Professional Documents
Culture Documents
Abstract: Turnarounds are unique maintenance projects with a high probability of scope change, time delay,
and cost overrun. Negative effects stemming from such uncertainties can be mitigated by following best practices
for turnaround planning and management. There has been no comprehensive review of best practices for
turnaround planning and management in past research. Our review presents guidelines and recommendations
based on existing best practices to support managers and engineers involved in turnarounds. Because they are
based on proven best practices, implementation of the recommendations should improve power plant turnaround
planning and management processes, leading to better project performance. Our paper compares planning and
management practices followed in a real turnaround project case to the best practices in order to find gaps and
commonalities; the systematic methodology we propose can be implemented by other companies involved in
turnaround projects in order to improve their planning and management processes.
Keywords: Best practices, turnaround projects, planning, management, process improvement
DOI: 10.7492/IJAEC.2014.014
168
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
pact schedule of activities during turnaround execu- cess to industry best practices for turnaround planning
tion such that the impact of any delay is magnified and management we obtained through our comprehen-
as the schedule may have higher critical activities. In sive literature review in order to identify any gaps in
order to prevent project delays and thus decrease the company’s existing practices. By identifying these
project cost, it is in the best interest of organizations gaps, we are able to highlight areas in which the com-
undertaking turnarounds to follow best practices of pany’s practices should be revised in future. Our paper
turnaround planning and management. also provides recommendations for the improvement of
Power plant turnarounds have been identified as the some company practices for future turnarounds.
most expensive and time-consuming of maintenance The contribution of this paper is in providing a com-
projects (McLay 2012). Trends in electrical energy prehensive review of best practices for power plant
production and demand indicate that the importance turnaround planning and management and a systemat-
of following best practices in turnaround planning and ic method of comparing a company’s own documented
management is likely to increase in future. A National practices against previously researched industry best
Energy Board of Canada (NEB) report (National En- practices so as to improve the planning and execu-
ergy Board of Canada 2013) showed that in 2012 elec- tion of future turnaround projects. The methodolo-
tricity generation capacity in Canada reached 134GW gy can be implemented by other companies involved
and is projected to reach 164 GW by 2035. The NEB in turnaround projects in order to improve their own
report further indicated that an average 1% increase in documented planning and management processes. Fur-
total electricity generation capacity in Canada is need- thermore, future research can be done to compare a
ed to meet growing demand, replace aging facilities, company’s documented practices to its actual practices
and to fulfill economic and environmental needs (Na- on turnaround projects to identify gaps between the
tional Energy Board of Canada 2013). In fact, rapid theoretical and applied; in this way, researchers can
growth in global energy demand requires power plants evaluate the consistency of the application of a compa-
worldwide to consistently run at near capacity. To ny’s documented practices across turnaround projects.
keep up with these increasing demands for electrical
energy, execution of turnaround projects will be sub-
ject to even tighter time constraints in future, making 2 RESEARCH METHODOLOGY
it all the more imperative that organizations imple-
ment whatever improvements they can and follow best In construction, many industry standard best practices
practices for turnaround planning and management have been developed and are widely applied. These in-
that have been shown to improve turnaround project clude best practices for project risk assessment, quality
performance. However, despite the considerable risk management, and front-end planning developed by the
and growing constraints associated with turnaround Construction Industry Institute (2014) (CII) and best
projects, to date, there has been no comprehensive practices for advanced work packaging and workface
review of best practices for turnaround planning and planning developed by the Construction Owners Asso-
management to which industry practitioners may refer. ciation of Alberta (2014). However, there is a lack of
This paper presents a comprehensive review of past industry standard best practices developed specifically
research regarding the best practices to plan, manage, for turnaround planning and management even though
and execute power plant turnaround projects. Each applicable best practices exist in published research lit-
best practice we recommend has been shown to im- erature. Industry practitioners were interested in im-
prove performance in the previous research studies. plementing best practices to better their organization’s
Because delays and expanding work scopes are ma- performance of turnaround projects would benefit from
jor contributors to turnaround project cost overruns, a comprehensive review summarizing available litera-
implementation of these performance-improving best ture on best practices relevant to turnaround planning
practices will help lower turnaround costs. To help and management; This paper provides such a review.
