SHIFT REPORT & RENCANA KERJA HARIAN (RKH)

Job Site PT Adhi Kartiko Pratama


Lameruru, Kec. Langgikima, Kabupaten Konawe Utara, Sulawesi Tenggara

RKH SHIFT 2 Sunday, March 17, 2024 WEATHER : CLOUDY

1
2 3
4
MESS HJS
3
2
PIT MAKALE PIT
RANTEPAO

1 1

ETO-IRC
PIT MAKALE
ETO-IRF

3
KETERANGAN :

n FLEET OB

n FLEET ORE
ETO-AKP4
PONDOK

PRODUCTION REVIEW & MONITORING PRODUCTION PLAN


Shift 1 Production Report Daily Production Report Date 17 Mar 2024 Plan Shift 2
Waste 2,882.36
Rain & Slippery
Ore Production 2,554.33
2,882 5,765 Barge 2,513.44
2,513 2.9
2,463 Plan Daily
2,554 2,300
Waste 5,764.72
5,109 5,027
Ore Production 5,108.67
1,741 Barge 5,026.88
2,463 1.5
1,741 2,300 Heavy Equipment Status
Unit Qty Plot Rfu Stb Bd
EXC 40 TON 2 1 1 1
0.0 0.0 EXC 30 TON 8 7 7 1
60% 96% 92% 30% 48% 46% 0% 0% EXC 20 TON 17 15 14 -1 3
Overburden (Bcm) Ore Getting (Wmt) Barging (Wmt) Overburden (Bcm) Ore Getting (Wmt) Barging (Wmt) Rain (Jam) Slippery (Jam)
BREAKER 3 2 2 1
Actual Plan Ach% Actual Plan Ach% Actual Plan Ach%
ADT 40 TON 6 6 6
DT 20 TON 50 45 45 5
Monthly Plan Report GRADER 2 2 2
DOZER 4 3 3 1
Monthly Production Plan & Ore Transfer Report Rain & Slippery Plan Stripping Ratio Plan
VIBRO 2 2 2
200,000 100.0 1.2
WT 2 2 2
182,985 90.3 FT 3 2 2 1
180,000 90.0
162,095 1.0 1.1
159,500 80.0 Stock Ore ETO Date 16-Mar-24
160,000
Ore WMT Ni Fe SiO2 Mgo SiMg
70.0
140,000 0.8
0.7 LOT 1 79,190.89 1.76 21.94 30.03 10.28 2.92
60.0 56.7 LOT 2 31,299.62 1.39 37.41 11.79 2.33 5.06
120,000
50.7 65% LOT 3 26,597.15 1.36 19.74 34.58 10.00 3.46
0.6
100,000
50.0
45.1 WASTE 14,216.11 1.23 35.78 13.51 3.35 4.03
77,795 Total 151,303.77 1.56 26.05 25.50 7.93 3.21
40.0
80,000 71,729 0.4 Stock Ore EFO
60,000
30.0 Ore WMT Ni Fe SiO2 Mgo SiMg
49,858 13,698.19
LOT 1 1.83 21.69 30.74 9.27 3.32
20.0 0.2
40,000
LOT 2 1,091.25 1.45 40.26 11.25 1.35 8.32
10.0 LOT 3 2,103.52 1.45 17.26 38.27 11.39 3.36
20,000
WASTE 0.00
0 0.0 56% 126%
0.0

0 27% 44% 49% SR Total 16,892.96 1.76 22.34 30.42 9.02 3.37
Overburden (Bcm) Ore Getting (Wmt) Barging (Wmt) Ore Transfer (Wmt) Rain (Jam) Slippery (Jam)
Actual Plan W. Assay 24,604.25
Actual Plan Ach% Actual Plan Ach% Ach%
G. Total 192,800.97 1.58 25.68 26.00 8.04 3.23

Daily Mine Planning


Plan Fleet
Lokasi Fleet Loader Hauler Support Trimming Area Dumping Jarak (Km)
OB Removal 1 EXC 40 TON 3 ADT 40 TON Parkiran Lama 0.97
Ore Production 1 EXC 30 TON 3 ADT 40 TON 1 EXC 20 TON 1 EXC 20 TON AKP4 0.83
PIT MAKALE

Lokasi Fleet Loader Hauler Support Trimming Area Dumping Jarak (Km)
OB Removal 1 EXC 30 TON 3 DT 20 TON 1 EXC 20 TON Disposal Makale 0.84
PIT RANTEPAO OB Removal 1 EXC 30 TON 3 DT 20 TON 1 EXC 20 TON Disposal Makale 0.84
OB Removal 1 EXC 30 TON 3 DT 20 TON Disposal Makale 0.84
Ore Production 1 EXC 30 TON 6 DT 20 TON 1 EXC 20 TON 1 EXC 20 TON IRA 2.21
Ore Production 1 EXC 30 TON 10 DT 20 TON 2 EXC 20 TON 1 EXC 20 TON EFO BL 6.58
Stock Quarry 1 BREAKER

Lokasi Fleet Loader Hauler Support Trimming Area Dumping Jarak (Km)

EFO BL Ore Barging 1 EXC 30 TON 3 DT 20 TON 1 EXC 20 TON BARGE 0.33
ETO IRC Ore Barging 1 EXC 20 TON 6 DT 20 TON 1 EXC 20 TON BARGE 4.26
ETO AKP4 Ore Barging 1 EXC 20 TON 9 DT 20 TON 1 EXC 20 TON BARGE 6.11
0.00
0.00

General Activity
Lokasi Fleet Loader Hauler Support Note :
Quarry Stock Quarry 1 EXC 20 TON 2 DT 20 TON 1 BREAKER 1. Kondisional apabila ada perubahan Fleet (Penambahan atau Pengurangan Fleet) sesuai dengan kondisi
Project Mhr di lapangan dan berkoordinasi ke pihak pengawas AKP.
Tapak Mess
Office/Whs/Wrks 2. Update populasi unit dan produksi per tanggal 17 Maret 2024 shift 1 jam 16:00 WITA.
2 GRADER
3 DOZER 3. 1 Fleet Ore Production Pit Makale menunggu EXCA 40 TON Ready.
2 VIBRO
All Area 2 WT
2 FT