Abstract
There is growing concern over the successful implementation of projects in various Public Works Department
(PWDs) at Metropolitan, Municipal and District Assemblies (MMDAs). In recent times MMDAs are challenged
with the issues of poor project delivery rendering. This has led to a low confidence in public service
administration in terms of construction projects delivery. The aim of this study was to appraise the challenges
faced by the PWDs in project delivery. Based on relative importance index analysis the trend of the challenges
were weather and other environmental challenges, unrealistic timelines for project delivery, influence of
processes by political heads, inadequate logistics and inadequate human resource to carry out supervision among
others. The implication is that Local Government Ministry should put in place measures for updating, assessing
and improving the knowledge base on contract management of projects teams within MMDAs.
Keywords: Public Works Departments (PWDs), Project Delivery, Metropolitan Municipal and District
Assemblies (MMDAs), Projects
Introduction
The government of Ghana in its bid to have an all- The Local Government Act (Act 462) of 1993
inclusive governance have over the years set up underpins the constitutional provision for the
various District, Municipal and Metropolitan based operation of these MMDAs. MMDAs have various
units. This is to help include more people at the departments that undertake planning, budgeting
community levels to participate in active governance control of finances but the department that is most
and also to bring governance to the grassroots. The relevant to this research is the Public Works
units have metamorphosed through what was called Department (PWD). This is because they are directly
the ‘Indirect Rule System’ (IRS) where the local responsible for the physical implementation of the
Government units were referred to as native construction projects. Section 10 of the Local
authorities, then through local, urban and district Government Act 462 of 1993 task MMDAs in Ghana
councils and presently the Metropolitan, Municipal to be the highest political and administrative body in
and District Assemblies (MMDAs) concept which the Districts, responsible for the entire development
was initiated in 1988. The MMDAs are an of the Districts. Specifically, PWDs under the
improvement on the previous set-ups established by MMDAs are to monitor as well as initiate to
Ghana’s decentralization process as encapsulated in completion, the delivery of rudimentary
the Constitution. The District Assemblies have been infrastructural projects. The construction industry
chosen to be the highest legislating, planning, accounts for a significant portion of the world’s
budgeting and political authority at the local level. Gross Domestic Product (GDP) (Basheka &
129
131
134
Methodology
The research adopted a mixed methodology researcher decided to undertake the research in only
approach, thus qualitative and quantitative the three regions mentioned due to resource
paradigms were the underpinning philosophies constraints. In this study a total number of 30
professionals were targeted in each of the three
considered. The qualitative approach involved the
selected regions namely: Brong Ahafo, Central and
use of semi-structured questions among top industry Volta regions, thus, certifying the central limit
players including contractors, consultants and theorem which states that 30 is an adequate sample
clients. The reason for the use of the semi-structured in a survey research context (Kar & Ramalinga,
interview was to triangulate literature review 2013). Hence, a total number of ninety (90)
findings in order to improve and expand the depth of professionals were considered for the study. In all,
the results. This was done by elaborating and six PWDs were considered for each region, for each,
five professionals were considered which included:
exploring the experience of the practitioners in
An engineer (2), planner (1), director (1) and a
relation to the phenomena under consideration. This contractor. This gave a total number of five (5)
helped in achieving variables that were peculiar to professionals per each selected PWD (See Table 2).
conditions pertaining to the Ghanaian construction In addition, the study adopted purposive and
industry. The second stage considered quantitative snowballing sampling techniques. The purposive
technique which involved the collection of primary sampling technique helped the researcher to exercise
data based on the nineteen (19) identified variables his or her own judgement about who will provide the
in the previous stage. The sample for the data best perspective of the area under consideration
collection consisted of professionals at the MMDAs (Polit & Hungler, 1999). Hence, the study
thus, representing the population of people who work intentionally invited specific professionals who work
at PWDs in relation to project delivery. The directly in PWDs within the MMDAs in the selected
questionnaire utilized closed-ended questions to regions. This study was further accomplished
challenges of PWDs on construction project delivery through the use of snowballing technique due to the
at MMDAs. This was done by measuring difficulties encountered in having access to the
respondents’ perceptions on the level of severity respondents using purposive sampling. According to
using a Likert scale, where: 1 = lowest (challenge); 2 De Vos (1998), snowball sampling is valued in
= low; 3 = high; 4 = higher; and 5 = highest. Thus, research as it is focused on individuals hard to find.
