Professional Documents
Culture Documents
COVER PAGE
DISCLAIMER
The information contained in this document has been prepared by L’Air Liquide S.A. and/or its controlled subsidiaries (“Air
Liquide”), exclusively for their use, and is Air Liquide property. Air Liquide believes the information is current and accurate,
but circumstances may warrant additional requirements or procedures. This document is subject to periodic review and
users are cautioned to obtain the latest edition.
Air Liquide makes no representations or warranties to third parties as to the quality, accuracy or completeness of
information contained in this document and EXPRESSLY DISCLAIMS ALL WARRANTIES, INCLUDING, BUT NOT
LIMITED TO, THE WARRANTY OF MERCHANTABILITY AND THE WARRANTY OF FITNESS FOR A PARTICULAR
PURPOSE.
No part of this document may be copied or otherwise shown or disclosed to third parties without the prior consent of Air
Liquide.
Unauthorized use of this document by any third Party, including Air Liquide contractors and subcontractors, shall be at
such Party’s own risk, and Air Liquide assumes no liability in connection with information contained herein. Air Liquide
disclaims any liability for any damage suffered by any company or person as a result of or in connection with the use,
application or implementation of the information contained herein or any part thereof. The benefit of this disclaimer shall
inure to Air Liquide and its affiliates.
This document should not be confused with federal, state, provincial, or municipal specifications or regulations, insurance
requirements or national safety codes.
This document is issued and administered by the Air Liquide Engineering Standards Department.
Paper copies of this document are considered to be “uncontrolled” and users should always
check for the most recent revision.
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 2 of 16
TABLE OF CONTENTS
1 INTRODUCTION 3
1.1 Scope 3
1.2 Definitions 3
1.3 Applicable Codes, Standards, and Air Liquide Reference Documents 3
1.4 Conflicts, Omissions and Alternatives 3
2 LIFTING RULES 5
2.1 Transport sketches 5
2.2 Cranes capacity 5
2.3 Maximum load transmission to the ground 5
2.4 Lifting gear 5
2.5 Tail crane 6
2.6 Manoeuvring rules 6
3 SCHEDULE & PRELIMINARY STUDY 7
4 LIFTING OPERATIONS REALIZATION 8
4.1 Lifting operations preparation 8
4.2 Lifting authorization 8
4.3 Lifting sequence 9
5 ENTITY SPECIFIC AMENDMENTS 10
ANNEX 1 – SKETCHES TAGS 11
ANNEX 2 - SCHEMATIC DIAGRAMS - LIFTING PROCEDURE 12
ANNEX 2 - PACKAGE LIFTING 13
ANNEX 3 - DISTILLATION COLUMN LIFTING 14
ANNEX 4 – VESSEL LIFTING 15
ANNEX 5 – TAIL CRANE SPREADER BAR STRESS CALCULATION 16
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 3 of 16
1 INTRODUCTION
1.1 Scope
1.1.1 Purpose
This standard defines the procedure and rules applicable to the heavy lifting operations.
1.1.2 Scope of Application
This standard is applicable to
• lifting of equipment and/or pieces of any kind with a weight equal or more than 10 t
• lifting, rigging, handling operations with specific difficulties
1.2 Definitions
ALE Air Liquide Engineering
Contractor Company and/or Persons carrying out the works
subcontractor Company to which the Contractor subcontracts works or services
TPAI Third Party Authorized Inspection company
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 4 of 16
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 5 of 16
2 LIFTING RULES
If transport sketches are available for the equipment to be lifted, the Contractor performs the lifting operations
according to the transport sketch requirements (lifting gear…).
No deviation from the transport sketch is granted by ALE on site, unless discussed and agreed during the
preliminary study stage.
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 6 of 16
It is not allowed to have the equipment resting on its lower extremity during the tilting operations to bring it in vertical
position.
Vertical loads only are allowed during lifting operations : slant loads (pulling the equipment with the crane) are not
allowed.
The Contractor assigns for the complete duration of each lifting operation one lifting leader who is designated to
each crane operator and to the rigging team as the only operation chief. During the operations, remarks and
warnings are adressed to the lifting leader only (and not directly to the crane operators). During the operations,
instructions to crane operators and to rigging team are given by the lifting leader only - nobody (Client, ALE,
Contractor…) is authorized to by-pass the lifting leader.
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 7 of 16
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 8 of 16
4.1.2 Organization
Success and safety of heavy and/or difficult lifting operations is based on the rigor and precision of the preliminary
organization.
Heavy and/or difficult lifting operations are started early in the morning in order to save time to adjust the equipment
and to cope with unforeseen events.
In order to ensure the early start of the operations, no later than the day the before the lifting,
• cranes are installed and tested (cranes ready to operate) and inspected by the lifting leader
• foundation / supporting structure preparation (shims installed, axis traced…) is completed, inspected and
accepted by ALE
• equipment to be lifted preparation (ground works completed, no loose item, anchor holes/ base plates
matching with the foundations embedded plates/anchor bolts…) is completed and inspected by ALE
• lifting gear and equipment lifting trunions/lugs preparation (slings, shackles, spreader bars hanging from
the crane hook, lifting trunions/lugs greased if necessary) is completed and inspected by the lifting leader
• Lifting leader is assigned, has visited the site, has been introduced to ALE and has prepared and check
personally the operations to be performed
• coordination procedure (sign language…) is agreed between the crane operators, the lifting leader and the
rigging team and necessary tools (radios…) are available on site and tested
• preliminary study is up-to-date and approved by ALE
• Authorization file as described in section 4.2.2 is submitted to ALE
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 9 of 16
Wind speed : Deviations from the limit of 7 m/s are granted by ALE only if
• the Contractor submits a wind speed limit calculation for the concerned operation
• the wind speed is acceptable in regards with the submitted wind speed limit calculation
Time for authorization granting : ALE keeps the right to grant lifting authorization after 10.00 am, on exceptional
basis. If the lifting authorization is granted after 10.00 am, the Contractor commits to carry on the works as late as
necessary to ensure the completion of the lifting operation at no extra cost for ALE.
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 10 of 16
Table of Revisions
Section Description
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 11 of 16
Tag Definition
A Main Crane
B Tail Crane
C Spreader bar
E1 Slings length between spreader bar and trunions/lugs
E2 Longest radiud between the trunions/lugs and the equipment extremity
F Length of the boom
H, H1 Boom height (and not height under hook)
P, P1 Lifting radius
X, X1, X2 Slings hook angle
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 12 of 16
X1
B
C C X2
C
E2 F
E1
B
A
C A
P
B
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 13 of 16
View according to A
X° < to 60°
E1 > E2
A X°
C
C E1
A
H E2
C
H1
P P1
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 14 of 16
View according to A
X° < to 60°
E1 > E2
A X°
C
E1
H
A
E2
B
C
H1
P P1
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 15 of 16
X° < to 60°
H X°
1 3 B
H1
P P1
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.
E-GS-9-3-1
GENERAL SPECIFICATION Rev. A
Page 16 of 16
Minimum length of E :
DUE
Smax calculation :
Smax is calculated according to the following formula :
W × LuG × D
Smax =
4E(LuLl + E)
In case of doubt, check with ALE head office if the calculated maximum stress is acceptable.
DISCLAIMER: Prior to using this document, all individuals must refer to the Disclaimer on the first page of this document.