Professional Documents
Culture Documents
Fresh X - CH CH Hyper Supermarkets Specification - May 2019-Cvm
Fresh X - CH CH Hyper Supermarkets Specification - May 2019-Cvm
FRESH “X”
CHECKERS & CHECKERS HYPER
&
SUPERMARKETS
SPECIFICATION
FRESH “X” CHECKERS
2019
EDITION
GENERAL CONTENTS
(REVISION – A)
SECTION DESCRIPTION PAGE
1 INTRODUCTION 1-5
2 GENERAL SPECIFICATION 6 - 19
3 CONCRETOR 20 - 31
4 BRICKLAYER 32 - 37
5 PLASTERER 38 - 46
7 CARPENTER 63 - 65
8 IRONMONGER 66 - 67
11 PAINTER 79 - 81
12 GLAZIER 82 - 83
13 WATERPROOFER 84 - 85
14 SITE WORKS 86 - 88
19 SIGNAGE 191
DETAILED CONTENTS
FRESH “X” CHECKERS & CHECKERS HYPER (REVISION – A)
SECTION 1: INTRODUCTION PAGE
1.1 NOTES 1
1.2 SPECIALIST CONSULTANTS 2
1.2.1 Architect 2
1.2.2 Electrical Consultant 2
1.2.3 Structural/Civil Engineer 2
1.2.4 Insulation Consultant 2
1.2.5 Mechanical Consultant 3
1.2.6 Fire Consultant 3
1.2.7 Acoustic Consultant 3
1.2.8 Plumbing Consultant 3
1.2.9 Refrigeration Consultant 3
1.3 SPECIALIST CONTRACTORS 3
1.3.1 Refrigeration Contractor 3
1.3.2 IT Contractor 3
1.3.3 Security Contractor 4
1.3.4 Service Department Equipment 4
1.4 SUPERVISION 4
1.5 PLANS 4
1.6 PROGRAMME 4
1.7 BENEFICIAL OCCUPATION 4
SECTION 2: GENERAL
2.1 NAME BOARDS AND PERMANENT SIGNS 6
2.2 PARKING AREAS 6
2.2.1 Lighting in Parking Area 6
2.2.2 Ramps 6
2.2.3 Bollards 6
2.9.3 Kiosk 15
2.9.4 Manager Office 16
2.9.5 Admin Office 16
2.9.6 Scanning Office 16
2.9.7 Camera Room 16
2.9.8 Cash Offices 16
2.9.9 Customer Service (Fresh “X” Checkers Hyper only) 16
2.9.10 Checkout Arcade 16
2.9.11 Dispensary 16
2.9.12 Health and Beauty 17
2.9.13 Trading Area 17
2.9.14 Hot Deli 17
2.9.15 Cold Deli 17
2.9.16 Back-Up Deli 17
2.9.17 Fish Area 17
2.9.18 Bakery Area 17
2.9.19 Butchery Area 17
2.9.20 Fruit and Veg Prep 18
2.9.21 Back of House Deli Prep 18
2.9.22 Wine Area 18
2.9.23 Receiving Office 18
2.9.24 Wet Refuse Room 18
2.9.25 Carton Store (Dry Refuse Room) 18
2.9.26 Receiving Yard 18
2.9.27 Crate Store 19
2.9.28 Yard Toilet and Shower 19
2.9.29 Gate House 19
2.9.30 Trolley Wash Bay 19
2.9.31 Returns and Returns Sorting Room 19
2.10 GALVANIZED BUMPER RAIL 19
SECTION 3: CONCRETOR
3.1 GENERAL 20
3.2 MATERIALS 20
3.2.1 Cement 20
3.2.1.1 General 20
3.2.1.2 Common Cements 20
(i) Composition 21
(ii) Strength Performance 22
3.2.1.3 Masonry Cements 22
(i) Composition 23
(ii) Strength Performance 23
3.2.1.4 Selecting Cements 23
3.2.1.5 Storage 24
3.2.2 Sand (Fine Aggregate) and Stone (Coarse Aggregate) 24
3.2.3 Admixtures 25
3.2.4 Water 25
3.2.5 Coarse Aggregate (Stone) 25
3.3 CONCRETE CONSTRUCTION 25
3.3.1 Mixing 26
3.3.2 Placing 26
3.3.3 Curing 26
3.3.4 Removal of Formwork and Props 26
3.3.5 Ready-Mix Concrete 27
3.3.6 Yard Paving 27
3.3.7 Surface Beds 27
3.3.8 Floor Trenches 27
3.3.9 Concrete Steps 27
SECTION 4: BRICKLAYER
4.1 MASONRY WALLS 32
4.2 SAND/CEMENT MORTAR 32
4.2.1 General 32
4.2.2 Materials 32
4.2.2.1 Fine Aggregate (Sand) 33
4.2.2.2 Admixtures 33
4.2.3 Mix Proportions 33
4.2.4 Construction: Consistency and Time Limits 33
4.2.5 Hardened Mortar or Plaster: Quality of Mortar 34
4.3 BURNT CLAY MASONRY UNITS 34
4.3.1 Strength 34
4.3.2 Tolerances 34
4.3.3 Water-Absorption 35
4.4 CONCRETE MASONRY UNITS 35
4.4.1 Strength 35
4.4.2 Tolerances 36
4.5 DAMP-PROOF COURSE 36
4.6 POINTING 37
4.7 BAGGED FINISH TO BRICKWORK 37
4.8 AIR BRICKS 37
4.9 CLEANING OFF 37
4.10 FLOOR TRENCHES 37
4.11 SEALER 37
SECTION 5: PLASTERER
5.1 SAND/CEMENT SCREEDS 38
5.1.1 General 38
5.1.2 Bonded Screeds 38
5.1.3 Monolithic Screeds 39
5.1.4 Materials 39
5.1.4.1 Fine Aggregate (Sand) 39
5.1.4.2 Admixtures 40
5.1.5 Mix Proportions 40
5.1.6 Construction 40
5.1.6.1 Consistency and Time Limits 40
5.1.6.2 Application of Screeds 40
5.1.6.3 Finishing 41
5.1.6.4 Curing of Screeds 41
5.1.7 Hardened Screeds 42
5.1.7.1 Quality of Screeds 42
5.1.7.2 Deviation from Datum Level and Surface Regularity 42
5.1.7.3 Screed Strength 42
SECTION 7: CARPENTER
7.1 HARDWOOD 63
7.2 TIMBER GENERALLY 63
SECTION 8: IRONMONGER
8.1 GENERAL 66
8.2 SCREWS 66
8.3 KEYS 66
8.4 STAMPING 66
8.5 KEY LABELS 66
8.6 DOOR FURNITURE AND IRONMONGERY 66
8.7 LOCKS 66
8.8 INDICATOR BOLTS 66
8.9 NAME PLATES 66
8.10 KICKING PLATES 66
8.11 BARREL BOLTS 66
8.12 TOWEL RAILS 67
8.13 TOILET ROLL HOLDERS 67
8.14 LOCK CHANGE AT BENEFICIAL HANDOVER 67
Table 2 165
Table 5 166
Method 1 - 5 167
Table 6 168
Table 7 168
Table 8 169
Table 9 170
Table 10 170
Table 11 171
Table 12 171
Table 13 171
Table 14 171
This specification must be read together with the finishing schedule and other
schedules attached hereto for further description and specification of all
material and workmanship for each section.
All materials etc. specified hereinafter under a trade name, catalogue number or
reference, to be either exactly as described or, in the opinion of the Shoprite Checkers
Architect, of equal quality specification in all respects.
All materials used in the construction of the proposed Supermarket to be the best of
their respective kinds.
Only new materials may be used. No second hand materials will be permitted.
All work done as specified hereunder is to be in accordance with the Local Authorities
Regulations. All structural work is to be in accordance with the National Building
Regulations SANS 10400:1990 (as revised November 2011 ISBN 978-0-626-26805-3),
SANS 10400 XA, and South African Bureau of Standards, at the discretion and to the
approval of the Local Authority.
These documents do not supersede standards of good building practice, which are at
all times to be adhered to.
All plans, sections and elevations depicting the true intent of the overall development,
including the area allocated to the supermarket premises, must be available for
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
2
inspection by the Shoprite Checkers Architect. Shoprite Checkers will not assume
responsibility for any abortive costs associated with early planning and
construction prior to their approval of a final store layout issued for
construction.
This Specification refers to Fresh “X” Checkers and Checkers Hyper stores with
differences in colour schemes and finishes. In some instances both elements of
finishes schedule will apply, and will be confirmed by the SRC Architect.
1.2.1 Architect
The Landlord/Developer is to appoint Shoprite Checkers’ nominated Architect
for that portion of the works contained within this Specification. The Architect
will be paid by Shoprite Checkers and Shoprite Checkers will recover the
relevant fees from the developer as per the lease agreement.
1.3.2 IT Contractor
Shoprite Checkers will appoint an IT Contractor who will be responsible for the
installation of IT related materials and equipment. The Landlord/Developer will
provide and install certain infrastructure for the reticulation of these services
as his cost.
1.4 SUPERVISION
A schedule of dates upon which site meetings are due to be held is to be circulated to
Shoprite Checkers’ Representatives, Consultants and Contractors, who shall be
entitled to attend these meetings.
1.5 PLANS
It is the responsibility of the Landlord/Developer to submit all building plans to the
Local Authority for approval. The date of approval is to be advised in order that
Shoprite Checkers may make the necessary application for a trading license well in
advance of the opening date of the store. Plan approval fees shall be paid by the
Landlord/Developer. If any plans are submitted by the Shoprite Checkers Architect
the Landlord/Developer will still be liable for the plan approval fees.
1.6 PROGRAMME
The Landlord/Developer must submit to Shoprite Checkers a construction
programme. Shoprite Checkers is to be advised of and agree with any changes in
programme dates.
The Shoprite Checkers Architect will in his/her sole discretion certify whether
the premise is suitable for Beneficial Occupation at the agreed date. Should the
Beneficial Occupation Date change during the course of the contract, Shoprite
Checkers must be given notice.
The receiving yard and doors shall be unobstructed and the road access thereto
completed. Access to the premises must be possible via the main entrance to the
trading floor for delivery of refrigeration cabinets and bakery ovens. The
landlord/Developer must provide adequate protection to mall floor finishes
when the delivery take place as no claims for damages will be accepted.
The A/C plant and Backup Generator must be completed and working.
Construction of the refrigeration plant room shall be complete and secured. The
Refrigeration Contractor must have access to the premises a minimum of two
weeks prior to Beneficial Occupation. The premises must be secure to prevent
theft of refrigeration materials and equipment.
Where external signs are to be illuminated, the electrical points and power thereto are
to be supplied by the Electrical Contractor to the required electrical loading.
All exterior space for signage whether on the building or on pylons will be made
available free of charge to Shoprite Checkers. Provision must be made for signs on
the building in positions that will provide maximum exposure in contexts of the
development, surrounding areas and approaches. The Landlord will provide all
structures required for external signage at his cost. Refer to Signage Section 19 for
details.
2.2.2 Ramps
Ramps are to be provided for the manoeuvring of trolleys and disabled
persons as per Architect details and or National Building Regulations.
2.2.3 Bollards
Bollards may be required at the discretion of the SRC Architect to all
Supermarket entrances for security reasons.
Escalators and passenger lifts are to be positioned in such a way as not to obscure
sight lines to the supermarket entrances
2.6 ROOF
Falls to the roof must be according to the roof sheet manufacturer's specifications,
but not less than 2,5˚.
All flashings and ridge cappings are to be made from the same sheeting
material as the roof sheeting.
Roof sheeting with “oil canning”, scratches, kinks or other visible damage
to the finish will be rejected.
All flashings and ridge cappings are to be made from the same sheeting
material as the roof sheeting.
Roof sheeting with “oil canning”, scratches, kinks or other visible damage
to the finish will be rejected.
Truss design must allow for all air-conditioning ducts, service pipes,
etc. to be located above the tie beam.
2.7 FLOORS
2.7.1 Trading Floor Surface Bed
Surface beds are to have a compressive strength of 30MPA and a thickness of
150mm. Allowance must be made for trenches to accommodate refrigeration
and other services. Recesses in the floor must be allowed for Freezer Rooms
(Refer to detail DET03).
2.7.3 Bulk Store Surface Bed, Receiving, Goods Handling and Service Passages
Surface beds to have a compressive strength of 40MPA and a thickness of
180mm. Recess in floor must be allowed for freezer rooms (Refer to detail
DET03 & 04). Smooth steel floated surface finishes as per engineer’s details.
2.7.4 Bulk store, receiving areas and goods handling area on suspended slab
Suspended slabs for bulk stores, receiving areas and goods handling areas
must be designed to accommodate a 12,5kN/m² live load. This also applies
where inter rack walkway systems are used. In the case where a mezzanine
floor is supported by independent columns, the engineer must make special
provision for the additional point loads. In this instance the engineer is to use
7,5kN/m² live load on the suspended slab and 5kN/m² live load on the
mezzanine floor above to determine the relevant point loads.
Allow waterproofing below cold and freezer rooms on suspended slab. Sleeves
for refrigeration and drainage must be allowed for on bulk store slabs with
drip trays below slab for services. Allow recess for cold and freezer rooms with
allowance for flexibility for future changes (Refer to detail DET02). See
engineers' details on thickness of slab. The height to underside of mezzanine
slab is to be minimum 3m from finished floor level.
In the instances where the receiving and/ or bulk store are on different levels
to the trading floor, allowance must be made for a minimum of two goods lifts
(minimum internal dimension of cart size 2,7m deep x 2m wide or visa verse).
In the event that butchery deliveries have to be transported in hoists the
internal finishes of at least one lift has to be stainless steel.
2.8.2 Conveyer
The Owner/Developer is to supply and install such vertical transportation
equipment, as specified and shown on Shoprite Checkers' ‘Architect’ drawings.
(Refer to detail DET26.)
In Fresh “X” Checkers and Checkers Hyper stores there will be a skimmed
plaster board ceiling/bulkhead of which the extent and height will be
determined by the SRC Architect.
Skimmed joint ceiling bulkhead of which extent and height will be determined
by the SRC Architect. Bump rail to be provided as per detail in front of
counter. (Refer to Typical Detail T02A, B, C Money Market.)
2.9.3 Kiosk
Dividing walls between Money market, Kiosk, manager’s office and customer’s
service will be constructed out of Glass partitioning. Refer to detail T01 – T03.
Skimmed joint ceiling bulkhead of which extent and height will be determined
by the SRC Architect. Bump rail to be provided as per detail in front of
counter. (Refer to Typical Detail T03A, B Kiosk).
Skimmed joint ceiling bulkhead of which extent and height will be determined
by the SRC Architect. Worktops to be provided by Landlord. (Refer to Typical
Detail T03 on Managers Office).
Shoprite Checkers will supply a safe for the cash float to be stored in the Cash
Office. The weight of this safe will be approximately 1,250kg. Loose standing
safes may also be positioned inside the Strong Room at the Cash Offices.
Refer to Typical Detail T06 & T07.
2.9.11 Dispensary
Refer to Dispensary Typical Detail T09-A and T09-B.
worktops in butchery manager’s office. These are typical layouts and will vary.
There can also be more than one butchery/fresh meat service area per
supermarket and is layout and customer profile dependent. Floor to be
waterproofed when on suspended slab.
The receiving yard has to be 1,350m lower than the level of the receiving
cages and stockroom to facilitate a docking platform 1,350m above finished
floor level. The retaining wall of the receiving platform must be constructed
out of concrete as per the SRC Architect drawings. Refer to Typical Detail T21.
2.12 BULKHEADS
All bulkheads are to be supported by an independent steel substructure which are
secured to the roof structure above. This substructure is to be designed by a
structural engineer.
The type and origin of the cement, water, stone and sand shall be submitted to the
Engineer prior to construction.
The Engineer shall specify the characteristic 28-day concrete strength (grade) and the
nominal size of the coarse aggregate for all structural elements.
Concrete mix designs with laboratory test results for the different concrete grades
shall be forwarded to the Engineer prior to the commencement of the project.
3.2 MATERIALS
3.2.1 Cement
3.2.1.1 General
Portland based cements used in building and construction are divided
into two broad categories: “common” cements intended for use in
concrete (although many are suitable for mortar and plaster mixes)
and “masonry” cements intended for bedding mortars and plasters.
(i) Composition
The composition of common cements is to comply with the
proportions of the constituents, i.e. Portland cement, extenders
and fillers, as shown in Table 1.
Blast-furnace
Constituents
Additions &
Description
Silica Fume
Lime-stone
Granulated
Notation
Clinker
Fly ash
Minor
Slag
D3
S
L
I Portland
I 95-100 - - - - - 0-5
cement
Portland II/A-S 80-94 6-20 - - - - 0-5
slag cement
II/B-S 65-79 21-35 - - - - 0-5
Portland
silica fume II/A-D 90-94 - 6-10 - - - 0-5
cement
II II/A-V 80-94 - - 6-20 - - 0-5
Portland fly II/B-V 65-79 - - 21-35 - - 0-5
ash cement II/A-W 80-94 - - - 6-20 - 0-5
II/B-W 65-79 - - - 21-35 - 0-5
Portland II/A-L 80-94 - - - - 6-20 0-5
limestone
cement II/B-L 65-79 - - - - 21-35 0-5
Portland II/A-M 80-94 6-204
composite
cement II/B-M 65-79 21-354
Blastfurnace III/A 35-64 36-65 - - - - 0-5
III cement
III/B 20-34 66-80 - - - - 0-5
Notes:
(1) The values in the table refer to the cement nucleus, excluding
calcium sulphate and any additives.
(2) Minor additional constituents may be filler or may be one or more
of the main constituents unless these are included as main
constituents in the cement.
(3) The proportion of silica fume is limited to 10%.
(4) The proportion of filler is limited to 5%.
32,5 - 16 min
32,5 min 52,5 max
32,5 R 10 min -
42,5 10 min -
42,5 min 62,5 max
42,5 R 20 min -
52,5 20 min -
52,5 min -
52,5 R 30 min -
(i) Composition
Masonry cements are to consist of Portland cement clinker,
inorganic material, and, where appropriate, organic material as
shown in Table 3.
Content (%)
Type
Portland cement clinker Organic material
MC 5 25 min 1 min
MC 12,5
MC 12,5X 40 min 1 min
MC 22,5X
Application Strength
Cement type Comment
class
Conventional structural
32,5 or
concrete in a non-aggressive As available -
higher
environment
Due consideration to be
As available,
Reinforced concrete in a 32,5 or taken of exposure
subject to
marine environment higher conditions. Specialist
comment
advice essential.