the numerical representation, statistical analysis and Employing this method, some likely respondents
subjectivity were the underlying individuals’ were known and then asked whether they know any
perceptions. other respondent with the characteristics that we are
looking for in the research. This technique was
Sample Size and Sampling Technique
The study focused on the professionals at PWDs employed to identify hard-to-get respondents.
within MMDAs in the following regions: Central, Professionals who were easy to locate in the
Brong Ahafo and Volta. The main reason for using municipality/region were contacted to give lead to
this category of people was that their activities other professionals with the same characteristics.
directly have a bearing on project delivery within the Respondents had enough working experience with
study area which is the scope for the study. The MMDAs as 29% had 1-5years’ experience, 31% had
135
Data Analysis
This section of the paper present analysis of the data collected from the field. The nineteen (19) challenges identified
were analysed using both mean and Relative Importance Index (RII) to determine the level of severity in terms of
importance to project delivery (see Table 3).
RII = ∑PiUi / Nn
N (n) Where RII = Relative importance index
Pi = respondent rating of severity of the challenges
Ui = respondent ‘s placing identical weighting or rating
N= sample size; n =the highest attainable score
136
Discussion
Weather and Other Environmental Challenges Unrealistic Timelines for Project Delivery
Weather and other environmental challenges with From the findings of the study, it was realized that
relative index of 0.851 were ranked first as the extremely unrealistic timelines for project was a huge challenge in
important cause of delay by respondents. Weather and project delivery amongst PWDs in Ghana. This the
its attendant environmental challenges act as a great deal respondents attributed to other challenges such as
of a challenge to project delivery. Ghana as a developing inadequate designs, poor estimates etc. One of the
country is faced with a myriad of problems in project interview participants argued that:
delivery. The meteorology department is ill-equipped to “Sometimes contractors are made to go to site
predict weather events with a high degree of accuracy. without design drawings to begin with. This
Even with the most sophisticated technology available, situation leads to projected project duration
forecasts are still subject to wide variability and which were too low to begin with”.
questionable accuracy in the developed world. This assertion is in line with Agyeman et al., (2016) who
Therefore, this poses a challenge to PWDs in effective argue that within the Ghanaian road sector some
and efficient delivery on projects without time and cost contracts were signed without project designs. The
overruns. According to Muir (2005), construction designs were prepared after the contractor had moved to
managers remain at the mercy of the weather. It is site. This situation resulted in design errors as engineers
particularly wearisome to those engaged in heavy civil were under pressure to produce the designs. These errors
work, site development and activities that involve were not detected earlier resulting in project delays and
earthwork or other weather sensitive operations. costly reworks.
137
Influence of Processes by Political Heads respectively submitted their plans, rendering inadequate
Political influence is a major challenge to project logistics management.
delivery within PWDs. Political heads try to influence
the processes by bringing in party-faithful for the award Inadequate Human Resource to Carry Out
of contracts. This is a major challenge to project delivery Supervision
as most of them are not competent to carry out these Human resource is an integral part of the construction
works. On the other hand, when there is a change of processes, thus in every construction process the
government projects are sometimes repackaged and initiator, spear-header and driver is the human resource
given to the new contractors. In the worst-case scenario, involved. Successful project delivery among other
projects are sometimes abandoned all together for new factors is dependent on the human resources managing
projects. According to Asante (2014) “In many areas of the projects. Furthermore, effective human resource
business, success comes down to who you know rather management enables workers to increase the level of
than what you know. This is especially true of productivity in achieving the company’s aim and
government contracts where political affiliations can visions. In the construction industry, it remains a vital
make all the difference in securing a contract. Political ingredient when it comes to project delivery as effective
pressures influence contract decisions such as awarding and efficient supervision rides on their shoulders. The
many contracts to a particular contractor at a time; not success of a project invariably depends on the level of
based on competition and also awarding contracts supervision of the project or the managerial skills of the
without making budget allocations” project manager or the site supervisor (Zwikael, 2009).
