You are on page 1of 7

Extending the use of risk

analysis in project management


S C Ward and C B Chapman

advantage much more pervasively throughout the


The paper is concerned with the expansion of the role of duration of most projects. This paper identifies the
risk analyst in project management. A broad definition scope for using risk analysis in project management,
of risk analysis is adopted that involves appropriate and raises a number of questions concerning its
identification, appreciation and management of project effective use, as part of a quest for a set of approaches
risks. The possible roles for risk, analysis in project to risk analysis that will achieve more widespread
management are examined. Initially, risk analysis can adoption.
assist in acceptlreject decisions and project design, and The body of this paper is in four parts. The first part
subsequently in the development of risk-management discusses basic roles for risk analysis given a
strategies, Where a project involves contracting parties, broad-based definition of risk analysis. The second part
risk analysis can help to determine the appropriate considers the impact on the previous discussion of
allocation of project risks. Reasons why risk analysis multiparty project situations. The third part discusses a
may not be as widely used as it should be are identified. number of reasons why risk analysis may not be as
A critical d~cuss~on of these arguments highlights widely used as it could be, despite its potential
additional aspects of the use of risk analysis in practice. contribution to project design and management.
Keywords: risk analysis, methodolog~~, project manage-
BASIC ROLES FOR RISK ANALYSIS
ment
The roles that risk analysis might be expected to take in
The development and execution of a project can be a project management clearly depend on what one means
difficult and uncertain process. The difficulties and by the term ‘risk analysis’. A wide range of formal
uncertainties depend on the size, complexity, novelty approaches in a project-management context have
and technical sophistication of the project, and they are been developed.
often compounded by the presence of constraints on Arguably, the simplest and the best known approach
time, resources and performance, and are frequently is PERT (the Programme Evaluation and Review
exacerbated by the conflicting objectives of the parties Technique), developed in the late 1950s for the US
involved. The need for efficient and effective project Navy’s Polaris Missile Project. The key features of this
management in the face of these difficulties and approach are the definition of a probability distribution
uncertainties has led to the development and successful for the duration of each activity defining a project, and
exploitation of a variety of management and the combination of these distributions to define a
management-science techniques in project manage- project duration-probability distribution, via a range of
ment. Risk analysis involves a number of such possible procedures, Monte Carlo simulation being the
techniques, but, despite its obvious relevance and current favourite.
considerable interest, it is not as widely exploited as it The most comprehensive approach that the authors
might be. Even in typical applications involving large are aware of was developed in the late 1970s by the
engineering works, risk analysis could be used to second author for BP International, for North Sea
projects. It is known as SCERT (the Synergistic
Department of Accounting and Management Science. University of Contingency Evaluation and Review Technique) , or
Southampton, Southampton SO9 5NH, UK
A shorter version of the paper was presented at the Internet Probabilistic Project Planning (PPP) as BP
International Expert Seminar on the State of the Art in Project Risk subsequently referred to it. The key features of this
Management in Atlanta, USA, 12-13 October 1989 approach are:

Vol 9 No 2 May 1991 0263-7863/91/02011747 @ 1991 Butterworth-Heinemann Ltd 117


Relatively few activities are used to describe a Development of project specification
project, to allow more detailed assessment within and base [target) plan
each activity (e.g. as few as 20 activities for a i
billion-pounds sterling project); description of what t
Initial risk analysis:
is involved in verbal or other appropriate terms is an as appropriate, identify alternative
explicit part of the model. technology choices, and project
All sources of risk associated with each activity are strategies, sources of risk and
responses, associated consequences
identified and described. and uncertainty, and then use
-
All feasible responses for risk, preemptive and changes to the base plan and con-
reactive, are identified and described. tingency plans to reduce risk and
uncertainty, increase efficiency,
Secondary risk associated with responses is and check the risk/expected-cost
identified, and appropriate responses considered as balance
appropriate. I
Responses are structured, to distinguish those I , / Abandon
Project assessment the
applicable to a range of risks and those specific to project
particular risks. t c t
A diagram summarizing the risk-response structure
within each activity and interactivity links is
produced for review purposes.
Probabilities are estimated for risks, and conditional
probabilities for associated responses, only when it is further risk analysis as appropriate
deemed useful, the analysis being explicitly
t
conditional on the nonoccurrence of other risks. r I
Project completion

