Professional Documents
Culture Documents
Operations Research.
Lecture One
- Network Analysis
- Critical Path Method
- The earliest start time: (the time at which an event can first begin).
The earliest time = start time first node + activity time between nodes
- The latest start time: it is the time during which an activity can be completed if it
starts early
- Slack time: The flexible time that an event has between its earliest event time and
latest event time.
2 4
1 6
3 5
- Node.
- Activities.
1
Application Example:
2 6 7
1
5
3
4
6
Figure (1)
10
Figure (2) 4 3
2
- The third step is to set the earliest start time
11+2=13
0+11=11 13+1=14 max 14+1=15
2 1
2 6 7
6
11
0+3=3 1
3 1
0
1 3 5 3+1=4
10+3=13 max
10
0+10=10
4 3
Figure (3)
The earliest start time = start time first node + activity time between nodes
- Note: if there are two activities, the value of the higher activity is taken.
EST (1) =0
EST (2) = 1+11=12
EST (3) = 1+3=4
EST (4) = 1+10=11
EST (5) =11+3=14 max
= 4+1=5
.
.
EST (7) = 15+1=16
- Note: if there are two activities, the value of the lower activity is taken.
3
12 14 15
2 1
2 6 7
6
11
12 1
0 3 1
1 3 5 13
10
10
4 3
Figure (4)
11 14 15
12 14 15
2 1
2 6 7
6
11 3
12 1
0 3 1 13
0 1 3 5 13
10
10
10
4 3
Figure (5)
4
earliest latest slack
Node
start time start time time
1 0 0 0-0=0
2 11 12 12-11=1
3 3 12 12-3=9
4 10 10 0
5 13 13 0
6 14 14 0
7 15 15 0
14 15
11
14 15
12
2 1
2 6 7
6
11 3
12 1
0 3 1 13
0 1 3 5 13
10
10
10
4 3
Figure (6)
- CP.
5
Example 2
A project has the following times schedule
Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-9 8-10 9-10
time in 4 1 1 1 6 5 4 8 1 2 1 8 7
weeks
15
15
6
.
.
.
EST (9) = 5+5=10
= 17+1=18 max
EST (10) = 18+7=17+8=25
LST (10) = 25
LST (9) = 25-7=18
LST (8) = 18-1=25-8=17
.
.
.
LST (3) = 5-1 =4
= 7-6 =1 min
LST (2) = 13-1=12
LST (1) = 12-4=8
= 1-1=0 min
7
Example 3
Determine the early start and late start in respect of all node point and identify
critical path for the following network.
8 6
2 5 8
10 13
8 16 12
1
3 7 10
0
9
15
7 5 9
4 6
Solution:
10 18 24
10 18 24
8 6
2 5
8
0 10 13
8 24
0
9 25
8 16 13 37
1
3 7 10 37
0
10
15
7 5 9
4 6
22
17
10 22
17
10
CP1= 1-2-5-8-10=37
CP2=1-4-6-9-10=37
8
Problems
1- Determine the CP by using CPM of the following projects
a-
Duration
Activities Path
(week)
A 1-2 1
B 1-3 4
C 3-5 3
D 3-4 5
E 2-4 2
F 5-6 3
G 4-6 6
Solution: CP= 1-3-4-6
b-
Duration
Activities Path
(week)
A 1-2 2
B 2-3 3
C 3-4 8
D 3-5 5
E 5-6 4
Solution: CP=1-2-3-4(check it)
3- For the following network, determine the critical path. The duration of each
activity (in day) is shown on the arrows.
4 9
2 6
3 3
5 5 5
1 3 5 7 8
7 2 4
6
5 4
Solution: CP= 1-3-5-6-7-8-9