Professional Documents
Culture Documents
Free Float vs Total Float (network diagram)
Free Float vs Total Float (network diagram)
https://pmstudycircle.com/total-float-versus-free-float/
Total floats and free floats are important in developing a network diagram. A
better understanding of both will help you draw one and analyze a critical
path.
Total Float
Total float is also known as “float.”
Total float is how long an activity can be delayed without putting off the
project completion date.
On a critical path, the total float is zero. Total float is often known as the slack.
You can calculate it by subtracting the Early Start date of the activity from its
Late Start Date.
Or
You can get it by subtracting the activity’s Early Finish date from its Late Finish
date.
Free Float
Free float is how long an activity can be delayed without delaying the Early
Start of its successor.
You can calculate the free float by subtracting the Early Finish Date of the
activity from the Early Start Date of the next activity.
Free Float = ES of next Activity – EF of Current Activity
Please note that if two activities converge into a single activity, only one of
these two activities may have a free float.
Both conventions are correct, and you are free to choose. I decided to refer to
the first day of the project as “one.”
The formula used to calculate free float differs for these two situations;
however, the result is the same.
I’m assuming that you know how to draw a network diagram, identify the
critical path, and calculate the Early Start, Early Finish, Late Start, and Late
Finish dates of activities.
If you struggle with these calculations, I have a blog post on the critical path
method. Read that post, and then come back.
Example: 1
In the above network diagram, you can see two paths:
Path A->B->D is the critical path because it has the longest duration.
There are two methods to calculate the total float. For the first, subtract the
duration of the non-critical path from the critical path.
For the second method, find the total float for any activity by subtracting the
Early Start date from the Late Start date (LS – ES) or subtracting the Early
Finish date from the Late Finish date (LF – EF) for any activity.
First Method
Total float = duration of the critical path – duration of the non-critical path
= 20 – 12
=8
Second Method
On path A->C->D, Activity A, and D are on the critical path; therefore, they will
not have a total float. Only Activity C can.
We can calculate the total float by using either the finish dates or start dates. I
will show you both ways.
First, we will go with the Late Finish and Early Finish dates:
= 15 – 7
=8
= 14 – 6
=8
The durations are the same, so both formulas will give you the same result.
= 16 – 7 – 1
=8
Example: 2
Find which activities can have a free float for the below-given network
diagram. Calculate it and the total float, considering the duration in days.
We know that:
In the above diagram, Activity G can have the free float because Activity D and
G converge.
Activity D will not have a free float because its successor, Activity E, starts the
day after the completion of Activity D.
=6–3–1
=2
= 18 – 3
= 15
You can see here that the free float for Activity G is two days, and the total
float is 15 days.
Summary
Total float and free float are important concepts in schedule management.
Total float is commonly referred to as float. Activities on a non-critical path will
have a total float. When two activities converge, one of them will have a free
float.
Please note that you have to find the total float if you are asked to calculate
the float for any activity on the exam.
How do you use total float and free float in your project? Please share your
thoughts in the comments section.