Professional Documents
Culture Documents
How To Calculate Daily Target Using SAM Vs Cycle Time
How To Calculate Daily Target Using SAM Vs Cycle Time
Qestion#2. He said that 3.40 minute already added 20% allowance to the
byPrasanta Sarkar -November 21, 2019
operators with unavoidable downtime in the work floor.
An industrial engineer wrote me the following email with questions and asked
for the clarifications. In this article, I will share my comments. We will try to
So as above all description, I need your help to explain the difference
understand the difference in calculating the daily production target of a sewing
between these two methods and introduce some article which you may
line using the standard time (SAM) and average operation cycle time.
already be written. I am waiting to read your reply explanation in the nearest
I have read and understood well to your explanation about how to calculate future.
SAM of a garment.
Thanks for following OCS tutorials and writing an email to me with questions
Formula:
and asking for clarification.
Standard Time = Basic Time + various Allowance (around 20%)
where Basic time = Observe Time x Performance Rating.
My comment to your first question
Using the above formula, we get the Standard Time. So, we can set daily In your calculation, the daily production target 911 units per day is correct. We
production target based on Standard Time. say this target is at 100% of the SAM.
My example:
52 workers, 10 hours/day, SAM =34.25 Reducing daily target to accommodate 20% downtime is not necessary. Whether
Line Target per day = (52x10x60)/34.25 = 911pcs to apply downtime in target calculation or not depends on the production
environment. I would suggest, your target for the production should be given
My understanding, 911pcs/day is at 100% target of the standard time that we @100 per cent of SAM. You calculate line efficiency based on 100% of the
need to calculate it into 80% which to cover around 20% downtime in the standard time. Check the average line efficiency.
production floor.
In case your average line efficiency is below 80% then you can consider setting
So, ((52x10x60)/34.25)x80% = 729 pieces/day up the daily production target at a reduced rate. If your line efficiency is more
than 80% and they can easily reach up to 80% of the given SAM, than no need
Question#1. Do you agree with this calculation? to add downtime.
But my boss's understanding is that I have added around 20% allowance to Many factories still work at 35-50% efficiency level of the standard time. (Not
normal time (BT) and again 20% to Standard Time when setting the daily sure how they establish the garment standard time). To them, it is necessary to
target that is too much allowance to operators. plan daily production target at a reduced rate, like a target at 60% or 70 %.
So, he discussed with me to calculate by this following method: My comment to the second question
Standard time = Average Cycle Time +20% (for all kinds of operation) The following statement is incorrect.
Standard time = Average Cycle Time +20% (for all kinds of operation).
In this case, you are not estimating the standard time of the operation. So, you How to Calculate the Rate of
can’t compare the time standard and cycle time for target calculation. Standard
time and cycle time of operation are two different measures. Normally, the cycle Individual Sewing Operations?
time is greater than the standard time. But in some situations, operation cycle
time can lesser than the standard time. The reason, in the cycle time, we don’t byPrasanta Sarkar -December 13, 2020
add allowances. We record operators’ cycle time when operators don’t take a
break or no downtime happen.
If you want to set up the line target based on average cycle time – there is no Question:
issue. I would say, your target would near to the actual production data when to
calculate target from average cycle time.
My doubt is how to calculate the rate for individual operation (ex: Shoulder attach,
When you establish average cycle time for an operation or a style, adding 20%
Neck rib attach, Sleeve attach, etc.) for any style and what are the factors to consider
downtime for calculating daily target is acceptable.
during calculating that price. My manager simply told me that the rate is 0.40 Rupees
for this operation, 0.90 rupees for that operation. But I do not know how to calculate
Difference between the two methods, you get cycle time after you start the
production. So, on the first few days, you would not get the accurate cycle time this one. Kindly give me the solution for this with some examples. Your guide will be
for the current operations. It is not a good idea for setting daily production target useful to me.
observing the operation cycle time from day 1. You cannot set a line target in
advance.
You should also remember that the rating factor that is applied in calculating Answer:
basic time is not downtime. That is a levelling factor for standardising the
minutes recorded through time study. The allowances added to the basic time to
establish SAM are like machine allowances, contingency allowance, personal
I had the same experience when I was working in a garment export house. We were
fatigue allowances. Combined all these allowances 20% is acceptable. Though
making knitted items and used piece-rate operators (provided by manpower
you know different allowances are given for different machines and different
contractors) for stitching garments. Our factory manager used to set up prices for each
working elements.
operation after analyzing the operations in a garment. To decide operation rates, he
used his experience of how many garments an operator can make in a day, rates
provided by the other factories for similar operations in that place.
Now, I know the scientific ways of estimating operation rate. I will share the procedure
of calculating the operation rate and share articles for further reading.
When you calculate the piece rate for the garment operations, you need to consider
these things -
Operation SAM
minimum daily wages and
the operator's capacity. I hope you will find this article helpful.
Form the daily wages, we calculate the hourly rate and per minute rate of the sewing
operators and other workers. From the operator’s capacity, we can estimate how Line Balancing using Capacity Study
many pieces an operator can make. Then calculate possible operator earning and the
hourly rate. Data and Work Sharing Among
You also need operation SAM (standard minute) for deriving the actual cost of an Sewing Operators (Question
operation. The scientific way of calculating an operation rate is as the following.
answered)
Operation Rate = (Operation SAM x Rate per minute)
byPrasanta Sarkar -October 15, 2020
Let us say, SAM of an operation is 2 minutes and the hourly rate is Rs. 60 (Rate per A few days back, I received an email from one of the OCS readers. He asked a couple of
minute is Re 1). Therefore, the operation rate for this operation is 2x1=Rs. 2 questions to clarify the calculation used in Line Balancing and shared a document. I am
sharing the line balancing sheet and capacity study data. He found the guide from
If an operator makes 25 pieces per hour, his daily production will be 200 pieces. His another website, but calculation methods are not explained in detail – so he wants
daily earning will be Rs (200 x 2) = Rs. 400. some clarification from me.
