You are on page 1of 3

Testing & Commissioning

Procedure For Staircase


Pressurisation System
 HVAC Method Statements
 Testing & Commissioning

1031



 0
 


 Share

The purpose of this procedure is to define the step by step method to implement the
correct practices for the precommissioning & commissioning of  Staircase Pressurisation
System through the guidelines contained herein so as to ensure that the job execution
complies with the project requirements and serves the intended function to satisfactory
level.

Precommissioning Procedure for


Staircase Pressurisation System
1. Ensure that the pressurization fan installation is complete and mechanical
completion is approved.
2. Ensure that vibration isolators are complete with proper alignment of fan.
3. Ensure that no damage has occurred between mechanical completion &
precommissioning.
4. Ensure that orientation of the fans are as per approved shop drawings &
requirement.
5. Repair all damages to the equipment finish paint.
6. Check the connection of fan inlet & outlet are done with proper alignment.
7. Check the fan is installed as per the approved shop drawings and manufacturer’s
instructions.
8. Check for free rotation of fan propeller.
9. Check the fire rated ductwork is properly installed & insulated in line with the
approved drawings & specifications.
10. Check all motorized dampers are installed & connected with power supply & controls
properly.
11. Check for proper electrical power, control panel and earthing connections as per
manufacturer’s recommendations. Field wiring to be pre-tested for continuity and
insulation resistance.
12. Check the interface of the pressurization fan with the fire alarm system & BMS.
13. Check for proper installation of pressure sensor in the shaft.
14. Check for proper setting of the overload relay.
15. Check the identification & labeling of the fan & ductwork.

Commissioning Procedure for Staircase


Pressurisation System
1. Ensure that all the precommissioning checks are carried out successfully.
2. Start the fan to check for correct direction of rotation of fan/motor.
3. Run the fan for 5 minutes.
4. Check for any undue vibration or noise.
5. Start the fan by inducing a fire signal from the Fire alarm control panel.
6. Check all the fire dampers in shaft in all the floors close completely and the shaft is
totally isolated.
7. Measure the air flow & inlet static & the static pressure in the shaft & record the
values.
8. Check whether the fan speed is properly controlled by the VFD vide the signal from
the pressure sensor in the shaft.
9. Clear the fire signal & check the fan stops & all the motorized dampers in the shaft
are opened.
10. Record all readings in the final performance check list
Attachments:
 Precommissioning of Staircase Pressurisation System
 Commissioning of Staircase Pressurisation System
 Performance Test Record for Staircase pressurisation system
 Risk Assesment

You might also like