Section 3 - Enq 14e0101 1406182266
Section 3 - Enq 14e0101 1406182266
:
Due Date :
Bharat Heavy Electricals Limited Supplier's Ref.:
Date :
2.1.10.4 Centre shift control within the stroke length of the weaver Vendor to specify
2.1.10.5 Stroke length of the torch weaving unit 75 mm approx. Vendor to specify
ESSENTIAL: Video Monitoring System to capture the position in
two views while welding through Monitor, so that the operator
2.1.11 monitors the same in one place and adjusts the torch using Vendor to confirm
joystick for fine tuning while welding. This unit shall comprise
of :
2.1.11.1 CCTV Camera with accessories Vendor to confirm
Page 1 of 5
S No. Description - BHEL's Requirement Specified Offered Deviations Remarks
2.2.3 Motor Power Vendor to specify
2.2.4 Working Height from floor level Vendor to furnish
2.3 CONSTRUCTION:
Vendor to furnish details of material, hardness & constructional
details, including explanatory drawings, of various components like
2.3.1 Vendor to furnish
Torch, frame, clamping & adjusting system, Lubrication system, etc
.of the machine.
Video images on CD including hard copy explaining the technical
2.3.2 features / Literature with photographs, drawings explaining the Vendor to furnish
technical features should be enclosed with the offer.
The working principle of the above mechanism shall be explained
2.3.3 Vendor to Confirm
clearly.
Digital display of major weld parameters like current, voltage, wire,
2.3.4 Vendor to Confirm
speed, programme w.r.t. material / thickness etc
2.3.5 Any other feature if required Vendor to Confirm
3.0 OPERATION AND CONTROL SYSTEM:
3.1 CONTROL PANEL:
Control Panel PLC based controlled panel unit which houses all the
3.1.1 electrical and electronics accessories for the complete control and Vendor to Confirm
automatic operations
Control panel side and Layout showing complete details shall be
3.1.2 Vendor to submit
submitted.
Machine shall be provided with main switch with key and signal
3.1.3 Vendor to Confirm
light.
4.0 OPERATOR PENDANT & MANUAL CONTROL :
The Operator Pendant provided with all the controls relevant for
operator functions like Emergency stop,On/Off,Cycle
4.1 Vendor to confirm
start/Stop,Weld on/Off,Side beam carraige speed control,joy stick for
Cross Slide adjustment,Auto/manual,etc.
First filling of all required Oils & Grease etc. to be supplied by
5.0 vendor. Indigenous (Indian) source or Indian equivalent and Vendor to confirm
specifications of oils/ greases are also to be provided by the vendor.
Lubrication shall be life time lubricated wherever possible. Other
5.1 lubrication points shall be of automatic type. Details shall be Vendor to confirm
submitted.
6.0 ELECTRICAL :
415V + 10% / -10%, 50HZ +/-3 HZ, 3 Phase AC (3 wire system with
out neutral) Power Supply Voltage will be provided by BHEL at a
single point near the machine, as per layout recommended by
Vendor. All types of cables, connections, circuit breakers etc.
6.1 required for connecting BHEL's power supply point to different parts Vendor to confirm
of the machine/control cabinets, shall be the responsibility of vendor.
Requirement of grounding/earthing with required material details is
to be informed by vendor well in advance so that same could be
incorporated during construction of foundation.
Tropicalisation: All electrical / electronic equipment shall be
7.0 Vendor to confirm
tropicalized
All electrical & electronic control cabinets & panels should be dust
7.1 Vendor to confirm
and vermin proof
All electrical components in the cabinets should be mounted
7.2 Vendor to confirm
systematically
7.3 Motors shall conform to IEC or Indian Standards Vendor to confirm
All cables and cable trays required for the machine should be
7.4 Vendor to confirm
included in the offer.
Vendor should ensure the proper earthing for the machine and its
7.5 Vendor to confirm
peripherals.
The electrical components used shall be from reputed international
7.6 makes such as Siemens / Telemechanique / Merlin Gerin / GE/ ABB Vendor to confirm
and shall be accordance with DIN/IEC Standards.
8.0 SAFETY ARRANGEMENTS:
Following safety features in addition to other standard safety
features should be provided on the machine:
Machine should have adequate and reliable safety interlocks /
devices to avoid damage to the machine, work piece and the Vendor to furnish details
8.1
operator due to the malfunctioning or mistakes. Details shall be
submitted in the technical bid.
8.2 Welding operation control through hand switch
In case of overloads due to wrong manoeuvres /malfunctions the
8.3
machine should stop to avoid damage to machine and man.
Detailed list of safety alarms / indications provided on the machine
8.4
shall be submitted along with the offer.
