NCR
NON-CONFORMANCE
REPORT
QWP- 009
NCR
TABLE OF CONTENTS
PAGE
TITLE 1
TABLE OF CONTENTS 2
1 PURPOSE 3
2 SCOPE 3
3 RESPONSIBILITIES 3
4 DEFINITIONS 3
5 PROCEDURE 3
6 PROCESS FLOW
7 QUALITY RECORDS
8 REFERENCE
9 APPENDICES
QWP- 009
NCR
1. Purpose
The purpose of this procedure is for the issuance and verification of non-conforming products/services that
does not comply based on the contract requirements, quality plan and other related documents. This shall serve as a
record which will help evaluate the performance of our partners. Non-conforming products is investigated of its root
cause or root cause analysis, actions to prevent re-occurrence and the action plan for the conforming item in order
to correct defects based from the recommendation of approving bodies and to improve the process in order to
establish preventive measures on the possible defective works in the upcoming works.
2. Scope
The scope of this procedure is for the verification and issuance of all non-conforming products. Including the
measurement of resolution rate or response of our partners about the issues/defects. NCR must include root cause
analysis and action to prevent re-occurrence from our partners to eliminate re-manifestation of defects.
3. Responsibilities
4. Definition
CM – Construction manager
5. Procedure
RLC Construction Engineer / Architect will generate a non-conformace report based on the identified
non-conformity using the Non-Conformance Report Form (RLC-CCM-GF-007).
5.2 Validate
RLC Safety & QA/QC Engr. shall review and validate the accuracy of Non-Conformance Report
Generated based on the section of non-conformity it violates.
Document Controller will record the non-conformance report and issue to the concerned
contractor/s and secure receiving copy.
QWP- 009
NCR
Contractor will receive the NCR and shall determine the root cause of the non-conformity then
recommend action plans to close-out existing Non-Conformity as well as the preventive actions to avoid re-
occurrence including their target schedule of close-out.
5.5 Review
RLC CM will review target schedule, root cause and action plans recommended by the contractor
and approves. RLC CM will review for cost impact/ deduction of the non-conformance (if any)
If the subject matter needs technical evaluation and recommendation, RLC CM will forward the
details of NCR thru document controller to the designers/consultants for their review, comments and
approval.
Document controller will check completeness and record the WIIR generated and attach to the NCR
Form.
Contractor may now proceed to the work activity based on the approval of RLC CM / Consultants
After the activity the contractor will request for the approval and close-out of WIIR to the RLC
Construction Engr. Arch. in charge, RLC Safety and QA/QC, RLC CM and Consultant/Designer (if deemed
necessary).
5.8 Close-out
Once non-conformance items are approved and accepted, Contractor will submit the close-out
documents to Document Controller for checking of completeness and recording and filling and distribution
of NCR. RLC CM shall attach copy of NCR in the next contractor’s progress billing for the cost impact
deductions.
Prepared by: Jan David Jeff M. Timpog Approved by: Ronald G. Paulo