Professional Documents
Culture Documents
II. Cut
This method has the advantage of giving undisturbed soil over the whole of
the site but has the disadvantage of the cost of removing the spoil from the
site.
Page15
III. Fill
A method not recommended because if the building is sited on the filled
area; either deep foundation would be needed or the risk of settlement at a
later stage would have to be accepted.
Surface Drains
These are used to drain pools of water that collect on a site due to rain.
Open ditches are made to drain the water before stripping of the site
begins.
Subsoil Drains
Subsoil drainage is normally carried out in the waterlogged or low-lying
sites to lower the water table.
Water table is the level at which water occurs naturally below the ground.
It varies with seasonal changes and the proximity (nearness) and the level
of water courses.
Because they are buried beneath the soil, they should be planned during the
landscaping or building stage in order to get the best possible results.
The pipe itself has a number of perforations through it to let the water
through to be drained away.
The geo-textile covering is important as it stops soil and other particles from
going through to the pipe and clogging it up so that it cannot serve its
purpose of draining the water away.
Another type of subsoil drainage that you can utilize is to bury some rocks
or pebbles.
These are free draining and will let water through quite readily
Page15
b) Grid
c) Moat
d) fan
Page15
Subsoil Drains
i. Trial holes
Hand augers or other tools like picks, jembes and mattock are used when
the hole is dug manually.
This is done to form a level ground base whose formation level is related to
the site datum.
Various methods are used to establish the formation level around the site.
Page15
Some of these methods involve the use of line level, spirit level, water level
and boning rods. On large sites a dumpy level may be used.
1) The Use of a Line Level
A peg is driven into the ground to the required formation level and a nail is
fixed on it from which a builder’s line with a line level is stretched to
another peg away from it.
The second peg is driven into the ground and adjusted until its top is level
with the first peg.
The process is repeated with other pegs within the site to establish the
formation level required.
One end of a straight edge is placed on top of the first peg while the other
end is rested on the second peg.
The bricklayer’s level is then placed on the straight edge and the second
peg is adjusted to the required formation level.
The process is repeated until all the required pegs are established
3) The Use of Water Level
The level of water at one end of the horse pipe is aligned with the top of a
peg driven into the ground to the required formation level.
A second peg is driven into the ground until the required formation level is
achieved.
Page15
4) The Use of Boning Rods
Two pegs are driven into the ground to the required formation level as far
apart as possible across the site.
By sighting over the top of the two boning rods, intermediate peg can be
established using the third boning rod.
The tripod is opened and the legs adjusted to provide a stable and firm
support to the instrument.
c) Focusing telescope.
This is done by placing a white paper in front of the telescope and focusing
the eye piece until the cross hair appear fine and black.
The staff is held vertically on the first peg that has been driven into the
ground to the required formation level.
The telescope is then directed to the staff, focused, as necessary and the
readings along the horizontal cross hair taken and recorded.
A second peg is driven into the ground at the required position with the
staff placed on it; the peg is adjusted until the same reading as before is
noted.
The same exercise is repeated until the required formation level of the site
Page15
is established.
Cutting and Filling to Formation Level
After establishing the formation level on site the next operation involves
cutting the high grounds and filling the lower portions.
A builder’s line or straight edge is used ti check the level of the ground
Page15
Any portion of the ground above or below the top of the pegs are cut or
filled respectively until all the ground is level.
If the excavated material is not enough to fill the lower portion, good
quality material should be imported from elsewhere to the site to complete
the fillings.
Damage may occur as result of weather action e.g. mixing with mud.
Cement should be used in the order it was supplied i.e. first arrival should
be used first.
This is because cement does not last for long time under site conditions
before it is damaged by moisture.
Page15
The stockpiles of sand should be free from organic impurities (leaves, mud
or clay)
v. Blocks
Blocks should be placed on a firmly prepared level bed free from sulphates.
vi. Wheelbarrows
Wheelbarrows should be cleaned and the wheels greased daily after use.
These should be washed to remove the mortar or concrete that may stick
on them.
They should be kept upside down in piles either in open or covered sheds.
Page15
For the leveling boards not to warp and twist, they should be kept on a flat
surface under a covered shed.
ix. Tiles
x. All small hand tools e.g. Jembes, pick axe, shovels, etc should be stored in a
locked store.
iii. Hand gloves to protect the hands when handling abrasives or chemicals.
iv. Open trenches should be provided with barriers to prevent people from
falling in them. They can also be covered.
v. A helmet should be worn to protect the head from falling bodies. Pegs and
lines
vi. Pegs should be clearly marked and lines should be removed as soon as they
have been used so as to guard against tripping by workmen.
vii. Excavations
Page15