Percentage of Co

2021
Contract Price Rp 8,500,000,000

Less : Estimated Cost


(-/-) Cost to Date Rp 3,355,275,000
(-/-) Estimated Cost to Complete Rp 5,359,725,000
Estimated Total Cost Rp 8,715,000,000

Estimated Total Gross Profit (Loss) -Rp 215,000,000


% of Completed 38.50%

Revenue Recognized Rp 3,272,500,000


(-/-) Cost Incurred Rp 3,487,500,000
Gross Profit (Loss) -Rp 215,000,000
Cost Recovery
Revenue Recognized Rp 3,355,275,000
(-/-) Cost Incurred Rp 3,355,275,000
Gross Profit (Loss) Rp -

Jurnal
2021
Cost of Construction :
Construction in Progress Rp 3,355,275,000
Material, Cash, Payable, Etc.

Progress Billing :
Accounts Receivable Rp 3,825,000,000
Billing on Construction in Progress

Cash Collections :
Cash Rp 1,912,500,000
Accounts Receivable

Accounts Receivable
Tahun 2022 Rp 3,825,000,000
Tahun 2023 Rp 4,462,500,000
Tahun 2024 Rp 2,794,375,000

Revenue Recognition :
Construction Expense
Construction in Progress
Revenue on Long-Term Contract

Construction Expense Rp 3,487,500,000


Construction in Progress
Revenue on Long-Term Contract

Completion Contract
Billing on Construction in Progress
Construction in Progress
Percentage of Completion
2022 2023
Rp 8,500,000,000 Rp 8,500,000,000

Rp 6,984,775,000 Rp 8,587,500,000 Rumus 1 = Cari Estimated Total Cost = Cost to Date + Estimated
Rp 1,365,225,000 Rp - Rumus 2 = Estimated Total Gross Profit (Loss) = Contract Price
Rp 8,350,000,000 Rp 8,587,500,000 Rumus 3 = % of Completed = Cost to Date / Estimated Total Co

Rp 150,000,000 -Rp 87,500,000 (- + -)


83.65% 100%

Rp 3,837,750,000 Rp 1,389,750,000 Rumus 4 = Revenue Recognized = Contract Price x Percentage o


Rp 3,472,750,000 Rp 1,627,250,000 Intermezzo = Lab atau Dosen caranya sama, kalau di tahun pert
Rp 365,000,000 -Rp 237,500,000 gross profit langsung dipindahin dari estimated total gross profi
Cost Recovery Method
Rp 3,629,500,000 Rp 1,515,225,000 Tapiiii kalau tahun pertama positif, cost incurrednya dipindahin
Rp 3,629,500,000 Rp 1,602,725,000
Rp - -Rp 87,500,000

Jurnal
2021 2022 2023

Rp 3,629,500,000 Rp 1,602,725,000
Rp 3,355,275,000 Rp 3,629,500,000

Rp 2,550,000,000 Rp 2,125,000,000
Rp 3,825,000,000 Rp 2,550,000,000

Rp 3,793,125,000 Rp 2,794,375,000
Rp 1,912,500,000 Rp 3,793,125,000

Accounts Receivable Sisa


Rp 1,912,500,000 Rp 1,912,500,000
Rp 3,793,125,000 Rp 669,375,000
Rp 2,794,375,000 Rp -

Rp 3,472,750,000
Rp 365,000,000
Rp 3,837,750,000

Rp 1,389,750,000
-Rp 215,000,000
Rp 3,272,500,000

Rp 8,500,000,000
Intermezzo :
st to Date + Estimated Cost to Complete Kalau +++
oss) = Contract Price - Estimated Total Cost Kalau -++
e / Estimated Total Cost Kalau +--
Kalau -+-

t Price x Percentage of Completion


ma, kalau di tahun pertama minus Rp 87,500,000
mated total gross profit (Loss) Rp 237,500,000
Rp 150,000,000
ncurrednya dipindahin dari cost to date x - 215.000.000 = 150.000.000