The emphasis of this approach is on comprehensive risk


identification, understanding and management. BP Figure 1. Basic roles for risk anaiysis
have used PPP for more than 30 major projects
worldwide, but no one else has used the methodology
in its most comprehensive form to the authors’ this analysis, the project may be rejected because it is
knowledge. unacceptably risky. The emphasis in ‘initial risk
Ranging between these extremes are a variety of analysis’ is on an unbiassed accept/reject decision,
approaches that have been used successfully by the while the emphasis in ‘additional risk analysis’ is on
authors and others2. For example, a series of studies for strategic and tactical decisions about managing risk
Gulf Canada Resources Incorporated in the early 1980s assuming that the project will proceed.
used a simplified version of the SCERT approach Assuming that the project is not rejected, further risk
involving explicit identification of about half a dozen of analysis may lead to modifications to the project
the most important sources of risk, and a single specification and base (target) plan, and should lead to
appropriate response. contingency plans to manage project risks. The purpose
Complementary to these approaches are a variety of of this analysis is, in part, to reduce uncertainty.
approaches that address somewhat different issues or However, equally important is the pursuit of increases
priorities. For example, Ashley’s3 use of influence in efficiency. This involves identifying ways to reduce
diagrams to identify risk structures was adopted by BP expected cost for the same level of risk, or to improve
to complement scnnr analysis4. the risk/expected-cost balance. For example, is it worth
Several other writers have argued for risk-analysis a slight increase in expected cost significantly to reduce
methodologies that are consistent with the SCERT risk, or a slight decrease in expected cost for an
approach, although they may have wished to make associated increase in risk? In this manner, risk analysis
distinctions and argue for a different emphasi?‘. can play a major role in shaping a project during the
The term risk analysis in the rest of this paper is design phase and in the planning of the execution.
taken to mean a SCERT approach, appropriate Once the project is under way, project management
simplifications, or complementary approaches. In any should involve ongoing attempts to control uncertainty
given situation, the exact choice of the most and limit undesirable effects of realized risks. For
appropriate approach must remain debatable, but the example, procedures might be implemented to reduce
underlying philosophy will remain consistent with the the risk of late arrival of required materials, and
issues addressed formally in a SCERT approach”. minimize effects on project progress if delays in the
Assuming this broad definition of risk analysis, arrival of materials actually occur.
Figure 1 summarizes feasible roles of risk analysis in the
treatment of project risk.
RISK ANALYSIS IN MULTIPARTY PROJECTS
Following an initial specification of the project, an
initial risk anaiysis is carried out. This should involve, The project-shaping role for risk analysis can be
at an appropriate level of detail, the systematic particularly important in projects that involve more
identification of sources of risk, the specification of the than one organization or contracting party, as, for
uncertainty associated with each source of risk, the example, in the case of most engineering and
assessment of appropriate responses, and the construction projects. In such multiparty projects, risk
assessment of the consequences for the cost, time and analysis may be performed by any party, each with
quality aspects of project performance. As a result of their own perspective of the project and its attendant

