Methodology For Puff Test at Descharge Pressure.
Methodology For Puff Test at Descharge Pressure.
Project Name:
Equipment Name:
Site Name:
Region:
Name of Contractor:
Date of Testing:
Methodology for Puff test at Discharge pressure (25 Bars) to check Piping
network of NOVEC/ FM-200 (fittings, hangers and piping system).
This test is addition to Pneumatic/flow test at 40 PSI in closed circuit to check leakages as agreed in
PAT document.
After the successful completion of test, remaining rooms shall also be prepared
by Vendor according to document signed.
For this test, Pressure Gauge shall be Calibrated, and Calibration Label installed
Step-2 on the Pressure Gauge by Vendor and verified by Client teams.
Once room is ready for test, Vendor shall conduct leakage test in a closed
circuit at 40 PSI in presence of client teams (Using air). After removing the
source of pressurizing gas, pressure in the pipe shall not be < 80% of test
Step-3 pressure after 10 mins.
Vendor shall Disconnect NOVEC 1230 / FM-200 Cylinder from the
Step-4 piping network to connect Nitrogen Cylinder.
Naqash Kazmi (CFPS®) NFPA
CERTIFIED FIRE PROTECTION SPECIALIST(CFPS®)
Regulator and Pressure Gauges shall be installed before high pressure ball valve
which shall be coupled with Piping system. High pressure ball valve, couplings
etc. shall be ensured to withstand pressure of 25 Bars.
Pressure Gauges shall Monitor Pressure being induced into piping network.
Once pressure of 25 Bars is achieved on Pressure Gauge, Ball valve shall be fully
Step-5 opened for 10 seconds to let Nitrogen flow through Piping system and
Discharge from Nozzles. Visual indicators shall be used to verify that Nitrogen
has discharged out of each and every nozzle in the system. After 10 sec, close
the ball valve.