Total alkali content of
As available,
Concrete made with alkali 32,5 or concrete to be limited.
subject to
reactive aggregates higher Specialist advice
comment
essential.
CEM I
Floors, roads and paving with 32,5 or Specialist advice
CEM II/A
sawn joints higher recommended.
CEM II/B (slag)
Large placements where CEM III
Specialist advice
temperature rise due to heat As available CEM II/B (fly
essential.
reaction is to be controlled ash)
42,5 or
High-strength concrete As available -
higher
Concrete exposed to sulphate CEM II/B (fly Specialist advice
As available
attack ash) essential.
CEM I
Other cements should
12,5 or CEM II/A
Mortars and plasters only be used with
higher MC 12,5 X
specialist advice.
MC 22,5 X
Other cements should
32,5 or CEM I
Floor screeds only be used with
higher CEM II/A
specialist advice.
3.2.1.5 Storage
Bulk storage silos are to be inspected on a regular basis to ensure that
the inspection hatch is watertight and filters are clean and unblocked.
Cement bags are not weatherproof and must be stored under cover,
off the ground to a maximum height of 12 bags (50kg).
75 7.5% 0%
150 15% 5%
300 35% 10%
600 60% 25%
1180 85% 50%
2360 100% 80%
4750 100% 95%
The fineness modules (FM) of the sand will fall in the range 1.6 to 3.5.
3.2.3 Admixtures
Admixtures in the concrete mix will only be allowed if approved by the
Engineer.
3.2.4 Water
Water is to be clean and free from injurious amounts of acids, alkalis, organic
matter and other substances that may impair the strength and/or durability of
concrete. In general, the criterion for water to be used in the concrete mix is
that it should be fit to drink.
3.3.1 Mixing
In mixing concrete, the aim is to obtain a uniform and intimate mixture of all
the ingredients. The mixture must be such that the various sizes of aggregates
are uniformly distributed throughout the mass, each particle of aggregate
being adequately coated with cement paste of uniform consistency.
For a 19mm coarse aggregate, the minimum cement: water ratio in the mix
and minimum kilogram cement for every cubic meter of concrete for different
grades of concrete is as follows:
3.3.2 Placing
The slump of the concrete must suit the placing and compaction method
(hand or vibration) adopted and should be between 30mm and 80mm. The
concrete is to be of such workability that it can be readily compacted into the
corners of formwork and around reinforcement without segregation of the
materials or excessive bleeding of free water to the surface. The concrete is to
be free from honeycombing and planes of weakness. Successive layers of the
same lift are to be thoroughly worked together.
3.3.3 Curing
All concrete is to be properly and continuously cured for a period of 5 days
after it has been placed. Flat surfaces of concrete are to be covered with clean
wet sand and all other surfaces are to be covered with wet sacks, mats or
other moisture-retaining material, and be kept wet.
Steps are to be neatly finished off in granolithic with a steel trowel and
provided with insets near the fronts of the treads. A steel angle nosing to
protect the edge of the step must be cast-in.
3.3.15 Jointing
Care is to be exercised in construction and saw-cut joints to floors that are to
receive applied porcelain tile finish so that joints in concrete correspond with
joints between tiles. It is important to determine the exact tile size (calibration)
from the tile supplier beforehand.
3.3.16 Reinforcement
3.3.16.1 Material
The type, standard and specification of reinforcement commonly
available in the country are to be passed on to the Engineer for
approval. Bars marked “Y” refer to high yield bars that have yield
strength of 450Mpa, whereas those marked “R” are mild steel bars
which have yield strength of 250Mpa. Thus a bar Y12 means that the
bar has a minimum diameter of 12mm and is of the high yield type.
(iii) Tolerances
The permissible deviation for the positioning of and the cover
to reinforcement is as follows:
(Cover is measured from the face of the concrete to the outside of the
reinforcing nearest to the face of the concrete).
3.4.2 Strength
The 28-day strength of the hardened concrete is to meet the grade specified
by the Engineer. The Contractor is responsible for acquiring cube samples of
the concrete for testing. The cubes should be kept submerged in water at a
temperature of between 22 to 25 degrees Celsius until they are taken to an
independent testing laboratory. The Contractor is to pass on the laboratory
cube strength results to the Engineer. At least one set of cubes is to be taken
from each day's casting and from at least every 50m³ of concrete of each
grade placed. One set of cubes is to consist of three cubes of 150 x 150 x
150mm in size.
3.4.3 Tolerances
Prior to installing floor finishes the flatness and levelness of the floor must be
surveyed and verified by a reputable surveyor and the data made available to
the Shoprite Checkers Architect.
The Contractor is to follow the Engineer's drawings, details and schedules and
to construct each of the various parts of the works within the limits of the
applicable permissible deviation as follows:
The masonry walls are to be constructed of units of regular shape, either solid or
hollow, that are in compliance with the requirements outlined below.
The dimensions of a hollow masonry unit are to be in compliance with the following:
Length between 300mm and 650mm
Width between 130mm and 300mm
Height between 120mm and 300mm
The dimensions of a solid masonry unit are to be in compliance with the following:
Length not exceeding 300mm
Width not exceeding 130mm
Height not exceeding 120mm
4.2.2 Materials
For cement and water, refer to the notes under Materials in the Concreter
Section 2.2.
The maximum drying shrinkage of the mortar mix is not to be more than
0,12%.
4.2.2.2 Admixtures
Admixtures will only be allowed if approved by the Engineer.
50kg common cement: 0-40 litres lime (optional): 200 litres (maximum)
loose damp sand
(1 Bag) (3 standard 65L wheelbarrows)
OR
Mortar in which initial set has occurred (i.e. thumbprint hard) is not to be used.
Any material that is not used or applied within two hours of mixing is to be
discarded.
4.3.1 Strength
The strength of the concrete masonry unit and its utilization must be in
accordance with the table below.
4.3.2 Tolerances
Only masonry units that are not warped, cracked or damaged may be used.
The allowable dimensions of solid and hollow masonry units have been
outlined above.
Table 7
Length +/-7
Width +/-4
Height +/-4
4.3.3 Water-Absorption
The water-absorption of face bricks must not exceed 13%.
The water-absorption of non-face bricks must not exceed 11%.
The water-absorption for bricks in a sea-spray zone (within 30m of the sea)
must not exceed 7%.
4.4.1 Strength
The strength of the concrete masonry unit and its utilization must be in
accordance with the tables below.
4.4.2 Tolerances
Only masonry units that are not warped, cracked or damaged may be used.
The allowable dimensions of solid and hollow masonry units have been
outlined above.
Table 10
Length +2
-4
Width +/-3
Height +/-3
4.6 POINTING
Face brick and semi-face brick to be pointed with a square recessed joint both
horizontally and vertically.
4.11 SEALER
Apply a brick sealant to completed face brick internal walls as specified. Apply only
after brick work is confirmed properly cleaned from excess mortar and mortar stains.
Sand-cement screeds are not suitable for heavy traffic or industrial premises.
Preferred methods of floor construction for such premises are full-thickness
trowelled concrete or concrete topping on the concrete base. A sand-cement
screed is to be specified only where placing and finishing the concrete floor to
acceptable standards are impracticable.
Also refer to the notes under General in the Concreter Section 2.1.
The base concrete is to be prepared in such a way that it is left with a surface
that is uniformly hard, clean, and free of dust, oil or other contamination. Any
screeds applied previously to the base are to be removed completely. The
whole of the surface of the base must be chipped and/or scabbled with
appropriate, preferably power-operated, tools. All debris is then to be
removed and the surface finally cleaned of dust with an industrial vacuum
cleaner. The surface is to be kept clean and free of dust pending further
operations on it.
The surface of the base to receive the screed is to be keyed with a sand-
cement grout to ensure a proper bond. The grout is to consist of equal
volumes of fine, clean sand and loose cement mixed thoroughly with sufficient
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
39
Immediate placing requires careful timing but has the advantage that no
preparation of the concrete surface is required.
Timing of delayed placing is not as critical but the surface of the concrete does
require some preparation. Laitance is to be loosened by light brushing and
thoroughly removed by sweeping, or preferably, by vacuum cleaning. Delayed
placing is to be done within an hour or two after the end of the bleeding
period.
5.1.4 Materials
For cement and water, refer to the notes under Materials in the Concreter
Section 2.2.1.
The fineness modules (FM) of the sand is to fall in the range 1,6 to 3,5.
5.1.4.2 Admixtures
Admixtures will only be allowed if approved by the Engineer.
5.1.6 Construction
5.1.6.1 Consistency and Time Limits
Screeds are to be mixed on a surface free of contaminants by a
method and for a period of time that ensures that all ingredients are
uniformly and evenly distributed throughout the mixture. Mixing is to
continue until the desired consistency is achieved (slump
approximately 40mm). Screed in its fresh state must be workable and
have water retention and cohesive properties.
The time that elapses between the start of mixing a batch and when
that batch is placed and compacted should not exceed 45 minutes,
and during that time the mix should be protected from drying out.
Batches not placed and compacted within this time, or which have
stiffened to a degree that their workability (consistency) cannot be
restored fully by turning them over a couple of times with spades, are
to be discarded.
5.1.6.3 Finishing
At no stage during laying or finishing may cement or mixtures of
cement and sand, to be applied to the surface to soak up bleed water.
Light foot traffic may be allowed over new work 24 hours after
finishing, provided that the plastic sheeting is not damaged or
displaced.
5.4.2 Materials
For cement and water, refer to the notes under Materials in the Concreter
Section 2.2.
5.4.2.2 Admixtures
Admixtures will only be allowed if approved by the Engineer.
OR
OR
5.4.4 Construction
5.4.4.1 Consistency and Time Limits
Plasters are to be mixed on a surface free of contaminants by a
method and for a period of time that ensures that all ingredients are
uniformly and evenly distributed throughout the mixture.
Plaster in which initial set has occurred (i.e. thumbprint hard) are not
to be used. Any material which is not used or applied within two
hours of mixing is to be discarded.
The Insulation Specialist Contractor will lay an insulation layer only, on top of which
shall be laid a 250 micron Gunplas membrane, on top of which shall be laid a 100mm
thick reinforced 30MPa concrete steel trowelled floated floor by the Main Contractor.
An 8mm wide joint is to be provided between the floor and the walls of the
prefabricated cold rooms/ deep freeze rooms and filled with soft board and sealed
with a polysulphide sealant finished flush with the floor surface.
Polysulphide sealant is to be applied around the floor drainage outlet where this
penetrates the floor.
All cold and freezer room floors are finished with a 10mm thick layer of Polyscreed
applied in strict accordance with the manufacturers specifications. The floor is to be
recessed across all door openings to accommodate the Polyscreed to be thickened to
20mm x 300mm wide at all thresholds. The Polyscreed is to have a smooth steel
trowel finish upon completion. Also see applicable cold and freezer room details.
WALL TILING: SPECIFICATION FOR FIXING CERAMIC WALL TILES ONTO INTERIOR
RENDERED WALLS
6.1.1 Allow all new wall-rendering to cure for at least 14 days. The rendering must
be firmly attached to the substrate, must be integrally sound (no crumbling,
cracking, etc) and must be of a quality and consistency suitable for tiling. The
background must be clean, dry, firm and sound and free from dust, loose
particles and surface contaminants before proceeding. Renders should be left
with a wood-float finish and must not be skim coated with gypsum plaster.
6.2.3 General
6.2.3.1 At no time spread more adhesive than can be tiled onto in 10 – 15
minutes. Depending on atmospheric conditions, this will normally be
around 1 square meter. This prevents the adhesive from drying or
“skinning” before the tiles is applied.
6.2.3.2 Bed dry tiles (do not soak) firmly into the wet adhesive with a twisting
action to ensure full contact between the background, tiles and
adhesive. Tiles should be well tapped home with a rubber mallet or
the wooden handle of a trowel. It is sound practice to remove the
occasional tile to ensure that good contact has been achieved.
6.2.3.3 Clean off any surplus adhesive remaining on the face of tiles and
between the joints with a damp sponge before the adhesive dries.
6.2.3.4 Never butt joint tiles. Joints are required to allow the individual tiles
to move with respect to each other and thus avoid a compressive
stress build-up. They are also required as vents for the tile adhesive
to cure. The joints between ceramic wall tiles must be a minimum of
2mm wide. The joints between brick-tiles must be a minimum of
5mm wide.
NOTE: The joints between the ceramic tiles must be a minimum of 3mm wide
in areas where TAL Fine Epoxy Grout is to be used.
6.2.3.5 Pot life of the adhesive will vary with climatic conditions. Under no
circumstances should adhesive which has been left standing for too
long be reconstituted by adding more liquid.
6.2.3.6 Do not tile over structural, expansion or cold joints in the background.
These joints must be extended through the various layers to the
surface.
6.3 GROUTING
Scrape out/clean joints and vacuum prior to grouting.
6.3.1 Application
Grouting must not be carried out until sufficient bond has developed between
the bedding mix and the tiles to preclude disturbance of the tiles during the
grouting operation. Grouting should therefore not be carried out for 1 – 3
DAYS after completion of laying, depending on atmospheric conditions and
different tiling situations.
* NOTE: TAL Super White Grout is only suitable for wall tile joints up
to 3mm wide.
6.3.2.2 WARNING:
Particular care must be taken to clean the grout off the tile face
before it hardens completely. This is especially important when a
latex additive such as TAL BOND has been used.
A sample of the tiles to be used should be tested beforehand to
ensure that no grout is absorbed through the glaze, or into the
tile body, causing permanent staining of the tiles.
It is important to use the stipulated amount of liquid in the TAL
Grout mixture. When cleaning, a damp, not wet, sponge must be
used. Over hydration (too much water) of the mix, or in cleaning,
causes colour variations in the grout joints, and also affects the
integrity of the grout.
6.3.3.2 Add ALL the Hardener to ALL the Resin in the bucket and mix
thoroughly, scraping down the sides, until the mix assumes a uniform
colour. A MECHANICAL MIXER IS ESSENTIAL FOR GOOD MIXING.
6.3.3.4 Apply TAL FINE EPOXY GROUT with a squeegee or palette knife.
6.3.3.5 Scrape the excess off immediately and wipe the installation with a
damp (not wet) sponge, cleaning the sponge regularly in a bucket of
clean water.
6.3.3.6 Do not use excessive water and do not wet the joints before grouting.
6.3.3.7 A mix is useable for approximately 1 hour at 20ºC, after which time
any portion unused must be discarded. In hot conditions the pot life
may be shorter.
6.3.3.9 NOTE:
If any epoxy is inadvertently spilled onto the tile face, it must be
removed using a damp cloth or sponge before it hardens.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
50
6.4.3 Movement joints should also be located in all horizontal and vertical corners,
against obstructions fixed to the structural background and over all
discontinuities in building materials, e.g. at interfaces of concrete and
brickwork. In addition, movement joints should be located around any fixtures
protruding through the tiled surface.
6.4.4 The joints should be at least 5mm wide and extend through the tile and
adhesive layers. All structural expansion joints in the background must be
extended through the tiles to the surface. The full width of the structural
joints must be extended through the tiles to the surface.
6.4.5 Where practical, the bulk of the depth of the movement joint can be filled with
TAL SEALMASTER CORD.
6.4.6 Seal the joint using TAL GOLD STAR SEALMASTER 1000 polyurethane joint
sealant in accordance with the manufacturer’s instructions. It is important that
the joint sealant bonds only to the sides of the movement joint.
6.4.7 For the key requirements common to all tiling situations, please refer to SABS
0107-1996 - Code of Practice.
6.5.1 Allow all new wall rendering to cure for at least 14 days. The rendering must
be firmly attached to the substrate, must be integrally sound (no crumbling,
cracking, etc) and must be of a quality and consistency suitable for tiling. The
background must be clean, dry, firm and sound and free from dust, loose
particles and surface contaminants before proceeding. Renders should be left
with a wood-float finish and should not be skim-coated with gypsum plaster.
6.6.3 General
6.6.3.1 In this tiling situation it is imperative that there is a solid bed of
adhesive at least 5mm thick beneath each tile. Use a notched FLOOR
TROWEL.
6.6.3.3 Bed dry tiles (do not soak) firmly into the wet adhesive with a twisting
action to ensure full contact between the background, tiles and
adhesive. Tiles should be well tapped home with a rubber mallet or
the wooden handle of a trowel. It is sound practice to remove the
occasional tile to ensure that good contact has been achieved.
6.6.3.4 Clean off any surplus adhesive remaining on the face of tiles and
between the joints with a damp sponge before the adhesive dries.
6.6.3.5 Never butt joint tiles. Joints are required to allow the individual tiles
to move with respect to each other and thus avoid a compressive
stress build-up. They are also required as vents for the tile adhesive
6.6.3.6 Pot life of the adhesive will vary with climatic conditions. Under no
circumstances should adhesive which has been left standing for too
long be reconstituted by adding more liquid.
6.6.3.7 Do not tile over structural, expansion or cold joints in the background.
These joints must be extended through the various layers to the
surface.
6.6.3.8 NOTE: Ensure that heavy and/or large format tiles are well supported
by means of a batten or some type of mechanical device until such
time that the adhesive has fully cured. In this situation it will be 6
hours.
6.7 GROUTING
6.7.1 Application Process
Grouting must not be carried out until sufficient bond has developed between
the bedding mix and the tiles to preclude disturbance of the tiles during the
grouting operation. Allow a minimum of 4 hours before grouting.
6.7.2.2 WARNING :
Particular care must be taken to clean the grout off the tile face
before it hardens completely. This is especially important when a
latex additive such as TAL BOND has been used.
A sample of the tiles to be used should be tested beforehand to
ensure that no grout is absorbed into the tile body, causing
permanent staining of the tiles.
It is important to use the stipulated amount of liquid in the TAL
Grout mixture. When cleaning, a damp, not wet, sponge must be
used. Over hydration (too much water) of the mix, or in cleaning,
causes colour variations in the grout joints, and also affects the
integrity of the grout, resulting in a friable product.
6.7.3.2 Add ALL the Hardener to ALL the Resin in the bucket and mix
thoroughly, scraping down the sides, until the mix assumes a uniform
colour. A MECHANICAL MIXER IS ESSENTIAL FOR GOOD MIXING.
6.7.3.4 Apply TAL FINE EPOXY GROUT with a squeegee or palette knife.
6.7.3.5 Scrape the excess off immediately and wipe the installation with a
damp (not wet) sponge, cleaning the sponge regularly in a bucket of
clean water.
