Professional Documents
Culture Documents
MTRC NEC4 Training Level 2 - Module 3 Rev 1.1
MTRC NEC4 Training Level 2 - Module 3 Rev 1.1
September 2021
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
Training modules
Roles &
responsibilities Compensation Time and the
Precontract Commercial
and risk events programme
management
Module 3 –
Compensation Events
■ Compensation events are events for which the Client takes the
risk of their occurrence
■ If a compensation event occurs the Contractor will be entitled
to be compensated for the effect of that event in terms of
both time and cost
■ time (Completion Date(s), Key Dates)
■ cost (direct, indirect, delay and disruption)
■ There is no separate extension of time (EOT) or claim clauses
■ Single opportunity to price for all the time and cost effects
resulting from the event!
(2) The Client does not provide access and use of the Site by the
later of its access date and the date shown the Accepted
Programme
■ The Client is obligated to provide access under clause 33.1
■ The Contractor can delay the date for access to the Site by
identifying a later date in the programme submitted for
acceptance and can bring this date forward in a later
programme submission but cannot require an earlier access
date than the access date in the Contract Data
(16) The Client does not provide materials, facilities and samples for
tests and inspections as stated in the Scope
■ A breach of an obligation set out in the Scope
(17) The Project Manager notifies a correction to an assumption
about a compensation events
1m depth
Junction Junction
box 1 box 2
rock
Junction Junction
box box
10m of
cable Compensation event notified
installation by the Contractor for
unforeseen physical
conditions, accepted by
Project Manager
rock
Junction Junction
Quotation to be provided by the Contractor
box box
10m of and this is there one chance to cover for all
installation of the time and cost effects of the event
90m of rock
rock
Junction Junction
box box
10m of
installation
10m of rock
Junction Junction
box box
5m of rock
Junction Junction
box box
-5m of rock
Junction Junction
box box
(18) A breach of contract by the Client which is not one of the other
compensation events under this contract
■ A “catch all” provision to allow the Project Manager to deal with
any breach of an obligation by the Client via the compensation
event process and to avoid time becoming “at large"
ECC PSC
60.1(1) Project Manager gives an 60.1(1) Service Manage gives an
instruction to change the Scope instruction to change the Scope
except except
• a change made in order to • a change made in order to
accept a Defect accept a Defect
• a change to the Scope provided • a change to the Scope provided
by the Contractor for its design by the Consultant which is made
which is made • at the Contractor’s request or
• at the Contractor’s request or • in order to comply with the
• in order to comply with the Scope provided by the Client
Scope provided by the Client
ECC PSC
60.1(2) The Client does not provide 60.1(2) Client does not allow access
access and use of the Site by the to a person, place or thing by the
later of its access date and the date later of its access date and the date
shown the Accepted Programme for access shown on the Accepted
Programme
60.1(3) The Client does not provide 60.1(3) The Client does not provide
something which it is to provide by something which it is to provide by
the date shown in the Accepted the date shown in the Accepted
Programme Programme
60.1(4) Project Manager gives an 60.1(4) Service Manager gives an
instruction to stop or not start any instruction to stop or not start any
work, or to change a Key Date work, or to change a Key Date
ECC PSC
60.1(5) The Client or Others do not 60.1(5) The Client or Others do not
work within the times shown on the work within the times shown on the
Accepted Programme, the Accepted Programme or the
conditions stated in the Scope, or conditions stated in the Scope
do work on Site not stated in the
Scope
60.1(6) The Project Manager or 60.1(6) The Service Manager does
Supervisor does not reply to a not reply to a communication from
communication from the Contractor the Consultant within the period
within the period required in the required in the contract
contract
60.1(7)The Project Manager
instructs how to deal with an object
of value or historical interest
ECC PSC
60.1(8) The Project Manager or 60.1(7) The Service Manager
Supervisor changes a decision changes a decision which the
which either has previously Service Manager has previously
communicated to the Contractor communicated to the Consultant
60.1(9) Project Manager withholds 60.1(8) Service Manager withholds
an acceptance for a reason not an acceptance for a reason not
stated in the contract stated in the contract
60.1(10) Supervisor instructs a
search for a Defect and no Defect is
found unless the search is only
needed because the Contractor
gave insufficient notice of doing
work obstructing a required test or
inspection
ECC PSC
60.1(11) A test or inspection by the
Supervisor causes unnecessary
delay
60.1(12) Unforeseen physical
conditions
60.1(13) A weather event over a 1
in 10 year event level
60.1(14) An event which is a 60.1(9) An event which is a Client’s
Client’s liability stated in these liability stated in these conditions of
conditions of contract contract
60.1(15) The Project Manager
certifies take over before both
Completion and the Completion
Date
ECC PSC
60.1(16) The Client does not
provide things for tests and
inspections as stated in the Scope
60.1(17) The Project Manager 60.1(10) Service Manager notifies
notifies the Contractor of a the Consultant of a correction to an
correction to an assumption which assumption which the Service
the Project Manager stated about a Manager stated about a
compensation event compensation event
60.1(18) A breach of contract by 60.1(11) A breach of contract by
the Client which is not one of the the Client which is not one of the
other compensation events in the other compensation events in the