industry practitioners discern the extent to which the This paper includes two parts. In the first part,
recommended best practices need or do not need to be we perform a comprehensive review of best practices
implemented in their organizations, we further present for turnaround planning and management. The litera-
a methodology for analysis of existing power plant ture review provides a collection of best practices from
turnaround planning and management processes. Us- which all companies involved in turnaround projects
ing a case study, we illustrate the methodology by can draw. While managers and engineers involved
evaluating the level of implementation of best practices in turnaround planning and management will benefit
for turnaround planning and management necessary in from the recommendations provided by the literature
a company based in Alberta, Canada. The compa- review, it is also important to have a method capable
ny has several power plants in North America, and of finding gaps in existing company practices for the
has a well-documented project management process purpose of process improvement. In the second part
used for turnarounds. In the case study, we compare of this paper, we therefore provide a generic, system-
the company’s documented project management pro- atic methodology that will enable any company that
169
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
engages in turnaround projects to compare its es are redundant based on the industry best practices.
existing, documented, company-specific practices with The timing of phases is compared so that a company
the published industry best practices we have re- may observe if it has planned some phases in a relaxed
viewed. We demonstrate application of the sys- schedule with high buffers or if it has forced its phases
tematic methodology using a case study. The into a compact and critical schedule.
challenge here is that best practices describe both The second step compares the output of each com-
general and detailed concepts for the planning and pany phase to the related phases recommended by in-
management of turnaround projects that have been dustry best practices. In our case study, both the case
compiled from various sources of published litera- company practices and the best practices recommend-
ture, whereas a company’s own internal practices ed by the literature we reviewed include details about
describe specific concepts particularly suited to com- tasks, task timings, and outputs of each phase. How-
pany projects. Fayek and Peng (2013) faced a ever, the industry best practices tend to focus more on
similar challenge when adapting industry standard pro- the outputs. Therefore, in this step, for each phase all
cedures related to workface planning to organization- the required outputs are compared between the compa-
specific procedures. Their study focused on three ny’s own practices and the best practices. In addition
different categories of procedures and practices: indus- to the outputs of each phase, task timings are also com-
try standard procedures and practices, organization- pared. Upon completing this step, the gaps between a
specific procedures and practices, and actual project company’s practices and the published industry best
practices (Fayek and Peng 2013). In order to overcome practices will be evident, giving companies following
the difficulty of comparing two sets of documents which our methodology a starting point for improving their
were written from two different perspectives, this pa- internal practices. We also demonstrate how to cal-
per proposes a methodology consisting of three steps: culate the percent extent to which company practices
phase-to-phase comparison, comparison of each phase diverge from best practices.
output, and missing best practices concepts. The steps The third step deals with any best practices concepts
of the proposed systematic methodology for comparing that are altogether missing from the company’s exist-
a company’s own best practices against published best ing documented practices. As a result of the previous
practices are illustrated in Figure 1. two steps, by this point all the company’s document-
Following this schematic, the first step is phase-to- ed practices have been compared to the best practices
phase comparison. This step compares consideration recommended by our literature review; however, there
and timing of phases between the two sets of practices is always the possibility that one or more best prac-
(internal/company-specific and industry/published). tice(s) are entirely excluded from the company prac-
Without going into the detail of each phase’s activity tices. Therefore, the third step re-examines the best
and outputs, the first step only provides an overview practices we compiled and identifies those concepts and
of how the case company’s practices are similar to or recommendations not covered by the company prac-
different from industry best practices. After complet- tices.
ing this step, a company following our comparison The proposed systematic methodology for compar-
methodology will have a general idea of which recom- ison, in addition to the performed comprehensive re-
mended phases were not included in their own compa- view, will help all companies involved in turnaround
ny’s practices as well as which company practices phas- projects identify areas of weakness in their planning
Figure 1. A systematic method for comparing company practices to published best practices
170
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
and management processes so that they can then ad- conceptual development, work development, detailed
dress these issues to improve their practices. planning, pre-turnaround work, turnaround execution,
and post-turnaround stages.