6.7.3.6 Do not use excessive water and do not wet the joints before grouting.
6.7.3.7 A mix is useable for approximately 1 hour at 20ºC, after which time
any portion unused must be discarded. In hot conditions the pot life
may be shorter.
6.7.3.9 NOTE:
If any epoxy is inadvertently spilled onto the tile face, it must be
removed using a damp cloth or sponge before it hardens.
Spillage should be avoided as far as possible at it causes
unnecessary waste of material and time. Cured epoxy is very
difficult to remove, so the area must be cleaned as soon as
possible after grouting.
Any faint haze left on the tiles after completion of grouting may
be removed using TAL EPOXY CLEANING FLUID.
A sample of the tiles to be used should be tested beforehand to
ensure that no grout is absorbed into the tile body, causing
permanent staining of the tiles.
6.8.3 Movement joints should also be made in all horizontal and vertical corners,
against obstructions fixed to the structural background and over all
discontinuities in building materials, e.g. at interfaces of concrete and
brickwork. In addition, movement joints must be located around any fixtures
protruding through the tiled surface.
6.8.4 The joints should be at least 5mm wide and extend through the tile and
adhesive layers. All structural expansion joints in the background must be
extended through the tiles to the surface. The full width of the structural
joints must be extended through the tiles to the surface.
6.8.5 Where practical, the bulk of the depth of the movement joint can be filled with
TAL SEALMASTER CORD.
6.8.6 Seal the joint using TAL GOLD STAR SEALMASTER 1000 polyurethane joint
sealant in accordance with the manufacturer’s instructions. It is important that
the joint sealant bonds only to the sides of the movement joint.
6.8.7 For the key requirements common to all tiling situations, please refer to SABS
0107-1996 - Code of Practice.
FLOOR TILING SPECIFICATION FOR FIXING FULL BODIED PORCELAIN TILES ONTO
INTERIOR SURFACE BEDS
6.9.1 Allow all new concrete work and screeds to cure for at least 28 days before
proceeding. All new concrete work and screeds must have a moisture content
of 5% or less before tiling can commence. When tiling directly onto concrete,
ensure that the surfaces are clean and free of all traces of curing agents,
laitance and any other surface contaminants, preferably by scarifying.
6.9.2 Any screed must be firmly attached to the underlying concrete, must be
integrally sound (no crumbling, cracking, etc) and must be of a quality and
consistency suitable for tiling. All defective areas must be removed and the
floor made good before proceeding, using TAL RAPIDFIX or TALCEM. The
surface must be clean and dry and free of all traces of dust, debris, loose
particles and surface contaminants.
6.9.3 If the surface has been wood floated it is possible to commence tiling.
However, if the surface has been power floated or steel floated it will be
necessary to first key the surface with a slurry consisting of 1 part TAL
KEYCOAT to 2 parts ordinary Portland cement (by volume), which is applied by
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
55
block brush. Allow this slurry coat to dry for 4 – 6 hours before applying the
adhesive.
6.10.2 In this tiling situation it is imperative that there is a solid bed of adhesive at
least 6mm thick beneath each tile. We would recommend the use of a
notched TAL FLOOR TROWEL.
6.10.3 At no time spread more adhesive than can be tiled onto in 10 – 15 minutes.
Depending on atmospheric conditions, this will normally be around 1 square
metre. This prevents the adhesive from drying or “skinning” before the tiles
are applied.
6.10.4 Bed dry tiles (do not soak) firmly into the wet adhesive with a twisting action
to ensure full contact between the background, tiles and adhesive. Tiles
should be well tapped home with a rubber mallet or the wooden handle of a
trowel. It is sound practice to remove the occasional tile to ensure that good
contact has been achieved.
6.10.5 Clean off any surplus adhesive remaining on the face of tiles and between the
joints with a damp sponge before the adhesive dries.
6.10.6 Never butt joint tiles. Joints are required to allow the individual tiles to move
with respect to each other and thus avoid a compressive stress build-up. They
are also required as vents for the tile adhesive to cure. The joints between
porcelain tiles must be a minimum of 3mm wide.
6.10.7 Pot life of the adhesive will vary with climatic conditions. Under no
circumstances should adhesive which has been left standing for too long be
reconstituted by adding more liquid.
6.10.8 Do not tile over structural, expansion or cold joints in the background. These
joints must be extended through the various layers to the surface.
6.11 GROUTING
6.11.1 Application Process
Grouting must not be carried out until sufficient bond has developed between
the bedding mix and the tiles to preclude disturbance of the tiles during the
grouting operation. Allow a minimum of 4 hours before grouting.
litres of TAL BOND (replacing the water in the mix) for filling tile joints
up to 8mm wide.
6.11.2.2 WARNING :
Particular care must be taken to clean the grout off the tile face
before it hardens completely. This is especially important when a
latex additive such as TAL BOND has been used.
A sample of the tiles to be used should be tested beforehand to
ensure that no grout is absorbed into the tile body, causing
permanent staining of the tiles.
It is important to use the stipulated amount of liquid in the TAL
grout mixture. When cleaning, a damp, not wet, sponge must be
used. Over hydration (too much water) of the mix, or in cleaning,
causes colour variations in the grout joints, and also affects the
integrity of the grout, resulting in a friable product.
6.11.3.2 Add ALL the Hardener to ALL the Resin in the bucket and mix
thoroughly, scraping down the sides, until the mix assumes a uniform
colour. A MECHANICAL MIXER IS ESSENTIAL FOR GOOD MIXING.
6.11.3.4 Apply TAL FINE EPOXY GROUT with a squeegee or palette knife.
6.11.3.5 Scrape the excess off immediately and wipe the installation with a
damp (not wet) sponge, cleaning the sponge regularly in a bucket of
clean water.
6.11.3.6 Do not use excessive water and do not wet the joints before grouting.
6.11.3.7 A mix is useable for approximately 1 hour at 20ºC, after which time
any portion unused must be discarded. In hot conditions the pot life
may be shorter.
6.11.3.9 NOTE:
If any epoxy is inadvertently spilled onto the tile face, it must be
removed using a damp cloth or sponge before it hardens.
Spillage should be avoided as far as possible at it causes
unnecessary waste of material and time. Cured epoxy is very
difficult to remove, so the area must be cleaned as soon as
possible after grouting.
Any faint haze left on the tiles after completion of grouting may
be removed using TAL EPOXY CLEANING FLUID.
A sample of the tiles to be used should be tested beforehand to
ensure that no grout is absorbed into the tile body, causing
permanent staining of the tiles.
6.12.3 Movement joints should also be located around the perimeter of all floors, in
all vertical corners, against obstructions fixed to the structural background and
over all discontinuities in building materials, e.g. at interfaces of concrete and
brickwork. In addition, movement joints should be located around any fixtures
protruding through the tiled surface such as columns or stairs.
6.12.4 Movement joints should also be created on either side of all sliding door
tracks.
6.12.5 The joints should be at least 5mm wide and extend through the tile and
adhesive layers. All structural expansion joints in the background must be
extended through the tiles to the surface. The full width of the structural
joints must be extended through the tiles to the surface.
6.12.6 Where practical, the bulk of the depth of the movement joint can be filled with
TAL SEALMASTER CORD.
6.12.7 Seal the joint using TAL GOLD STAR SEALMASTER 1000 polyurethane joint
sealant in accordance with the manufacturer’s instructions. It is important that
the joint sealant bonds only to the sides of the movement joint.
6.12.8 For the key requirements common to all tiling situations, please refer to SABS
0107-1996 - Code of Practice.
Note: Tiling onto SUSPENDED concrete slabs require special precautions to be taken
as the installation is prone to increased movement caused by slab deflection, loading,
etc. TAL BOND needs to be incorporated in the adhesive mix or a single part flexible
adhesive such as TAL GOLDFLEX needs to be used to allow for the increased
movement.
6.13.1 Allow all new concrete work and screeds to cure for at least 28 days before
proceeding. All new concrete work and screeds must have a moisture content
of 5% or less before tiling can commence. When tiling directly onto concrete,
ensure that the surfaces are clean and free of all traces of curing agents,
laitance and any other surface contaminants, preferably by scarifying.
6.13.2 Any screed must be firmly attached to the underlying concrete, must be
integrally sound (no crumbling, cracking, etc.) and must be of a quality and
consistency suitable for tiling. All defective areas must be removed and the
floor made good before proceeding, using TAL RAPIDFIX or TALCEM. The
surface must be clean and dry and free of all traces of dust, debris, loose
particles and surface contaminants.
Portland cement (by volume), which is applied by block brush. Allow the
priming coat to dry before TAL SUREPROOF is applied.
6.15.2 Apply a coat of TAL SUREPROOF by block brush or red enamel paint roller to
these interfaces. Immediately roll out the SUREPROOF MEMBRANE (200mm
wide) into the wet SUREPROOF with the membrane extending 100mm equally
on either side of the interface, ensuring that there are no wrinkles or air
bubbles trapped beneath the membrane. The membrane must be pushed into
the corners, ensuring that the entire interface is covered with SUREPROOF
MEMBRANE. Apply a heavy topcoat of SUREPROOF to completely saturate the
membrane before the first coat of SUREPROOF dries.
6.17.2 It is essential to ensure that the main SUREPROOF application overlaps the
corner joints/interfaces, i.e. the interface application must be completely
covered by the main area application.
6.18.2 In this tiling situation it is imperative that there is a solid bed of adhesive at
least 6mm thick beneath each tile. Use a notched FLOOR TROWEL.
6.18.3 At no time spread more adhesive than can be tiled onto in 10 – 15 minutes.
Depending on atmospheric conditions, this will normally be around 1 square
metre. This prevents the adhesive from drying or “skinning” before tiles is
applied.
6.18.4 Bed dry tiles (do not soak) firmly into the wet adhesive with a twisting action
to ensure full contact between the background, tiles and adhesive. Tiles
should be well tapped home with a rubber mallet or the wooden handle of a
trowel. It is sound practice to remove the occasional tile to ensure that good
contact has been achieved.
6.18.5 Clean off any surplus adhesive remaining on the face of tiles and between the
joints with a damp sponge before the adhesive dries.
6.18.6 Never butt joint tiles. Joints are required to allow the individual tiles to move
with respect to each other and thus avoid a compressive stress build-up. They
are also required as vents for the tile adhesive to cure. The joints between
porcelain tiles must be a minimum of 3mm wide.
6.18.7 Pot life of the adhesive will vary with climatic conditions. Under no
circumstances should adhesive which has been left standing for too long be
reconstituted by adding more liquid.
6.18.8 Do not tile over structural, expansion or cold joints in the background. These
joints must be extended through the various layers to the surface.
6.19 GROUTING
6.19.1 Grouting must not be carried out until sufficient bond has developed between
the bedding mix and the tiles to preclude disturbance of the tiles during the
grouting operation. Allow a minimum of 4 hours before grouting.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
61
6.19.3 Use grey or coloured TAL WALL & FLOOR GROUT mixed 20kg with 6 litres of
TAL BOND (replacing the water in the mix) for filling tile joints up to 8mm
wide.
6.19.4 WARNING :
Particular care must be taken to clean the grout off the tile face before it
hardens completely. This is especially important when a latex additive
such as TAL BOND has been used.
A sample of the tiles to be used should be tested beforehand to ensure
that no grout is absorbed into the tile body, causing permanent staining
of the tiles.
It is important to use the stipulated amount of liquid in the TAL Grout
mixture. When cleaning, a damp, not wet, sponge must be used. Over
hydration (too much water) of the mix, or in cleaning, causes colour
variations in the grout joints, and also affects the integrity of the grout,
resulting in a friable product.
6.20.2 Add ALL the Hardener to ALL the Resin in the bucket and mix thoroughly,
scraping down the sides, until the mix assumes a uniform colour. A
MECHANICAL MIXER IS ESSENTIAL FOR GOOD MIXING.
6.20.4 Apply TAL FINE EPOXY GROUT with a squeegee or palette knife.
6.20.5 Scrape the excess off immediately and wipe the installation with a damp (not
wet) sponge, cleaning the sponge regularly in a bucket of clean water.
6.20.6 Do not use excessive water and do not wet the joints before grouting.
6.20.7 A mix is useable for approximately 1 hour at 20ºC, after which time any portion
unused must be discarded. In hot conditions the pot life may be shorter.
6.20.8 The installation should not be subjected to normal service conditions until the
epoxy is fully cured (24 – 48 hours for light service conditions, and 7 days for
optimum chemical resistance). Should the grout be exposed to water, cleaning
agents, etc before full cure has taken place the integrity and performance of
the product will be compromised.
6.20.9 NOTE:
If any epoxy is inadvertently spilled onto the tile face, it must remove
using a damp cloth or sponge before it hardens. Spillage should be
avoided as far as possible at it causes unnecessary waste of material and
time. Cured epoxy is very difficult to remove, so the area must be cleaned
as soon as possible after grouting.
Any faint haze left on the tiles after completion of grouting may be
removed using TAL EPOXY CLEANING FLUID.
A sample of the tiles to be used should be tested beforehand to ensure
that no grout is absorbed into the tile body, causing permanent staining
of the tiles.
6.21.3 Movement joints should also be located around the perimeter of all floors, in
all vertical corners, against obstructions fixed to the structural background and
over all discontinuities in building materials, e.g. at interfaces of concrete and
brickwork. In addition, movement joints should be located around any fixtures
protruding through the tiled surface such as columns or stairs.
6.21.4 Movement joints should also be created on either side of all sliding door
tracks.
6.21.5 The joints should be at least 5mm wide and extend through the tile and
adhesive layers. All structural expansion joints in the background must be
extended through the tiles to the surface. The full width of the structural joints
must be extended through the tiles to the surface.
6.21.6 Where practical, the bulk of the depth of the movement joint can be filled with
TAL SEALMASTER CORD.
6.21.7 Seal the joint using TAL GOLD STAR SEALMASTER 1000 polyurethane joint
sealant in accordance with the manufacturer’s instructions. It is important that
the joint sealant bonds only to the sides of the movement joint.
6.21.8 For the key requirements common to all tiling situations, please refer to SABS
0107-1996 - Code of Practice.
7.1 HARDWOOD
Hardwood is to be the best-selected quality, well-seasoned, and kiln dried.
Joints between boards are to be covered with scrim wire and the joints are to be
plaster skimmed.
Skimmed ceilings may be required to highlight or define certain areas on the trading
floor and entrances. Refer to the Shoprite Checkers Architect for detailed drawings.
Fixing and roof guarantee must be provided to the Shoprite Checkers Architect.
Note that the trading floor will be insulated with 50mm Isoboard, and all other areas
insulated with Sisalation, all fitted over purlins.
A 0,6mm galvanised mild steel plate is to be fitted to the outside face of all external
doors.
8.2 SCREWS
All visible screws are to be of the same metal, colour and finish as the parts they
secure, solid and not plated.
8.3 KEYS
Each lock must be supplied with two keys.
8.4 STAMPING
All locks must be stamped with a reference number and the keys must be similarly
stamped with a corresponding number to the lock which they control.
8.7 LOCKS
All locks throughout the premises are to be 3 or 4 lever Mortice locksets with lever
furniture as approved.
Pressed steel doorframes for coastal areas are to be hot-dip galvanised before leaving
the manufacturer’s works.
9.4 BULKHEADS
Skim plastered Rhino board bulkheads supported on steel framework (steel
substructure supported from roof structure) to be erected over service departments
and various other areas of which the extent will be indicated on the SRC Architect
work drawings. Bulkhead structural support needs to be provided as per the
Structural engineer's detail.
Bulkheads for Checkers and Checkers Hyper stores usually start between 2,7m – 3,3m
above FFL, extending (depending on circumstances) to either 4,5m or tie beam or full
height to underside of ceiling. Refer to the work drawings of the SRC Architect.
9.7.1 Anodizing
Anodising is to be Grade A quality (25 microns) for coastal regions. Samples
are to be submitted for approval.
9.7.3 Construction
Construction is to comply with the minimum performance requirements
contained in the relevant “Selection Guides” as published by AAAMSA from
time to time.
Designs not covered by AAAMSA are to comply with SANS 10160 in particular
and current National Building Regulations.
The manufacturer must at all times ensure that contact between incompatible
materials is prevented.
The Shop front Manufacturer is to take responsibility for the design stability
and performance of his units, and is to provide workshop drawings for final
approval before manufacture commences.
9.7.4 Fittings
Weather sealing is to be of materials that are compatible with aluminium and
to be such that any degradation, shrinking, warping or adherence to sliding or
closing surfaces does not impair the performance of the installation.
Glazing beads, gaskets and glazing compounds are to be of materials that are
compatible with the aluminium, finishes, the glass and any other glazing
materials.
Doors are to be fitted with deadlocks and flush bolts on the leading edge of
the doors.
All locks are to be of the replaceable cylinder type, temporary cylinder being
provided during building operations and the final cylinders handed to
Shoprite Checkers at the time of Beneficial Occupation.
9.7.5 Glazing
All glass to shop fronts is to be safety glass and glazing is to be carried out in
accordance with current National Building Regulations read in conjunction
with SANS 10137 : 2002, as well as other applicable SANS Standards and SABS
0400.
All gaps between channel guides and walls and at the top and the bottom of
roller shutter doors are to be suitably sealed.
9.8.2 Receiving
Refer to Door Schedule for details in Section 21.2.
10.7 STONEWARE
To comply with SANS 559.
10.8 GRATINGS
To comply with SANS 60335-1: 1995.
In the event that water pressure is below 3 bar non-metallic ball-floats intended for
use with ball valves specified above are to comply with SANS 1006.
All water taps and stopcocks are to comply with the requirements of SANS 266: 2000
and bear the standardisation mark of the South African Bureau of Standards.
With the approval of the SRC Architects, water taps (metallic) are to comply with
SANS 226.
Provide a cast iron meter box of suitable size, with a hinged lid, set level in the ground
on a half brick chamber, built up from bottom of pipe trench in cement mortar.
The capacity of electrical hot water cylinders for the various areas is as follows:
(a) Tea kitchen (Canteen) and all toilet facilities 150 litre
(b) All Service Departments (i.e. Butchery/Deli’s,
Bakery, Fish etc.) 200 litre
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
73
It may be possible in certain instances to share hot water cylinders between facilities.
It will be up to the sole discretion of the SRC Architect.
Refer to SRC Architect/ Plumbing consultant drawings for number and positions of
cylinders.
Water taps are reviewed frequently and the make and model may differ from the time
when the specification is considered by the developer to when work drawings are
prepared by the SRC Architect. The SCR Architect work drawing specification will then
supersede this specification at no additional cost to Shoprite Checkers (Pty) Ltd.