118 Project Management


risks. Moreover, multiparty projects can involve risk efficiency, and to check the risk/expected-cost
substantial additiona uncertainty associated with the ba1an~e, as in the context of Figure 1. However, it has
temporary organizational arrangements necessary and an additional possible role if the risk analysis allows
with problems in the principal-agent relationships project risk to be divided into four identifiable sets of
present. Two basic problems can occur in a sources of risk: one controllable to some extent by the
principal-agent relationship: the agency problem and owner, one controllable to ‘some extent by the
the risk-sharing problem *. The agency problem arises contractor, one controllable to some extent by both,
when the goals of the principal and the agent conflict, and one controllable by neither. In such circumstances,
and it is difficult or expensive for the principal to verify analysis reported elsewhere suggests that the retention
what the agent is actually doing. The risk-sharing by the owner of risk that is controllable by the owner
problem arises when the principal and the agent have may be in the owner’s interest, even if the contractor is
different attitudes to risk, leading them to prefer more willing to take risk than the owner; sharing other
different courses of action. Any such differences in risks may ‘also be in the owner’s interest’. More
willingness to accept risk should influence the form of generally, risk analysis can be used as a basis for the
contract between a project owner and contractor, and efficient allocation of risk without the constraints of a
the associated allocation of project risk between the simple fixed-price or cost-plus contract.
parties. Together, these factors necessitate another One problem is that, even with the help of advisers,
look at the role of risk analysis. the owner may not be in a position to assess many of the
Figure 2 summarizes three separate, and somewhat risks associated with the project. Such risks may be
different, possible locations for risk analysis within a better assessed by potential contractors. Unfortunate-
framework analogous to that of Figure 1, but extended ly, in current competitive-tendering practice, it is not
to recognize the different parties involved and the usually possible to tap this source in such a way as to
bidding process. materially influence the basic form of the contract. Yet
the form of the contract will motivate the contracting
Analysis by the project owner parties to address the management of risk to a greater
or lesser extent.
Risk analysis by the project owner should be A further difficulty here is that perceptions of risk
undertaken to reduce uncertainty and risk, to pursue are dependent on the assessment of subsequent
risk-avoidance and risk-reduction actions likely to be
taken by the contractor and other parties. Such actions
Development of project specification
depend in turn on the form of contract agreed and the
consequent motivations and behaviour of the contract
parties. Rational allocation of risk depends on the
+EzzEz&~,;E”don,
systematic evaluation of risks under different project
scenarios characterized by different contractual
arrangements. This is a potentially time-consuming and
1
I I 7
[project demanding exercise.
Development of tender documentation
Analysis by the bidding contractors
Development of project Contractors B, C, D etc.,
Risk analysis by each bidding contractor could be based
specification and base plan as for Contractor A on the project owner’s risk analysis if it were provided
by Contractor A in the tender documentation. The greater the detail
+ provided by the owner in relation to risks that are to
Risk analysis by Contractor A be borne in whole or in part by the contractor, the less
the contractor has to price for risk related to the
contractor’s uncertainty about what the project
involves.
Discussing construction projects, Barber” has
Contractor selection by owner
suggested that detailed itemization does not correspond
to the way in which construction contractors assess the
Development of project specification risks and costs involved in contract proposals. He
~~
argues that experienced contractors are able to
evaluate most project risks with a sufficient degree of
certainty using a broad approach, rather as insurers are
Risk analysis by the contractor
able to evaluate insurable risks. In the same way as
insurers, however, contractors cannot evaluate risk if
information is withheld or they are not given an
base plan and contingency plans opportunity to price it; nor can they break down the
risk into minute detail. Barber suggests that, if
contractors are expected to act as quasiinsurers,
perhaps contracts should be treated as being subject to
the doctrine of uberrima fides, at least as regards the
Figure 2. Possible locations for risk analysis in a supply of information~a. Although Barber was
ma~ti~arty project primarily concerned with construction projects and