171
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
prior to project execution and hence cannot be planned turnaround if the right people occupy leadership posi-
for in advance. Major sources of emergent scope in- tions, but in other situations, an established knowledge
clude unanticipated scope, scope that is anticipat- transfer process crucially helps overcome disparate in-
ed but under-estimated, and scope that is generated dividual points of view (Cormier and Gillard 2009).
while carrying out the tasks. Turnaround management Reducing risks during the scoping phase of a pow-
should plan to handle any emergent job items. Recom- er plant turnaround will improve the cost effectiveness
mendations for managing the emergent scope include of the installation (maintenance work). This risk re-
identifying an early scope freezing date, establishing an duction process combines improvements in the cate-
additional work procedure, and developing a manage- gories of organization, process, technique, and technol-
ment process for scope changes. ogy (Lazeroms 2011). These improvements will help
reduce the level of risk related to installation during the
Risk Mitigation in Turnarounds scoping phase of a turnaround. Lazeroms (2011) stated
that a significant portion of the total lifecycle costs of
Risk mitigation is a crucial consideration for a power plant are accrued during the operational phase
turnaround projects. Accordingly, practitioners should of an asset. Within the operational phase of a power
plan to minimize the amount of required work. The de- plant, the majority of costs occur during a turnaround,
sign review process and constructability reviews should and the actual cost of performed turnarounds usually
both consider the risks posed by construction activities exceeds the budget. Lazeroms (2011) provides insight
during the turnaround. The potential risks of com- into installation risks, the effects they have on opera-
pleting excessive work during the turnaround increase tional decision-making during turnaround scoping, and
project complexity and may result in increased costs, methods and techniques for reducing these risks so as
schedule delays, or in the worst case scenario, failure of to improve cost effectiveness.
the project to complete objectives. Planning and coor-
dinating efforts during the pre-construction phases of
3.2 Turnaround Management Teams
the turnaround can help mitigate potential problems
(Whittington and Gibson 2009). The CII presented It has been recognized that there is a need for mul-
some critical management issues that were identified tifunctional or interdisciplinary teams to handle the
as requiring additional care during turnaround plan- diverse activities of the turnaround planning process,
ning (Construction Industry Institute 2008). and to ensure that the disparate requirements of all
Cormier and Gillard (2009) stated that the imple- those who contribute to the turnaround are reflected
mentation of a rigorous, structured knowledge trans- in the final plan (Oliver 2002). Oliver (2002) recom-
fer system can improve the success of any turnaround. mends the following teams to manage the turnaround
Additionally, conveying appropriate process- and unit- projects: the core team, steering committee team, and
specific information, specifications, and procedures to reviews or audits team. Firstly, a core team should
the multitude of parties involved in a turnaround can be established to handle the planning process. Assem-
also reduce risk. Accordingly, Cormier and Gillard rec- bling this team is often considered as an end in itself,
ommend communicating all of the specific tasks, sched- but really this is just the first step. Potential members
ules, priorities, contingencies, and perceived risks that should be assessed for their ability to work as part of a
should or might occur to each group of workers. The team and, where needed, appropriate training should
documentation, structure, and delivery of this infor- be given. Not everyone is suited to being a team mem-
mation should be tailored to the destination audience ber in this context; this should not imply that such in-
while considering that any given group of workers may dividuals are ineffective workers, but rather that their
range widely in terms of craft, experience, and level individual talents are best utilized outside a team en-
of responsibility. To ensure these needs are met, the vironment (Duffuaa and Ben-Daya 2004; Duffuaa and
communication process should be verified. Implement- Ben-Daya 2009). Secondly, the turnaround steering
ing a rigorous, structured knowledge transfer system committee team should be established to provide di-
ensures that everyone involved in the turnaround fol- rection and guidance to the core team and ensure that
lows a common set of best practices that can be refined the turnaround meets the needs of the business. More
over the years rather than relying on the combination of importantly, the steering committee ensures that the
backgrounds, expertise, and biases of key players, who scope aligns with the budget for the turnaround. The
differ from one turnaround to the next. For instance, steering committee must regularly communicate with
planning styles vary depending on the planner, and for- the core team to ensure the latter is kept informed of
mal communication of the plan to all parties involved the work scope and current estimated costs of execu-
tends to relax as the event draws closer, leaving room tion. Thirdly, in order to ensure that the planning
for diverse interpretations. Furthermore, training for and execution process is receiving appropriate atten-
turnaround projects tends to be general in nature, ca- tion and that progress is steady, a series of reviews or
sual in format, and dependent on the experience of the audits should be carried out at intervals throughout the
trainer. In other words, it is possible to have a good process. The individuals conducting the audits should
172
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
be appointed by the steering committee and should be “probability of meeting the project duration” (Megow
knowledgeable in turnaround matters but should not et al. 2011).
