You are on page 1of 2

GREATER HYDERABAD MUNICIPAL CORPORATION

OCCUPANCY CERTIFICATE
[Rule 26 of A.P Building Rules, 2012]

Application No. 2/C21/01899/2020-OC


Applicatoin Date: 20 February, 2018 Date : 18/11/2020
Proceedings No:/OC 2/C21/11807/2020 Occupancy Issued Date: 18 November, 2020
Building Permit No: 2/C12/03056/2018 Building Permit Date: 19 February, 2018
Building Application File No: 2/C12/16700/2017.
Building Commencement Notice submitted by the Applicant 20 February, 2018
Ref:
Building Completion Notice submitted by the Applicant 23 January, 2020

The Owners/Builder/Developer /Licensed Architect/Engineer / Structural Engineer have given the Building Completion
Notice that the building has been completed as per the specifications of Sanctioned Plans and it is declared that the
building conforms in all respects to the requirements of the building regulations contained under the statutory
provisions in the respective Municipal Act and Building Bye Laws/Rules issued by the Govt.
This is to certify that the building has been inspected and is declared fit for occupation.

NAME OF THE KANUGANTI MALLESH


A H.NO.8-2-269/464/A,ROAD NO.2,BANJARA HILLS,HYD
OWNER/Developer
B LOCATION OF THE PROPOSED SITE
1 Plot No. 2A AND 4A, H NO. 2. Sanctioned Layout No. / LRS No. -
2-50/16/G
3 Survey Number 41/12 AND 41/13 OF 4. Village NA
KHANAMET VILLAGE
5 Mandal SERILINGAMPALLY 6. District Rangareddy
7 Road/Street KHANAMET AND IZZATH 8. Zone SERILINGAMPALLY
NAGAR ZONE
9 Locality KHANAMET AND IZZATH
NAGAR
C DETAILS OF THE COMPLETED BUILDING
1 Building Permit / Proceedings No. 2/C12/03056/2018 Building Permit / 19 February, 2018
Proceedings Date

a Due date for completion of the building 19 February, 2024


2 b Date on which completion notice submitted 23 January, 2020
c Whether it is completed within the stipulated time YES
As per sanctioned Plan Road Widening Area(If any) Net Area
3 Site Area (m2)
409.44 0.00 409.44
Payment of Compounding fees calculated: 0/-
4

D BUILDING WISE DATA


Building Name Building Name KANUGANTI MALLESH
No. of Floors Cellar + Stilt Ground +Upper Floors
1 a As per Sanctioned Plan Stilt 4 Upper Floor
b As per Site Building Plan Stilt 4 Upper Floor
Use of the Building
2 a As per Sanctioned Plan Residential
b As per Site Building Plan Residential
Setbacks(m) Front Rear Side-1 Side-2
a As per Sanctioned Plan 3.00 2.50 2.50 2.50
3
b As per Site Building Plan 3.00 2.50 2.50 2.50
c Extent of deviation in % - - - -
Height (m)
4 As per Sanctioned Plan 11.95
As per Site Building Plan 11.95
E PLOT WISE DATA
Floor Area (m2)
1 a As per Sanctioned Plan 888.32
b As per Site Building Plan 888.32
i) Parking Area (m2) ii)Tot -lot area (m2)
2 a As per Sanctioned Plan 236.9 0
b As per Site Building Plan 236.9 0
RWH(Rain Water Harvesting )
3 As per Sanctioned Plan 0
As per Site Building Plan 5

To,
KANUGANTI MALLESH
H.NO.8-2-269/464/A,ROAD NO.2,BANJARA HILLS,HYD

Name : R SREENIVASA RAO


Designation : City Planner
Date : 18-Nov-2020 13: 20:09

TextToSearch

For COMMISSIONER,GHMC
Copy to:
1. The Addl. Commissioner (Fin.), GHMC.
2. The Zonal Commissioner, SERILINGAMPALLY ZONE, GHMC.
3. The Dy. Commissioner, Circle 21 CHANDA NAGAR, GHMC with a request for
assessment of PT / VLT upto date.
4. The Asst. City Planner, Circle 21 CHANDA NAGAR, GHMC.
5. The Sub-Registrar, ______________ with a request to release the mortgaged area.
6. The Addl. Commissioner (Revenue), GHMC with a request for assessment of
property tax at once from the date of issue of O.C.