On the source I got the document, it says for the line to be balanced, operator # 7
should work for 50 minutes and should help operator # 8 for 10 minutes. Now my
question is:
Question-1: Why operator # 7 helps operator # 8 for 10 minutes? Why not for 8
minutes, why not for 12 minutes, etc.?
Answer:
You can allocate an employee for a second process#8 as many minutes as needed to
meet the hourly target. Though in the example it is suggested for 10 minutes for
balancing. Actually, the engineer who made this document has calculated balancing
with 7 minutes allocation for the second process (#8). 7 minutes is enough for making
201 pieces on the operation#8
Question#2: If operator# 7 works for 50 minutes on his main operation, his output
(balanced capacity) will be 200 but inside the table, the calculation says 212. How that
is calculated?
Answer:
As I said in the above question, the employee worked 7 minutes for the process#8. Ans
Image-1: Line balancing using capacity study data she worked 53 minutes for process#7. Calculate using 53 minutes of work on
operation#7, you will get 212 pieces of production.
Style Changeover Time is the time between the last piece output of the previous style
from the last machine of a line and the first piece output of the next style from the last
Apart from these general causes, there are some other factors also which we see in External elements are those elements that are independent of your sewing line. For
our day to day life. I am trying to list a few of them. example, you need a special machine for next style. You can arrange that machine
before the line change over starts.
Prolonged machine setting time
Non availability of tools for initial machine setting Internal elements are those elements for which you need to stop the line, or you have
Sudden plan change to wait till the last piece is out. For example, you want to set that new special machine
Supervisor sample not ready in your line for next style. This activity can’t be performed till the old style is out of
Initial quality setting takes a longer time line.
Old style creates a blockage
Operator training is given at the time of Batch Setting
Now our approach will be converting internal activity into external activity and
No measure of operator COT performance
reducing time duration of both activities.
Parallel Batch Settings making it difficult to control
Non availability of specialized machines
Cut part feeding not available Here is another example, mechanic is setting that special machine after placing that
machine in line. Now you say that this setting can be done before start of changeover
outside the line. Here you have converted internal activity into external activity. Now
All these factors are quite reasonable (part of the production process). At first sight, there can be another condition where mechanic does not have a proper toolbox and
you will not find them troublesome, but after in-depth process study, they will show for each tool, he is going back to the tool room. In this case, time consumption will be
their true nature. With proper break-up one can find hidden wastes in these activities. higher.
Tis is an example sheet and more detailed study should be done. The best way to do
that is to record all the activity done by changeover team (IE, Mechanic & Supervisor)
and alo making video simultaneously. Once all activities are reordered in study sheet, Low COT has numerous benefits, the most eminent and visible one is that it increases
we will get a changeover time data of a particular line. After this, we need to analyze Available Time thus increasing floor OEE.
that data for internal and external activities.
For this, we need to do a detailed study of each activity. We have to segregate the into
Standard Minute Value (SMV):
value added, non-value added and essential non-value added activities. Once we
remove non-value adding activity from our process/line change over time will further
Definition, Calculation and Use
reduce. byPrasanta Sarkar -September 21, 2019
There is no more secret in Standard Minutes Value (SMV) calculation. Now,
The above discussion can be summarized as SMV is a common language between fashion brands and manufacturers for
discussions on cost, time and floor capacity. Most of the garment manufacturing
Observe the current style changeover process; identify all the activities as companies calculate the SMV of their garments. Industrial engineers take
internal or external set-ups. responsibility for measuring standard time for the given garment samples. Let
Separate the external and internal set-up and note them down. me define SMV, the most critical factor, widely used and much talked about
Convert internal set-up actions into external ones. term in the garment industry.
Further, optimize internal and external set-ups to improve overall
effectiveness of style changeover process.
Definition of Standard Minute Value
Standard Minute is the time value arrived at for a task based on the average
Conclusion rate of output which qualified workers will naturally achieve without over
exertion provided that they know and adhere to the specified method and
Some key points in consideration before style changeover: provided that they are motivated to apply themselves to their work.
- This definition is written in the ILO work study book.
1. The new style needs to be allocated to that line only where there is a
minimum style variation. Operation cycle time or average time, taken by an operator completing an
2. The batch Supervisor and QC along with the COT team should be there at pre- operation is not the Standard minute value. SMV is the given time that should be
production meetings to judge critical operations and operator availability. taken to complete operation if she works at 100% performance level. SMV of
3. New Style Requirement (NSR) to be made and discussed. It will ensure the the same operation will be different if the working condition is changed – like
availability of trims, machines, skilled operators, cutting before the line setting. operator using a different machine, the operator sews a bigger component, an
4. Supervisors/IE need to analyze the skill-matrix prior to the style changeover; operator using attachment and work-aids when sewing a garment. Most
the concerned Floor Manager must ensure the availability of operators along
importantly, movement and motions involved in performing a task.
with the skill.
5. The spare machines should be allotted before the start of the process to
stimulate the offline batch setting. SMV calculation method
6. The mechanic needs to ensure the availability of templates, guides,
attachments with settings. You can calculate garment SMV using SMV calculation software or through
time study method. Standard minute value calculation method using Time Study
is explained in this article with an example. First, you measure operation wise Standard Minute Value = (Basic minute + Bundle allowances + machine
SMV. Then SMV of all operations in style are combined to calculate total SMV allowance + personal fatigue allowances).
of a garment. Normally, when SMV is measured through time study method, the operation
cycle is broken down into operation elements and observed time is captured
In time study, you capture the observed time of the selected operation. You rate element-wise. Machine allowances are added only to machine elements.
operator performance in the work. You use standard allowances for different
types of machines, bundle allowance and contingency allowances. Also, note that bundle allowance is distributed across the pieces in a bundle. If
bundle allowance is 60 seconds for a 10 pieces bundle, bundle allowance would
Steps for calculating SMV be added as 6 seconds to the basic time.
