation 262 19% 262 19%


complete

Remediation 211 16% 473 35%


started

Remediation not 506 38% 979 73%


started – plans in
place

Remediation not 366 27% 1345 100%


started – no plans
in place

Total 1345 100% 1345 100%

Table 6: Remediation status of buildings requiring works under the developer


remediation contract, 31 October 2023.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 24/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Developer remediation: key statistics


As at 31 October 2023, of the 1,345 buildings identified as having life-critical fire
safety risks that will be remediated by developers:

262 (19%) are reported to have completed remediation


473 (35%) are reported to have started or completed remediation
506 (38%) are reported to have not started remediation but have plans in
place.

The 1,345 buildings identified as requiring remediation have an estimated cost


of remediation of around £2.7 billion.

There are an estimated 91,000 dwellings in buildings with defects that


developers are committed to remediate. Of these, there are an estimated
32,000 dwellings in buildings that are reported as having either started or
completed remediation works.

Based on start and completion dates reported by developers, 433 buildings are
expected to start works and 164 buildings are expected to complete their
remediation between 1 November 2023 and 31 October 2024.

Height breakdown
Figure 17: 39% of the 18m+ buildings have started or completed
remediation, compared to 29% of the 11-18m buildings.

Cladding defects
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 25/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Not all remediation being undertaken by developers on buildings with life-critical


fire safety risks are regarding cladding defects. When excluding buildings
reported with only non-cladding defects, there are 1,273 buildings which
developers have reported as having unsafe cladding. Of these:

245 (19%) are reported to have completed remediation


445 (35%) are reported to have started or completed remediation
476 (37%) are reported to have not started remediation but have plans in
place.

Self-reported information
The figures reported for developers above combine information received
directly from developers as well as information held by the department
regarding additional buildings that require or previously required remediation
work to help better estimate a figure for buildings requiring remediation.
Developers have self-reported that 1,170 buildings require remediation to life-
critical fire safety risks and of those 1,035 buildings will be directly remediated
by the developer, rather than remaining in the BSF or ACM fund to be
remediated and then reimbursed by the developer. Of these:

156 buildings (15%) have completed remediation


298 buildings (29%) have started or completed remediation
455 buildings (44%) have not started remediation but have a plan in place

Further information on the progress developers have made regarding the


buildings they’ve reported on is available in the accompanying management
information tables (https://www.gov.uk/government/publications/building-safety-
remediation-monthly-data-release-november-2023).

Social Housing Sector


Information in this section is correct as at 31 August 2023 and remains the
same as the previous publication.

The estimates in this section include some buildings which are also included in
other sections of this data release e.g., those reported under the following
sections: ‘ACM Remediation’, ‘Building Safety Fund’, ‘Cladding Safety Scheme’
and ‘Developer Remediation’.

Figure 18: 31% of buildings reported by registered providers to have


unsafe cladding have started or completed remediation works, with 7%
https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 26/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

having completed remediation works.

Remediation Number of Percentage Cumulative Cumulative


Stage buildings Buildings Percentage

Remediation 106 7% 106 7%


complete

Remediation 394 25% 500 31%


started

Remediation 591 37% 1091 68%


works planned

Remediation 510 32% 1601 100%


plans unclear
from survey

Work is not 7 0% 1608 100%


required –
planned for
demolition

Total 1608 100% 1608 100%

Table 7: Remediation status of buildings with unsafe cladding reported by


registered providers of social housing, 31 August 2023.

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 27/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Social Housing Remediation: key statistics:


1,503 registered providers of social housing were invited over the summer of
2023 to respond to a survey on their 11m+ stock. So far, 88% of registered
providers have responded.

As reported in the surveys submitted at aggregate level across the


respondents, 1,608 buildings were reported to have unsafe cladding.

Of the 1,608 buildings reported to have unsafe cladding:

106 buildings (7%) are reported to have completed remediation


500 buildings are reported to have started or completed remediation (31%)
591 buildings are reported to have not started remediation but have plans in
place (37%).
7 buildings are reported as not requiring work are buildings planned for
demolition (<1%).

Height breakdown
Figure 19: 34% of the 18m+ buildings reported to have unsafe cladding by
the registered providers of social housing have started or completed
remediation, compared to 28% of the 11-18m buildings.

Enforcement

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 28/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

Information in this section is correct as at 30 November 2023 and shows a


monthly update from the previous publication.

Local authority enforcement action: key statistics


As of 30 November 2023, enforcement action has been, or is being, taken
under the Housing Act against:

277 high-rise buildings with unsafe cladding – an increase of 20 since the


end of October
including 103 buildings with Joint Inspection Team support – an increase of 3
since the end of October

Of the 277 buildings where a local authority had undertaken an inspection, we


are aware that:

62 had a Category 1 HHSRS rating


172 buildings had a Category 2 HHSRS rating.