2023

Rp 1,602,725,000

Rp 2,125,000,000

Rp 2,794,375,000
-Rp 237,500,000
Rp 1,627,250,000

Rp 8,500,000,000
Percentage of C
2022
Contract Price Rp 9,000,000,000

Less : Estimated Cost


(-/-) Cost to Date Rp 2,760,000,000
(-/-) Estimated Cost to Complete Rp 6,440,000,000
Estimated Total Cost Rp 9,200,000,000

Estimated Total Gross Profit (Loss) -Rp 200,000,000


% of Completed 30.00%

Revenue Recognized Rp 2,700,000,000


(-/-) Cost Incurred Rp 2,900,000,000
Gross Profit (Loss) -Rp 200,000,000
Cost Reco
Revenue Recognized Rp 2,760,000,000
(-/-) Cost Incurred Rp 2,760,000,000
Gross Profit (Loss) Rp -

Ju
2021
Cost of Construction :
Construction in Progress Rp 2,760,000,000
Material, Cash, Payable, Etc.

Progress Billing :
Accounts Receivable Rp 2,700,000,000
Billing on Construction in Progress

Cash Collections :
Cash Rp 1,080,000,000
Accounts Receivable

Accounts Receivable
Tahun 2022 Rp 2,700,000,000
Tahun 2023 Rp 5,220,000,000
Tahun 2024 Rp 2,961,000,000

Revenue Recognition :
Construction Expense
Construction in Progress
Revenue on Long-Term Contract

Construction Expense Rp 2,900,000,000


Construction in Progress
Revenue on Long-Term Contract

Completion Contract
Billing on Construction in Progress
Construction in Progress
Percentage of Completion Method
2023 2024
Rp 9,000,000,000 Rp 9,000,000,000

Rp 6,090,000,000 Rp 9,020,000,000
Rp 2,610,000,000 -
Rp 8,700,000,000 Rp 9,020,000,000

Rp 300,000,000 -Rp 20,000,000


70.00% 100%

Rp 3,600,000,000 Rp 2,700,000,000
Rp 3,100,000,000 Rp 3,020,000,000
Rp 500,000,000 -Rp 320,000,000
Cost Recovery Method
Rp 3,330,000,000 Rp 2,910,000,000
Rp 3,330,000,000 Rp 2,930,000,000
Rp - -Rp 20,000,000

Jurnal
2021 2022

Rp 3,330,000,000
Rp 2,760,000,000 Rp 3,330,000,000

Rp 3,600,000,000
Rp 2,700,000,000 Rp 3,600,000,000

Rp 4,959,000,000
Rp 1,080,000,000 Rp 4,959,000,000

Accounts Receivable Sisa


Rp 1,080,000,000 Rp 1,620,000,000
Rp 4,959,000,000 Rp 261,000,000
Rp 2,961,000,000 Rp -

Rp 3,100,000,000
Rp 500,000,000
Rp 3,600,000,000
-Rp 200,000,000
Rp 2,700,000,000
2023

Rp 2,930,000,000
Rp 2,930,000,000

Rp 2,700,000,000
Rp 2,700,000,000

Rp 2,961,000,000
Rp 2,961,000,000

Rp 2,700,000,000
-Rp 320,000,000
Rp 3,020,000,000

Rp 9,000,000,000
Rp 9,000,000,000
Percentage of Completion
2021
Contract Price Rp 8,500,000,000

Less : Estimated Cost


(-/-) Cost to Date Rp 3,355,275,000
(-/-) Estimated Cost to Complete Rp 5,359,725,000
Estimated Total Cost Rp 8,715,000,000

Estimated Total Gross Profit (Loss) -Rp 215,000,000


% of Completed 38.50%

Revenue Recognized Rp 3,272,500,000


(-/-) Cost Incurred Rp 3,487,500,000
Gross Profit (Loss) -Rp 215,000,000
Cost Recovery Meth
Revenue Recognized Rp 3,355,275,000
(-/-) Cost Incurred Rp 3,355,275,000
Gross Profit (Loss) Rp -

Jurnal
2021
Cost of Construction :
Construction in Progress Rp 3,355,275,000
Material, Cash, Payable, Etc.

