Execution Schedule TR1 & TR2

S. No. TR 1 & TR 2 Day Time Remarks


SHUTDOWN ACTIVITIES
1 Positive isolation from Blending for TR 1 & TR 2 valves Day 1 1 hrs
2 Product Decanting (of the spools to be dismantled) Day 1 2 hrs This time may vary if any leakage found on the isolation of the valves
3 Existing Spool dismantling and temporary blinding & preperation for Hot work on the next day Day 1 5 hrs
4 New spools Installation Day 2 4 hrs
5 Hot work on three joints & QC inspection Day 2 5 hrs
6 Bolting & Torquing & Inspection of Bolting & Torquing Day 3 2 hrs
7 PSSR & SOF & Commissioning Day 3 7 hrs
Avanceon Resource List for LOBP TR 1 & TR 2 Shutdown
S/N Name Designation
1 Saqlain Haider CM
2 M Waqas Younis QA/QC Engineer
3 Asad Hussain HSSE Engineer
4 Haider Ali PTW H/SUP
5 M Ijaz PTW Holder
6 Shamshad Ali Fabricator
7 Sarfraz Ahmed Welder
8 M Imran Fitter
9 Hafeez ur Rehman Fitter
10 M Adeel Helper
11 Rashid Iqbal Painter
12 Sohbat Ali Fire Watcher
13 Jumshaid Ali Electrician
Avanceon Resource List for TR1 & TR2 LOBP Shutdown (Day-1)
S/N Name Designation Work Scope Estimated Time for Activity Completion
1 Team 1 Shamshad Fabricator
2 Team 1 Hafeez Fitter Isolation with the help of SHELL resources, Draining of the produt, De-Bolting of the flanges for
5 hours working in parallel
3 Team 1 Imran Fitter easy dismantling of the existing spools on Blending for TR 1 & TR 2 and dismantling the spools
4 Team 1 Haider Ali PTW H/SUP
5 Team 2 Sarfraz Ahmed Welder
Team 2 will be preparing for the next day activities to be
6 Team 2 M Adeel Helper 5 hours
performed on the Hot Work of Re-Fabrication of the TR 1 & TR 2 spools
7 Team 2 M Ijaz PTW Holder
8 Team 1 & 2 Sohbat Ali Fire watcher Working with the welding teams 1 & 2
9 Team 1 & 2 M Waqar Younis QA/QC Engineer Supervising the welding activities
10 Team 1 & 2 Asad Hussain HSSE Engineer Supervising all the activities
11 Team 1 & 2 Saqlain Haider CM Supervising all the activities

Avanceon Resource List for TR1 & TR2 LOBP Shutdown (Day-2)
S/N Name Designation Work Scope Estimated Time for Activity Completion
1 Team 1 Sarfraz Ahmed Welder
2 Team 1 Hafeez Fitter Team 1 working on two welding joints with 2.5 hours on
5 hours for Completion of two joints
3 Team 1 Adeel Helper each joint
4 Team 1 M Ijaz PTW H
5 Team 2 Shamshad Fabricator
6 Team 2 Imran Fitter
Team 2 working on prepration on Hydrotesting Activites 3 hours for Completion of two joints
7 Team 2 Rashid iqbal Painter/Helper
8 Team 2 Haider Ali PTW H/ SUP
9 Team 1 & 2 Sohbat Ali Fire watcher Working with the welding teams 1 & 2
10 Team 1 & 2 M Waqar Younis QA/QC Engineer Supervising the welding activities & performing DPT
11 Team 1 & 2 Asad Hussain HSSE Engineer Supervising all the activities
12 Team 1 & 2 Saqlain Haider CM Supervising all the activities

Avanceon Resource List for TR 1 & TR 2 LOBP Shutdown (Day-3)


S/N Name Designation Work Scope Estimated Time for Activity Completion
1 Team 1 Rashid Iqbal Painter
2 Team 1 Adeel Helper Finishing & Final coat of paint 2 hours
3 Team 1 Hafeez Fitter
4 Team 2 Shamshad Fabricator
5 Team 2 Imran Fitter Bolting & Torquing & final inspection 2 hours working simultaneously
6 Team 2 M Waqar Younis QA/QC Engineer
7 Team 1 & 2 Sohbat Ali Fire Watcher Working with teams 1 & 2
8 Team 1 & 2 Asad Hussain HSSE Engineer Supervising all the activities
9 Team 1 & 2 Saqlain Haider CM Supervising all the activities