Ball valves are to comply with the requirements of SANS 752: 2000 and bear the
standardisation mark of the South African Bureau of Standards.
10.20 SINKS
Stainless steel sinks with drainers and 150mm high splash backs are to be supplied
and fixed to steel pipe supports all set 100mm clear from walls.
All sinks are to have 38mm waste outlets and 25mm diameter overflow pipes
connected to the drain above the trap.
All service departments to be provided with prep sink and a double bowl pot sink.
Refer to Schedule of Finishes Section 20.
Refuse Room
Hand wash basins are reviewed frequently and the make and model may differ from
the time when the specification is considered by the developer to when work
drawings are prepared by the SRC Architect. The SCR Architect work drawing
specification will then supersede this specification at no additional cost to Shoprite
Checkers (Pty) Ltd.
10.22 URINALS
Ceramic as per Schedule of Finishes or as shown on the SRC Architect's drawing.
Urinals are reviewed frequently and the make and model may differ from the time
when the specification is considered by the developer to when work drawings are
prepared by the SRC Architect. The SCR Architect work drawing specification will then
supersede this specification at no additional cost to Shoprite Checkers (Pty) Ltd.
Pans are to be fitted with double flap heavy-duty type seats on chromium plated
hinge fixings.
10.24 CISTERNS
Refer to Schedule of Finishes Section 20.
This pipe is to project 50mm above finished floor level and to be fitted with a 15mm
diameter gate valve.
The outlet is to terminate 2,550mm above finished floor level with stop valve and
threaded T-piece. New paint added.
10.30 OVERHEAD SPRAY UNIT FOR FRUIT & VEG AND FISHERY
Provide a 38mm diameter water supply pipe to overhead spray point as indicated on
the SRC Architect's drawings.
This condensation drain may also serve all cold and freezer rooms and refrigerated
cabinets. The condensation pipe is to be suitably trapped and vermin proofed at the
exit to the main sewer line. These outlets are to discharge over galleys. The
condensation drain is to have a minimum fall of 1 to 80.
10.37 GULLEYS
Gulley’s are to be formed with a 100mm diameter PVC gulley trap.
Drip tray detail to be submitted and approved by the SRC Architect. Drip tray to slope
with the slope of the piping with a minimum 50/75mm outlet at the end of the tray.
Drainage from tray to discharge into an open area specified by the SRC Architect.
10.44 TRENCHING
All trenching, bedding and backfill shall be in accordance with SABS 1200-DB/L/LB/LD
(as amended) or an approved equal and to the manufacture's recommendations.
All excavation and backfill shall be by the Plumber. The Plumber shall be responsible
for the coordination of the trench routing, slope and elevation and shall supervise the
grading, backfilling etc. of trenches in which plumbing work is laid.
Normal fillings of the trench should then proceed in layers not exceeding 300mm in
thickness, each layer well rammed. Heavy mechanical rammers should not be used
until the fill has reached a depth of 300mm above the top of the pipe. Special
consideration and selection of backfilling material will be necessary. That is, no stones
or rocks are to be in the backfilling mentioned below.
10.47 COMPACTION
Compaction under paved areas and under roads shall be kept to within 2% of the
optimum moisture content while compacting, it to the specified density. Compaction
will be carried out in layers as described in the previous paragraph. A 95% modified
AASHTO density shall be applicable where no density is specified. Except for the
above cases, the major part of the backfilling of pipes shall be done to 80% modified
AASHTO or unless specified by the Structural Engineer.
In addition to these the SRC Architect may elect to paint different colours and or
paint types in different areas at no additional cost to Shoprite Checkers (Pty)
Ltd.
All oil paints, oil stains, varnish, linseed oil, knotting, driers, distempers, etc. are to be
the best of their respective kinds and of approved brand and colour. Each coat of
paint is of a distinctive colour selected by the Shoprite Checkers Architect.
All materials for paintwork, for which South African Bureau of Standards Specifications
have been published, are to comply with the requirements of such specifications and
bear the standardisation mark of the Bureau. Materials for paintwork for which no
SANS Specification has been published are to be of brands approved by the Shoprite
Checkers Architect.
All materials for paintwork must be brought on to the site in unopened containers
and no adulteration is allowed.
Undercoats for paintwork are to be supplied by the manufacturer of the paint being
used for the finishing coat.
The various primers, undercoats, paints, eggshell, etc. are to comply with the
requirements of the specifications quoted hereunder and to be of the type and grade
stated:
(a) Wood Primer: SANS 678, Type I for exterior woodwork and Type III for interior
woodwork.
(b) Metal Primer: For steel windows, doors, doorjambs and other articles normally dip
or spray primed at the manufacturer's works – SANS 5909.
(c) Metal Primer: SANS 679, Type I.
(d) Undercoats: For all surfaces under High Gloss, Oil Gloss, Flat and Eggshell finishing
paints – SANS 681, Type II.
(e) High Gloss Enamel Paint: SANS 630, Grade I.
(f) Flat Paint: SANS 515.
(g) Acrylic Emulsion Paint (Interior): SANS 1586: 1995, Grade I (Polyacrylic Resin Base).
(h) Acrylic Emulsion Paint (Exterior): SANS 1586: 1995 (Polyacrylic Resin Base).
Woodwork being painted is to be brushed down, knots treated with knotting and all
surfaces primed, stopped with hard stopping and rubbed down to an even surface.
Woodwork being oiled or stained must be thoroughly cleaned, stopped with tinted
stopping and well rubbed down.
All metal surfaces being painted are to be cleaned of all rust, scale, dirt, salt deposits
and grease by scraping, brushing or degreasing with alkali detergent solution as
required.
New galvanised metal surfaces and surfaces of all non-ferrous metals being painted
are to be cleaned down as above and given one coat of wash primer (metal etch
primer) complying with the requirements of SANS 723. After cleaning off rust on
metal work, the portions so affected are to be treated with an approved rust inhibitor.
All plastered surfaces being painted are to be filled where necessary with suitable
stopping and rubbed down.
All ceilings cover strips and cornices being painted are to be filled where necessary
with suitable stopping and all nail heads are to be primed with flat paint.
All work to be finished to colour approved by the Shoprite Checkers Architect. The
tints of undercoat are to approximate those of the finishing coat but with a slight
difference in the tint of each coat.
Backs of frames and other joinery in contact with brickwork, etc. must be primed
before building in, whether the article is painted or not.
Wood fillets, cover strips, etc. are to be knotted, primed and stopped before being
coated with emulsion paint or eggshell.
All prime coats are to be applied by brush, the priming being well brushed in to
obtain maximum penetration.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
81
The use of a spray gun on site is not permitted, except in the case of cellulose or
other special paints where spraying is the accepted method of application.
All materials are to be used in strict accordance with the manufacturer’s instructions.
Steel windows, burglar bars, pressed steel door frames and other metal work built in
as the work proceeds and primed before being built, must be cleaned and rubbed
down on exposed surfaces, touched up with zinc chromate primer where required,
and painted with one undercoat and one coat high gloss enamel paint.
All other exposed metalwork, except cast iron pipes, must be cleaned down, primed
with zinc chromate primer and painted as above.
General glass is to comply with the requirements of SANS CK 55 and safety glass with
the requirements of SANS 1263-1.
Sheet glass, unless otherwise specified, is to be clear float glass of ordinary glazing
quality, free from bubbles, stains or scratches, 4mm thick.
Obscure glass, unless otherwise specified, is to be small arctic glass, 4mm thick.
(a) High impact Fadeban (9,5mm thick) is to be used to all fixed and opening
sections below door head height in external shop fronts.
(b) Normal strength Fadeban (6,5mm thick) is to be used to all fixed and opening
sections above door head height only in external shop fronts.
(c) Glass for adjustable glass louvers is to be clear sheet glass, 6mm thick.
12.2 GLAZING
Glazing to shop fronts is to be in accordance with SANS Code of Practice “Glazing and
Fixing Glass in Buildings” and as required by the National Building Regulations and
any other current regulations.
Glass panes exceeding 0,4m2 in area must, in addition, be secured with glazing
springs in wood sashes and with glazing clips inserted in holes in steel framing.
All other windows, fanlights, etc. shall be glazed with clear sheet glass.
12.3 MIRRORS
Over all wash hand basins fix 400mm wide x 600mm high x 6mm thick bevel edged
silver plated glass mirrors to wall with double-sided adhesive tape.
12.4 WINDOWS
Glaze all external windows from the inside.
Prime fully with bitumen primer all verges, flat surfaces and other areas to receive the
waterproofing membrane (allow solvents to flash off). The roof shall be waterproofed
by one layer of 4mm thick Derbigum SP (or similar product approved by the SRC
Architect) sealed to the roof deck by torch-on fusion. Side-laps of 75mm and end-
laps of 100mm shall be sealed together by torch-on fusion. Turn-ups and turn-downs
shall be similarly fused to the primed surface and well fixed to angles, outlets, fillets
and flat edges, including all square cutting and waste. This work shall be done in
strict accordance with the manufacturer’s specifications and recommendations.
The contractor shall lodge a 10 year insurance backed watertight guarantee on all
roof waterproofing with the SRC Architect prior to the commencement of the work.
13.3 SPECIALISTS
The specialists must be satisfied with the grading, screeds, etc. before any
waterproofing is laid.
13.4 SURFACE-BEDS
Damp proof membrane across brick foundation walls and under surface beds shall be
250 micron PVC sheeting laid in accordance with manufacturer’s instructions.
13.5 WATER-TIGHTNESS
The premises shall be rendered completely watertight and any defects allowing the
ingress of rain or seepage shall be rectified by the Owner/Developer at his own cost.
13.6.2 Food Prep Areas, Service departments, Cleaners Room, Toilet Areas, Staff
Canteen Prep and Wet Returns Room
Sika Cemflex with membrane in service area on slabs. (Refer to detail DET05
and the SRC Architect's drawings).
Provision shall be made for differentiation between heavy-duty traffic and general
customer parking.
The final surface of the parking area must be either concrete, brick paving,
interlocking cement paving or premix of appropriate specification.
The general planting and landscaping of external areas and their maintenance must
be to the approval of the Local Authority and Shoprite Checkers (Pty) Ltd.
14.2 DEMARCATION
Parking areas, driveways, etc. shall be demarcated in accordance with accepted
standards, allowing for adequate circulation of customer vehicles and separation from
delivery vehicles.
Parking bays shall be of minimum size 5,0m x 2,5m. Width of isles between parking
bays shall be 7,5m minimum.
The development must make provision for adequate routes for the collection and
replenishment of trolley bays in the supermarket. (Specifically multi-level shopping
centers and preferably not by means of customer service lifts).
The position of trolley parking bays and the protection of it from damage by
customer vehicles shall be as indicated by the SC Architect or assigned Shoprite
Checkers representative.
14.4 BOLLARDS
Bollards may be required at exits from the premises to:
14.5 SIGNAGE
Parking bays for the disabled shall be demarcated and suitably signposted with
international signs.
All pole and indicating signs shall be protected by suitable bollards or crash rails and
shall be mounted on raised walkways.
All appropriate signage to ensure the free flow of traffic, the direction of the public
and the prohibition of entry, shall be demarcated and/or erected in accordance with
acceptable standards.
On »
300mm G7 selected material, CBR>15 compacted to 93% MOD AASHTO
density (100% for sand);
On »
Fill material from site or imported, compacted as described under Filling;
On »
In-situ material, compacted to 93% MOD AASHTO density.
14.7.4 Filling
Backfilling material must be placed in layers not exceeding 200mm and each
layer must be compacted to 93% MOD AASHTO density. If sand is used for
the backfilling, it must be compacted to 100% MOD AASHTO density.
(a) Grading analysis and Atterberg limits for each type of material used;
(b) CBR results for each type of material used;
(c) Thickness of each selected layer; and
(d) MOD AASHTO density tests for all the layers.
Frequency of tests for every layer, selected layer (thickness as specified) or fill
(200mm).
The Contractor shall forward results of all laboratory tests to the Engineer for
approval.
The entire installation must comply with the by-laws of the Local Power Supply
Authority, international standards applicable to the geographical areas and/or the
South African Bureau of Standards (SANS) Code of Practice 10142 and the latest
amendments thereof, where applicable.
The SANS code of practice 10142 will govern the minimum standards of systems,
material and workmanship.
The Developer must pay costs such as connection fees, project approval
fees, etc. which will be due to the Local Supply Authority.
15.1.2.4 Supermarket
The electrical installation shall consist of the main cable supplies, main
distribution board, sub-main distribution boards, reticulation systems,
lighting, power, emergency power supply unit, voltage stabilising control
units (CVT’s), auxiliary services, wire ways and conduit system, etc. This is
also to include a mains power check meter of the mullet function
electronic memory type and space allocation for a full automatic power
factor control unit for Checkers.
The sleeves and ducts for cable reticulation will be supplied and installed
by the Developer and his Electrical Contractor must allow for attendance
to the Main Contractor to ensure the correct placement of the
aforementioned. The Developers Electrical Contractor must also protect
the open ends of the sleeves against ingress of water and debris. The
sleeves must also be sealed off after cable installation to render same
vermin proof.
Where possible, the CVT should be a part of the main distribution board.
Power factor capacitors shall be in its own enclosure next to the Main
distribution board with a physical separation between the two to prevent
a fire from spreading from one unit to the other.
Monitoring Meter
A Monitoring Meter, measuring the supermarket load only, must be
supplied, installed and commissioned for every main incomer of the
supermarket.
The monitoring meter will be an Elster Kent A1700 Type (3 phase 4 wire
Class 0,5 meter) and must be ordered with the following communication
devices and settings:
This meter will remain the property of the supermarket and may not be
used by the reseller or supplier to bill the supermarket on. A separate
meter needs to be installed for billing purposes.
Billing Meter
A meter used for measuring and billing the supermarket supply should be
installed as per the Electricity Reseller requirements. This meter should
not be confused with the Monitoring Meter. The Billing Meter is to be
installed such that it is accessible to the Electricity Reseller or Supplier and
should not be installed within the supermarket premises leasable area or
MDB as far as possible.
allow for the termination of the cable onto or inside the board,
connecting onto the main switch and ensuring correct phase rotation. As
the final position of this board is not known at this stage, 5m of additional
cable must be provided for.
The final connection from the Isolator to the HVAC equipment will be by
others. It is essential that the Electrical Contractor co-ordinate the
positions of isolators with the HVAC Contractor.
All field wiring for the main A/C equipment and controls will be supplied
and installed by others (unless otherwise instructed via the Checkers
Electrical Design Consultant).
Refer to the layout drawing of the Electrical Consultant for the position of
the plant outside the supermarket, which will determine the route of
supply and return cables between the auto mains failure panel and MDB
Emergency Section/DB1 Emergency Section.
New stores with GLA between 3,000m² and 5,000m² : Prime Rated
at 600kVA.
The above sizes are indicative and it remains the Electrical Design
Engineer’s responsibility to calculate the generator size and submit
calculations to the Checkers Technical department for review and
approval.
Automatic Mains Failure Control Panel will be fitted with the following:
Set mounted heavy gauge sheet metal cubicle primed with etch type
zinc chromate and finished with two coats baked enamel and fitted
with the following components:
Voltmeter Phase to phase and Phase to neutral;
Frequency meter;
Ammeters for each phase;
Indicating LED light to indicate generator on load/set on automatic
and load on normal supply;
Set generator start/stop push buttons for manual control;
Audible alarm switch.
Equipment to automatically shut down the set and indicate the respective
fault should any one or more of the following faults occur, as a minimum:
Start failure
Low oil pressure
High engine temperature
Low fuel supply
Over speed
The Checkers IT Department will confirm the size (kVA) UPS required with
associated battery run time at specified load. The Electrical Contractor
must confirm unit requirements prior to procurement.
The approved supplier are Tower UPS Distribution (3300 Series) for all
units. This needs to be confirmed with Checkers as suppliers might have
change.
Technical Specification
VA rating 20 000VA (To be confirmed)
Voltage 400V +/- 2%, 3-phase in & 3-phase out
Waveform sine wave
Input pf 0,98
Input current THD THD <9% (<5% with optional)
Frequency 50Hz
Overload 110%
Battery runtime 40 minutes at full load
Batteries 12 V 7 AHR lead acid (maintenance free)
Recharge time 5 - 8 hours
Noise (at 1m) 45dBA
Display LED Type
Ports RS 323, RJ 11, RJ 45
Scanning points.
The number and position of the fittings will be determined by the store
layout and as shown on the lighting drawings.
Conduits are to be allowed in the floor slab for EAS equipment. Draw
boxes and conduits to be installed in positions and reticulated as shown
on the drawings.
Socket and Data Outlets for electronic displays will be provided on back
wall at heights as shown on drawings.
Lighting Provision
For Checkers, the light fittings to be installed in the ceiling are recessed
LED downlighters, the number and position of the fittings will be
The lights are to be switched with the trade floor lighting circuits.
15.1.6.3 Kiosk
Power & Data Provision
Power skirting will be provided in the counter by the Store Shop Fitter.
16A Switched Sockets normal power (white socket) and 16A Dedicated
Switched Sockets (red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Sockets and outlet points for the following will be provided as shown on
the detail drawing:
Coffee Bar Equipment;
Cigarette Displays & Fridges;
Under counter Geyser;
Ice Cream Freezer;
Soft Serve Machine.
Lighting Provision
For Checkers, the light fittings to be installed in the Ceiling are recessed
LED downlighters, the number and position of the fittings will be
determined by the store layout and indicated as such on the lighting
drawings.
The lights are to be switched with the trade floor lighting circuit.
16A Switched Sockets normal power (white socket) and 16A Dedicated
Switched Sockets (red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Socket and data outlets for electronic displays will be provided on back
wall at heights as shown on drawings.
Lighting Provision
For Checkers, the light fittings to be installed in the Ceiling are recessed
LED downlighters,
The number and position of the fittings will be determined by the store
layout and as shown on the lighting drawings.
A Key Switch to control the store trade floor and associated area lighting
for each stage will be provided at the manager’s office or at the front
entrance. A control wire will be provided to the relevant DB as shown on
the schematic diagrams.
The lights are to be switched with the trade floor lighting circuits.
16A Switched Sockets normal power (white socket) and 16A Dedicated
Switched Sockets (red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
The following control and display panels are to be installed on the back
wall of the office:
Roof Vent or Smoke Extract fan either or being applicable to store
fire design;
Fire Detection;
Intruder alarm Keypad;
Refrigeration remote panel;
Air Conditioning control panel.