Vol 9 No 2 May 1991 119


contractors, much of his argument appIies equaffy to La& of ~~~~~~~~~~The project owner may be
other types of projects. unf~ili~ with risk analysis and unaware of its
A likely obstacle to the transfer of ~~~u~at~on from pot~~t~a~ ~un~bution.
project owner to potentiaf contractor is the owner% Lack of expert&.~ The project owner may lack the
perceived vulnerability to legal action in respect of resources and expertise to carry out risk analysis.
a;lleged errors or misrepresentations in information. Risk analysis is unnecessary: The project owner
This may particularly hamper the transfer of stochastic considers that a formal detailed, quantitative
information, for example about ground conditions in a analysis of project risks is not needed because risks
construction project, However, it is not at all clear how are well understood or not large enough. A related
the veracity of stochastic information could be concern is to avoid ‘paralysis by analysis’.
challenged in the courts, and so this concern may be a Luck of time: The project owner may take the view
false one. that there is not enough time to carry out risk
The role of the bidding contractors’ risk am&is at analysis within the specified project deadfines.
this stage is quite different to that of the owner’s Each ~~~ci~~~* or impo~~~~fe-to-qut~~~ FL&X Risk
~~~tr~etor wants a bid that gives an approp~ate analysis may seem to require risks to be ~u~t~~ed
balance between the risk of not getting the contract and that may be perceived as too difficult to quantify.
the risk associated with profits and Iosses if the contract ~j~~r~~ ofrisk analysis: The project owner may take
is obtained. the view that the rest risks are those that are
unantici ated, and these wilf not be included in risk
analysis F:.
Analysis by the adopted contractor Risks will be borne by other pawties: The project
Risk analysis by the adopted contractor should be owner may take the view that risk,s do not need to be
undertaken to reduce uncertainty and risk associated evaluated because they will be borne by someone
with the contractor’s profits, to pursue efficency, and else I
to check the risk/expected-profit balance. If the owner
has aheady undertaken such an analysis, and provided In the authors’ view, virtually all of these arguments
it to al bidding ~ontra~tors~ the adopted contractor can indicate a lack of understanding of the potential
use it as a starting point. If the contractor has to start ~u~~b~tio~ of risk analysis to project m~agement_
from scratch, there are several drawbacks: However, while some reasons far not performing risk
analysis might amount to Iame excuses, there can be
The scope for modifications to the project good reasons for limiting the complexity of analysis if it
specification and base plan will be less than would be is carried out at all. For example, managers might wish
the case during an owner’s risk analysis. This implies to limit the complexity or level of detail in risk analyses
a less efficient project specification and base plan, for reasons of managerial mot.ivation, resource
The level of detail adopted by the contractor will be constraints, avoidance of detailed planning, and the
determined by the benefit to the cantractor of more need to persuade others about recommendations’2.
or less detail. Risks that involve costs that can be Additionally, it may be argued that project-
recovered from the owner, and contingency plans ~a~~g~rn~nt practices to control uncertainty and risk
associated with the contractor’s possible bankrupt~y~ do not depend on previous detailed risk analysis and
will not be relevant. This implies less efficient risk planning. Indeed, control of ~~~e~~nty and
project specification, base plans and contingency damage limitation are established aspects of the
plans. coordination role of project rn~na~~rne~t~ even if no
formal risk analysis is undertaken. Recognition of this
may be that these two effects discourage contractors has led to good project-management practices that
from undertaking risk analysis in practice. They include generic strategies for minimizing risks and
certainly strengthen the case for an owner’s risk reducing related uncertainty. To the extent that such
analysis prior to the development of tender practices exist and are effective, detailed risk analysis
documentation. may not be cost-effective. By way of illustration, Figure
3 shows how a number of generic project-management
practices work together to minimize uncertainty about
cost, time and quality in construction projects. Any of
The previous discussion has suggested that risk ;inalysis these strategies might be enhanced by risk analysis, but
can make an important ~o~tr~b~tio~ to efficient and this may only be cost-effective to the extent that
effective project management. In practice, the extent s~~ifi~all~f high tevels of risk are present, requiring
of any risk analysis should reflect the need for a novel responses or special care in respect of usuaI