Of the 277 cases, we are aware that at least 84 improvement notices, 24


hazard awareness notices and 1 prohibition order have been served to date.
We understand that 14 of the 84 improvement notices have been subject to
appeals.

Accompanying tables
Additional management information tables are available here
(https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-
release-november-2023).

The tables provide data on:

the remediation progress of high-rise (18 metres and over) residential


buildings identified with unsafe Aluminium Composite Material (ACM)
cladding systems,
the remediation progress of high-rise residential buildings with unsafe non-
ACM cladding systems that are pursuing successful applications from their
Building Safety Fund (BSF) Registration,
data on buildings in the Cladding Safety Scheme (CSS),
the remediation progress of buildings covered by the developer remediation
contract, including a developer-by-developer breakdown,

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 29/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

the remediation progress of buildings monitored under the social housing


survey,
the progress of the Waking Watch Relief Fund and Waking Watch
Replacement Fund, and
building safety enforcement action undertaken by Local Authorities in
England.

Related Statistics

BRE Testing
Previously, DLUHC published a table on samples
(https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/837937/T
able_4_Building_Safety_Data_Release_September_2019.csv/preview) received by
BRE for testing which has been discontinued as of October 2019 (see Technical
Notes). The data table of descriptions of large-scale system tests
(https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachmen
t_data/file/934665/Table_4_Building_Safety_Data_Release_October_2020.csv/preview)
undertaken by the BRE and the number of buildings with similar cladding
systems was discontinued in November 2020.

Developer Data
DLUHC has published data provided by developers
(https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-
release-november-2023/developer-remediation-contract-data-release-november-2023)
who have signed the developer remediation contract. This release provides
information on the number of buildings in scope of the contract, assessments in
place, number of buildings requiring remediation works and status of those
works by developer.

English Housing Survey: Feeling Safe from Fire


DLUHC has published the English Housing Survey 2020 to 2021: Feeling Safe
from Fire report (https://www.gov.uk/government/statistics/english-housing-survey-

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 30/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

2020-to-2021-feeling-safe-from-fire), providing information on the extent to which


people feel safe from fire in their homes.

Estimating the prevalence and costs of external wall


system life-safety fire risk in mid-rise residential
buildings
DLUHC has published data on the prevalence of external wall system life-safety
fire risk in mid-rise (11-18m) residential buildings in England
(https://www.gov.uk/government/publications/estimating-the-prevalence-and-costs-of-
external-wall-system-life-safety-fire-risk-in-mid-rise-residential-buildings-in-england),
and the estimated cost as at July 2021 to remediate or mitigate these buildings.

EWS1 requirements on residential buildings in England


DLUHC has published information on estimates of EWS1 requirements on
residential buildings in England
(https://www.gov.uk/government/publications/building-safety-programme-estimates-of-
ews1-requirements-on-residential-buildings-in-england), including indicative analysis
on the cladding coverage of residential buildings and the number of leasehold
dwellings in those buildings.

EWS1 (or equivalent) lender data on mortgage valuation


for flats
DLUHC publishes quarterly data on the numbers of EWS1 forms (or equivalent)
that have been required on mortgage valuations for flats
(https://www.gov.uk/government/collections/ews1-or-equivalent-lender-data-on-
mortgage-valuations-for-flats).

Population and Dwelling Numbers


Previously, DLUHC published estimates on population and dwelling numbers of
residential buildings in the Building Safety Programme data release
(https://www.gov.uk/government/publications/building-safety-programme-monthly-data-

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 31/32
31-03-2024 03:43 Building Safety Remediation: monthly data release - November 2023 - GOV.UK

release-october-2023). Should these figures change, DLUHC will publish a new


update.

Waking Watch costs


On 16 October 2020, DLUHC published information on Waking Watch costs
(https://www.gov.uk/government/publications/building-safety-programme-waking-watch-
costs) based on data collected through a range of external stakeholders from
July to September 2020:

RSH publication
On 16 November 2023, the Regulator of Social Housing published findings from
the Fire Safety Remediation Survey (FRS)
(https://www.gov.uk/government/publications/fire-safety-remediation-in-social-housing-in-
england) for buildings 11 metres and over in height, which opened to all
landlords on 23 August 2023 and closed on 15 September 2023.

Technical note
Please see the accompanying technical notes document
(https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-
release-november-2023) for further details.
Back to top

All content is available under the Open Government


Licence v3.0, except where otherwise stated © Crown copyright

https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-november-2023/building-safety-remediation-mo… 32/32

You might also like