The outlet boxes to the panels are to be installed at heights and positions
as shown on elevation drawings so as to ensure panels line up in a neat
manner.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers. The number and position of the fittings will be
determined by the store layout and as shown on the lighting drawings.
16A Switched Sockets normal power (white socket) and 16A Dedicated
Switched Sockets (red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers.
The number and position of the fittings will be determined by the store
layout and as shown on the lighting drawings.
16A Switched Sockets normal power (White socket) and 16A Dedicated
Switched Sockets (Red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Dedicated sockets at high level are required for the Data Cabinet and on
the Powerskirting rising to the ceiling for equipment in the shelfs of the
cupboard.
The data trunking from the tills and for the trading floor shall be linked to
the IT cabinet. The consulting engineer to ensure the correct amount of
trunking is indicated to cater for all the IT cables. The UPS unit and
battery cabinet will be located in this room and connected to the DB as
shown on the Schematic diagrams. Sufficient slack must be allowed on
the trailing cable to the DB so as to allow the unit to be drawn away from
the wall.
The Air-Conditioning unit in the room will be a split type and the isolator
must be wired to an Emergency circuit.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers. The number and position of the fittings will be
determined by the store layout and indicated as such on the lighting
drawings.
16A Switched Sockets normal power (White socket) and 16A Dedicated
Switched Sockets (Red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers. The number and position of the fittings will be
determined by the store layout and indicated as such on the lighting
drawings.
Access Control
The Security doors to the office are interlocked to limit one person access
at a time. Access will be by means of a tag reader or intercom.
The conduits and outlet point must be installed as shown on the layout
drawings for the access control infrastructure.
16A Switched Sockets normal power (White socket) and 16A Dedicated
Switched Sockets (Red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers. The number and position of the fittings will be
determined by the store layout and indicated as such on the lighting
drawings.
Cash Safe
A pilot light must be installed above the safe door on the office side wired
to a light switch located inside the safe. This light switch will control both
the light fitting inside the safe together with the pilot light. A buzzer
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
107
installed above the safe door must be controlled from bell press inside
safe
A draw box and conduit linked to the intruder alarm system must be
installed on the inside of the safe.
16A Switched Sockets normal power (White socket) and 16A Dedicated
Switched Sockets (Red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Power skirting will be installed vertically from the ceiling void to the under
counter power skirting for CCTV system field wiring.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay in LED luminaires
with prismatic diffusers. The number and position of the fittings will be
determined by the store layout and indicated as such on the lighting
drawings.
NOTE: All “red” sockets + normal “white” sockets are supplied with the
checkout unit. Wiring to be completed by the Electrical Contractor.
Lighting Provision
For Checkers stores, if there are no ceilings then a continuous suspended
LED linear fitting.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
16A switch socket outlets for the beverage fridges will be mounted on a
wiring channel at 500mm AFFL behind the fridges. Conduits to the wiring
channel to be cast into the floor slab.
P8000 and P9000 channel suspended above lighting channels to link data
and power from BOH receiving office and service departments to front of
house offices will be installed as shown on the layout drawings. The same
channel combinations will be provided to cross over from the scanning
room to the check-out gantry as shown.
Any cable ladder visible on the trading floor should be fitted with a cover
or be perforated cable tray.
All trunking and cable ladders/trays visible on the trading floor should be
painted either by the builder or powder coated before installation. The
require colour should be confirmed by the Architect.
Lighting Provision
Specialist areas (such as fruit and veg area, Kitchen Shop, etc.) will
have different fittings such as track spots etc. as indicated in the
luminaire schedule and the drawings.
The average light intensity in new stores will be designed for a minimum
average of 1,200lux initial intensity and approximately 1,000lux
maintained over the entire trading area.
It will be required from the Electrical Contractor to liaise with both the
A/C and the Refrigeration Contractor during the construction period, to
prevent any clashes resulting in abortive works and delays. The Electrical
Contractor must protect the trunking installations against damage by
others. Deformed or damaged systems are not acceptable, and
replacement thereof will not be to the client’s account.
The wiring to the various rows of P2000 (41 x 41mm) galvanised wiring
channel feeding and supporting the light fittings, shall be done via P9000
(75 x 128mm) wiring channel at a level of approximately 300mm above
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
110
Where rows of light do not coincide with the purlins for fixing, a portion
of additional P2000 must be fitted between two purlins for suspension
purposes. Wiring channel to be painted the same colour as the trusses.
Trade floor light fittings should not be suspended lower than 3,800mm
AFFL with the optimum height being 4,300mm AFFL. The suspension
height however to confirmed with the electrical design consultant prior to
fixing rows of P2000 channel.
Minimum wiring size will be 2,5mm2 copper conductors and circuits over
60m will be reticulated with 4mm2 copper conductors.
The lighting to the trading area shall be controlled by means of two key
switch at the manager’s pulpit or front door, to select 40% (emergency
circuits) and a further 60% (normal circuits). Some night lights will stay on
24 hours. These circuits will be indicated on the lighting layout drawings.
Shelves stocked with electrical appliances will be fitted with LED strip type
luminaires. The specification for the type of LED luminaires together with
the fixing detail will be provided by the Electrical Design Engineer once
the location of the appliance shelf has been determined.
The fixing and connection of the LED lights will be done by the Electrical
Contractor.
15.1.6.13 Dispensary
Power & Data Provision
Power skirting will be provided in the dispensing counter by the Store
Shop Fitter. 16A Switched Sockets normal power (White socket) and 16A
Dedicated Switched Sockets (Red socket shaven earth) will be installed by
the Electrical Contractor and wired as shown on the drawings.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
111
Note that the SSO for the fridge in the kitchen is on emergency supply.
Lighting Provision
Light fittings to be installed between racks will be lay in 600 x 600 LED
fittings and recessed LED downlighter over the counter and indicated as
such on the lighting layout drawings and specified in the legend.
15.1.6.14 Deli
Power & Data Provision
The basic electrical installation to these areas is to be completed before
the commencement of the Beneficial Occupation period. A large variety
of fixed and loose standing equipment will only be placed in position
after commencement of Beneficial Occupation. The Electrical Contractor is
required to co-ordinate with the equipment supplier, and to perform the
final connections in a neat, robust and flexible manner. The final
connection from power outlets to equipment must be wired with
insulated heat resistant wiring.
The power outlets (three and single phase) and SSO indicated on walls as
per the electrical layout drawings must be fed by means of a 25mm
diameter conduit, installed from the DB via the floor slab, terminating in
draw boxes at the heights indicated on the drawings.
Should equipment however been located against a wall, the three phase
electrical outlets will be hard wired from recessed Isolators at 1,400mm
AFFL, located to the side of the equipment. Connection will be by means
of an outlet point located behind the equipment in the form of an un-
switched 5-Pin socket and plug top. All wiring will be routed via recessed
conduits. The position shall be as per the Electrical Engineers drawing.
The DB will be recessed and must be dust proof rated. The DB will be
positioned at a location out of public view and will have a white epoxy
finish. Circuits and wiring sizes are as per schematic diagrams.
Data and telephone on walls will consist of a 100 x 100 x 50mm draw box
with blank cover at height indicated.
Hand wash basins are fitted with auto taps. Supply to the auto tap will be
by means of a transformer in the ceiling, plugged into a 16A socket
located in the ceiling void above the basin. A 25mm dia. conduit flush to
the wall will be extended from the ceiling void (adjacent to socket) to
underneath the basin, ending in a 60mm dia. draw box. Wiring from the
auto tap transformer to the basin tap will be drawn in for final connection
by others.
A STOP/START (S/S) station for the extract canopy fan control will be
positioned as per the layout drawing. Fan Motor control (MCC) will be
provided either in the local DB or in the HVAC Contractors control panel.
The location of the MCC must be confirmed with both the Electrical and
Mechanical Consultant prior to installation. Cabling according to the
schematic diagrams must be installed to an appropriate Isolator within
1,5m of the fan motor.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay-in LED luminaires in
the lay in ceilings and recessed LED down lighters in the bulkhead.
Note the extract canopy will be fitted with its own luminaires and the
Electrical Contractor is to allow for connection for this canopy luminaire to
the lighting circuit.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
15.1.6.15 Bakery
Power & Data Provision
The basic electrical installation to these areas is to be completed before
the commencement of the Beneficial Occupation period. A large variety
of fixed and loose standing equipment will only be placed in position
after commencement of Beneficial Occupation. The Electrical Contractor
is required to co-ordinate with the equipment supplier, and to perform
the final connections in a neat, robust and flexible manner. The final
connection from power outlets to equipment must be wired with
insulated heat resistant wiring.
The power outlets (three and single phase) and SSO indicated on walls as
per the electrical layout drawings must be fed by means of a 25mm
diameter conduit, installed from the DB via the floor slab, terminating in
draw boxes at the heights indicated on the drawings.
The DB will be recessed and must be dust proof rated. The DB will be
positioned at a location out of public view and will have a white epoxy
finish. Circuits and wiring sizes are as per schematic diagrams.
Data and telephone on wall will consist of a 100 x 100 x 50mm draw box
with blank cover at height indicated.
Hand wash basins are fitted with auto taps. Supply to the auto tap will be
by means of a transformer in the ceiling, plugged into a 16A socket
located in the ceiling void above the basin. A 25mm dia. Conduit flush in
the wall will be extended from the ceiling void (adjacent to socket) to
underneath the basin, ending in a 60mm dia. Draw box. Wiring from the
auto tap transformer to the basin tap will be drawn in for final connection
by others.
A STOP/START (S/S) station for the extract canopy fan control will be
positioned as per the layout drawing. Fan Motor control (MCC) will be
provided either in the local DB or in the HVAC Contractors control panel.
The location of the MCC must be confirmed with both the Electrical and
Mechanical Consultant prior to installation. Cabling according to the
schematic diagrams must be installed to an appropriate Isolator within
1,5m of the Fan motor.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay-in LED luminaires in
the lay in ceilings and recessed LED down lighters in the bulkhead.
Recessed tilted spots shall be installed in front of the bread baskets.
Note the extract canopy will be fitted with its own luminaires and the
Electrical Contractor is to allow for connection to the lighting circuit.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
15.1.6.16 Fish
Power & Data Provision
The basic electrical installation to these areas is to be completed before
the commencement of the Beneficial Occupation period. A lessor amount
of fixed and loose standing equipment will only be placed in position
after commencement of Beneficial Occupation. The Electrical Contractor is
required to co-ordinate with the equipment supplier, and to perform the
final connections in a neat, robust and flexible manner. The final
connection from power outlets to equipment must be wired with
insulated heat resistant wiring.
The power outlets (three and single phase) and SSO indicated on walls as
per the electrical layout drawings must be fed by means of a 25mm
diameter conduit, installed from the DB via the floor slab, terminating in
draw boxes at the heights indicated on the drawings.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
115
The DB will be recessed and must be dust proof rated. The DB will be
positioned at a location out of public view and will have a white epoxy
finish. Circuits and wiring sizes are as per schematic diagrams. The Fish
Shop can be fed from the Butchery DB if these two departments are next
to each other.
Data and telephone on wall will consist of a 100 x 100 x 50mm draw box
with blank cover at height indicated.
Hand wash basins are fitted with auto taps. Supply to the auto tap will be
by means of a transformer in the ceiling, plugged into a 16A socket
located in the ceiling void above the basin. A 25mm dia. conduit flush in
the wall will be extended from the ceiling void (adjacent to socket) to
underneath the basin, ending in a 60mm dia. draw box. Wiring from the
auto tap transformer to the basin tap will be drawn in for final connection
by others.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay-in LED luminaires in
the lay in ceilings and recessed LED down lighters in the bulkhead.
Recessed tilted spots shall be installed. Note the extract canopy will be
fitted with their own luminaires and the Electrical Contractor is to allow
for connection of this luminaire to the lighting circuit.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings
15.1.6.17 Butchery
Power & Data Provision
The basic electrical installation to these areas is to be completed before
the commencement of the Beneficial Occupation period. An amount of
fixed and loose standing equipment will only be placed in position after
commencement of Beneficial Occupation. The Electrical Contractor is
required to co-ordinate with the equipment supplier, and to perform the
final connections in a neat, robust and flexible manner.
The power outlets (three and single phase) and SSO indicated on walls as
per the electrical layout drawings must be fed by means of a 25mm
diameter conduit, installed from the DB via the floor slab, terminating in
draw boxes at the heights indicated on the drawings.
Note that the one band saw and sealer/wrapping machine are on
emergency power supply.
The DB will be recessed and must be dust proof rated. The DB will be
positioned at a location out of public view and will have a white epoxy
finish. Circuits and wiring sizes are as per schematic diagrams.
Data and telephone on wall will consist of a 100 x 100 x 50mm draw box
with blank cover at height indicated.
Hand wash basins are fitted with auto taps. Supply to the auto tap will be
by means of a transformer in the ceiling, plugged into a 16A socket
located in the ceiling void above the basin. A 25mm dia. conduit flush in
the wall will be extended from the ceiling void (adjacent to socket) to
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
117
underneath the basin, ending in a 60mm dia. draw box. Wiring from the
auto tap transformer to the basin tap will be drawn in for final connection
by others.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay-in LED luminaires in
the lay in ceilings and recessed LED down lighters in the bulkhead.
Recessed tilted spots shall be installed.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings
Lighting Provision
The lighting shall be by means of suspended track and track mounted
LED spot lights.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
Lighting Provision
The lighting shall be by means of track and track mounted LED spot.
Note that this frame may be store specific and the frame type to be
confirmed with the Electrical Consultant prior to ordering light fittings.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
Isolators and outlets for Hand dryers and Auto taps will be positioned as
shown on the drawings.
Lighting Provision
The light fittings to be provided in these facilities are as follows:
Passages – Surface mounted LED Linear fitting;
Toilet stalls – Surface Mounted Linear LED Fitting or Surface mounted
round LED fittings if cubical are full height;
Toilet basins & circulation – Surface mounted LED Linear fitting;
Staff change rooms – Surface mounted LED Linear fitting.
The positions and number of light fittings will be indicated as such on the
lighting layout drawings.
Lighting Provision
The light fittings to be provided are 600 x 600mm lay-in LED luminaires if
there is a ceiling otherwise LED Linear Luminaire.
The positions and number of light fittings will be indicated as such on the
lighting layout drawings.
16A Switched Sockets normal power (White socket) and 16A Dedicated
Switched Sockets (Red socket shaven earth) will be installed by the
Electrical Contractor and wired as shown on the drawings.
Dedicated sockets at high level are required for the Data Cabinet to be
installed by others.
Due to the number of data cables to the cabinet P9000 must be allowed
to the cabinet as indicated.
Lighting Provision
The light fittings to be provided 600 x 600mm lay-in LED luminaires
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
Lighting Provision
The light fittings to be provided in these facilities are as follows:
Drop Temp – Surface Vapour proof LED Luminaire;
Dry Goods – Surface Vapour proof LED Luminaire;
All BOH – Surface Linear LED Luminaire.
The number and position of the fittings will be determined by the store
layout and indicated as such on the lighting drawings.
Access Control
For night drop facility draw boxes on the outside in receiving yard will be
linked to positions in receiving passage by means of 25mm dia. conduits
as shown on the drawings. Draw wires must be installed.
For Conveyors in bulk store a power outlet point must be provided at the
conveyor controls and will be wired to an emergency circuit as shown.
The supply rating and cable will be as shown on the drawings and
schematic diagrams.
Lighting Provision
Although the bulk stores appear on drawings as a double volume space,
Checkers will introduce a Mezzanine floor for extra storage space.
The average light intensity in the bulk store new stores will be designed
for a minimum average of 220lux between racking.
The Electrical Contractor will liaise with both Fire Protection (sprinklers)
and Fire Detection Contractors during the construction period to prevent
any clashes resulting in abortive works and delays.
P2000 (41 x 41mm) galvanised wiring channel feeding and supporting the
light fittings will be fixed under the store mezzanine structure and
suspended from purlins by means of 6mm galvanised rods. The rods will
be fixed at a maximum spacing of 1,5m apart.
Where rows of light do not coincide with the purlins for fixing, a portion
of additional P2000 must be fitted between two purlins for suspension
purposes.
Surface Linear LED Luminaire or Open Channel with LED tubes shall be
installed.
The light fittings are to be spaced and installed as per lighting layout
drawings.
A Dedicated SSO and data outlet shall be installed near the staff
entrances for the Krones Clock.
Access Control
The security mesh doors at the entrance are interlocked to limit one
person access at a time on entry and exit.
The conduits and outlet point must be installed as shown on the layout
drawings for the access control infrastructure. Note point for Emergency
break glass unit must be allowed as shown.
The Electrical will allow for and perform the connection from the point
above the rooms to a 24hr circuit (circuit breaker switched). The
connection may be looped together due to the low power consumption.
The positions and circuits will be indicated on the layout and schematic
drawings.
Lighting Provision
Surface Vapour LED Luminaires shall be installed in these rooms suitable
to withstand the temperature in the room. The Contractor shall ensure
that the fitting does not block the airflow form the blower coils in the
rooms.
The luminaires are installed surface on the room roof panelling. The
Electrical Contractor must ensure wiring through the panel to the light
fitting is formed in a ‘U’ shape to allow any condensation to gather at the
bottom of ‘U’ to drip off and not enter the light fitting.
The light switch controlling the room lights must be fitted with a pilot
light in the toggle to indicate if the light fittings are on.
Data point for scale to consist of recessed 100 x 100 x 50mm draw box
with blank cover. Conduit is to be linked to the data wire-way.
Lighting Provision
Surface Vapour LED Luminaires shall be installed.
The luminaires are installed surface on the room roof panelling. The
Electrical Contractor must ensure wiring through the panel to the light
fitting is formed in a ‘U’ shape to allow any condensation to gather at the
bottom of ‘U’ to drip off and not enter the light fitting.
The light switch controlling the room lights must be fitted with a pilot
light in the toggle to indicate if the light fittings are on.
The lighting circuits will be over ridden by the BOH key switch.
Lighting Provision
Surface LED Luminaires shall be installed.
The light switch controlling the room lights must be fitted with a pilot
light in the toggle to indicate if the light fittings are on.
The number and position of the fittings indicated as such on the lighting
drawings.
Wall mounted LED flood lights will be installed between receiving RSD
and switched by means of a water tight light switch located externally at
the nearest access door.
The number, positions and switching of the light fittings will be indicated
as such on the lighting drawings.
The night lights will remain switched on 24 hours. These are the trading floor lights
connected to the UPS.
