You are on page 1of 3

TESTING & COMMISSIONING OF FIRE FIGHTING SYSTEMS

I. DESCRIPTION OF WORK
The purpose of the testing & commissioning process is to provide the owner/operator of the
facility with a high level of assurance that the fire protection systems have been installed in the
prescribed manner, and operate within the performance guidelines.

II. RELATED DOCUMENTS


 Fire Fighting Approved Shop drawings
 specifications.
.
III. REFERENCES
 NFPA: Commissioning Fire Protection Systems
 Specialist recommendations.

IV. FIRE PROTECTION SYSTEMS INCLUDED IN THE TESTING &


COMMISSIONING PROCESS
1. Sprinkler System
2. Fire Pump (Duty & Stand By)
3. Jockey Pump
4. Stand Pipe
5. Fire Hydrants

V. Pre Commissioning Procedure for Fire Fighting System:-


1. Ensure that the system installation is complete and mechanical completion is approved.
2. Ensure that no damage has occured between mechanical completion & precommissioning
3. Repair all damages to the equipment & piping.
4. Check that the Fire Fighting piping network is complete with fire
hose reel cabinet, pressure gauge, fire extinguishers proper valves
drains vents strainers pressure switches instruments & sprinklers drains vents strainers,
switches in place as per final approved shop drawing.
5. Ensure that the Fire Fighting network is hydraulically pressure tested and approved.
6. Ensure that the entire system is cleaned internally & externally.
7. Ensure that the Fire Fighting pumps are precommissioned & commissioned
as per approved procedure
8. Ensure all the pressure switches are installed & wired properly.
9. Ensure that all supervisory isolation valves & sectional control assembly valves are
installed & wired.
10. Ensure that all drain valves & vents are installed.
11. Ensure that the identification of all valves & pipe work is complete.
12. Ensure the wiring to the Fire Alarm from the pump panel is complete.
13. Ensure that the Fire Alarm & BMS connections (if any) are complete.
14. Ensure that the wiring diagram of pump set controls & schematic piping drawings are
displayed near or inside the pump panel.

VI. Start-Up:-

A. The Engineer & 3rd Party Contractor will witness start-up of the fire pump and jockey pump.
The appropriate contractors and/or manufacturer’s representative will be required on site to
perform start-up. No system will be started until the manufacturer’s checklists have been
completed. Start-up will be performed according to the manufacturer’s recommended
procedures. The Engineer & 3rd Party Contractor will visit the site to review completeness of
installation in conjunction with progress meetings prior to starting equipment.

B. Contractor team involved in installation, fabrication, manufacturer, control, or designs of


equipment are required to be present at the time of start-up.

VII. Commissioning of Following Fire Protection Systems :-


The Functional Performance Tests shall include fire protection equipment / system as mentioned
below.

1) Sprinkler System: The fire protection trade representative, with the Engineer & 3rd Party
Contractor , will demonstrate hydrostatic, operational and main drain testing of the system.
These tests shall meet the requirements of NFPA 13 and the AHJ. The fire protection trade
representative shall hydrostatically test the system, placing the system under a working water
pressure of 200 psi for a period of 2 hours or by an approved method from the AHJ. A visual loss
in gauge pressure or visual leakage shall be considered a failure in testing. The leak in the system
shall be repaired and the system will require testing again in the same manner. The fire
protection trade representative shall coordinate the operational testing with the fire alarm
contractor. The fire protection trade representative shall open the inspector’s test connection, the
water gong shall sound within 5 minutes and the fire alarm shall be initiated within 90 seconds.
The fire alarm trade representative shall conduct a main drain test. The fire protection trade
representative shall open the main drain and it shall remain open until the system stabilizes. The
static and residual pressures shall be recorded.

2) Fire Pump (Duty & Stand By): The fire protection trade representative, with the Engineer &
3rd Party Contractor present, will demonstrate acceptance testing of the fire pump system. The
fire
protection trade representative shall conduct the field acceptance test with the
manufacturer’s representative according to NFPA 20. The fire protection trade representative
shall provide all testing equipment. The fire protection trade representative, with the CA and
AHJ, will demonstrate fire pump controller acceptance testing.
3) Jockey Pump: The fire protection trade representative, with the Engineer & 3rd Party
Contractor present, will demonstrate acceptance testing of the jockey pump. The fire
protection trade representative shall conduct the field acceptance test with the manufacturer’s
representative according to NFPA 20. The fire protection trade representative shall provide all
testing equipment. The fire protection trade representative, with the CA and AHJ, will
demonstrate jockey pump controller acceptance testing.

4) Standpipe: The fire protection trade representative, with the Engineer & 3rd Party Contractor
present, will demonstrate hydrostatic and flow testing of the system. These tests shall meet the
requirements of NFPA 13, 14 and the AHJ. To hydrostatically test the system the fire protection
trade representative shall place the system under a working water pressure of 200 psi for a period
of 2 hours or by an approved method from the Engineer. The pressure shall be monitored using a
pressure gauge installed at the top of each standpipe. A visual loss in gauge pressure or visual
leakage shall be considered a failure in testing. The leak in the system shall be repaired and the
system will require testing again in the same manner. The fire alarm trade representative shall
coordinate the flow test with the local fire department. The flow test shall meet the requirements
of NFPA 14 and the AHJ.
5) Fire Hydrants: The fire protection trade representative, with the Engineer & 3rd Party
Contractor, will demonstrate a hydrostatic and flow test of the system. These tests shall meet the
requirements of NFPA 24 and the AHJ.

VIII. CHECK LIST:-

You might also like