1. Record observed time. Example: Let’s say you are making a blouse. You observed an operation and
record its cycle time. Following the above steps let’s derive SMV of an
Following the Time Study procedure, you conduct Time Study for a selected operation.
operator and on the selected operation.
Observe Time = 2 Minutes
2. Convert observed time into Basic time using this formula. Rating of the operator = 90%
Basic Time = (2 Minutes x 90%) = 1.8 Minutes [Why multiply Rating
The observed time for the same operation done by two different operators might factor?]
be different. Our objective is to establish the standard for the selected operation. Machine allowance =10%
So, for the levelling of the observed time, it is multiplied by the rating factor. Other Allowance = 10%
The new time is called as basic time. Total allowance to add = 10% + 10% = 20%
Basic Minute =(Observed time in minute x Performance Rating) Allowance in minutes = 1.8 x 20% = 0.36 Minutes
3. Know the applicable allowances.
Calculated SMV = (1.8 Minutes + 0.36 Minutes) = 2.16 minutes
When an operator will be working there would be changes of a machine
breakdown, they may need to change the needle, replace empty bobbin, change In the operation bulletin, after measuring operation SMV, hourly and daily
thread spool, may need of threading needle. There will be personal needs and production capacity is calculated. For further study on the capacity calculation,
fatigue allowance. For all these allowances, some amount of time will be machine requirement calculation, check this post.
consumed from the operator’s standard time. To estimate more practical SMV
allowances are added to the basic time. The Second method
The second method of establishing SMV is using PMTS software. For this
Normally, in progressive bundle system, garment components reached to an method, you need to know different motion codes and you need to study real-life
operator in bundle form. For every bundle, the operator spends a few minutes in operator hand and body movement. You need to learn how to operate software
opening the bundle and tying it. So, you need to add bundle allowance as well for calculating sewing operation SMV. Once you learn that you can measure
where applicable. SMV for any kind of operations whether it is cutting, pressing, sewing, folding
etc. (Essential thing you must have the software).
4. Calculate Standard minute
Add machine allowance, bundle allowance and other allowances to the basic
time to calculate standard minute.
2. SMV is the main data in the operation bulletin. Based on the operation
SAM machine requirement and manpower requirement is calculated.
Further based on the machine requirement machine layout and initial line
balancing is done.
3. SMV is used for labour costing for garment production
4. SMV is used for performance benchmarking
5. SMV is used for efficiency calculation
6. SMV is used in Payroll calculation in piece rate payment. Earning is
equal to garment produced x operation SMV x rate per minute
7. When performance incentive is provided to the operators, SMV is
essential for calculating individual operator efficiency
8. Preparing operators’ performance-based skill matrix
9. Who is responsible for calculating garment SMV in a garment factory?
SMV calculation Software Definition of different terms used in SMV calculation process
If you want accurate SMV of garment (and other sewn product), you need a Rating factor: Rating is a subjective comparison of any condition or activity to
software to calculate the SMV. Most of the SMV calculation software uses a benchmark, based upon our experience. While the mechanics of time study
motion codes and predetermined times. Few of the well-known SMV calculation record the time a task did take, applying a rating will determine the time a task
software included should take. Read the concept of performance rating.
GSDCost Cycle Time: It the time actually taken by an operator at the work. Cycle time is
SewEasy measured from the time stamp of pick-up of the garment component to the next
ProSMV pick-up time stamp of an operation cycle. The starting point of an operation
TimeSSD cycle can be chosen by the engineer. Normally the cycle time value is higher
than the standard time.
Application of SMV (SAM value)
Observed time: Here observed time is the same as the cycle time. The time
I have listed a few of the application of garment SMV. recorded as it was and operation cycle time calculated.
Or conversely
In our cycle time record, the allowances, like machine breakdown, threading needle
1 second = 27.78 TMU and bobbin change, bundle opening and tieing the bundle, personal needs, are not
1 minute = 1667 TMU included. Combining all add 20% allowance on the average cycle time.
1 hour = 100,000 TMU
In your example, the operation cycle time is 30 seconds. After adding 20 allowances,
the calculated cycle will be 36 seconds. This is derived from (30 seconds x 1.20)= 36
seconds
Application of TMU in the apparel industry
Therefore, estimated production quantity per hour = (3600/36 ) = 100 pieces
For establishing the standard time (SAM) of sewing operations by using the PMTS
system, motion codes are applied for each motion (movements) and each motion
carries time in TMU. In Standard time calculation, initially, standard time is measured
and calculated in TMU. Later the total TMU is converted into minutes.