All indoor lighting circuits shall be switch from the Key switches other than the 24
hour circuits. Even if an offices or room have a separate light switch it shall still be
switched form the key switches. All the services departments and back of house
lights must be switch off with the 40% trading floor stage.
The switched socket outlets for non-essential circuits must be connected to an Earth
Leakage Unit and must consist of:
Dedicated type with a “shaven” earth pin with RED insert, toggle and cover plate.
15.1.9 Signage
Checkers supermarkets, the illuminated entrance sign and additional outside sign
points are each to be a separate circuit fed from MDB/DB1 via contactors as per
schematic diagrams.
The Checkers supermarkets will have various LED lit signage inside the store on
displays and on bulkheads. Signage will be controlled from MDB/DB1, via a contactor
linked to the stores key switch system.
Draw boxes are to be fitted with white epoxy coated cover plates and distribution
panels are to be fitted with lockable doors.
It will also be required from the Electrical Contractor to allow for draw wires in all
conducts, and to give full assistance to a subsequent specialist.
Note all data conduits are ‘Spur’ reticulated to outlet points at scales, scanners, etc.
Note that the ‘Black’ sockets in the check outs are for the EAS equipment.
Further sockets in the ceiling above the Money market are for the EAS
equipment and wiring circuits must be strictly according to the circuitry
shown on the drawings. All circuits will be on emergency supply
(Generator backed).
The preferred meters are the Elster Kent with LAN card.
15.1.12.5 Sub-Circuits
Each of the line shops is to be fitted out with lighting, power and
telephone points as set out in the drawings. The light fittings are to be of
the approved type and the installation is to be either on the surface or
fitted into the “T” ceiling grid as applicable to the project to render light
level between 350 - 400lux.
Line relays to be installed to shut down aircon system, extraction unit and
an interface link installed to link the intruder alarm system. All conduit
work to be done by the Electrical Contractor, with draw wires in conduit.
All work to be carried out as per SANS 10400 standards and SANS 10139
standards.
South African Bureau of Standards (SANS) code of practice 10142 is to govern the
minimum standards of systems, material and workmanship.
15.2.2 Regulations
The installation shall be erected and tested in accordance with the following
regulations:
(a) The Occupational Health and Safety Act (South Africa);
(b) The Regulations of the local Gas Board where applicable;
(c) The Code of Practice for the Wiring of Premises, SANS 10142 (South Africa) or
the Code of Practice applicable to the Country where the project is carried out;
(d) The local Municipal by-laws and Regulations of the Electrical Supply Authority;
(e) The Standard Regulations of any Government Department, where applicable;
(f) The local and National Fire Regulations; and
(g) Telephone Regulations.
All materials and equipment required are to comply with the requirements of the
approved international standards and the local regulations. All materials are to be of
the best quality; unused, corrosion resistant, in good condition and complete.
The Contractor, without any additional cost to Checkers, is to replace any material
considered faulty or incorrectly erected or badly fixed. The Contractor shall be held
responsible for the correctness of all dimensions as set out.
The Engineer will conduct progress inspections during the execution of the works.
Discrepancies will be pointed out to the Contractor and these are to be remedied at
the Contractor's expense. Under no circumstances shall these inspections relieve the
Contractor of his obligations in terms of accuracy of dimensions, regulations or any
other documented matter.
The Contractor is to supply and install, as part of the tender price, all notices and
warning signs that are required by the relevant laws, regulations and/or the
documents.
15.2.6 Conduit
15.2.6.1 Plain-End Conduit
Bosal conduit with accessories may be used, and the system details must
be submitted to the Engineer for approval if requested. The conduit shall
be hot-dipped galvanised inside and outside.
Light switch boxes are to be 100mm x 50mm x 50mm with 20mm knock-
outs on the sides and one 20mm knockout on the top, bottom and back.
Socket outlet boxes shall be 100mm x 100mm x 50mm with two 20mm
knock-outs each on top, bottom and sides and backs.
All conduits, draw boxes etc., are to be securely fixed to the shuttering to
prevent displacement. Where the Builder uses fibreglass shuttering, the
equipment is to be fixed to the steel only and no holes may be drilled or
made in shuttering. All draw boxes and outlet boxes are to be plugged
with wet paper before they are secured to the shuttering.
When two or more conduits are laid parallel in concrete floors or slabs,
these conduits are to be spaced at least 25mm apart.
All round conduit boxes to be used in concrete must be of the deep type.
No elbows and sharp bends are allowed in the concrete slabs, and sharp
sets must avoided. Draw boxes are to be installed, so as to ensure that
there are nowhere are there more than two 90 degree bends between
one end of a run and a draw box, or between draw boxes. Draw boxes
must be arranged so as to be accessible after completion of the work.
Cover plates for draw boxes and expansion joints are to be of metal, and
finished to suit the finished surfaces, and where possible, draw boxes are
to be grouped under one common cover plate.
All draw boxes, conduits, etc. that are installed in concrete are to be
cleaned with compressed air and provided with draw wires two days after
removal of the shuttering. Errors that occurred during the installation of
the conduits, and any lost draw boxes or blocked conduits, are to be
reported to the Main Contractor and Architect immediately, in order that
an alternative route can be planned before additional concrete is cast.
Any additional cost shall be for the Contractor's account.
The use of inspection bends must be avoided. The conduits are preferably
to be evenly bent and connected with inspection couplings. No screw
threads must be visible after the completion of the conduit installation,
except where running joints occur.
All surface mounted conduits and accessories are to be painted with high
quality enamel paint or as otherwise specified. The colour is to comply
with the colour code specified for the installation, or where no code has
been specified, it is to match the colour of the surrounding finishes.
Under flat rooves in false ceilings, or where there is less than 900mm
clearance, or in instances where the ceilings are insulated with glass wool
or other insulating material impeding access, the conduits are to be
installed in a manner which allows for wiring from below the ceilings, i.e.
loop in system. Draw boxes are to be installed in such a way that they
can easily be inspected from above.
Conduit ends are to be cut at right angles to ensure that ends butt
squarely at joints.
The conduit ends are to be reamed and all joints tightly fitted. Only
approved couplings may be used. Running joints with long threads must
be kept to a minimum and locknuts must be provided to ensure a strong
mechanical and a continuous electrical joint.
Where the galvanising has been damaged, the area is first to be cleaned
and a coat of zinc-based paint applied. Additional coats of paint may
only be applied after the undercoat has completely dried. All surface-
mounted non-galvanised metallic conduits must be painted.
All draw boxes and outlets are to be fitted with cover plates, either as part
of the switch or socket assembly, or with blank cover plates if unused.
Blank cover plates are to match other cover plates in the same area.
Cover plates in both ceilings and walls are to overlap the draw box and
edges of any opening. If the fixing lugs are substantially deeper than the
finished wall surfaces, suitable coiled steel wire or tubes are to be used as
spacers. The edges of flush mounted outlet boxes are not to be deeper
than 10mm from the final surface.
The gap between the box and the sliding conduit is to be sealed with
Pratley Tic Tac or equivalent compound, to prevent the ingress of wet
cement.
All channels are to be supplied with cover plates, which are to be of the
clip-in type and may be manufactured from PVC if the cover is 76mm
wide or less. Channel covers for P9000 are to be galvanised type.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
136
All trunking bends are to be of easy sweep design, with smooth, rounded
corners, and where branch or crossover connections are made, the edge
of the apertures must be rendered smooth with approved edging strips.
Bends in trunking are to be such that the inner radius is at least three
times the external diameter of the trunking.
The space factor of cables in trunking may not exceed 40%, where the
space factor is the relation of the sum of the overall cross sectional areas
of cables to the internal cross sectional area of the trunking.
The ends of the trunking are not to be left open, but to be provided with
end pieces. Corner pieces are to be used for direction changes, as 90
degree direct bends will not be allowed.
When cable trunking is cut, the edges are to be treated as described for
conduit to prevent rust.
PVC insulated or equivalent copper conductors and copper earth conductors are to
be used exclusively. The insulation is to be general purpose PVC, 600/1000V grade.
The conductors are to be of high conductivity annealed stranded copper and the
cores may be shaped or circular.
The above wire ways are only permitted for relatively light current-carrying
conductors such as lighting and socket outlet circuits. Heavy current-carrying
conductors such as feeders to distribution boards and large power points must be
installed in separate conduits or wire ways.
Separate circuits are to be employed for lighting, power and plug circuits, with a
maximum of two single-phase circuits per 20mm diameter conduit. Conduit
capacities are to be as laid down in the enclosed tables (see Section 15.4).
All switch and phase conductors are to be PVC insulated. Red or multi colours may
be used for identification of different circuits or switching purposes. Neutral
conductors are to be black PVC insulated, and earth wires are to be green or
green/yellow.
Wiring is to be executed according to the loop-in system and no joints are allowed
inside conduits or boxes.
When conductors are drawn through conduits, care must be taken that they are not
kinked or twisted. Care must also be taken that the conductors do not come into
contact with materials or surfaces that may damage or otherwise adversely affect the
durability of the conductor.
Conductors installed in vertical wire ways are to be secured at intervals not exceeding
5m to support the weight of the conductors. Clamps must be provided in suitable
draw boxes for this purpose.
The insulation of conductors may only be removed over the portion of the
conductors that enter the terminals of switches, socket outlets or other equipment.
When more than one conductor enters a terminal, the strands are to be securely
twisted together. Under no circumstances may strands be cut off.
The following conductor sizes shall be used, except where stated otherwise:
The space factor of the cables in the trunking Cis not to exceed 40%.
The correct size and type of gland for the particular cable termination
application must be used, and only Pratley or equal approved quality
products may be used.
Cables that are connected to clamp type terminals, where the clamping
screws are not in direct contact with the conductor, need not be lugged,
but the correct terminal size must be used.
When cutting away insulation from cable conductors to fit into lugs, care
must be taken that no strands are left exposed. Under no circumstances
may any of the conductor strands be cut away to fit into lugs.
The Contractor must make all arrangements, pay all fees and provide all
equipment for these tests. The cost of testing is included in the tender
price.
Metal cable trays, ladders and all accessories are to be manufactured from perforated
rolled steel, which is to be hot-dip galvanised.
The top of the up stands of trays listed in (a) and (b) must be smooth.
allow cable clamps or metallic binding bands to affix the cables to the
tray.
15.2.13.3 Accessories
Horizontal and vertical bends, T-junctions and cross connections are to be
supplied by the Contractor. The dimensions of these connections are to
correspond to the dimensions of the linear sections to which they are
connected.
15.2.13.4 Supports
Cable tray supports are to consist of two steel hanger rods, at least 8mm
in diameter, on both sides of the tray, with a substantial steel cross-
member on the underside of the tray, and bolted to the rods. Alternately,
cable trays may be cantilevered from walls on suitable brackets.
The supports must be strong enough and fixed at a distance, which will
prevent the cable tray from sagging more than 6mm over a 2m distance.
Metal trays and ladders are to be bonded to the earth bar of the
switchboard to which the cables are connected. Additional bare copper
stranded conductors or copper tape must be bolted to the tray or ladder
where the electrical continuity cannot be guaranteed. These additional
conductors or tapes must, in any event, always be installed in outdoor
applications and in coastal regions.
Where the fixing holes in bricks or concrete walls are smaller than 10mm diameter,
and where the mass of the equipment is less than 10kg, wall plugs may be used to fix
conduits, cables and other equipment. Fibre or plastic plugs may be used. Wooden
plugs are not acceptable. Aluminium plugs may be used in face bricks. Plugs
installed in joints between bricks are not acceptable. A masonry drill of the correct
size must be used to drill holes for plugs. Round head screws of the correct diameter
to match the specific plug must be used throughout.
Where the fixing holes are 10mm or larger, or where the mass of the equipment
exceeds 10kg, equipment must be fixed by means of expanding anchor bolts or by
means of bolts cast into the concrete or built into walls.
Brass screws bolts and nuts must be used to fix galvanised equipment.
Where light switches are installed in partitions, they must, where possible,
be of the special narrow type intended for installation into the mullions.
The switch colour is to be white and the switch must be fitted with a
nylon cord 1,25m long.
Switches are to be of the tumbler operated micro gap type rated at 16A.
The yoke fixing holes are to be slotted to allow for easy alignment.
Where 13A flat pin switched socket-outlets are specified, these must
comply with the international standard.
The socket outlets are to have shuttered live and neutral openings.
All switches and socket outlets are to be fitted with PVC cover plates. The colour of
cover plates is to be as specified or otherwise to match the surrounding finishes as
closely as possible. Cover plates in the same area are to have the same colour. Cover
plates of flush mounted socket outlets must overlap the draw-box and edges of the
recess. Cover plates may under no circumstances be cut, unless authorised by the
Engineer.
The sides of adjacent switches, plugs, push buttons, etc. must be parallel or
perpendicular to each other and uniformly spaced. A common escutcheon plate is to
be placed around flush mounted outlets and accessories where the standard cover
plates do not cover the cut-outs in the finishes.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
145
All socket outlets are to be installed at least 150mm away from the doorframes.
Unless specified to the contrary, switches adjacent to doors are to be installed on the
side containing the lock. If the position of the lock is not shown on the drawings, the
position is to be verified before the switch-box is installed. Switch-boxes in brick or
concrete walls are to be installed 150mm from the doorframe. Light switches
installed in partitions or doorframes are to be of the type designed for that purpose.
Outlet boxes are not to be recessed more than 20mm from the finished wall surface.
The unit is to be of the wall mounting or panel type and be fitted into an
approved polycarbonate bulkhead fitting, complete with a suitable
bracket.
(iii) Doors
Doors are to be constructed from 1,2mm sheet steel, have a smooth flat
finish and be recessed flush in the architrave frame. The width of the
single doors may not exceed 0,6m. Door catches are to be chromium
plated brass and mounted flush in the door.
Title charts with numbers and functions of the circuits typed on them is to
be covered by 1mm acrylic plastic sheet in the slots fixed to the inside of
the doors.
(iv) Chassis
A reinforced chassis is to be fixed to the architrave frame and to be
equipped with mounting clips or brackets for the fixing of the switchgear.
A distance of 100mm (or more, depending on the cable size) must be
allowed between rows of equipment and care must be taken to allow
enough space for the termination of the incoming cable to the main
isolator.
Screwed-on engraved PVC labels are to be provided under all the cut-
outs in the panel with all the equipment clearly marked to indicate the
number of the circuit and its function. Names of distribution boards must
be on label strips at the top of the panel. Label strips are to be made
from black celeron with 6mm white engraved letters.
(vii) Busbars
Busbars are to consist of solid copper with adequate cross-section for
each phase and to be mounted on suitable insulators. Busbars are to be
drilled and tapped for 7mm diameter chromium plated steel bolts, which
must be screwed in from the back and soldered to prevent them from
coming loose. Washers, spring washers and hexagon nuts are to be
supplied for each bolt. An approved method is to be used to mark the
live busbars with the appropriate phase colours.
(viii) Wiring
Wiring is to be carried out in front of the chassis and the conductors are
to be bound together with cable clips in neat vertical and horizontal
looms. PVC insulated conductors with sizes to suit the relevant
switchgear are to be used. The ends of the wires connected to busbars
are to be provided with suitable crimping lugs, firmly crimped, and the
ends of the wires connected to clamps of miniature circuit breakers are to
be turned together firmly, before they are inserted into the terminals.
Where wiring channels are used, they are to be installed horizontally and
vertically. Under no circumstances may power and control circuit wiring
be installed in the same wiring channel. Channels may not be more than
40% full.
The colour of the conductors for all 240V circuits is to correspond to the
colour of the supply phase for that circuit. Neutral conductors must be
black. All other conductors in the board, supplying control circuits, etc. be
coded in colours other than those specified above. A colour code is to be
devised for each board and the colour code to be shown on the wiring
diagrams.
All conductors that terminate at wiring terminals and all conductors used
for the internal wiring of the switchboard are further to be identified at
both ends by means of durable cable marking ferrules. PVC or other tape
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
149
The steel reinforced tray is to be suitably braced and stiffened to carry the
chassis, door and equipment. Lugs to secure the switchboard to a vertical
surface are to be provided.
(ii) Instrumentation
All metering instruments are to be flush mounted in the front panel or
door. The rear terminals of instruments mounted on doors are to be
covered with an insulating material to prevent accidental contact. Current
transformers for metering are to be mounted so that the rating plate is
clearly visible. Fuses for instrumentation are to be mounted in an easily
accessible position and clearly marked.
(iii) Busbars
Busbars are to be manufactured of solid drawn high conductivity copper
with a rectangular cross-section in accordance with the international
approved standard.
(iv) Finish
Welding joints and steel work are to be ground smooth and to be free
from blemishes.
Prior to painting, all metal parts are to be thoroughly cleaned of rust, mill
scale, grease and foreign matter to a continuous metallic finish.
Sand, shot blasting, or acid pickling and washing are to be employed for
this purpose.
Other metal parts e.g. switchboard panels, etc., are to have a minimum
paint thickness after painting of 0,06mm. In coastal areas, the dry film
thickness shall be increased to at least 0,1mm.
(v) Labelling
Care is to be taken to ensure that all equipment is fully labelled and that
accurate descriptions and safety warning notices appear in English or the
official local language.
The following guidelines apply to determine the type and size of label:
(a) On the main distribution and sub-distribution boards, and on
busbar sections, the lettering is to be at least 10mm high and the
labels are to be fixed on the outside in a prominent position.
(d) The make, catalogue number and capacity of all equipment such as
isolators, circuit- breakers, fuses, contactors, etc.
Kilowatt-hour meters are to be graded and calibrated for the specific application to
avoid the application of multiplication factors where possible. Where multiplication
factors are unavoidable, this is to be clearly indicated in unit form and not a
combination of several factors. Current transformer ratios must be incorporated in
the factor.
Facilities for a security seal are to be provided on the fixing screws of the cover.
The ammeter is to have 100mm2 dial with a clear scale showing the instantaneous
current value and maximum demand mean current value on the basis of a 15 minute
period, and is to be fitted with a residual pointer to indicate the maximum mean
current value during any period between manual resetting.
Ammeters are not to impose a burden exceeding three V.A. at the current
corresponding to full-scale deflection.
15.2.22 Voltmeters
Voltmeters are to be manufactured to the international standard. They are to be of
the moving iron, spring controlled pattern totally enclosed in robust insulated dust
proof housings, suitable for flush mounting in a vertical position.
The voltmeters are to have 100mm2 dial scaled to suit the system voltage and having
a suppressed zero. The nominal voltage must be marked with a red line.