MMDAs’ inability to supervise construction projects
Inadequate Logistics effectively has resulted in a lot of conflicts, variations
Logistic supply challenges in the government sectors and poor site co-ordination. These results stem from the
remain a common phenomenon in all MMDAs. The inadequate knowledge base of professionals who are
general assertion has been that government’s work meant to be in-charge of the construction processes.
generally delays. This inadequacy has the tendency to
affect project delivery, as any delay will influence the Conclusion
cost, time and quality. Effective logistics management is From the findings and the discussions of this study, it
one of the major factors for productivity increase, as was noted that there are a considerable number of
such the need for efficient project delivery challenges associated with construction project delivery
(Abdulmohsen & Janaka, 2011). Logistics therefore among professionals working in the PWDs within
should be planned and coordinated efficiently; however, MMDAs. Challenges that were found and ranked
its achievement in terms of the materials, tools and according to their levels of severity includes weather and
equipment is a difficult task (Jha & Iyer 2006). other environmental challenges, equipment and tools
Furthermore, an improvement in logistics systems in the shortage, labour shortage, poor site management,
project delivery will lessen the cost sustained in low material shortage, unrealistic time lines for project
productivity and reduce unnecessary cost associated delivery, contractors’ financial difficulties, inadequate
with transportation and handling of construction logistics, inefficient contractor selection methods and
materials (Shakantu et al., 2003). Inadequate logistics in procedure, lack of coordination and cooperation of other
the construction processes in various MMDAs have stakeholders. These were the most ranked challenges
brought most construction projects to a standstill. according to the data obtained from respondents and
Further indication in the industry shows that this trend discussed in the previous sections of this study. The
will continue, as policy makers are reluctant in planning following are recommended based on the findings of the
before any development project start. Public study:
Procurement Act 663 of 2003 section 21 stipulates that • There is the need for central government and
‘all procurement entities including MMDAs, shall other managers of the economy to put the needs
prepare a procurement plan to support its approved of PWDs high on the priority list and provide
programmes’ including contract packages. However, them better incentives and logistics for them to
according to the Public Procurement Authority (2010; be able to perform their roles effectively;
2011) 66 out of the 1000, and 32 out of 1,046 entities • In addition, there should be a policy that will
regulate when governmental agencies and
138
organisations should embark on infrastructural Al-Momani, A. H. (2000). Construction delay: a
projects; quantitative analysis. International Journal of
• Furthermore, PWDs must follow the Project Management, 18(1): 51-59.
procurement laws and rules for contractors, Ali, A.S., Rahmat, I. and Hassan, H. (2008). Involvement
consultants or service providers’ selection so as of key design participants in
to procure very suitably qualified personnel for refurbishment design process, Facilities, 26
projects. (9/10): 389-400.
• Issues such as resources, technological abilities, Ali, A.S., & Rahmat, I. (2010). The performance
finances and experience should be key measurement of construction projects managed
determinants of who shall be engaged to ensure by ISO-certified contractors in Malaysia.
slip-ups are kept to the minimum in project Journal of Retail & Leisure Property 9(1): 25–
delivery; and 35.
• Finally, it is also recommended that, further Amoah, P., Ahadzie, D.K. & Dansoh, A. (2011). The
studies should be done to establish the specific factors affecting construction performance in
roles of the professionals at the PWDs. This is Ghana (the perspective of small-scale building
because the researcher observed that there were contractors). The Ghana Surveyor 1: 41-49.
many professionals whose roles were not well Anonymous (2010). Dong Nai faces severe labour
defined. This will enhance and contribute to shortage after Lunar New Year. Bernama.
better performance by the PWDs in managing Retrieved from
projects and contribute to better construction http://www.bernama.com/bernama/v5/newswor
project delivery in the Ghanaian Construction ld. php?id=477821.