How to Calculate Garment
How to Calculate Pieces per Hour Production Cost from SMV and
from Cycle Time? Monthly Salary Data
byPrasanta Sarkar -August 03, 2019
byPrasanta Sarkar -August 04, 2019
Some of factories calculate CM (cost of manufacturing) of a garment by the machine
SMV multiply with earnings per minute. And this earning per minute calculate based
on monthly factory cost divided by monthly produced minute. Is this logical? ... by
Emon What is Standing Time in the
Yes, many factories in the apparel industry use the method that you mentioned in your Garment Manufacturing Process
question for calculating the direct cost of production. From garment SMV and minute
cost data, direct labour cost is calculated. byPrasanta Sarkar -June 20, 2019
This is logical, provided the standard minutes (SMV) of operations are correct and cost
per minute is derived from a reasonable monthly salary amount (maybe minimum In the garment manufacturing, Standard Time (SAM/SMV) is a common term. But
wages/higher than minimum wages). Further, you need to incorporate line efficiency when someone asked me about the 'Standing Time', I thought he might be using the
for deriving the labour cost. The monthly salary of direct manpower may vary wrong word for standard time. This term 'Standing Time' was new to me.
depending on the employee's skill and grading. You also need to adjust the combined
daily earning of an operator, to make it a satisfactory amount. I asked him whether he is talking about Standard Time of a garment. If not where he
found this term.
When you talk about production cost, either it is an estimated production cost or the
actual garment production cost. In the subject line, production cost means the He confirmed that it is standing time. This term is used in Fast React planning system.
estimated production cost before you make the style. The actual production cost per But he doesn't know the meaning of 'Standing Time'.
day and the actual cost incurred in a style can be calculated from the real employee
attendance data (number of manpower involved in making the style) and their daily I checked with a Fastreact system user and got the answer.
wages.
As per the Fastreact user, standing time means waiting time between two processes.
On the other hand, when we need to estimate production cost (direct labour cost) for Like, waiting time in between embroidery and stitching process. In production
the whole order, it can not be calculated directly as we don't know how many scheduling and event planning, waiting time in between two processes are
manpower will actually involve making the order. Salary will be different for different considered.
employees. Most importantly, we can't guess how many garments they will produce
daily and how many days will be consumed to complete the order. Though the 'Standing Time' is a term used by a software system, it is good to know the
meaning and use of this term.
In such a situation, the best ay of estimating garment production cost is following
standard time, cost per minute and benchmark efficiency.
What is SMV (Standard Minute
Labor cost per garment = (Garment SAM x Labor cost per minute)/ Line Efficiency%
Production cost for the whole order = (Labour cost per garment x Order Quantity) Value)
Let's see one example. One team made 400 shirts of 23 minutes SMV in a day. Another
byPrasanta Sarkar -June 14, 2019
team made 350 shirts of 23 minutes SMV in a day. If the same number of manpower
(50 manpower in each team) involved in two teams who are getting a similar salary, The full form of SMV is Standard Minute Value. The work study team and industrial
cost per garment would be different for these two teams. As a result, the cost of the engineers in the garment industry, use 'SMV' term to define the standard time of an
whole order will be different in these two cases. individual garment operation as well as for the whole garment SMV. The SAM is
another term used for standard time.
In such cases, you need to consider line efficiency for calculating production cost.
What is SMV
Considering the SMV as the standard time required for making each garment, factory earning, wrong employee performance, wrong factory performance, and wrong
plans manpower and machine requirement for the garment orders. planning.
The daily production target of a line is calculated from the SMV. Overall Efficiency Vs On-Standard
Efficiency
Individual employee performance, as well as the production line's performance, is
byPrasanta Sarkar -March 21, 2019
measured based on SMV produced by the employee and by the line.
You may know the definition of Efficiency. You may know how to calculate the
efficiency of a production line or an individual sewing operator. But do you
For example, say SMV of a shirt is 22 minutes (including stitching and non-stitching
know -
operations), that means the established standard time for the shirt is 22 minute (given
time). What is On-standard efficiency and overall efficiency?
How to calculate on-standard efficiency and overall efficiency?
The Garment SMV is used for labour costing for garment production. SMV is used for What are the differences between these two efficiency terms?
performance benchmarking as well.
These are the new terms to many industrial engineers and production people. If
You see the importance of the SMV in the garment manufacturing industry. these terms are also new to you, read this post.
SMV is an estimated time. In practice, the average time taken by the operator does not When the On-Standard Efficiency and Overall Efficiency are
match most of the time. measured
How to calculate on-standard efficiency, off-standard efficiency Total shift hours (8 hours) is broken down as follows
and overall Efficiency
(A) Total hours worked on standard work = 7 hours (total shift hours – lost time)
To measure on-standard efficiency, off-standard efficiency and overall
Efficiency we need to collect the following data (B) Standard minutes produced while working on standard work = 300*1 minute
= 5 hours
(A) Total hours worked on the standard work (C) Total hours worked on off-standard work = no off-standard work performed
(B) Standard minutes produced while working on standard work (D) Standard minutes produced while working on the off-standard work = No
(C) Total hours worked on off-standard work off-standard minute production
(D) Standard minutes produced while working on the off-standard work (E) Total lost time in hours = 1 hour
(E) Total lost time in hours
(F) During lost-time, practically, no garment will be produced, so no produced On-standard Efficiency = (5*100/7) =71.43%
minute for lost time hours.
Overall Efficiency = (5*100)/(7+1) = (500/8)%=62.5%
The standard produced minute is calculated as operation SAM x Number of
pieces stitched. Conclusion:
On-standard Efficiency (%) = (Total on-standard minute produced You see efficiency loss in the line efficiency. Some of the reasons for efficiency
*100)/(Total on-standard hours worked * 60) = (B*100)/60*A) loss in a plant are unmeasured lost-time, off-standard work done by sewing
operators. When on-standard efficiency is measured, you can get an accurate
Off-standard Efficiency (%)= (Total off-standard minute produced operator performance (efficiency data). For preparing the operator skill matrix
*100)/(Total off-standard hours worked * 60) = (D*100)/60*C) factory should consider their on-standard efficiency instead of considering
overall efficiency.
Overall Efficiency (%) = (B+D)*100/(60*(A+C+E))
The challenges in measuring on-standard efficiency are not having the right tool
for capturing lost time data. With a print format, you can capture lost-time data
but that would be limited, not the true lost-time hours.