cost-effective approach - some projects wiII warrant good-management practices.
more analysis than others, However, given the flexibIe The third point above, that risk analysisisunnecessary,
definition of risk analysis adopted, it would seem expresses an all-too-common perception of risk analysis
reasonable to expect some level of formal risk analysis as an ‘all or nothing’ technique _ either a detailed,
for any project involving significant uncertainty. All quantitative analysis must be carried out, or none at all.
too frequently this is not the case. Why? Is it simply a This is an unfortunate and mistaken view. There is a
lack of awareness of the roles for risk analysis discussed need for cost-effective risk analysis, and a wide range of
above, or are there other reasons’? approaches is available to allow a cost-effective choice
Failure to use risk analysis can usually be attributed of approach.
to one or more of rhe following arguments: The extent to which sources of uncertainty and

120 Project Management


minimize Minimize Minimize
uncertainty uncertainty uncertainty
about time about cost about quality

l
I/---
Procurement Early involvement
and management of management
skills contractor

Figure 3. Pathways to minimizing project uncertainty in construction projects

contingency plans should be considered at a detailed project specification in an iterative process. This
level will vary from project to project, as a function of implies development of the risk analysis in a learning
the size of the project, the importance of uncertainty, mode, starting with an outline project specification and
and improvements in risk efficiency associated with associated risk analysis, and moving to more detailed
such planning’. For example, an oil major about to specification and risk analysis as considered
release funds and contract for a major offshore appropriate. Thus risk identification and analysis can
development may find it worth identifying some 30 or indicate a need for redesign, more detailed design,
40 sources of uncertainty for each of 50 activities further investigation of aspects of the project, or
encompassing the whole project, and considering three different methods of proceeding. Even in the early
or four responses for each source of uncertainty, in a stages, incorporating detail may be advantageous. For
highly structured, formal, probabilistic manner. example, estimating a distribution for available laying
Alternatively, a shopping-development sponsor may days in an offshore pipe-laying operation may be
find it worthwhile to identify only half a dozen major difficult and involve unreliable guesswork, whereas
risks for a dozen key activities, and consider a single building up the distribution from underlying causal
response for each source of uncertainty in an informal factors may prove much more justifiable and reliable.
nonprobabilistic manner. Including more detail in the analysis can also lead to a
To some degree, the level of detail incorporated in greater understanding and appreciation of factors likely
any risk analysis depends on the purpose of the to affect project performance, and can be more helpful
analysis. In the early stages of project design, the in the identification of suitable risk-avoiding and
emphasis may be on project evaluation in economic uncertainty-reducing strategies*.
terms, involving the aggregation of project risks to The fourth point above, that there is no time to carry
determine the total impact on the project’. More out risk analysis, is evidence of a failure to appreciate
importantly for present purposes, risk analysis is these issues. Risk analysis should be an integral part of
helpful in developing the project design and project the design stage of any project. Setting project
plans that serve to reduce uncertainty and avoid risks deadlines in the absence of any assessment of the risks
altogether. This suggests more detailed analysis than involved in that schedule makes no sense.
that required for earlier evaluation. The fifth point above, that it is difficult or impossible
As indicated previously in Figure 1, risk analysis to quantify risks, has some credibility, especially if one
should proceed alongside the development of the thinks of factors such as ground conditions, effects of

Vol 9 No 2 May 1991 121


weather f delivery dates, quality variations in from a failure to appreciate the importance of
construction projects7 or competitor reactions in a new considering project risk in relation to the conniving
product-launch project, Such risks are indeed difficult objectives of parties at an early stage.
to quantify, but, to the extent that their impact on the For example, insistence on a simple fixed-price
project may be significant, they need to be considered. contract with all risk borne by the contractor, and
Limiting the extent of any risk analysis because there acceptance of the lowest bid, brings its own risks. Even