Industry. Arditi, D., & Pattanakitchamroon, T. (2008). Analysis
methods in time-based claims. J. Constr. Eng.
Acknowledgement Manag. 134 (4):242–252.
Sincere gratitude goes to Diatuo for helping with the http://dx.doi.org/10.1061/(ASCE)0733-
data collection during their master dissertation. 9364(2008)134:4(242)
Arshi S. F. & Sameh, M.E. (2005). Contributions of the
References Construction Project Team to Cost Overruns:
Abdulmohsen A., & Janaka R. (2011). Logistics The Contractors’ Perspective. In Construction
Management in the Construction Industry Proceedings Research Congress 2014(a), Construction in a
of the CIB W78-W102: International Conference – Global Network pp. 1528-1536. ASCE.
Sophia Antipolis, France, 26-28 October. Arshi, S.F. & Sameh, M.E. (2006). Significant factors
Adhikari, B. (2010). Integration of ISO 9001 and ISO causing delay in UAE construction industry.
14001: A Study of Common Elements Construction Management and Economics, 24:
unpublished MSc dissertation. University of 1167-1176.
Wisconsin-Stout, Menomonie, WI. Assaf. S. A., AL -Khalil, M and AL- Hazmi, M., 1995,
Agyeman S., Kwaku A. E., & Nsiah A. E. (2016). The Cause of delay in large building
effects of Design Information on reliability of construction projects, Journal of Management
progress and cost estimates of construction in Engineering 11(2): 45 -50.
projects: The case of two Civil Engineering Asante J. A. (2014). Financial Distress Related Causes
projects. American Journal of Civil of Project Delays In The Ghanaian
Engineering. 4(6): 326-336. doi: Construction Industry, A Thesis submitted to
10.11648/j.ajce.20160406.19 the Department Of Building Technology,
Aibinu A.A & Jagboro G.O., (2002). The effects of KNUST, Ghana.
construction delays on project delivery in Association for Project Management (APM) (2006).
Nigerian construction industry. International APM Body of Knowledge (5th ed.).
Journal of Project Management, 20(8): 593- Buckinghamshire: APM
599. Binici, H. (2007). Effect of crushed ceramic and basaltic
pumice as fine aggregates on concrete mortars
139
properties, Construction and Building (1998), Research at grassroots. A primer for the
Materials 21: 1191-1197. caring professions, Pretoria: Van Schaik.
Bank of Ghana, (2009), Ghana Shared Growth and Dunkelberger, L. (2009). How to Stop Losing Money on
Development Agenda (GSGDA), Accra, Ghana Inefficient Communication. Retrieved
Basheka, B.C. & Tumutegyereize, M. (2011). Measuring fromhttp://www.articlesbase.com/business-
the performance of contractors in government articles/how-to-stop-losing-money-on-
construction projects in developing countries: inefficient-communication-943893.html
Uganda’s context’ African Journal of Business Ellis, R.D., & Herbsman, Z.J. (1991). Cost-time bidding
Management. 6(32): 9210-9217. concept: an innovative approach,
Berg, B. (2001). Qualitative Research Methods for Transportation Research Record 1282,
Social Science. Boston: Allyn and Bacon. Washington D.C., 89-94.
Bouma, G., & Atkinson, G. (1995). A Handbook of Eden, C., Williams, T. and Ackermann, F., (2005).