In the new year, you may be starting some new improvement projects for the
betterment of the work and factory performance. Before you start a new
improvement project and become busy with the new assignments, it would be a good
idea summarising last year's data and review last year's performance.
It is time to look back and review the last year's performance. How much you have 2. Production Volume and Shipped quantity
achieved in the previous year. What all KPIs are not meet your goal. In which all KPIs
you have beaten the last year's benchmark performance. You can analyse the You earn revenue when you ship garments. More you ship, more you earn. Review
available data as many as you want. the monthly production volume and shipped quantity. Prepare a trend chart month by
month. Here is an example of 100 machines factory that makes knits tops, t-shirts.
A factory must review these 5 KPIs.
3. Cost per garment
To earn more profit, it is necessary to reduce garment production cost. With the
The last year's factory performance trends would help you in planning this year's goal.
continuous increase in wages, consumables and machine maintenance cost, how the
Let's prepare the last 12 months monthly performance trend and last 5 years Yearly
production cost changing month by month. Is your production cost per garment is
Performance Trend on the below KPIs
meeting the buyer's target cost?
1. Line Efficiency Trends
Assuming your factory is making a similar product range year after year. If not, still
measuring cost per garment and analysing its trend is a good way of understanding the
Calculate monthly line efficiency and draw a trend chart on a spreadsheet with 12
factory's performance growth.
months of efficiency data. Efficiency is a common performance measure and I assume
you calculate line efficiency and you have the monthly efficiency data. If not, you can
calculate it now. Check this post to learn the line efficiency calculation method. 4. Cost per SAM (production cost per standard minute)
Cost per SAM is the labour cost per minute. Calculate actual labour cost per standard
Here is an example.
minute. Cost per SAM may increase due to many reasons. It may be increased due to
the rise in minimum labour wages. Cost per SAM may higher in case line performance are working in production must know how to estimate daily production in a
goes down due to some other reasons. garment factory.
Similarly, if SAM of style reduces at that also you can expect higher output. It is required to calculate monetary saving after introducing new SMV
You must measure all your improvement works. It will help one get
Factors that hamper production: noticed by managers.
You must keep the record for the previous method and the new method
Anyone of the followings can reduce production of the assembly line. So to get with respective operation SMV. (if the improvement is brought by
estimated output, you have to take on the following areas. improving method).
You can consider this improvement as a continuous improvement project
Machine breakdown (Kaizen)
Imbalance line (WIP control) Easier to keep track of operation wise and product wise SMV
No feeding of cuttings improvement.
Quality problems
Low operator performance Calculate SMV Improvement Percentage
Operator absenteeism
Let's measure SMV improvement in your factory. This formula is used for
Some of these are non-productive time. calculating SMV improvement.
SMV improvement percentage = (Old SMV - New SMV)*100/Old SMV
Measure SMV Improvement Example: Let's say old SMV of a sewing operation was 0.85 minute. After
improving it, you got a new SMV 0.75 minute. Therefore, SMV improvement
Percentage will be
= ((0.85- 0.75)/0.85)*100
= 11.76%
byPrasanta Sarkar -December 29, 2018
In the garment industry, the industrial engineering department does a lot of If you are not yet measuring it, you can initiate it and in turn, you can measure
improvement work in a factory, like improving productivity, reducing cost per how much money is saved by reducing the operation/garment SAM.
garment, setting up SOPs. The improvements they do, are measured through Work in progress (WIP) includes the set at large of unfinished items for products
various KPIs. But many engineers are not yet measuring some important KPIs. in a production process. These items are not yet completed but either just being
One such KPI is SMV improvement percentage. The SMV reduction or SMV stitched or waiting in a queue for further processing or in a buffer storage. WIP
improvement percentage is also considered a KPI for the engineering is in-process inventory.
department.
In garment manufacturing, WIP is normally measured in a number of garments.
In this post, I will show you the importance of measuring SMV improvement The end-of-day WIP of a process is the number of total pieces loaded today in
and the formula for calculating this KPI. the process plus the previous day’s WIP minus total pieces come out from that
process. In a garment factory, production WIP is measured every day by the
Importance of measuring SMV improvement production department or the industrial engineering department.
While industrial engineers aim for the production cost reduction, it is often done
by reducing the standard time of the operation. The SMV can be reduced by
Why measure WIP? machine productivity productivity are measured for a production line for the selected
products.
Maintaining a minimum level of WIP at each sewing workstation is necessary to
have continuous work for workers. But neither a high WIP nor the low WIP is SAM productivity and production productivity both are new terminologies. Though this
good for a production line. is the first time I come across these productivity terms, I can relate and explain how
these productivity can be calculated.
Here are a few reasons for which factory need to production WIP.
Let me first define these two terms and then I will compare.
To know whether a line (or workstation) has high WIP level or low WIP
level compared to the targeted/planned WIP SAM productivity
If a line supervisor doesn’t look at operations where WIP is piling up, the
production line will become imbalance soon. SAM productivity can be defined as total SAM produced by per operator per shift. SAM
Allowing unnecessary WIP in the line would increase the inventory productivity is measuring the manufacturing productivity of a production line or a
requirement as well as financial involvement in a period.
factory in terms of standard time produced per operator.
To keep the production line running, it is necessary to feed the
production lines and workstations continuously. If the workstation
For an example, let's say in a line 40 operators make 400 shirts in a day (8 hours shift
doesn’t get enough work, it will be on the idle situation and no
production would be generated from that workstation. In such cases, a time) and SAM of that shirt is 25 minutes. SAM productivity will be (25*400)/40
line would loss potential output from that workstation. minutes= 250 minutes per operator per shift
High WIP is the main source of many issues like quality issues, low
productivity, and unnecessary delay in production. Production productivity
By measuring the WIP, the factory can plan for their next day’s work Production productivity is similar to the labor productivity and machine productivity. In
requirement. these cases, productivity is presented in production quantity.