All the pipes, cables etc. on the machine should be well supported
8.5 and protected. These should not create any hindrance to machine
operator's movement for effective use of machine.
Emergency Switches at suitable locations as per International Vendor to furnish details
8.6
Norms should be provided.
Necessary protection shall be provided to prevent from over
8.7
loading.
Page 2 of 5
Vendor to furnish details
Page 3 of 5
S No. Description - BHEL's Requirement Specified Offered Deviations Remarks
Competent experts shall be arranged by the vendor during training
12.3 Vendor to confirm
for satisfactory & effective training of BHEL personnel.
12.4 Vendor to quote for training on per diem basis Vendor to confirm
13.0 FOUNDATION :
13.1
Vendor shall submit the layout drawing within one month from the
date of Letter of Intent (LOI) / P.O. Layout should contain layout of
the machine and load points including details viz. static / dynamic
load details etc. The layout should consist of all requirements
pertaining to complete machine including space requirement for
Voltage Stabilizer, Isolation Transformer, Air compressor, Chip Bin &
any other accessories. Foundation of the machine if required will be Vendor to agree
designed by supplier. BHEL shall construct complete foundation for
the machine under supervision of supplier and at supplier’s
responsibility. supplier should arrange equipments required for the
testing of foundation, if required . The vendor shall also indicate
detailed specifications of grouting compound and Grouting
procedure etc. for foundation bolts of the machine.
14.0 ERECTION & COMMISSIONING
Supplier to take full responsibility for carrying out the erection, start
up, testing of machine, it’s control & all types of other supplied
equipment, machining of test pieces etc. Service requirement like
power, air & water shall be provided by BHEL at only one point to
14.1 Vendor to agree
be indicated by supplier in their foundation/layout drawings. Other
requirements like crane and helping personnel shall also be
provided by BHEL. Details of these requirements should be informed
by vendor in advance.
Successful working of full capacity of the machine by the supplier
shall be considered as part of commissioning. All tests, as
14.2 Vendor to agree
mentioned at clause 15 & 16 shall form part of the commissioning
activity.
Tools, Tackles, instruments and other necessary equipments
14.3 required to carry out all above activities should be brought by the Vendor to agree
supplier.
Commissioning spares, required for commissioning of the machine
14.4 within stipulated time, shall be brought by the supplier on returnable Vendor to agree
basis.
All Cover Plates required for the machine and its peripherals
14.5 Vendor to agree
including pits, if any, shall be supplied and installed by the vendor.
Page 4 of 5
S No. Description - BHEL's Requirement Specified Offered Deviations Remarks
Demonstration by actual use of all supplied attachments and
16.2.5 Vendor to agree
accessories to their full capacity for actual jobs.
17.0 PACKING:
Rigid packing for all items of complete machine with all Accessories
and other supplied items to avoid any damage/loss in transit. When
17.1 Vendor to confirm
machine is despatched in containers, all small loose items shall be
suitably packed in boxes.
18.0 GUARANTEE :
Guarantee for 24 months from the date of acceptance of the
machine at BHEL works . During this Guarantee period at least 2
visits per year and/or whenever called by BHEL (within 24 hours
of call) by the service engineer of the supplier to be made & the
18.1 Vendor to confirm
parts, items, spares etc. needing replacement to be replaced by the
supplier free of cost. In support a Performance Bank Guarntee of
10% of Basic Value of P.O. valid for 24 months from the date of
commissioning will have to be furnished by supplier
19.0 GENERAL :
19.1 Machine Model Vendor to furnish
19.2 Total connected load (KVA): Vendor to furnish
Floor area required (Length, Width, Height) for complete machine &
19.3 Vendor to furnish
accessories
Painting of Machine / Electrical Panels : RAL 6011 Apple Green
19.4 Vendor to confirm.
(Polyurethane Paint)
19.5 Total weight of the machine Vendor to furnish
19.6 Weight of heaviest part of machine Vendor to furnish
19.7 Weight of the heaviest assembly / sub-assembly of the Machine Vendor to furnish
19.8 Dimensions of largest part/ sub-assembly/ assembly of the machine Vendor to furnish
Detailed catalogues, sketch/photographs of the m/c and
19.9 Vendor to submit
accessories/ attachments should be submitted with the offer.
Formula for calculating required time/speed of torch/job for welding
19.10 Vendor to confirm.
Aluminium plates to be furnished by the vendor.
Hydraulic, Pneumatic & oil pipings should be preferably metallic
except places where flexible pipings are essential. All the pipes
19.11 Vendor to confirm.
required for the same shall be included in the standard scope of the
machine.
Signature & Seal of Tenderor
Page 5 of 5