have direct responsibilities in respect to the turnaround Determining a suitable project duration depends on
under review. It is desirable to include someone from several aspects that need to be balanced against each
outside the plant or organization for some, if not all, other. These include the total resource cost for hiring
of the audits (Oliver 2002). resource units, the total production loss caused by the
Other authors recommended creating an organiza- shutdown during the turnaround period, and a “risk
tional unit within the plant operations division called cost” due to unexpected repairs and delays that are in-
the Plant Turnaround Services (PTS) department that herent in maintenance jobs and tend to become more
is solely dedicated to managing the planning, prepa- influential the shorter and more ambitious the project
ration, and execution of the plant turnaround main- duration becomes. Elshout and Garcia (2009) stated
tenance. With this organizational arrangement, all that shutdown plans have to be well organized so that
turnaround activities within the corporation are cen- all the work dovetails within the allotted shutdown pe-
tralized and administered by PTS (Ghazali and Halib riod. They suggest that when developing the schedule,
2011). PTS is one of the functional departments in the to maintain flexibility, the activities should be broken
plant operations division and is responsible for: (1) down into a large number of steps, each of which has an
strategizing and developing turnaround maintenance early start date and last-possible completion date. The
operation plans for the company’s plant turnaround objective is to pre-install and complete as much of the
maintenance activities; (2) managing and leading the construction as possible in advance of the shutdown.
preparation and implementation of the turnaround; (3) Because shutdown time is very limited, only tasks that
managing the material and service requirements of the absolutely must be done during the unit shutdown are
turnaround; and (4) developing, implementing, and re- undertaken at this time. This approach also allows for
viewing the turnaround’s health, safety, and environ- fewer people onsite during the critical period of shut-
mental protection (HSE) and quality control/assurance down activities. Elshout and Garcia (2009) suggest
(QC/QA) plans and performance. Furthermore, Ghaz- that before developing a high level of schedule detail,
ali and Halib (2011) suggest an organizational struc- practitioners may use a simpler bar chart-type schedule
ture for a turnaround project’s execution team. The to chart the timings for ordering long-lead-time equip-
organizational structure consists of two main elements, ment such as thick-walled reactors, alloy equipment,
namely, the resource structure at the bottom and the and high-pressure vessels. Working back from the de-
administrative structure at the top. sired start of work in the field, the project manager
can determine the latest time at which an order can be
3.3 Turnaround Scheduling placed. Ordering requires some lead time during which
necessary pre-purchasing activities can be completed.
Having a good strategy for turnaround scheduling will Sometimes, equipment purchases must be made before
help practitioners develop a feasible schedule. A fea- the final design is completed.
sible schedule appropriately allocates resource units to
jobs and provides temporally feasible job plans that re-
3.4 Turnaround Management
spect given precedence constraints and working shifts.
It is in an organization’s best interest to minimize both There are some general practices in managing
the project’s duration and its cost; however, there is a turnaround which should be followed to better over-
trade-off: fast project executions increase costs, where- come turnaround challenges. Duffy and Tregoe (2012)
as less expensive project executions take a long time. define the top challenges and critical areas in man-
A balance needs to be struck. aging turnaround projects. Ensuring workforce safety
Megow et al. (2011) developed and presented a two- of both employees and contractors is the number one
phase approach for scheduling turnarounds. The first priority for the turnaround management team. Oth-
phase supports the project manager in finding a suit- er challenges and critical areas include the develop-
able project duration that respects his or her risk pref- ment, deployment, and communication of an effective
erences, and the second phase optimizes the use of turnaround process; managing project scope creep dur-
resources for the chosen duration. In the first phase, ing the turnaround execution; the capture, analysis,
the strategic planning phase, the project manager must and availability of relevant information and metrics;
determine the turnaround project’s start and finish the existence of business processes which do not sup-
dates (i.e., the makespan) as well as quantify the avail- port the needs of the turnaround; cost management
able workers and resources. In the second phase, the and control in executing complex turnarounds; the
detailed planning phase, practitioners allocate and lev- coordination and management of complex resources;
el resources for the heuristically determined deadline the transformation of an organization from reactive to
by completing a risk analysis of the computed, de- proactive; and managing the expectations of diverse
tailed schedule. This risk analysis should provide upper stakeholders. In order to overcome turnaround man-
bounds for the risk measures “expected tardiness” and aging challenges the following areas should be consid-
173
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
ered during the planning, management, and execution the turnaround scope of work. Al-Qadda (2009) has
of turnaround projects: development, deployment, and presented the following recommendation for how to do
communication of an effective turnaround process; cap- so:
ture, analysis, and availability of relevant information
and metrics; overcoming business processes which do i The original scope must be clearly and properly
not support the needs of the turnaround; coordination defined;
ii Plant equipment failures and defects that arise be-
and management of complex resources; overcoming a
tween the scope sign off and the execution time
reactive culture by moving toward anticipating and re-
must be recorded immediately for immediate and
solving issues before they impact; and managing the
necessary action;
expectations of diverse stakeholders (Duffy and Tregoe
iii Historical information, including that related to
2012).