Difference between SAM Productivity garments in a 8 hours shift. Total labor count is 40+5 = 45. Labor productivity of that
line will be (400/ (40+5)) = 8.89 pieces per labor per shift.
and Production Productivity Machine productivity: Number of garment produced by machine per shift.
byPrasanta Sarkar -July 11, 2018 Let's say, in a line 40 machine is used to make 400 garments in a 8 hours shift. Machine
productivity of that line will be (400/ 40) = 10 pieces per labor per shift.
What is the difference between SAM Productivity and Production Productivity? Asked
by an OCS reader.
Difference between SAM productivity and Production
In the apparel industry, manufacturing productivity is measured in terms of labor Productivity.
productivity, machine productivity and value productivity. The labor productivity and
machine productivity is presented as number of garment produced (quantity) per Here I have listed few points to compare these two productivity terms.
labor per shift and per machine per shift respectively. Normally labor productivity and
#1. SAM productivity is presented in standard minutes produced irrespective of In apparel manufacturing industry, most garment manufacturers use the
product SAM. On the other hand the production productivity is presented as number assembly line for making clothes and garments. In the assembly line, a number
of garment produced. of sewing machines (including different types of sewing machines and non-
sewing equipment) are placed in a line according to the process sequence
requirement. Garment bundles are loaded at one end of the line and moved from
#2. Through SAM productivity you can easily compare performance of two lines or two one workstation to another, and finally stitched garments come out from the
factories, irrespective of the apparel product types, style. line.
Do you use these measures in your garment factory? Have you seen people using
these two types of productivity?
I would be great learning if you can share your understanding on the SAM productivity
and Production productivity.
When you prepare the line layout, you will see following cases and you will
define a workflow on the line layout.
You may need to assign more than one workstation for the same
operation,
You may need to use same machine (workstation) for more than one
operations
You may need to load bundles or garment component in multiple
workstations
Followings are some of the primary benefit and application of line layout
The line layout helps line supervisors to set the line for a new order in
the least time.
From the layout, you will get the exact requirement of machines and
equipment. Production team can be better prepared
Style changeover time can be reduced by preparing a detailed line layout
and doing line set-up based on the line layout
For new plant set-up, designing the line layout is an essential part.
Looking at line layout, overhead wiring, air connection, installation of
ironing tables, QC tables and fixture installed.
In case a factory produces same product for all the time, still they need to
change the line layout depending on the product design. In such cases factory
may need minimum change of sewing machines and workstation.
When a new style is loaded to a line, sewing operators (machinists) take time to Also see: 9 Ways to Increase Sewing Operator Efficiency
reach their maximum speed (or normal speed). A sewing operator takes higher
time to stitch a garment when she starts working on a new style. After doing the Use of Learning Curve:
same task for many times, the time taken to stitch the garment or an operation is
reduced. It may be due to new operation (job), a different machine with different
settings and guide or a different kind material need to handle. Following are few reasons, a learning curve is made by industrial engineers.
Individual operators learning curve is normally prepared at the operator training Industrial engineers use learning curve data to calculate daily production
stage. But you can even prepare learning curve for each and every sewing target in the initial production days of the new style.
operator working in the production line. I have seen some factories prepare all In production planning and target setting, the learning curve is used to
operators learning curve. plan day wise production target.
A learning curve is also used to derive lead time of an order.
Normally a learning curve is prepared for the production line. This is easier to For the incentive calculation in the learning period, the learning curve is
develop Line wise learning curve when you don't have individual employee used. If you have incentive scheme and you want to give incentive to
efficiency data. See the learning curve of a typical production and typical your workers based on their efficiency level, learning curve helps to
garment style. design target efficiency (eligibility level to earn incentive) for the initial
days.
In the next post, I will share how to develop a learning curve for your production
line. Keep reading and keep sharing the knowledge.
Cycle Time:
Cycle time is defined as the time duration from the starting point of a job to the
starting point of the next job. This time is established from the observation data
of an operator while working at a certain pace.
Basic Time:
Basic time = (Observed time X Performance Rating)/100 Chart: This shows how standard time is made up
Or
Basic Time = (Standard Time - Allowances) Conclusion: For a specific task following conclusion can be drawn
In Basic Time no allowances are included. Observed Time may be greater or lower than Basic Time.
Basic Time is always lower than Standard Time
Standard Time: To set Standard Time of a job you must add allowances to Basic Time
(normal time)
Standard time is the time allowed to an operator to carry out the specified task
under the specified condition and defined level of performance. This is a
standard definition for standard time. What is the Meaning of SAM in
Some additional time is added to the basic time to arrive standard time of a task.
In practice, none can work throughout the day without taking rest. Operators Garment Industry?
need time for relaxation from fatigue. Various allowances are relaxation
allowance, contingency allowance (like machine breakdown) and bundle byPrasanta Sarkar -December 13, 2013
allowance (for PBS system). The meaning of Standard allowed minute (SAM) is explained here. As defined
in the book Introduction to Work Study, ILO, Standard minute is defined as the
Standard Time = Basic Time + Allowances following.
The basic constituents of standard time are shown in the following chart. This SAM is the time value arrived at for a task based on the average rate of output
chart shows how standard time is made up of the observed time and basic time which qualified workers will naturally achieve without overexertion provided
of a job. (Click on the image to enlarge) that they know and adhere to the specified method and provided that they are
motivated to apply themselves to their work.
