S/N Name Designation Work Scope Estimated Time for Activity Completion
1 Team 1 Sarfraz Ahmed Welder
2 Team 1 Hafeez Fitter Team 1 working on two welding joints with 2.5 hours on
5 hours for Completion of two joints
3 Team 1 Adeel Helper each joint
4 Team 1 M Ijaz PTW H
5 Team 2 Shamshad Fabricator
6 Team 2 Imran Fitter
Team 2 working on prepration on Hydrotesting Activites 3 hours for Completion of two joints
7 Team 2 Rashid iqbal Painter/Helper
8 Team 2 Haider Ali PTW H/ SUP
9 Team 1 & 2 Sohbat Ali Fire watcher Working with the welding teams 1 & 2
10 Team 1 & 2 M Waqar Younis QA/QC Engineer Supervising the welding activities & performing DPT
11 Team 1 & 2 Asad Hussain HSSE Engineer Supervising all the activities
12 Team 1 & 2 Saqlain Haider CM Supervising all the activities