each completed turnaround, must be documented
Synchronizing turnaround project execution can im- so that it can be referenced in future;
prove turnaround performance impressively. (Gup- iv A suitable strategy for accepting scope changes
ta 2011) suggested the use of critical chain project must be adopted so that the number of scope
management (CCPM) to coordinate priorities during changes can be minimized;
turnaround execution because it enables managers to v Action must be taken to appropriately address
synchronize work items despite uncertainties related turnaround scope objectives with the intent of
to engineering, planning, and execution. To synchro- reducing scope changes on future turnaround
nize project execution, CCPM prescribes three rules: projects; and
pipelining, buffering, and buffer management. The vi A proper database system to store historical data
first rule is pipelining, which limits the number of work should be constructed as it will be useful in reduc-
streams in execution so as to avoid spreading resources ing the scope changes.
too thinly and causing bottlenecks, local prioritization,
and unsynchronized work. The second rule is buffer- Secondly, practitioners should minimize the impact
ing, which discards local schedules and measurements of changes on safety, duration, cost, and quality. Al-
and uses an aggregate buffer to protect projects from Qadda (2009) also presented the following recommen-
uncertainties. This approach favours the final project dations minimizing the impact of changes on safety,
deadline over task deadlines. The third rule is buffer duration, cost, and quality:
management. Following this rule, practitioners focus i Scope changes that arise at later stages must be
efforts on task prioritization instead of creating de- attended to immediately or, if possible, deferred
tailed and rigid plans, as such exactitude may result to the next turnaround so that present turnaround
in conflicting priorities. By closely monitoring the rate duration is not affected;
of project buffer consumption, practitioners can quick- ii Practitioners should devote enough time to devel-
ly spot which tasks are consuming buffer most quickly oping turnaround scope so as to minimize the pos-
and can then adjust resources to support tasks most sibility of scope changes at later stages;
likely to cause the biggest delays in project comple- iii If a change can be accommodated immediately,
tion (Gupta 2011). The results of this methodology it must be completed and not deferred so that
are impressive. Gupta (2011) cites several examples, turnaround quality is not affected; and
including a Spanish nuclear power plant that by using iv All alternative methods of performing scope
buffer management succeeded in increasing its due date changes must be investigated, and in each situa-
performance by 35% (to 95%) and its throughput by tion the alternative with the lowest cost must be
30%, and another European nuclear plant that dramat- applied.
ically increased its due date performance to 90% and
its throughput by 25% for pre-shutdown engineering One potential strategy for reducing the time it takes
activities. to process scope change requests is to create pre-
defined formats that can be quickly and easily ap-
Scope change management (SCM) should also be
proved. To reduce the impact of work scope changes
conducted for turnarounds. Al-Qadda (2009) has
on the turnaround process, a suitable combination of
conducted research regarding scope change in petro-
these SCM principles and a company’s existing change
chemical plant turnarounds. He recommended that
management principles should be adopted.