Progress Billing :
Accounts Receivable Rp 4,250,000,000
Billing on Construction in Progress

Cash Collections :
Cash Rp 1,700,000,000
Accounts Receivable

Accounts Receivable
Tahun 2022 Rp 4,250,000,000
Tahun 2023 Rp 4,675,000,000
Tahun 2024 Rp 2,358,750,000

Revenue Recognition :
Construction Expense
Construction in Progress
Revenue on Long-Term Contract

Construction Expense Rp 3,487,500,000


Construction in Progress
Revenue on Long-Term Contract

Completion Contract
Billing on Construction in Progress
Construction in Progress
Percentage of Completion method
2022 2023
Rp 8,500,000,000 Rp 8,500,000,000

Rp 6,984,775,000 Rp 8,587,500,000
Rp 1,365,225,000 -
Rp 8,350,000,000 Rp 8,587,500,000

Rp 150,000,000 -Rp 87,500,000


83.65% 100%

Rp 3,837,750,000 Rp 1,389,750,000
Rp 3,472,750,000 Rp 1,627,250,000
Rp 365,000,000 -Rp 237,500,000
Cost Recovery Method
Rp 3,629,500,000 Rp 1,515,225,000
Rp 3,629,500,000 Rp 1,602,725,000
Rp - -Rp 87,500,000

Jurnal
2021 2022 2023

Rp 3,629,500,000 Rp 1,602,725,000
Rp 3,355,275,000 Rp 3,629,500,000

Rp 2,125,000,000 Rp 2,125,000,000
Rp 4,250,000,000 Rp 2,125,000,000

Rp 4,441,250,000 Rp 2,335,162,500
Rp 1,700,000,000 Rp 4,441,250,000

Accounts Receivable Sisa


Rp 1,700,000,000 Rp 2,550,000,000
Rp 4,441,250,000 Rp 233,750,000
Rp 2,335,162,500 Rp 23,587,500

Rp 3,472,750,000
Rp 365,000,000
Rp 3,837,750,000

Rp 1,389,750,000
-Rp 215,000,000
Rp 3,272,500,000

Rp 8,500,000,000
2023

Rp 1,602,725,000

Rp 2,125,000,000

Rp 2,335,162,500
-Rp 237,500,000
Rp 1,627,250,000

Rp 8,500,000,000
Percentage of Compl
2020
Contract Price Rp 9,000,000,000

Less : Estimated Cost


(-/-) Cost to Date Rp 4,207,500,000
(-/-) Estimated Cost to Complete Rp 5,142,500,000
Estimated Total Cost Rp 9,350,000,000

Estimated Total Gross Profit (Loss) -Rp 350,000,000


% of Completed 45.00%

Revenue Recognized Rp 4,050,000,000


(-/-) Cost Incurred Rp 4,400,000,000
Gross Profit (Loss) -Rp 350,000,000
Cost Recovery
Revenue Recognized Rp 4,207,500,000
(-/-) Cost Incurred Rp 4,207,500,000
Gross Profit (Loss) Rp -

Jurnal
2021
Cost of Construction :
Construction in Progress Rp 4,207,500,000
Material, Cash, Payable, Etc.

Progress Billing :
Accounts Receivable Rp 4,050,000,000
Billing on Construction in Progress

Cash Collections :
Cash Rp 2,025,000,000
Accounts Receivable

Accounts Receivable
Tahun 2022 Rp 4,050,000,000
Tahun 2023 Rp 5,805,000,000
Tahun 2024 Rp 4,072,500,000

Revenue Recognition :
Construction Expense
Construction in Progress
Revenue on Long-Term Contract

Construction Expense Rp 4,400,000,000


Construction in Progress
Revenue on Long-Term Contract

Completion Contract
Billing on Construction in Progress
Construction in Progress
Percentage of Completion Method
2021 2022
Rp 9,000,000,000 Rp 9,000,000,000

Rp 7,384,125,000 Rp 8,500,000,000
Rp 1,103,375,000 -
Rp 8,487,500,000 Rp 8,500,000,000

