CONTRACT TITLE: PRODUCED WATER TREATMENT & CRUDE OIL DESALTING PROJECT AT HALUL
1 Code 3 Accepted without comments Raiding the document for the AFC status
QA00D-271C-GX-0017 revA PAGE 2 OF 9
Doha Petroleum Construction Co. Ltd
Post Box 1744, Doha-Qatar, Tel:44600350 – Fax: 44601066
This report details the Internal audit activities of the contract/ project no. 1646000544, Produced Water Treatment
& Crude Oil Desalting Project at Halul to verify compliance to Contractual/Project Quality Plan requirements.
The audit comprised the review of the Quality management system documentation, project startup activities
and an assessment to verify, continued implementation of the system. The following areas were audited.
Quality Management System including Project Quality Plan and QP Contractual requirements
Projects Management including Organization, Resources, Planning, Monitoring and Control
Civil Sub Contractor (Oriental )
QA/QC
Document Controller
The audit by nature itself is a sample exercise therefore it does not warrant that all existing weaknesses are
identified under this audit. Deficiencies identified during the course of audit are hereby identified as Corrective
Action Request.
th
Audit Achedue: 11thJune 2018 to 24 June 2018, M/s Oriental _ Civil Subcontractor at Halul Site.
Availability of controlled copy of PQP with Construction Manag er as per distribution list of Project Quality Plan
a. checked.
g Communication of project team with TEPQ checked. ( MOM of weekly meeting checked )
h Identification of equipment and manpower resources ver ified through planning package
j Internal communication and document flow within discipline departments (Project, Engineering, QA/QC and
Production Etc.) checked.
K Process of raising RFI is checke d. RFI for Civil activities are checked .
N Cube test process and equipments calibration status are checked at laboratory.
R Document Master List and latest copies of drawings & documents are verified.
Positive Notes:
Ref Document(s) /
Sl Objective
Process Observations/CAR
No Evidence(s) and
remarks
CAR:01
Requirement of
Project Management Civil Sub Contractors Project Manager was not able to show Project Quality
availability of following required to manage the project: Plan & Document
01. Sub Contractor Control
1. Organization Chart
Procedure
(Oriental ) 2. QA/QC Inspector
3. Approved Project Plan/Schedule
4. TEPQ Specification & Drawings
CAR:02
Requirement of
Investigation and Corrective action on the two NCRs (NCR -
Project Quality
Project Management 001 & 002) are not yet completed and submitted to
Plan & Non -
Dopet/TEPQ.
Conformities
02. Sub Contractor
An improvement action has been carried out after the NCR Control
(Oriental) about the failure of mechanical tests of concrete samples. Procedure
This action was supported by Dopet QAQC and TEPQ QAQC,
a new way forward was defined, But, this new way is not
developed into a sampling procedure.
QA/QC CAR:03
Requirement of
Inspection and
03. Sub Contractor Evidence of review of MTC/Mill Test report of Rebar and
Test Plan of
Back fil ling material’s test report s are not available.
(Oriental) Offshore Works
CAR:04 Requirement of
Document control
04. Document Controller Site Document Control system and record control found not in as per the Project
compliance based on the below objective evidences: Quality Plan
Observation:01
Sub Contractor
1. None.
Environment Monitoring (Temp. & Humidity) log is to be
(Oriental)
maintained at Laboratory.
Observation:02
Sub Contractor
2. Identification mechanism after sample taking & during cube None.
(Oriental) pouring to be established and implemented in the laid down
area.
Observation:03
Sub Contractor
3. None.
Identification tags to be put in the various lying un identified
(Oriental)
reinforcement bars at laid down area.
4. None.
(Construction Approval of latest Project Schedule is not available.
Manager)
Observa tion:05
Project Management
Awareness about the Project Execution Procedure and other
(Construction applicable procedures is poor among construction team. An
5. awareness cum tool box meeting to conducted to make None.
Manager)
concerned persons aware about Project Execution/Quality
Plan and applicable Procedures like Materi al Control,
Document Control Procedures.
Observa tion:06
Observa tion:07
7 QA/QC Inspector
Off Shore ITP for Civil activities to be revised to incorporate
Discipline handover process.
Observa tion:08
Observa tion:09
Observa tion:10
10. QA/QC Inspector None.
Log to track Site NCRs to be maintained.
Observa tion:11
Observa tion:12
12. Document Controller Data Back -up of standalone PCs to be taken. None.
A separate follow -up audit is not required, however Dopet Project Team to initiate actions on,
CAR/OBSERVATIONS identified during the audit , and nonconformance Implementation record duly filled -in
and forwarded to auditor for early close out .