SCM should follow a change procedure that consists of
activities such as change request initiation, change re-
quest review, evaluation of change request, and change 4 CASE STUDY ANALYSIS OF AN
request approval. The addition, modification, or dele- ACTUAL POWER PLANT
tion of scope can all prompt the initiation of a change TURNAROUND PLANNING AND
request. Further to following the change procedure for MANAGEMENT PROCESS
turnaround there are two other important issues that
should be considered as part of SCM. Firstly, practi- We conducted a case study in order to help provide
tioners should take care to minimize the changes in recommendations for improving a certain company’s
174
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
project management processes for turnaround projects. ish turnaround-related work four months after breaker
The company in question is active in the energy sec- closed. However, the BP consider turnaround plan-
tor with several coal and gas power plants in Alberta, ning and management in a more general sense, calling
Canada. The case study compares and contrasts the for five-year plans for each turnaround. Such a five-
best practices for power plant turnaround planning and year plan may include ongoing business processes and
management derived from the literature review in Sec- turnaround-specific processes. The other gap relates to
tion 3 of this paper (referred to from hereon in as “best the timing of phases. In CP, each phase is scheduled to
practices” or “BP”) to the company’s existing, docu- start only after the previous phase has been completed,
mented standards for managing its turnaround projects and there are no gaps in time between phases. In BP,
(referred to from hereon in as “company practices” or however, in some cases a time interval between phases
“CP”). The presented case study follows the steps de- exists. Accordingly, it can be inferred that these time
scribed in the methodology in order to better illustrate intervals can include work related to ongoing processes
how the proposed methodology can be applied by com- and can also accommodate possible delays.
panies involved in turnaround projects. The main ob- Other companies involved in turnaround projects can
jective in conducting this comparison is to point out apply the first step of our proposed methodology to
the similarities and differences between the two sets of their own context. Although the CP will differ from
practices so as to identify any gaps in the company’s one company to another, this step is generic and will
existing standards. give any company a better perspective of how their
It is important to consider that BP describes both practices are similar or different to BP.
general and detailed concepts for the planning and
management of turnaround projects that have been 4.2 Comparison of Outputs and Task Tim-
compiled from various sources of published literature, ings of Each Phase
while CP describes practices intended for a specific
According to our proposed methodology, in the second
company project management team. Therefore, CP
step, practitioners should compare outputs of each CP
tend not to highlight more general concepts; instead,
phase with related aspects of BP in order to find gaps
they focus on the outputs of each phase, templates
and commonalities between the two sets of practices.
used, and the responsible persons. In order to com-
Furthermore, they should also compare the start and
pare CP with BP, we follow the methodology shown in
end times of activities in each turnaround phase de-
Figure 1. Accordingly, in the first step, we introduce
tailed by CP with those prescribed by BP. It is impor-
and compare the different phases suggested by BP and
tant to note that the comparison carried out in the sec-
CP. Next, we compare the activities and outputs of
ond step of the proposed methodology is more detailed
each CP phase with related aspects of BP. In the third
than that in the first step, and the results achieved
step, we identify the BP recommendations excluded by
are therefore very specific. Because of this difference
CP.
in level of detail, companies should still complete the
second step of our methodology even if the comparison
4.1 Phase-to-Phase Comparison
in the first step showed that the CP were well aligned
Our proposed methodology stipulates that the system- with BP, as there still is a possibility of finding signif-
atic comparison should begin by comparing the CP icant gaps between phase outputs and the timings of
turnaround phases to those recommended by BP. The phase activities between the two sets of practices. For
BP divide turnaround planning and management in- this case study, we performed a detailed comparison of
to phases that are part of five-year plans. In CP, outputs and task timings; Table 1 shows part of this
turnaround phases are described in detail for a peri- comparison and provides details regarding each phase’s
od beginning about two years prior to breaker open major outputs and their timings. Note that the blank
(the Project Execution sub-phase start time) and end- spaces in the table are related to items documented in
ing about four months after breaker closed (the end one set of practices that have no direct parallels in the
of the Project Execution sub-phase). The beginning other. Findings will of course vary for different com-
and end of the turnaround management phases de- panies applying our methodology; however, the level
scribed by CP and BP are different in some cases. of detail discussed here shows how specific the second
Furthermore, the BP describe some phases for which step of the comparison should be. Our intention is to
there are no matches in CP and vice versa. Figure help potential users of our methodology visualize what
2 illustrates the comparison of turnaround phases de- benefits they can anticipate from this step.