contract contract
ECC PSC
60.1(19) An event which 60.1(12) An event which
• stops the Contractor completing the • stops the Consultant completing the
whole of the works or whole of the service or
• stops the Contractor completing the • stops the Consultant completing the
whole of the works by the date for whole of the service by the date for
planned Completion shown on the planned Completion shown on the
Accepted Programme, Accepted Programme,
and which and which
• neither Party could prevent, • neither Party could prevent,
• an experienced contractor would • an experienced consultant would
have judged at the Contract Date to have judged at the Contract Date to
have such a small chance of have such a small chance of
occurring that it would have been occurring that it would have been
unreasonable to have allowed for it unreasonable to have allowed for it
and and
• is not one of the other compensation • is not one of the other compensation
events stated in the contract events stated in the contract
ECC PSC
60.1(13) The Consultant corrects a
Defect for which it is not liable
under the contract – obligation is
provide the service using
reasonable skill and care, a Defect
caused even when reasonable skill
and care has been exercised will
still need to be corrected but this
will be a compensation event
60.1(14) The Service Manager gives
an instruction correcting information
provided by the Client – Client
warrants the information it provides
to the Consultant
ECC PSC
60.1(20) the Project Manager 60.1(15) the Service Manager
notifies the Contractor that a notifies the Consultant that a
quotation for a proposed instruction quotation for a proposed instruction
is not accepted is not accepted
60.1(21) Additional compensation 60.1(16) Additional compensation
events stated in the Contract Data events stated in the Contract Data
Procedure
PMI / SI
Decision on
NCE NEC – 8
validity - 1
(cl 61.1) weeks
week (cl 61.3)
(cl 61.3)
Not a
compensation
event
Quotation -
Instruct
3 weeks
quote
(cl 62.3)
(cl 61.2 /
61.4)
Respond to
quote - 2
weeks (cl Issue quote
62.3)
Project
Manager’s
assessment
(3 weeks) Implemented
Notification
■ Either the Project Manger or the Contractor can notify the other
of a compensation event
■ The Project Manager is required to notify certain compensation
events – those that arise from an action of the Project Manager or
Supervisor, 60.1(1), (4), (7), (8), (10), (15), (17), (20) (cl 61.1)
■ As part of the notification, they will also instruct the Contractor to
submit a quotation for the compensation event unless
■ the event arose due a fault of the Contractor
■ the event has no effect on the Prices, Completion Date or Key
Dates (cl 61.2)
Notification
Notification
Notification
1 week X weeks
Notification
PMI / SI
Decision on
NCE NEC – 8
validity - 1
(cl 61.1) weeks
week (cl 61.3)
(cl 61.3)
Not a
compensation
event
Instruct
quote
(cl 61.2 /
61.4)
Quotation
■ The Project Manager can enter into discussion with the Contractor
about alternative ways of dealing with the compensation event and
can ask for alternative quotes (62.1)
■ This process allows for different options for dealing with the
compensation event to be considered such as mitigating cost or
mitigating delay
■ This could include considering delay recovery measures and
instructing quotations be prepared on this basis
■ Contractor has to submit the required quotations and can offer
further alternatives
■ To support delay recovery measures instructions changing the Scope
could be issued – if required – which in themselves would be
compensation events but the Contractor would not be entitled to the
same costs and time effects twice
Quotation
Assessment
Assessment
Compensation
event
notification
Assessment
Compensation
event
notification
Assessment
Compensation
event
notification
Assessment
Compensation Compensation
event event quotation
notification assessment
Assessment
Assessment
Compensation
Compensation event 3 cannot
event 2 can be be dealt with by
Compensation dealt with by the existing
event 1 can be the existing management
dealt with by management team and
the existing team but they additional
management are now at resource is now
team capacity
Cost
required
Additional resource
Management resources
Time
Assessment
Assessment
Assessment
■ The Project Manager can make its own assessment of the effects
of a compensation event if
■ the Contractor has not submitted a quotation and details of its
assessment in the time allowed
■ the Project Manager decides that the Contractor has not assessed
the compensation event correctly and does not request a revised
quotation
■ the Contractor fails to submit a programme or alterations to a
programme which this contract requires it to submit
■ when the Contractor submits quotations for a compensation event,
the Project Manager has not accepted the Contractor’s latest
programme for a reason stated in the contract
■ The assessment made by the Project Manager cannot be
challenged or rejected by the Contractor, except through the
dispute process under the contract
Turner & Townsend MTRC NEC4 Level 2 – Module 3 65
Turner & Townsend Confidential
Implementation
PMI / SI
Decision on
NCE NEC – 8
validity - 1
(cl 61.1) weeks
week (cl 61.3)
(cl 61.3)
Not a
compensation
event
Quotation -
Instruct
3 weeks
quote
(cl 62.3)
(cl 61.2 /
61.4)
Respond to
quote - 2
weeks (cl Issue quote
62.3)
Project
Manager’s
assessment
(3 weeks) Implemented
Proposed Instructions – cl 65
Proposed Instructions – cl 65
© Turner & Townsend Limited. This content is for general information purposes only and does not purport to constitute professional advice. We do not make any
representation or give any warranty, express or implied, and shall not be liable for any losses or damages whatsoever, arising from reliance on information contained in this
document.
It must not be made available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our express written
permission and we accept no liability of whatsoever nature for any use by any other party.