Interim joint delay analysis-replacement of Utility line and process line segments at panna and

Tapti and B-193 platforms as on 02.05.2024

02/05/2
Analysis date
024
02/05/2
Date of NOA
022
Expected date of
02/08/2
project completion
023
as per NOA
No of days passed 731
Contractor-M/s Offshore Marin Tech, Mumbai
Days Days
attributa attributa
Start
End date ble to ble to remarks
date
M/s M/s
OMTECH ONGC
Contractor had applied for
Manifest for date of
Completion of pre- 25/08/20 07/09/2 traveling 03.08.2022. but
30 22
engineering survey 22 022 delay due to chopper and
accommodation issue at
platforms
Contractor had submitted
WPS and PQR very old of
year 2007, contractor had
Detailed design and 05/12/2 01/06/2
140 38 submitted incorrect
Engineering 022 023
documents, and hence
revision was reviewed many
times.
Project material M/s Omtech had supplied
05/07/2 04/11/2
delivery at Nhava 110 0 materials in various lots at
023 023
Pipe, valves Nhava.
Boat was not available,
Project material
25/11/2 25/11/2 hence, material was laid
delivery at Nhava 0 115
023 023 down at Nhava about 115
GRE material
days.
Delay due to non-availability
Manpower
10/07/2 26/04/2 of chopper and
mobilization for site 126 150
023 024 accommodation constraints
execution
at Tapti and Panna
New Sales Gas line 2-3 days Shutdown is
modification work required for modification
in Panna Platform job
Total days 406 325