Here SAM stands for Standard Allowed Minute. same operation, and expressed as a percentage. The general formula for calculating
efficiency is:
In garment industry, specifically in production SAM is used for measuring work.
In the factory work study department (also know as Industrial Engineering
department) measure and calculate SAM for sewing operation using standard (Work output /work input) X 100
calculation method. Read 'How to calculate SAM of the garment'
SAM is used many ways directly and indirectly. Some of those are If you consider work input and output in 'minute', the efficiency formula would be like
this - the ratio of total standard minutes produced and total minutes spent on the
Factory as well as individual operator performance is measured by work.
means of SAM
Labor cost and associated cost ratios are measured by SAM I am working in the apparel manufacturing sector. In a garment manufacturing factory,
Operators payroll and incentive amount is calculated based on earned we calculate line efficiency every day to check and measure their line performance.
SAM We use the following formula for calculating efficiency.
Latest production scheduling systems like line balancing system and
performance measuring systems use SAM as one of the primary
parameters.
To derive most appropriate SAM value of a garment, factories use PTS based
systems. Standard Time is also derived from time study method.
Also Read: How to calculate hourly production target? In this article, I will show you
In the garment manufacturing sector, production efficiency data is calculated in many 1. How to calculate hourly production target for an individual operation
forms. Like, Individual employee efficiency for the day, individual efficiency per hour, 2. How to calculate hourly production target for a production line.
line efficiency, and factory efficiency.
Hourly production target calculation is a part of an operation bulletin preparation
In all cases, the efficiency calculation formula remains the same. The total minutes and daily production report. In an OB production target is calculated for each
produced and total minutes worked need to be calculated based on where the formula operations.
is used.
Following formula is used to calculate hourly target.
Calculate individual operator efficiency Hourly production target = (60 / Operation SAM)
Let's find the efficiency of a stitching machine operator.
An hour is equal to 60 minutes. Divide the 60 by the operation SAM. The end
result of this calculation tells you the number of pieces can be produced per
hour, which is the hourly production target for the selected operation.
The machine operator is worked 8 hours and he has produced 400 garments in the
given job. The standard time of the job was 30 seconds. Note that to calculate
Let’s take an example. SAM of an operation is 0.5 minute. Hourly production
produced minutes you need to know the standard minute of the job (operation). target would be
=(60/0.50) =120 pieces
He has produced minutes (400 X 30)/60 = 200 minutes. He has worked 480 minutes. Note: This target is calculated at 100% efficiency. In case you want to plan
hourly production target at particular percentage, multiply the above by
So, his efficiency is (200/480)*100 = 41.67 % individual operator efficiency.
Let’s say skill level of that operator is 80% efficiency, in that case production
target would be
(60/0.50)*80% =120*80% =96 pieces Estimated time to do each operation for one unit
One sample operation breakdown of Polo shirt is shown in the below
The information you need for calculating hourly production target are image.
On the other hand for calculating hourly production target for a production line
use the following formula
Hourly Production Target of a line =((60 * No. of operators working in a line *
Line efficiency %) /Garment SAM)
If you need to calculate daily production target of a line, just multiply the hourly
line target by shift hours.
Sewing and non-sewing operations Sample operation breakdown sheet of a Polo Shirt
Name of the machines to use for doing the specific operations
prepare OB sheet,
The garment operation bulletin is also called as operation breakdown. An measure key performance indicators (KPIs)
operation bulletin includes more information than the operation breakdown. prepare daily reports on factory performance, and
line performance in terms of productivity and efficiency.
I have posted an article how to make operation bulletin. In that post the method
of making operation bulletin is explained. They also measure line capacity as well as individual operator capacity in the
given hours. All these are essential for production management, balancing work
and planning production and manpower.
Application of operation breakdown
As these are common measures in apparel production, most of the factories use
The operation breakdown of a garment is done to understand garment excel templates preparing such reports and calculations where the excel template
construction - like stitch class and seam types used in making the sample are pre-filled with formula. We just follow the report template. We don’t need to
garment. calculate every time we make a report. So, many times we are not clear about
To make a operation bulletin the first step is doing operation breakdown how to calculate a particular measure.
of the sample garment.
To make the list of sewing machines and equipment for the style. Let’s discuss 10 basic production measures and formula used calculating those
To set set a line for new style operation breakdown is followed by line measures.
supervisors and engineers.
While estimating thread consumption per garment for given style, 1. Hourly production target
operation breakdown id referred for operation list and machine types.
byPrasanta Sarkar -November 29, 2016 Hourly production target = (60 / Operation SAM)
You might be using formula for calculating standard time or labour productivity Note: This target is calculated at 100% efficiency. In case you want to plan
or labour cost per minute. There are many such common measures we need to hourly production target at certain percentage, multiply the above by line
calculate everyday for preparing daily reports and measuring performance in efficiency / individual operator efficiency based on your need.
various parameters. In this article we will try to understand how the basic
performance measures are calculated and formulas that are used for calculating In the table-1 few examples are shown for calculating hourly production target
those measures. at 100% efficiency.
In the apparel industry, industrial engineers, production managers and Table-1: Examples of hourly target calculation
production planners measure the factory performance on daily basis by Sl.
following standard formula for each measure. You might be already using such No. Operation SAM Hourly Target (60/SAM)
formulas for calculating your factory performance. For example, industrial 1 operation-1 0.78 76.92
engineers 2 operation-2 0.85 70.59
3 operation-3 1.2 50.00
4 operation-4 0.9 66.67 Total minutes produced = Total units produced X operation SAM
Machine productivity is measured as production per machine per shift day. See
the following example (Table-5).