fined by BP to the phases defined in CP. As shown Providing a detailed comparison similar to what pre-
in Figure 2, this phase of the comparison shows two sented in Table 1 for all activities will help reveal gaps
major gaps between BP and CP. One gap relates to in the outputs and task timings of each CP phase. Ex-
the definition of phases. According to CP, the project perienced managers and engineers can use a document
management team should commence work by about like this one to help improve turnaround planning and
two years before a turnaround project and should fin- management processes; as they know by experience the
175
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
177
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
al Development phase, 5 did not exist in CP. Table 2 Figure 3 reveals the percentages of deviations and
summarizes the comparison of BP and CP phase out- gaps identified from the comparison of CP to BP. It
puts. Deviations are outputs considered by CP in diff- can be observed from Figure 3 that there is no devia-
erent phases than recommended by BP whereas gaps tion or gap between CP and BP during the Turnaround
are outputs absent from CP that are required by BP. Execution phase. However, when it comes to the BP
One way to present the results of this comparison is Business Plan and Conceptual Development phases,
to list them by item. For example, a gap may be pre- the gaps between the two sets of practices are more
sented as “BP recommend forecasting the turnaround than 50% (55.6% and 62.5% respectively). The chart
budget for the next five years as part of the business also shows that overall, the deviation between the two
plan, but CP do not consider five-year forecasts in the sets of practices is 6.8% and the gap between CP and
turnaround budget”. Similarly, a deviation may be BP is 20.3%. Illustrating the results of this compar-
presented as “While BP recommend that long lead ma- ative analysis as we do in Figure 3 makes it easy for
terial purchase orders are finalized in the Work Deve- turnaround managers to perceive which phases have
lopment phase, CP specify that vendor contracts are more deviations and gaps and thus require more pro-
to be signed in the Project Optimization phase”. Ear- cess improvement attention.
lier in this section, we presented all the deviations and
gaps we found by comparing CP to BP. While it may 4.3 Missing Best Practices Concepts
be useful for engineers involved in turnaround projects
to know the item-wise details of this comparison, In the third step of the proposed methodology, the ma-
presenting the results to turnaround managers will be jor BP concepts and items that should be included in
more effective as an illustration of overall trends. For CP in future should be discussed. As we demonstrat-
example, for our case study we compiled the deviations ed, in the previous two steps, CP and BP are compared
and gaps discussed above and displayed them in a bar and discrepancies between the two sets of practices are
chart (Figure 3). identified and presented so as to highlight areas for
Table 2. Summary of phase output comparisons between best practices and company practices
Phase Total No. of Outputs No. of Deviations No. of Gaps
Business Plan 9 1 5
Work Development 17 3 1
Detailed Planning 9 0 1
Pre-turnaround Work 10 0 2
Turnaround Execution 8 0 0
Post-turnaround 13 1 1
Conceptual Development 8 0 5
Overall 74 5 15
Figure 3. Overall comparison of deviations and gaps (company practices versus best practices)
178
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
179
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
mented practices on turnaround projects to identify Elshout, R. and Garcia, D. (2009). “Strategies for a
gaps between the intended and followed practices so smooth turnaround.” Journal of Chemical Engineer-
that it would be possible to examine how consistent- ing, 116(7), 34–39.
ly documented practices are applied across turnaround Ertl, B. (2004). Applying PMBOK to Shutdowns,
projects. Turnarounds and Outages. Plant Maintenance Re-
source Center. Available at <http://www.plant-
maintenance.com/> (accessed 09/10/2014).
ACKNOWLEDGEMENTS
Fayek, A. R. and Peng, J. (2013). “Adaptation of work-
We would like to thank the partner company who par-
face planning for construction contexts.” Canadian
ticipated in our case study for providing access to doc-
Journal of Civil Engineering, 40(10), 980–987.
umented company practices and sharing personnel ex-
Ghazali, Z. and Halib, M. (2011). “Towards an alter-
pertise. We would also like to thank Dr. Adel Awad
native organizational structure for plant turnaround
for his preliminary research into best practices for pow-
maintenance: An experience of PETRONAS Gas
er plant turnaround planning and management, which
Berhad, Malaysia.” European Journal of Social Sci-
informed the development of this paper. This research
ences, 25(3), 40–48.
was conducted under the NSERC Industrial Research
Gupta, S. (2011). “Completing turnaround projects
Chair in Strategic Construction Modeling and Delivery,
faster with full scope.” Electric Light and Power,
held by Dr. Aminah Robinson Fayek. We grateful-
89(2), 36–39.
ly acknowledge the financial support of the industrial
Lazeroms, H. (2011). Reducing Risks in the Scoping
partners to this Chair and of the Natural Sciences and
Phase of a Power Plant Turnaround will Improve the
Engineering Research Council of Canada.