The voltmeters are to be protected by HRC cartridge fuses and housed in suitable
insulated fuse carriers with a panel-mounting base.
15.2.24 Isolators
This section covers switches suitable for panel mounting for use in power distribution
systems of 50Hz, 600V. Switches for motor isolation are included.
The switches are to be of the single- & triple- pole, on load, hand operated type.
The switches are to be suitably rated for the continuous carrying, making and
breaking of the rated current specified, as well as the through-fault current capacity
as specified.
To distinguish the switches from circuit breakers the operating handles are to have a
distinctive colour and/or the switch is to be clearly and indelibly labelled "ISOLATOR".
The continuous current rating, trip rating and rupturing capacity are to be as
specified.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
154
The contacts are to be silver alloy and to close with a high pressure wiping action.
The operating handle is to provide clear indication of "ON", "OFF" and "TRIP"
positions.
The mechanism is to be of the TRIP-FREE type, preventing the unit from being held in
the ON position under overload conditions.
A single manufacturer must, as far as is practical, supply all moulded case circuit
breakers in a particular installation.
The incoming terminals of single pole miniature circuit breakers are to be suitable for
connection to a common busbar.
The circuit breaker is to have a rating plate indicating the current rating, voltage
rating and breaking capacity.
Extension type operating handles are to be provided for units of 600A rating and
above.
The units are to be suitable for installation in switchboards in clip-in trays or bolted to
the chassis.
On-load switches used integrally with earth leakage units (two pole for single-phase
units and three pole for three phase units) are to comply with the international
standard.
15.2.27 Contactors
Contactors are to be of the open or totally enclosed, triple or double pole,
electromechanical operated, on load, air-break type suitable for 400V or 250V
supplies.
Contactors that are not located in switchboards are to be housed in enclosures that
comply with IP 54 of IEC 144 (international standard).
The current rating of the contactors is to be as specified for the circuit with a
switching duty in accordance with the manufactures data plate, utilisation category
ACI for lighting and power circuits and utilisation category AC3 for motor starting.
All laminations of the magnetic system of the contactor are to be tightly clamped.
Noisy contactors will not be accepted.
Latched contactors are to be provided with a trip coil and a closing coil. The
contactor is to remain closed after de-energising the closing coil and shall only trip
on energising the trip coil.
silent operation with filters for interference. No visible flicker of light may
be apparent and no dark and bright zones may occur anywhere along the
length of the lamps.
Light fittings be complete with lamps, of which the colour will be specified
elsewhere.
Cover plates are to be fitted over all draw boxes and outlets intended for luminaries
that are not covered by the luminaries’ canopy, lamp holder, ceiling rose or similar
accessories.
Where an outlet box or draw box provides the necessary support for luminaries, all
luminaries, with the exception of fluorescent luminaries mounted against ceilings, are
to be fixed directly to the box. Fluorescent luminaries and luminaries with a mass in
excess of 10kg are to be suspended independently of the outlet box.
Where wooden blocks are used to suspend luminaries, ceiling battens may not be
cut. The wooden blocks are to be cut to fit around battens and shall be screwed to
the ceiling.
Only self-tapping or similar screws are to be used to suspend fluorescent fittings from
the wooden bearers.
Where provision has not been made for the fixing of luminaries, the Engineer must
approve conduit extensions or angle brackets or any other fixing method.
In the case of tiled ceilings with exposed or concealed T-section supports, surface
mounted luminaries are to be fixed only to the “T” by means of course thread self-
tapping screws. Luminaries may, alternatively, be fixed to metal crosspieces resting in
the ceiling tees.
Drilling of holes in ceiling tees to support luminaries is not allowed. Luminaries are to
be fixed in neat relation to the ceiling layout.
In all false ceilings where wiring channels are used, recessed luminaries are to be
connected to the wiring channels by means of unswitched 5A socket outlets.
High bay luminaries are to be securely suspended from the roof structure. The
luminaries may be fixed to suspended wiring channels, containing the wiring, on
condition that:
(a) 2 x 10mm2 PVC insulated conductors and 6mm2 bare copper earth
conductor for single phase; or
(b) 4 x 4mm2 PVC insulted conductors and 2,5mm2 bare copper earth
conductor for three phase connections.
A 60A double pole or 30A triple pole micro gap isolator flush mounted in
a wall outlet box is to be installed 1,4m above floor level to the left or
right of the appliance. A white baked enamel cover plate is to be
provided on the finished surface as applicable.
15.2.33 Earthing
15.2.33.1 General
The whole of the completed installation is to be effectively and efficiently
earthed in accordance with the requirements of the Local Supply
Authority.
In his price, the Contractor must allow for copper bonding straps, wiring
and the proper bonding of the whole installation, including the bonding
of the sheeting, down pipes, gutters, etc., where applicable. Only brass
bolts, nuts and washers may be used.
Single- & three- phase supplies up to 80A are to consist of a 10mm2 bare
copper conductor (BCEC), to be installed with the service connection
cable up to the point of supply, where it must be connected to the main
earth bar. Copper coated earth spikes must be installed to reach the
equivalent earthing value as prescribed above.
All 16Amp socket outlets, fluorescent and mercury vapour light fittings,
fixed heater and hot water cylinders shall be earthed by means of 2,5mm²
green PVC insulated copper conductors.
15.2.33.4 Buildings
All metal hot and cold water pipes and waste pipes are to be
interconnected by means of 12,4mm x 1,5mm solid tapes, which are to be
clamped with brass bolts and nuts. The tapes are to be fixed to the walls
by means of brass screws at intervals not exceeding 230mm. Earth clips
are to be manufactured from 1,0mm copper tape, which must be at least
12,5mm wide and supplied complete with 25mm x 5mm diameter brass
bolts, washers and nuts.
Water earthing must consist of a 10mm2 copper wire connected from the
distribution board to the nearest water pipe in the roof area.
Iron roofs, gutters, down pipes etc. are to be interconnected in the same
way. Iron roofs are to be connected at intervals not exceeding 15m by
means of a 10mm² bare copper wire. The common earth conductor is to
be installed under the roof, over its full length and to be firmly fixed to
the upper purlins. It is to be bonded to the main earth conductor of all
distribution boards.
In cases where high voltage cable runs are parallel to telephone cable
runs for long runs, the correct spacing is to be determined by conferring
with Telkom (South Africa) or the local telephone supply authority.
A 20mm thick soft wooden panel (fine grade pine without knots) is to be
installed in the main telephone distribution board and cover the entire
inside back of the board. Chipboard or similar materials are not
acceptable.
All conduits and all ducts or channels are to be provided with galvanised
steel draw wires.
On completion of the Contract, any damage that may have been done to plaster
work, ceilings, floors, woodwork, etc., in the execution of the Electrical Contract, is to
be rectified and made good by the Contractor at his own expense and to the
satisfaction of the Architect.
15.2.37 Inspection
Once the Contractor has completed the installation, written notice is to be given to
the Engineer in order that a mutually acceptable date can be arranged for a joint
inspection. During the course of the inspection, the Engineer or his representative
will compile a list of items (if any) requiring further attention. A copy of this list will
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD.
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
163
be provided to the Contractor who will have a period of 7 days in which to rectify the
offending items of the installation.
The Contractor is to test all circuits, in the presence of the Engineer or his
representative, with respect to:
(a) Phase balance;
(b) Insulation level; and
(c) Polarity.
15.2.38 Guarantee
The Sub Contractor is to guarantee to the Principal Contractor (who will pass same
onto the Landlord) all the material and workmanship pertaining to the electrical
installation and Specialist Sub Contractors of this Contract for a period of 12 months.
The guarantee is to be valid for the full period from the date when the Engineer has
accepted the installation in good working condition on the final hand-over date.
The only exclusion to the 12 months will be lamps of luminaries, which are to be
guaranteed for a period of 18 months, and the fluorescent ballasts for a period of 5
years.
The Client has the right to replace faulty equipment or rectify poor workmanship at
the Landlord's cost during the guarantee period, should the Landlord fail to effect the
corrective action within a period of 48hr of notification. The Client reserves the right
to deduct the actual cost of repairs from the rental.
Should the Contractor fail to comply with the above, the Client will not submit the
certificate of completion, which will result in the withholding of the outstanding
retention funds.
Shoprite Checkers’ Mechanical Consultant will specify in which area of the supermarket the
above systems will be applicable.
The positioning of all openings in structural elements to suit the installation of air
conditioning ducts, cables, fans, etc. are to be confirmed with the Shoprite Checkers Architect
and Mechanical Consultant.
Mechanical services shall be unobtrusive and shall be properly coordinated with other
services. Design layouts shall be submitted to the Shoprite Checkers Architect and
Mechanical Consultant for comments and approval.
Outdoor condensing units, including refrigeration and condensate drain piping, shall be
located out of sight.
16.2 AIR-CONDITIONING
The air-conditioning installation for the supermarkets is to operate independently of
the systems feeding the neighbouring tenants, and shall be designed and installed in
accordance with the requirements of Shoprite Checkers, SANS 10400 and the Local
Authority By-Laws.
Ducted split type and ceiling cassette type systems will not be acceptable.
The Bulk Store Air-Conditioning remote control panels shall be installed inside
this office and the position of the panels coordinated with shelving etc.
16.2.7 Dispensary
The Dispensary, including the office and Consultation Area shall be air-
conditioned by means of an independent AC system that shall be able to
operate for 24 hours per day. The conditions in these rooms shall be
maintained at 22,0°C db and 50% RH (±1,5°db and 5% RH) in summer and
winter at the outside design conditions applicable. The air-conditioning
systems are to be designed and installed complete with minimum fresh air
supply as required.
Ducted split type and ceiling cassette type systems will not be acceptable.
16.3 VENTILATION
16.3.1 Back-Up Service Areas
The back-up service areas (bulk store, softs store, returns store, staff toilets
and change rooms, butchery, sausage prep, bakery, flour store, dry store, fish
prep, fruit and veg prep, refuse room, deli, night drop, security office, receiving
areas, dispensary kitchenette and toilet etc.) shall be mechanically ventilated.
These areas shall be supplied with fresh air and/or extract air, in accordance
with the requirements of SANS 10400 & SANS ‘1850 Kitchen Extract Canopy
Systems’.
Bakery
Ovens canopy: stainless steel exhaust canopy complete with stainless
steel baffle filters, and two rigid aluminium flexible ducts
(per oven) from the flue discharge of the oven to the
back of the extract canopy.
Deck Oven canopy: stainless steel exhaust canopy complete with stainless
steel baffle filters, and two rigid aluminium flexible ducts
(per oven) from the flue discharge of the oven to the
back of the extract canopy.
Deli
Chicken grillers, etc. canopy: stainless steel exhaust canopy complete with stainless
steel baffle filters.
Fish Prep
Fish/chips fryers, etc. canopy: stainless steel exhaust canopy complete with stainless
steel baffle filters.
Pasta Prep
Pasta cookers, etc. canopy: stainless steel exhaust canopy complete with stainless
steel baffle filters.
The extract canopies shall be complete with Halton or ‘Cycloclean’ baffle type stainless steel
grease filter sets, which shall include stainless steel, filter holding frames and drip trays.
Baffle filters comprise a number of interlocking vanes which, when assembled, form a two-
pass grease removal device. The pressure drop remains constant and the blades provide a
barrier in the event of a flash fire. Baffle filters should be fabricated entirely from stainless
steel. The canopies shall have a discharge plenum and a drip gutter all around and two off
plugged drains for washing purposes. The canopies are to be installed complete with the
necessary stainless steel spigots, steel hangers, steel supports, flashing plates and shall be
neatly sealed against the walls and against each other where installed back to back or next to
each other to form one canopy. The canopies shall be fitted with recessed vapour-proof
fluorescent light fittings (Illumination of 600lux).
If an island canopy is required for an island Deli, the extract canopy shall be of the box type
(island mounted) and shall be installed back to back or next to each other to form one single
canopy and shall be complete with make-up air.
The stainless steel extract canopy over the front side of the bakery oven shall be of the box
type and shall be installed at high level over the front side of the oven. The canopy shall be
complete with brushed grade 304 stainless steel baffle plate type filters. The canopies shall be
neatly flashed and neatly sealed against the oven. All discharge points (two per oven
typically) on top of the oven shall be connected to the back (exhaust plenum) of the canopy
by means of rigid aluminium flexible ducting and matching stainless steel spigots.
All extract and make up air systems shall be interlocked and connected to the Checkers key
switch. All extract canopy systems and make-up air systems, to switch ‘on’ in the morning
when the store is opened by the store manager and switched ‘off’ when the store is closed
and night. No local controls inside the departments will be allowed.
The extract canopy systems and make up air systems will be interlocked with the smoke
detection system, to switch off on a double knock smoke or fire signal.
Care shall be taken with the location of the make-up air supply grilles so as not to affect
service below.
All extract canopies shall be fitted with a fire suppression system that is designed to suppress
fires and complies with an acceptable standards.
NOTE : Acceptable standards are ISO, EN, BS, NFPA, UL, FM and SANS standards.
Air Curtains to the front doors of the store shall not be a requirement in a
‘closed mall’ arrangement.
Air curtains shall operate automatically and shall be switched with the store
‘key switch”.
The smoke ventilation systems shall be interfaced with a double knock smoke
detection system and shall operate automatically.
Vertical penetrations through side cladding shall take preference over roof
penetrations.
All the electrical distribution boards, electrical equipment and cables related to the
air-conditioning and ventilation installation shall be adequately sized to withstand the
design electrical fault level and shall incorporate all the necessary phase failure and
voltage fluctuation protection.
The main AC system’s electrical and control circuits shall incorporate all the necessary
relays for the interface with the smoke detection system.
i) A list with the contact names and numbers (for breakdowns and emergency
call outs).
The Refrigeration Contractor is responsible for off-loading on site. Lifting and fixing in
position of all the equipment required in completing the installation. The
Refrigeration Contractor will be responsible for the transport of equipment to site.
The developer is to provide adequate security to the construction site during
installation and should pay special attention to areas where copper piping has been
installed by the refrigeration contractor.
The supply of the refrigerated and non-refrigerated display cabinets will be a direct
contract between Shoprite Checkers and the Specialist Cabinet Supplier.
At the time of Beneficial Occupation of the Store by Shoprite Checkers (or shortly
thereafter), the refrigerated and non-refrigerated cabinets will be delivered to site. The
developer is to ensure that there is sufficient space such that the cabinets can be
delivered and moved into position on the trading floor. Where the store is part of a
larger development the developer is to ensure a path for delivery through any part of
the development leading to the store entrance. If the centre layout does not allow for
delivery then the developer must make provision for an alternative way into the store
for cabinets such as the breaking open of a wall. Openings through which cabinets are
to be moved are to have minimum dimensions of 2,5m x 2,5m. In general, the delivery
of refrigerated and non-refrigerated cabinets will take place in phases, over a period
of three days or more.
The minimum floor space required for the open and closed refrigeration plant areas is
summarised in Table 17.1 below. Please note that the table is intended for indicative
purposes only and the developer is to consult the Shoprite Checkers Professional
Team before finalising the plant room size.
The Refrigeration Contractor is responsible for the rigging of all equipment into
position. The Developer shall be responsible for ensuring that adequate access to the
plant room to facilitate the rigging of equipment with a crane or alternative rigging
equipment is provided. This includes access to the open refrigeration condenser area
as well as access to the closed plant area housing compressor packs. The developer is
to ensure that adequate and easy access to the plant room(s) is provided for any
authorised persons involved in the maintenance of the plant, for the entire life cycle of
its operation. In the case where the plant room is not situated at ground level, access
to the plant room is to be via a staircase and not a cat ladder. The staircase is to
conform to the Shoprite Checkers standard staircase detail and the South African
Building Regulations.
Plant room slabs (both for the enclosed compressor area and the open condenser
area) are to have a weight bearing capacity of at least 500kg/m². Note that the
dynamic load introduced by refrigeration equipment and the static load introduced
by walls etc. is not included in the above figure. The Structural Engineer is to include
the associated safety factor for dynamic loading and the final weight bearing capacity
of the slab is to be approved by the Structural Engineer.
b) The condenser plant areas are to be open so as not to restrict air flow to the
condensers. Where this is not practically possible due to security, aesthetic,
acoustic, building structure requirements or up stand beams etc the developer
is to have any obstruction approved by the Shoprite Checkers Professional
team before construction. However, all necessary structures around the open
refrigeration condenser area such as palisade fencing, bollards, acoustic
louvers, breezeblocks or any other structural equipment as approved by the
Shoprite Checkers Professional Team shall be provided by the Developer at his
cost. Notwithstanding the above, at least two of the adjacent sides of the
condenser area are to be left open to allow for the unimpeded flow of air to
the condensers. Where there is limited allowance for free flow of air to the
open condenser area, the Shoprite Checkers Professional Team is to advise on
the minimum free space required for proper operation of the plant.
c) The Developer shall provide a water tap in the open condenser area in
accordance with the standard schedule as provided by the Shoprite Checkers
Architect.
d) The floor of the enclosed plant room area housing the refrigeration equipment
is to be painted battleship grey chemically resistant epoxy by the Builder.
17.1.4 Penetrations
The provision of all the openings in slabs, walls, ceilings, bulkheads, roofs, etc. shall be
by the Builder according to the Shoprite Checkers Architect’s plan. The sealing of
openings through which refrigerant piping runs shall be done by the Refrigeration
Contractor according to the standard detail.
b) Any finishing of other pipe risers shall be the full responsibility of the Builder
and shall be done in accordance with the Shoprite Checkers Architect’s
Specifications.
and are to be capped to avoid builder’s rubble ingress. The Shoprite Checkers
Architect shall provide a drawing of the trading area, service areas, back of
house, plant room and cold-rooms to the Builder detailing the location of
condensate drain points.
17.1.8 Trenches
The Builder is to provide all trenches necessary for the reticulation of refrigerant
piping to serve cabinets on the trading floor. A drawing detailing the position, size
and layout of the required trenches shall be issued by the Shoprite Checkers Architect.
Trenches are to be installed according to the Structural Engineer’s specification. No
other services such as condensate drains, water supplies etc. are allowed in the
refrigeration trench. Only refrigeration piping and associated electrical cabling is
allowed to be placed in the refrigeration trenches. Similarly, no other services are
allowed to cross a trench unless the crossing takes place below the concrete surface
bed of the trench.
17.1.9 General
Water supply must be provided to the non-refrigerated cabinets where specified by
the Shoprite Checkers Architect.
NOTE:
It is the responsibility of the Builder to check and confirm that all drainage,
condensate drain and water points are as per the Shoprite Checkers Architects
Drawing after installation and before floor casting and reconfirmed after floor casting.