Social Science Research: A Comprehensive Analysing project cost overruns comparing the
and Practical Guide for Students. Oxford “measured mile” analysis and system dynamics
University Press. modelling, International Journal of Project
Bower, D.M. (1989). Innovative Contracting Practice, Management. 23 (2): 135-13
Proc., ASCE, Highway Conf., ASCE, New Frimpong, Y., Oluwoye, J., Crawford, L. (2003). Causes
York, NY. of delay and cost overruns in construction of
Bruce, D. & Dulipovici, A. (2001). Results of CFIB groundwater projects in a developing country:
Surveys on the Shortage of Qualified Labour. Ghana as a case study. International Journal of
Retrieved from Project Management, 21 (5): 321-326.
http://www.cfib.ca/research/reports/ sql_e.pdf Gerskup, M. (2010). Design Errors, Construction
Burns, N., & Grove, S. (2001). The practice of nursing Mistakes and Building Failures. Paper presented
research: conduct, critique and untilization at the International Program of Project
(4th ed.). Philadeiphia: WB Saunders. Management Engineering System, Rome, Italy
Chang, C.L., Ogunlana, S. and Saeed, K. (1991). Gesuka, D., & Namusonge, G. (2013). Factors affecting
Construction Project Management: A system compliance of Public Procurement Regulations
dynamics approach. Paper presented at the 9th in Kenya: A case study of Butere District.
International Conference of the System International Journal of Human Resource and
Dynamics Society, Bangkok, Thailand. Procurement, 1(5): 1 - 14.
Coulter, C. & Kelley, C.A. (1992). Contractor Financial Gibbon, Donald L. (2006). How Roebling did it: Building
Management and Construction Productivity the world's first wire-rope suspension aqueduct
Improvement- Phase1 Vol.1; Contractor in 1840s Pittsburgh Journal of Minerals 58 (5):
Financial Management. Retrieved from 20-29.
http://www.dca.state.fl.us/fbc/committees Government of Ghana (1993) District assemblies act
/education/educaton_tac/ (1993). Act 462 of Parliament of Ghana.
bldg_research_files/research_reports/financial_ Gransberg, D. D., Koch, J. E., & Molenaar, K. R. (2006).
management/87.pdf. Preparing for design-build projects: a primer for
Dada M., Petruzzi N.C. & Schwarz L.B. (2007). A owners, engineers, and contractors. Reston, VA:
Newsvendor’s procurement problem when American Society of Civil Engineers.
suppliers are unreliable. Manufacturing & Hanim, A. (2010). Labour shortage affecting oil palm
Service Operations Management. 9(1): 9-32. plantations. The Star. Retrieved from
DOI: 10.1287/msom.1060.0128 http://biz.thestar.com.my/news/story.asp?file=/2
Dawson, C. (2007). A Practical Guide to Research 010/ 2/9/business/ 5637194&sec=business.
Methods: A User-friendly manual for Harrington H.J. and Voehl F. (2012). Applying TQM to
mastering research techniques and projects the construction industry, The TQM Journal. 24
(Third ed.). United Kingdom: How to Content. (4): 352-362.
De Vos, A. S., (1998). Combined quantitative and Hatush, Z. & Skitmore, M. (1998). Criteria for contractor
qualitative approach, IN: De Vos, A. S., (Ed) selection, Construction Management and
Economics, 15: 19–38.
140
Heggie, I. G. (1999). Commercially managed road funds: Laryea, S. A. (2010) Challenges and opportunities facing
managing roads like a business, not like a contractors in Ghana. In: West Africa Built
bureaucracy. Transportation, 26 (1): 87-111 Environment Research (WABER) Conference,
Herbsman Z. and Ellis R. (1992). Multi-parameter 2728 July 2010, Accra, Ghana, 27 & 28 July
bidding system: innovation in contract 2010, Accra, Ghana, pp. 215-226. Available at
administration, Journal of Construction http://centaur.reading.ac.uk/16282/
Engineering and Management 118: 142-150. Latham, M. (1994). ‘Constructing the Team HMSO’
Holt, G.D., Olomolaiye, P.O., Harris, F.C., (1994). London Local Government Act 462 of 1999
Factors influencing UK Construction clients' Macmillan English dictionary (2002),
choice of contractor, Building and Macmillan publication, London UK 4th edition.
Environment, 29(2): 241-248. Liu, Z. (2010). Strategic financial management in small
ISSER (2008). The state of the Ghanaian economy. and medium-sized enterprises. International
Institute of Statistical Social and Economic Journal of Business and Management 5(2):
Research, University of Ghana, Legon. 132-136.