Cost Effectiveness of the Installation. MSc Thesis,
Asset Management Control Centre Academy, Inter-
REFERENCES national Masters School, Den Helder, Netherlands.
Lenahan, T. (1999). Turnaround Management. Butter-
worth Heinemann, Oxford, United Kingdom.
Al-Qadda, M. S. (2009). Sabic Plant Shutdowns and
Levitt, J. (2004). Managing Maintenance Shutdowns
Turnarounds, Scope Variation Practical Approach.
and Outages. Industrial Press Inc., New York, New
M.Sc. Thesis, Open University Malaysia, Kuala
York, United States.
Lumpur, Malaysia.
McLay, J. A. (2012). Practical Management for Plant
Construction Industry Institute (2008). Front End
Turnarounds. JMC Consulting Ltd., Edmonton, Al-
Planning of Renovation and Revamp. Projects Im-
berta, Canada.
plementation Resource 242-2, Construction Industry
Megow, N., Möhring, R. H., and Schulz, J. (2011).
Institute, Austin, Texas, United States.
“Decision support and optimization in shutdown
Construction Industry Institute (2014). CII best prac-
and turnaround scheduling.” INFORMS Journal on
tices (Project risk assessment, Quality managemen-
Computing, 23(2), 189–204.
t, and Front end planning). Construction Industry
National Energy Board of Canada (2013). Canada’s
Institute. Available at <https://www.construction-
Energy Future 2013: Energy Supply and Demand
institute.org/> (accessed 08/02/2014).
to 2035. Available at <http://www.neb-one.gc.ca/>
Construction Owners Association of Alberta (2014).
(accessed 07/21/2014).
Advanced Work Packaging & Workface Plan-
Obiajunwa, C. (2007). “Optimization of turnaround
ning. Construction Owners Association of Alberta.
maintenance project implementation.” ARCOM
Available at <http://www.coaa.ab.ca/> (accessed
Doctoral Workshop: Facilities, Refurbishment and
08/27/2014).
Maintenance Management, Sheffield Hallam Univer-
Cormier, B. and Gillard, C. F. (2009). “Beyond
sity, Sheffield, United Kingdom.
turnaround planning.” Petroleum Technology Quar-
Obiajunwa, C. (2010). A Framework for the Suc-
terly, Q1, Available at <http://www.eptq.com/>
cessful Implementation of Turnaround Maintenance
(accessed 08/27/2014).
Projects. PhD Thesis, Sheffield Hallam University,
Duffuaa, S. and Ben-Daya, M. (2009). Hand-
Sheffield, United Kingdom.
book of Maintenance Management and Engineer-
Oliver, R. (2001). “Organising the plan for
ing. Springer, London, United Kingdom, Chapter
turnarounds.” Petroleum Technology Quarter-
Turnaround maintenance.
ly, Q3, Available at <http://www.eptq.com/>
Duffuaa, S. O. and Ben-Daya, M. (2004). “Turnaround
(accessed 08/26/2014).
maintenance in petrochemical industry: Practices
Oliver, R. (2002). “Complete planning for maintenance
and suggested improvements.” Journal of Quality in
turnarounds will ensure success.” Oil and Gas Jour-
Maintenance Engineering, 10(3), 184–190.
nal, 54–62.
Duffy, K. and Tregoe, K. (2012). “Strategies to optimize
Project Management Institute (2010). A Guide to the
shutdowns, turnarounds and outages.” Reliable Plant
Project Management Body of Knowledge (PMBOK
Available at <http://www.reliableplant.com/> (ac-
Guide). Project Management Institute, Newtown
cessed 01/20/2013).
180
Raoufi and Fayek /International Journal of Architecture, Engineering and Construction 3 (2014) 168-181
181