Line capacity per day= {(No. of machine x daily work hours x 60)*(1 –
absenteeism %)} x Efficiency % (capacity in minutes)
Production capacity (in pieces) = Available minutes / Garment SAM
Chart-1: This chart shows how standard time is made up. Source: Introduction to Table-6: Example of production capacity calculation
work study by ILO No. No. of Minutes/Day Line Absenteeism Capacity Garm
Machines (Daily Efficiency % available SAM
working (in
8. Machine utilization percentage Hrs. X 60) minutes)
Line 1 30 480 60% 10% 7776.00
Machines and equipment are primary resources of garment manufacturing unit. Line 2 28 480 72% 8% 8902.66
These resources must be utilized as much as possible to improvise factory Line 3 32 480 65% 9% 9085.44
performance. But due to work unavailability or less work, some machines (like Line 4 32 480 55% 10% 7603.20
specialized machines) are partially utilized by the factory. In such case, same
machine is shared for multiple lines. Machine utilization is calculated using
below formula. Conclusion:
Various Positions 9. Responsible for providing training to team members on Method study, Time study
and improve their competencies.
byPrasanta Sarkar -March 17, 2016
It is important to know your role to accomplish the maximum task and get motivated 10. Review Daily MIS reports
to work. Do you have this in your factory for your department and for your profile?
Note: Operation bulletins (OB), thread consumption are not done by the IE manager in
An industrial engineer of a garment export house based in Bangalore shared job their factory, all OBs are done at the head office.
responsibility of IE department followed by the company. See what they do to manage
and control garment production and improve the production process. Just in case, if
you don’t have defined roles and responsibilities for IE department in your factory you 2. Junior IE's Roles and Responsibilities:
can follow this.
Buyer pays you CM on total quantity you shipped. Therefore every piece you
1. Headcount operators and provide to Junior IE to fix day’s target. Follow up on produce, you are virtually earning dollar equivalent to CM.
critical operations and do a time study.
In this method CM earned is calculated as total line output (pieces produced by
2. Hourly productions follow up and update hourly production to supervisor/IE. the line) multiply by CM cost per garment.
Maintain logbook on loading status and production status.
If you want calculate CM achieved by your factory then find total production
done by the factory and multiply it by CM cost.
How to Calculate CM Produced by a Calculation method:
Line in Dollar?
1. From cost sheet collect garment CM (CM is fixed for an order). This
byPrasanta Sarkar -May 05, 2016
data is normally available with merchandiser. In case cost of
An OCS reader asked me this question: Sometimes people ask me "how much
manufacturing is in local currency, convert it into dollar using currency
CM (in USD) is achieved today in your factory". It seems confusing to me.
ratio.
Would you please tell me how can I calculate CM in daily basis? And why I
2. Count total piece produced by a line
need to calculate every day?
On daily basis you calculate line output. And you have the SAM for the style(s)
Now calculate CM achieved (in dollar)= Production quantity X Garment CM (in
you are making in the line. With these data you calculate how much SAM is
dollar)
produced by the line.
SAM Produced by line = (Line output * Style SAM) The second method:
2. Calculate total standard minute (SAM) produced by the line. Again there are Difference between Productivity and
two different ways to calculate Standard minute produced–
Efficiency
Standard minutes produced = Line output * garment SAM
byPrasanta Sarkar -September 20, 2016
3. Calculate total hours worked by all workers (those are included in the SAM)
6. Excess paid (Make up amount) = (Dollars paid - Dollars earned) First let me define these two terms.
Productivity is the ratio of output (products or services) and input (labour, machine,
On daily basis calculate total standard minutes produced by a line and total
man-hours). Productivity can be measured as labour productivity, machine
garments produced by the line. I hope you do this every day. So whenever you
are asked this question, just follow one of the above methods. productivity, and value productivity for a production line or of a whole factory. Let’s
consider you are measuring labour productivity of a production line. Labour
To make the calculation simple follow first method. Multiply CM cost (Dollar productivity is defined as output (in pieces) per labour (direct +indirect) in a given time
per garment) to the pieces produced by a line to calculate CM achieved by your frame. Example of labour productivity of a Shirt line is 10 pieces per day per labour on
line. 8 hour shift.
Efficiency is the ratio of total minutes produced and total minutes worked by an
Also Read: Garment CM cost estimation using SAM individual operator, or a line. Efficiency is expressed in percentage. For example,
stitching line efficiency of a typical stitching line is 56%.
Why you need this figure daily? Formula use to calculate productivity and efficiency
Productivity formula:
In a line, every day you are spending money (dollars) as workers’ salary. You
should know how much dollars you are earning on daily basis against the dollar Productivity = Output / Input
you are paying to your workers. You also need to check the progress if earning Labour productivity = (Total garments produced / Number of labours involved) in
is increasing or not after loading a new style in a line? That is why you need to given time frame
Machine productivity = (Total garments produced / total number of machine utilized) lines. But how will you compare if these two lines are making two different products?
And have different number of manpower. With productivity data you couldn’t do that.
Efficiency Formula: In such situation line efficiency in the only measure to compare production
Efficiency = (Total SAH produced / Total hours worked)*100 performance of these two lines.
We can write the same formula as produced work in minutes A case is shown in the following for calculating labour productivity and line efficiency.
A line of 35 operators and 5 helpers produced 400 pieces in day of 8 hours shift.
Efficiency = (Total Minute produced / (Total hours worked*60))*100
Garment SAM is 25 minutes. Considering helpers SAM is included in garment SAM.
To calculate line efficiency you must have garment SAM (standard minutes) for your
products. On the other hand you don’t need SAM to calculate labour productivity.
Factories those don’t have industrial engineering department and don’t calculate
garment SAM are not in position to measure accurate line efficiency. For them
productivity measure is one that they can follow.