Jha, K.N., & Iyer, K.C. (2006). Critical determinants of Majid M.Z. & McCaffer R. (1998). Factors of non-
project coordination, International Journal of excusable delays that influence contractors’
Project Management, 24 (4): 314-322. perception. Journal of Management in
Joyce, M. (2006). Building boom creates shortage of Engineering 14(3): 42-48.
Cranes. Construction Equipment Guide. Mansfield, N.R., Ugwu, O.O. & Doran, T. (1994). Causes
Retrieved from of delay and cost overruns in Nigerian
http://www.constructionequipmentguide.com/B construction projects. International Journal of
uilding-Boom-Creates-Shortage-of- Project Management 12(4): 254–60.
Cranes/8771/ Megha, D. & Rajiv, B., (2013). A methodology for
Kadir, M.R.A., Lee, W.P., Jaafar M.S., Sapuan S.M. & ranking of causes of delay for residential
Ali, A.A.A. (2005). Factors affecting construction projects in Indian Context,
construction labour productivity for Malaysian International Journal of Emerging Technology
residential projects. Structural Survey 23(1): 42- and Advanced Engineering, 3( 3): 396-404.
54. Merna, A. & Smith, N.J. (1990). Bid evaluation for UK
Kagioglou, M, Cooper, R. & Aouad, G. (2001). public sector construction contracts,
Performance Management in construction: a Procurement Inst Civil Engineers, Pt 1, 91-105.
conceptual framework. Construction Mochal T. (2003). Poor planning is project management
management and economics, 19(2): 85-95. mistake number one. Retrieved from
Kar S.S. & Ramalingam A. (2013). Is 30 the magic http://articles.techrepublic.com.com/5100-
number? Issues in sample size estimation, 10878_11-5034294.html
National Journal of Community Medicine. Moore, M.J. (1985). Selecting a contractor for fast-track
4(1): 75-179. projects, Pt II, Quantitative Evaluation Method’,
Kedikilwe, P. (2009, November 27). PHK attributes Plant Engineering, 39(18: 54-56.
dysfunctional solar panels to poor workmanship. Mwale, S. M. (1997). Media dissemination of road sector
Botswana Press Agency (BOPA). Retrieved reforms (English). Sub-Saharan Africa
from http://www.gov.bw/cgi- Transport Policy Program (SSATP) technical
bin/news.cgi?d=20091127&i= PHK_ attributes_ note; no. 4. Washington, DC: World Bank.
dysfunctional_solar_panels_to_poor_workmans http://documents.worldbank.org/curated/en/104
hip 921468741633551/Media-dissemination-of-
Lamptey, J.L. and Elle, L. (2000). Evaluation Ghana: road-sector-reforms
Joint Evaluation of the Road Sub-sector Muir B. (2005). Challenges Facing Today’s Construction
Programme 1996-2000 (online). Available Manager
from: http://www.ce.udel.edu/courses/CIEG%20486/
www2.jica.go.jp/ja/evaluation/pdf/2000_GH- Challenges%20Facing%20Today's%20CM.pf
P12_4f.pdf (Accessed 10 July 2013 Assessed 17/12/2016 at 15: GMT
141
Nguyen, V.U. (1985). Tender evaluation by Fuzzy strip. Master Thesis, The Islamic University of
Sets, Journal of Construction Engineering Gaza, Palestine.
and Management, 111 (3): 231-43. Shakantu, W., Tookey, J. & Bowen, P. (2003). The
Ofori, G. (1984). Improving the construction industry in hidden cost of transportation of construction
declining developing countries. Construction, materials: An overview. Journal of
Management and Economics, 2: 127-132. Engineering, Design and Technology. 1: 103-
Osei-Assibey D. (2005). Implementation of total quality 118.