is insufficient information reminds one of organizations with prior or postbidding screening out of any
who perform little in the way of strategic planning contractors not deemed capable, reliable and sound,
because the future is too uncertain. An obvious the successful bidder will have to be that member of the
response is that, where project risks are high, it may be viable set of contractors who scores best overall in the
highly desirable to put resources into obtaining following categories:
information and developing appropriate information
systems, much as oil companies have done in the most optimistic in relation to cost uncertainties: this
context of onshore-drilling operations. may reflect expertise, but it may reflect a willingness
The problem is really one of making efforts to to depart from implicit and explicit specification of
identify explicitly all effects of each source of risk, and the project, or ignorance of what is required,
to describe appropriate responses and secondary risks most optimistic in relation to claims for additional
where appropriate. While it is clearly useful, there is no revenue,
absolute necessity to uantify all risks. For example, least concerned with considerations such as impact
Chapman and Cooper 9’ describe an application of risk on reputation or chance of bankruptcy,
analysis to the formulation of a bid for a turnkey least informed about the likely behaviour of other
construction project. Representation scenarios were contractors,
used, but the likelihood of their occurrence was not most desperate for work.
assessed in precise numerical form. The concern was
This suggests that selecting the lowest fixed-price bid is
that of avoiding or neutralizing all significant sources of
an approach that should be used with care in a limited
risk via contractual arrangements, home gove~ment
set of circumstances. It is particularly risky if any of the
guarantees, sub~ontra~ors and insurance companies.
following apply:
Risk analysis took a verbal form in terms of structured
lists of risks and responses, with backup discussion and * Uncertainty is important. It may not be clear to
documentation. Most managers with experience of risk potential contractors what is required, and what may
analysis would probably argue that any systematic be required.
exercise to identify and rate risks, secondary risks and o Performance specifications are not comprehensive,
likely responses is a valuable exercise in itself, whether clear, and legally enforceable.
quantification is involved or not. e The expertise, reputation and financial security of
It is precisely this kind of exercise that should deal the contractor are not beyond question.
with the sixth point above, that the real risks are those
that are unanticipated and are not therefore included in The situation is summed up by Barnes’:
any analysis - the wrong risks are anaiysed”.This is The problem is that when conditions of contract piacing large total
clearly a possibility. However, the early stages of risk risk upon the contractor are used and the work is awarded by
analysis should be devoted to the generation of a competitive tender, the ~ontra~torwho accidentally or desperately
comprehensive list of project risks, including force underestimated the risks is most likely to get the work. When the
risks materialise with full force he must then either struggle to
mujeure. A significant stage in any risk analysis is the
extract compensation from the client or suffer the loss. This
conscious decision about which risks to include in stimulates the growth of the claims problem.
further analysis, and which should be acknowledged The remedy seems to be to take factors other than lowest price
but should not influence subsequent planning. into account when appointing contractors. ‘In particular, a
Finally, the seventh point above, that risks will be reputation gained for finishing fast and on time without aggressive
pursuit of extra payment for the unexpected should be given very
borne by other parties, and so there is no need for risk great weight and should be seen to do so.
analysis, is a real possibility when projects require the
employment of other parties, consultants and The alternative remedy suggested earlier, that of
contractors. Certainly, much of the current difficuity carrying out an analysis of project risks prior to
with risk allocation and associated claims and contract formulation, to determine an appropriate
arbitration arises because of contractual parties’ allocation of risks, and to provide all bidders with this
preoccupation with transferring risk to other parties. information, is unusual in current practice. However, it
As long as one party believes that project risks can be would seem worthy of serious consideration.
transferred or offloaded onto someone else, any
assessment of risks is likely to be half-hearted, and CONCLUSIONS
inadequate attention may be given to risk-avoidance or