Rp 512,500,000 Rp 500,000,000
87.00% 100%

Rp 3,780,000,000 Rp 1,170,000,000
Rp 2,917,500,000 Rp 1,182,500,000
Rp 862,500,000 -Rp 12,500,000
Cost Recovery Method
Rp 3,176,625,000 Rp 1,615,875,000
Rp 3,176,625,000 Rp 1,115,875,000
Rp - Rp 500,000,000

Jurnal
2021 2022 2023

Rp 3,176,625,000 Rp 1,115,875,000
Rp 4,207,500,000 Rp 3,176,625,000

Rp 3,780,000,000 Rp 1,170,000,000
Rp 4,050,000,000 Rp 3,780,000,000

Rp 2,902,500,000 Rp 4,072,500,000
Rp 2,025,000,000 Rp 2,902,500,000

Accounts Receivable Sisa


Rp 2,025,000,000 Rp 2,025,000,000
Rp 2,902,500,000 Rp 2,902,500,000
Rp 4,072,500,000 Rp -

Rp 2,917,500,000
Rp 862,500,000
Rp 3,780,000,000

Rp 1,170,000,000
-Rp 350,000,000
Rp 4,050,000,000

Rp 9,000,000,000
2023

Rp 1,115,875,000

Rp 1,170,000,000

Rp 4,072,500,000
-Rp 12,500,000
Rp 1,182,500,000

Rp 9,000,000,000
Percentage of Compl
2021
Contract Price Rp 2,500,000

Less : Estimated Cost


(-/-) Cost to Date Rp 1,200,000
(-/-) Estimated Cost to Complete Rp 1,200,000
Estimated Total Cost Rp 2,400,000

Estimated Total Gross Profit (Loss) Rp 100,000


% of Completed 50.00%

Revenue Recognized Rp 1,250,000


(-/-) Cost Incurred Rp 1,200,000
Gross Profit (Loss) Rp 50,000
Cost Recovery
Revenue Recognized Rp 1,200,000
(-/-) Cost Incurred Rp 1,200,000
Gross Profit (Loss)

Jurnal
2021
Cost of Construction :
Construction in Progress Rp 1,200,000
Material, Cash, Payable, Etc.

Progress Billing :
Accounts Receivable Rp 1,250,000
Billing on Construction in Progress

Cash Collections :
Cash Rp 1,250,000
Accounts Receivable

Accounts Receivable
Tahun 2022 Rp 1,250,000
Tahun 2023 Rp 625,000
Tahun 2024 Rp 625,000

Revenue Recognition :
Construction Expense Rp 1,250,000
Construction in Progress
Revenue on Long-Term Contract

Construction Expense
Construction in Progress
Revenue on Long-Term Contract

Completion Contract
Billing on Construction in Progress
Construction in Progress
Percentage of Completion Method
2022 2023
Rp 2,500,000 Rp 2,500,000

Rp 2,000,000 Rp 2,300,000
Rp 600,000 Rp -
Rp 2,600,000 Rp 2,300,000

-Rp 100,000 Rp 200,000


76.92% 100%

Rp 673,077 Rp 576,923
Rp 823,077 Rp 276,923
-Rp 150,000 Rp 300,000
Cost Recovery Method
Rp 800,000 Rp 500,000
Rp 800,000 Rp 300,000
Rp 200,000

Jurnal
2021 2022 2023

Rp 800,000 Rp 300,000
Rp 1,200,000 Rp 800,000

Rp 625,000 Rp 625,000
Rp 1,250,000 Rp 625,000

Rp 625,000 Rp 625,000
Rp 1,250,000 Rp 625,000

Accounts Receivable Sisa


Rp 1,250,000 Rp -
Rp 625,000 Rp -
Rp 625,000 Rp -

Rp 576,923
Rp 50,000
Rp 1,200,000

Rp 673,077
-Rp 150,000
Rp 823,077

Rp 2,500,000
2023

Rp 300,000

Rp 625,000

Rp 625,000

Rp 276,923
Rp 300,000
Rp 2,500,000