Professional Documents
Culture Documents
Solution:
The concept of expected time and the estimation of variability of activity
times (which is necessary before solving the problem) is given below.
1. Estimation of Activity Time: -For dealing with uncertainties associated
with different activities,
PERT approach computes expected time for each activity from the
following three-time estimates:
(a)Optimistic time (to): - It is the shortest possible in which an activity
can be completed if everything goes exceptionally well.
(b)Most likely time (tm). It is the time in
which the activity is normally expected to
complete under normal contingencies.
(c)Pessimistic time (tp). It is the time which
an activity will be to complete in case of
difficulty, Le, if mostly the things go wrong.
It is the longest of all the three-time
estimates.
The to, tm, tp are combined statistically to develop the expected time
(te) for an activity. The fundamental assumption in PERT is that the
three-time estimates form the end points and mode of Beta
distribution (Fig. 10.3). It is further assumed that t and f are about
equally likely to occur whereas the probability of occurrence of tm is
4 times that of tp and to.
Therefore, te is given by,
te=to+(tmx4) +tp (1)
6
(1) Estimation of Variability of Activity Times: - The purpose is to
find, how reliable – ‘te’ as got from the equation (1) is
Assume
Case I Case II
to= 5 to = 5
tm= 6 tm= 10
tp= 7 tp= 21
te= 5+(6x4) +7 te= 5+(10X4) +21
6 6
te=6 te= 11
te=tm te not equal to tm
This indicates that, if the time required for an activity shows high
variability (Case Il) and there is wide range of (21-5=16) three
times estimates, the certainty and confidence to correctly
anticipate the actual time from relation (1) decreases and thus the
need to measure the variability in the time of an activity arises.
Knowing the variability, the reliability of t, values can be assessed,
PERT, using statistical probability concept, employs standard
deviation (St) and variance (Vt) as measures of variability. They are
given by,
St= tp-to
6
Vt= (tp-to) ^2
(6)
Thus, for these cases I and II above
(St)1 = 1/6 ; (St)2 = 2.66
(Vt)1 = 1/36 ; (Vt)2 = 7.1
This supports the above concept.
Coming to actual problem:
(a) the Table 10.2 gives the values of to, tm and tp for each activity.
The values of te, St, and Vt are calculated by using equations
(1), (2), and (3) and have been added in the Table 10.2.
Activity to tm tp te St Vt
1-2 2 5 14 6 2 4
1-6 2 5 8 5 1 1
2-3 5 11 29 13 4 16
2-4 1 4 7 4 1 1
3-5 5 11 17 11 2 4
4-5 2 5 14 6 2 4
6-7 3 9 27 11 4 16
5-8 2 2 8 3 1 1
7-8 7 13 31 15 4 16
The network diagram is given below with Te, EST, LFT and Critical Path on the
same
(d)
Activity EST LST Total Slack
LST-EST
1-2 0 0 0
1-6 0 2 2
2-3 6 6 0
2-4 6 20 14
3-5 19 19 0
4-5 10 24 14
6-7 5 7 2
5-8 30 30 0
7-8 16 18 2
_______________ X _______________