-reduction measures. For example, some project owners This paper has considered the various ways in which
prefer to refer to risks in a general way, or as obliquely risk analysis might usefully be employed in the design
as possible, presumably in the hope of finding a and management of projects. The value of risk analysis
contractor who will not allow for them fully in his as a means for understanding and managing project risk
price I4 . This situation tends to occur with a project have been highlighted. An important focus has been
owner who insists on fixed-price contracts. As the management of project risks where projects involve
discussed below, this form of contract may not be in the a number of parties, and agency and risk-sharing
owner’s best interests. Failure to recognize this follows problems can arise. The authors believe that there is

122 Project Management


considerable scope to make more use of risk analysis in and cost planning’ ht. J. Project Manage. Vo13 No
the design and management of projects. However, 1 (1985)
substantial increases in the use of risk analysis may 5 Barnes, M ‘Effective project organisation’ Building
require more detailed answers to the following Tech. & Manage. (Dee 1984) pp 21-23
questions: 6 Perry, J G and Hayes, R W ‘Risk management for
project managers’ Building Tech. & Manage.
Why is risk analysis not used as extensively as it (Aug/Sep 1986) pp 8-11
might be? 7 Hertz, D B and Thomas, H Risk Analysis and its
How far is it possible to identify or characterize Applications John Wiley (1983)
situations where risk analysis is cost-effective? 8 Eisenhardt, K M ‘Agency theory: an assessment
What level of detail is appropriate for the analysis of and review’ Acad. Manage. Rev. Vol 14 No 1
different risk situations? (1989) pp 57-74
What are the implications of risk analysis for the 9 Chapman, C B, Ward, S C and Curtis, B ‘Risk
design of organizations’ information systems? theory for contracting’ in Uff, J and Capper, P
How do conflicting interests affect risk analysis, and (Eds.) Construction Contract Policy: improved
what is the relationship between risk analysis and Procedures and Practice Centre of Construction
alternative forms of contract? Law and Management, King’s College, London,
UK (1989)
is hoped that this paper will act as a stimulus to 10 Barber, J N ‘Risks in the method of construction’ in
Uff, J and Capper, P (Eds.) Construction Contract
further discussion and research on these issues.
Policy: Improved Procedures and Practice Centre of
Construction Law and Management, King’s
College, London, UK (1989)
REFERENCES
11 Hall, W K ‘Why risk analysis isn’t working’ Long
Chapman, C B ‘Large engineering project risk Range Plan. Vol 8 No 6 (1975) pp 25-29
analysis’ IEEE Trans. Eng. Munage. Vol EM-76 12 Ward, S C ‘Arguments for constructively simple
(1979), pp 78-86 models’ J. Operat. Rex Sot. Vol40 No 2 (1989) pp
Cooper, D F and Chapman, C B Risk Analysts for 141-153
Large Projects John Wiley (1987) 13 Chapman, C B and Cooper, D F ‘Contract risk
Ashley, D B ‘Risk distribution and influence analysis for a turnkey project bid: a case study’
diagramming’ Proc. Construction Risk Identifica- Geneva Papers on Risk and Insurance No 10 (1985)
tion and Prevention Techniques Sem. Hamburg, pp 293-305
Germany (1982) 14 Abrahamson, M ‘Contractual risks in tunnelling:
Chapman, C B, Phillips, E D, Cooper, D F and how they should be shared’ Tunnels & Tunnelling
Lightfoot, L ‘Selecting an approach to project time (Nov 1973) pp 587-598

Stephen Ward is a senior lecturer in Chris Chapman is Professor of


Business Economics and Academic Managemeilt Science and Head of
Deputy IXrector of the Manage- the department of ‘4ccol~nting and
ment School at the ~n~vers~t?~of Management Science at the Univer-
.~out~ta~npton. UK. Before joining sity of Southampton. For about IS
the University in I%%, he worked in year.s his consulting and research
operational research with the have centred on the management of
National Westminster Bank, UK. risk. Mast of his consulting has
and in merchandizing with Boots. been concerned with large energy
UK. His research interests include projects in the UK, and USA and
project and contract risk manage- Canada, but other concerns have
ment, strategic-investment ap- included computer hardware and
praisal and problem-solving software systems, financial asset
methodology. He recently com- and commodity broking portfolio
pleted a UK Science and Engineer- management. He holds a BASc in
ing Research Council research contract on the roles, risks and Industrial Engineering (Toronto),
res~~~~n~sibilitiesof management contractors in the construction an MSc in Operational Research
industry. He holds a BSc in Mathematics and Physics ~~ottingharn ~Birming~lam) and a PhD in
lJniversit.v, UKj and an MSc in ~anugement Science ~~mperia~ Economics and Econometrics
Collqe. London ~in~versit~t,UK), ~So~~thampton).

Vol 9 No 2 May 1991 123

You might also like