management for District Assemblies common Shree, S. (2007). Equipment rentals hit construction
fund projects at the Atwima District Assembly- industry. Live Mint. Retrieved from
pre-contract stage. Unpublished MSc thesis. http://www.livemint.com/2007/09/20020703/
KNUST, Kumasi-Ghana. Equipment-rentals-hit-construc.htm
Owusu-Diatuo, K. (2016). A study of the roles of public Smith, H., (2011), Remedies for delay in construction
works departments of metropolitan, municipal contracts, Construction Dispute Avoidance
and district assemblies in the delivery of Newsletter number 33, November 2011
construction projects in selected regions in Sonmez M., Yang J.B. & Holt G.D. (2001). Addressing
Ghana. Master thesis, Department of Building the contractor selection problem using an
Technology and Management, Kwame Nkrumah evidential reasoning approach, Engineering,
University of Science and Technology, Kumasi, Construction and Architectural Management,
Ghana. 8(3): 198-210.
Polit, D.F., Hungler, B.P. (1999). Nursing Research: Sweis, G., Sweis, R., Hammad, A.A. & Shboul, A.
Principles and Methods 6th ed. Philadelphia: (2008). Delays in construction projects: The case
J.B. Lippincott. of Jordan. International Journal of Project
PPA Annual Report (2011). The Public Procurement Management 26(6): 665-674.
Authority: Improving efficiency and Taskforce report (2007). Improving the performance of
transparency in Public Procurement, Accra: the local construction industry. The Ghanaian
Public Procurement Authority. Times, November 12 (2013) No. 17056 ISSN:
Public Procurement Authority of Ghana (2010): E- 0855-1502.
Procurement Bulletin May – June. Thomas, P.I. (1991). The Contractor’s Field Guide. New
Royal Institute of Chartered Surveyors, (2013). RICS Jersey: Prentice Hall.
workshop on Project Management Perspectives Thornton, G. (2007). Surety Credit Survey for
on Planning, Cost Management and Construction Contractors: The Bond Producer’s
Performance, India Perspective. Retrieved from
Russell, J. S., Hancher, D. E., & Skibniewski, M. J. http://www.grantthornton.com/ static files.
(1992). Contractor prequalification data for Trendle, B. (2008). Skill and labour shortages -
construction owners, Construction definition, cause and implications. Department
Management & Economics, 10(2): 117–135. of Education, Training, and the Arts. Retrieved
Sambasivan, M. & Yau, S. W. (2007). Causes and effects from http://www.trainand
of delays in Malaysian construction industry. employ.qld.gov.au/resources/employers/pdf/wp
International Journal of Project Management, 54-skill-labour-shortages.pdf
25 (5): 517-526 Wang, F. (2010). China's exporters fret over labour
Sanvido, V. E., & Konchar, M. D. (1998). Project shortage. My Sinchew.
delivery systems: CM at risk, design-build, Retrieved from
design-bid-build. Austin, TX: The Construction http://www.mysinchew.com/node/36157
Industry Institute – The University of Texas at Wendle, J. (2008, July 15). Heavy trucks, construction
Austin. equipment, stolen in Russia Western models
Schexnayder, C. J., & Mayo, R. E. (2004). Construction safer because of advanced technology. The
management fundamentals. New York, NY: Moscow Times. Retrieved from
McGraw-Hill. http://www.truenorthperspective.com/July_08/J
Shaban, S. S. A. (2008). Factors affecting the uly_18/heavy_trucks_stolen.html
performance of construction projects in Gaza
142
Yang, J.B. and Ou, S.F. (2008). Using structural equation Government. Nam News Network. Retrieved
modeling to analyse relationships among key from http://news.brunei.fm/2010/03/10/poor-
causes of delay in construction. Canadian workmanship-on-some-zambian-schools-erode-
Journal of Civil Engineering 35: 321-332. peoples-confidence-in-gov
Zagorsky, J.L. (2007). Do you have to be smart to be
rich? The impact of IQ on wealth, income and Zwikael, O. (2009). Critical planning processes in
financial distress. Intelligence 35(5): 489-501. construction processes, Journal of Construction