A detailed marked up drawing must be made available by the Builder in this regard.
c) The electrical contractor shall provide the main incoming electrical supply to
the refrigeration plant room DB including termination. The Refrigeration
Contractor shall be present to witness termination of the main electrical supply
and is to be responsible for coordination with the Electrical Contractor. This
electrical supply shall be on emergency (backup) power.
f) Two standard 16A socket outlets are to be provided in the plant room by the
Electrical Contractor. Refer to the standard plant room layout detail.
The Builder is to fully co-ordinate and schedule the Insulation Contractor within the
Building Programme. The Builder is to issue to the Shoprite Checkers Professional
Team, within 1 week of receiving the instruction to appoint the Insulation Contractor,
a comprehensive integrated programme of works, fully detailing the manufacturing,
installation, commissioning and hand-over phases of the project. The Builder is also
to fully co-ordinate the installation of the insulation accessories, including Meat Rail
Systems, door mechanisms, strip curtains, pressure relief valves, door heaters and sill
details. On completion of the insulation installation, the Builder is to co-ordinate the
installation of the cold and freezer room electrical installation (lights and switches).
Prior to the site establishment of the Insulation Contractor, the Builder is to ensure
that the site is suitably prepared as per the Standard Insulation Details and
Specifications and that temporary lighting is installed to provide an acceptable
lighting level for the installation.
The floor finish in the cold and freezer rooms and (conditioned) receiving, processing
and preparation areas is to be as per the Standard Insulation Details and
Specifications. The Builder is to apply the final hard wearing topping on all completed
concrete floors as per the Architects specification.
The provision of floor drains to cold and freezer rooms must be carried out by the
Builder according to the drainage layout as provided by the Shoprite Checkers
Architect.
The fire protection services shall incorporate the following as applicable, as required
by SANS 10400 and the local and any other authority having jurisdiction:
- Fire hydrants
- Hose reels
- Portable fire extinguishers
- Automatic sprinkler installation
- Fire detection and manually activated alarm system
- Smoke ventilation
- Emergency lighting
- Statutory safety signage
- Voice evacuation system
- Fire blankets
The Architect and Fire Protection Consultant shall liaise closely with the Fire
Prevention Officer of the Local Authority to ensure that the minimum fire protection
measures are incorporated in the development. They shall also ensure that any
special requirements imposed by the Fire Safety Officer in respect of any other service
are forwarded to the respective designers of these services for incorporation in the
development.
At the end of the project the Fire Protection Consultant shall arrange and conduct
inspections and performance tests with the fire department with the view of obtaining
the Local Authority’s approval for the issue of an Occupancy Certificate.
Portable fire extinguishers shall be of DCP (dry chemical powder), gas (CO2) or wet
chemical type, to suit the particular application and the requirements of the Local
Authority.
Water based sprinkler systems shall not be used or fitted on canopies and
kitchen cooking appliances.
A fire signal is to be sent from the gas suppression control panel to the fire
detection control panel to indicate activation of the gas suppression system, and
in order to raise alarm.
19 SIGNAGE
19.1 SRC shall be entitled to erect external signage at its own cost on the lease premises,
the building and the shopping centre in such a manner and such number of as
accords with SRC national signage policy from time to time, provided that the
minimum size of any one of SRC external signage are:
19.2 As a major anchor tenant in the shopping centre, SRC shall be entitled and have
preference to position its external signage in such a manner to the exterior of the
building as to gain maximum exposure to both vehicular and pedestrian customer
accesses to the building.
19.3 The Landlord/Developer shall submit to SRC elevation drawings of the building as
soon as these have been prepared, to enable it to select its signage positions
timeously.
19.4 The Landlord/Developer shall ensure that the building design make provision for the
above signage requirements. In the event that suitable signage walls are found to be
lacking, the Landlord/Developer will at his cost construct additional signage walls or
structures to facilitate the installation of signage in accordance with SRC national
signage policy.
W5 Porcelain - 200 x 600 DOLCEVITA 26L (SHDVL 26) - Fish Service Area
Wall Tiles wall tiles, from floor to U/S bulkheads
(By Tilespace) or to above suspended ceilings where
applicable.
- 2mm joints to be pointed in TAL super
white wall and floor grout with Talbond
fungicidal additive, adhered to plaster
substrate with TAL professional
adhesive, fully covering back of each
tile.
- Full height horizontal stretcher bond.
pattern.
W8 Ceramic Wall - 600 x 600 LUNE SKATHI- SHLS60 - Coffee Seating Area
Tiles - 3mm Flush joint with High traffic dark
(By Tilespace) grey grout.
- Up to 1,100mm AFFL
- Stack bond
- Adhered to plaster substrate with TAL
professional adhesive, fully covering
back of each tile.
W10 Porcelain - 400 x 400 x 8,0mm (SHG 140) 1st grade - Toilets
Tiles unpolished porcelain tiles with 2mm - Lockers (if not face
joints, tiles adhered to slab with TAL brick)
Goldstar-6HR rapid set adhesive, - Fruit & Veg Prep
ensuring that each tile is 100% coated. - Cleaners Room
- To height of 1,400 AFFL. 200mm cut tile - Returns (decanting
at top. area)
- 2mm Flush joint with light grey grout
W11 Ceramic Wall -300 x 300 x 8,3 ZERO DARK GREY (DG) - Canteen
Tiles (SHZDG30).
(By Tilespace) - 2mm Flush joint with High traffic dove
grey grout.
- Stack bond up to 1,400mm AFFL.
200mm cut tile at top.
- Adhered to plaster substrate with TAL
professional adhesive, fully covering
back of each tile.
-
W12 Matt Beige - 600 x 300 BROADWAY CEMENT ROAD - Money Market
Porcelain 36 (SHBCR 36) 1st grade porcelain tiles. - Kiosk
Tiles - 2mm Flush joint with oatmeal grout - Manager Office
(By Tilespace) - Stack bond up to 1,500mm AFFL - Checkout Arcade
- Adhered to plaster substrate with TAL - Fire Escape Doors
professional adhesive, fully covering - FHR cubical
back of each tile. - Around impact doors
W14 Checker Plate - 2mm Thick Aluminium checker plate - Cold Room & Freezer
or Height: 1,200mm. Room
Sureprotect - Screwed and plugged to wall surface,
from Gradus with stainless steel dome-headed
screws, to Fischer wall-plugs all evenly
spaced OR fixed by panelling sub-
contractor to refrigeration panels facing
service corridors.
W15 White Glazed - 200 x 200 WHITE GLOSS 20 (SHGW20) - Medirite Kitchen and
Tile 2mm Flush joint with super white grout WC
With Talbond fungicidal additive. - Café Kitchen Area
BOH (If not face x1 coat masonry x2 coats DULUX 00NN 25/000 Seal Gray matt
brick) paint OR
From ffl to 1,4m x2 coats PLASCON Castle Gate Prof. low sheen
acr.
PB=22.00 PI=1.50 PL=20.00 PK=32.50
BOH (If not Face x1 coat masonry x2 coats DULUX 00NN 25/000 Seal Gray matt
Brick) paint OR
From ffl to 1,4m x2 coats PLASCON Castle Gate Prof. low sheen
acr.
PB=22.00 PI=1.50 PL=20.00 PK=32.50
1,4m to full height x1 coat masonry x2 coats DULUX 00NN 53/000 Veil matt
paint OR
x2 coats PLASCON Castle Gate Prof. low sheen
acr.
PB=22.00 PI=1.50 PL=20.00 PK=32.50
Bulkheads Fascia & x1 undercoat x2 coats DULUX 00NN 25/000 Seal Gray matt
Walls paint OR
Above control line x2 coats PLASCON Castle Gate Prof. low sheen
(3,200mm) acr.
PB=22.00 PI=1.50 PL=20.00 PK=32.50
Wine Section
(Internal)
Medirite (Interior x1 coat masonry x2 coats PLASCON Acrylic PVA, colour WHITE to
Walls & Ceilings) paint full height of walls.
Medirite Doors x1 Coat masonry x2 coats PLASCON Acrylic PVA, colour WHITE to
paint full height of walls.
OR
Other approved paint supplier
SAN2
Pot Sink - Sink Unit: Franke Double bowl 1,650 x 650 x - Deli Prep
(As Specified by 910 high (code 2620011-001).
Architect) - Bowl Size: 600 x 500 x 300, 420 Stainless
SAN3
Prep Sink - Franke SCBS single bowl preparation sink - Fish Area
1,650 x 650 x 910mm high (code 2620012). - Deli Prep
500 x 500 x 230mm deep pressed bowl AI SI
340CR N1 grade stainless steel with 150H
splash back, on stainless steel stand frame,
with adjustable feet and stainless steel
tubular shelf under bowl with overflow outlet.
- Unit mounted on floor, 75mm away from wall.
Base of nozzles 250 above sink-top 1 mixer
tap. Centred on bowl.
- Black PVC heavy duty waste trap with 86f
flange, 93mm shank slotted, with plug and
backnut.
OR
- Grohe- Euroco Safety – Taps - Basin mixers-
Chrome (Grohe-32793000).
OR
- Cobra (Taps & Mixers) - Medical Elbow
Action - Mixer - Chrome - Wall Mixer
(515/055-21). Cobra - Traps - Waste, Traps
and Overflows - Chrome Plated - Bath/Sink
Waste (317 - 40). Cobra - Traps - Waste,
Traps and Overflows - Chrome - Bottle Trap
(365/40).
SAN4
Basin Single - Vaal Daisy Basin (code 700803) 510 x 400 - Bakery
Semi-rectangular vitreous china with one tap - Deli Prep
hole. Chrome bottle trap (365/40). - Fish Area
Bolted to wall with two 10mm bolts (code - Butchery
8448ZO). - Fruit & Veg
- Hansgrohe flow regulating valve at water Prep
supply from wall and chromium plated pipe,
connection from wall flange to tap basin.
Clear silicone sealant between tip of tiling key
and tile.
SAN5
Hot Water Cylinder - Kwikot megaflow dual 1000: 200 litre 1,380 - Bakery
long x 540 horizontally mounted with - Deli Prep
complete with all standard accessories, - Butchery
mounted on drip tray bracketed to wall in - Fish Area
ceiling, supplies hot water to pot sink and - Fruit & Veg
SAN6
Heat Pump - Enerflow heat pump or equal approved. - Where
Specified By
Notes: Includes Heat pump unit Insulation the SRC
for the exposed pipes Mounting brackets & Architect
Fasteners Strainer (1) 22mm Ball valves (2)
Anti-vibration mounts Hard switch-over
switch for manual override LCD monitor
Probe pocket Thermostatic Diverter Valve
Solar drain cock 4,7kW Energy output unit
Uses only 1,4kW electricity COP rating of
3,66* Suitable for 200l> geysers Electricity
savings on water heating household products
of 67% Water outlet temperature 55°C Uses
CFC-free gas only Cobra Heat Pumps have
been fitted with a disinfect cycle function in
conjunction with the 2kW back-up element
to prevent the growth of bacteria such as
Legionella.
SAN7
Hydroboil (Canteen - 10 litre Franke Hydroboil in canteen - Canteen
Unit Sink Detail) OR
- 10 litre hot water dispenser from E-Boil
SAN8
Floor Trap Outlets
1) - Herbish floor drain HB200 V (H) NW 100 - Cold Rooms
stainless steel, with top flange flush with floor
finish 100mm PVC waste pipe connected to
WWP (Note: Floor finish graded to fall toward
floor drain).
- Refer to Architect's detail
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
210
SAN9
Gully - Gully outlet for wet waste - Wet Refuse
- Trolley Wash
Bay
SAN10
Oven Proover and
Convection Oven
Outlet
1) - Oven: Cobra brass shower trap 50mm (code - - Bakery
373SQ) placed in precise position. In front of
oven, outlet pipe to be galvanized mild steel.
1 per oven as indicated on the SRC Architect's
plan.
SAN11
Grease Trap - Herbish Grease Trap HBGT500 with 50 inlet - Bakery
and outlet. - Deli Prep
- Butchery
- Fish Area
- Fruit & Veg
Prep
- Deli Cold
SAN12
Hose - Cobra 207EC-20-STAR - Female Toilet
- Male Toilets
Tap - Tap: Chromium plate-threaded nozzle with - Drop Temp
hose union and chromium plated extension Area
pipe and flange: Cobra 058 + 059 cold water - Fruit & Veg
supply only, via supply pipe chased into wall. Prep
- Butchery
Receiving
- Ref. Plant
Room
- AC plant room
- Returns
Sorting
- Cleaners
Room
SAN13
Basin - Vaal Daisy Basin (code 700803) 510 x 400 - Dispensary x2
Semi-rectangular vitreous china with one tap - Kitchen
hole. Chrome bottle trap (COB-365/40). - Office
Bolted to wall with two 10mm bolts (code - Gatehouse
8448ZO). (Robust and
Simple Tap)
Tap - Hansgrohe - Décor E2 - Basin Mixer 100 – - Managers WC
Chrome. - Disabled
- Hansgrohe angle valve regulating valve at
supply from wall and chromium plated pipe
connection from wall flange to tap against
wall. Clear silicone sealant along back rim and
sides.
- Waste: Cobra 301 - 32, basin waste, CHR.
PL/62 f Flange, 80mm sank, slot.
OR
- Grohe Euroeco special - tap-basin mixer-
Chrome (code GRO-3276500.
© Copyright of this document vests with SHOPRITE CHECKERS (PTY) LTD
FRESH “X” CHECKERS & CHECKERS HYPER
PAGE
212
SAN14
Staff Basin - Vaal Quail underslung vanity basin product - Female Toilets
(code 700400). - Male Toilets
- Canteen
Tap - Hansgrohe - Décor E2 - Basin Mixer - 100 -
Chrome - Single lever.
(1 tap/basin)
- Angle Valves: Hansgrohe - Chrome Angle
Valves.
- Trap Waste: Cobra 301 - 32, basin waste, CHR
PL/62 f flange, 80mm sank, slot.
- Hansgrohe angle valve regulating valve at
supply from wall and chromium plated pipe
connection from wall flange to tap flange to
tap.
- Clear silicone sealant along back rim and
sides against wall.
OR
- Cobra (Taps & Mixers) - Noka - Mixer -
Chrome Plated - Single Lever Basin Mixer.
- Cobra - Miscellaneous - Chrome - Angle
Regulating Valve.
- Waste, Traps and Overflows - Chrome Plated
Basin Waste.
- Traps and Overflows - Chrome - Bottle
Trap.
OR
- Grohe Eurosmart single lever basin mixer –
Chrome (code GRO-32467001).
SAN15
WC 1 - Vaal Orchid wall hung paraplegic pan (code - Disabled
439016). Complete with lid, fitments and C.P. Toilets
side-flush lever or a back inlet exposed flush
valve.
- Double flap toilet seat with sta-tite hinges
- 32mm Stainless steel side grab rail (code
D12).
OR
- Franke (code 2510012)
- Paper holder: Kimberley Clark professional
SQ3 white code SA 405 607.
- Seat & Lid: Bemis 16 SS toilet seat with sta-
tite hinges.
- Flushmaster FM1.100 with C-FM8.80
Extension lever
OR
- Grohe 120 concealed cistern (code
8962Z000) for floor mounted applications
with pneumatic push button.
OR
- Geberit Sigma 10 brushed stainless steel
actuator 115.787.SN.5 with kombifix cistern
110.772.00.1 - Pneumatic single flush and
stainless steel cover.
SAN16
WC 2 - Vaal Afsan low level 90 degree outlet - Female Toilets
washdown pan (code 750100). - Male Toilets
- Paperholder: Kimberley Clark professional S - Dispensary
Q3 white code SA 405 607. - Managers
- Seat & Lid: Bemis 7200 AR Toilet
- White PVC convection bend with cleaning
eye access & screw-cap.
- Cobra Watertech Junior Flush Master
Flush valve FJ2.100
OR
- Grohe 120 Concealed cistern (code
8962z000) with Grohe inlet/outlet connector
(code 8962z100).
- With Skate SS control panel (code 8965Z000)
OR
SAN18
MIRROR 1 - 400w x 700 high x 6mm thick: Silver edge - Manager's
polished all round, fixed to wall with 4 no. Toilets
cupped mirror screws, fixed into fisher wall - Female Toilets
plugs, waterproofed backing. Mirror flush - Male Toilets
with wall tiles around. Mounted on wall, - Dispensary
centred over basin unit, starting from top
basin unit.
SAN19
Sink in Canteen - Franke NVN621 Nouveau double bowl - Canteen Sink
stainless steel drop in sink (code 1990002). - Canteen Basin
SAN20
Washtroughs - Franke: Model LDS drip sink (code 2630026). - Cleaners
Size 600 x 500 x 258mm deep, manufactured Room
in grade 304 (18/10) stainless steel size 600 x - Returns
500 x 257mm deep single compartment. Sorting
Fitted on a pair of eagle brackets mounted
600mm AFFL.
- Bibtap: Cobra 207 EC - 20- Star (cold water
supply) Chromium plate - Treaded nozzle
with hose union and chromium plated
extension pipe and flange: Cobra 058 + 059.
- Bibtap: Cobra 206 -15 - Star (hot water
supply) Bibtap with chromium plate extension
pipes and flange: Cobra 058 +059.
- Sealant: Silicone sealant along back rim and
sides against wall.
SAN21
Mixer Tap for Deli - Hansgrohe - Focus E - Mixer - Chrome - - Deli
Prep Bowl Single Lever Basin Mixer (code 31806000)
with waste, plugs, outlets, extension pipes
and traps.
- Angle Valves: Hansgrohe - Chrome Angle
Valves (Supplier code HG90610800).
OR
- Cobra - Tugela - Mixer - Brass - Sink Mixer
(TU-970).
- Cobra - Miscellaneous - Chrome - Angle
Regulating Valve (832 - 10).
- Cobra - Traps - Waste, Traps and Overflows -
Chrome Plated - Bath/Sink Waste (317 - 40).
- DPE - Du Bois - Waste, Traps and Overflows -
White - 40mm - Sink P-Trap (DB3A).
OR
- - Grohe Sink mixer-Chrome (code GRO-
31812001).
- - Grohe Universal angle valve –Chrome
(code GRO-2201700M).
SAN22
Sink & Vanity Basin - Dispensary Sink Unit: Kwikot Stainless - Sink
in Dispensary Classique (code SDI-880-DBR 870 x 470mm). - Vanity Basin
- Dispensary Vanity Basin Unit: Vaal sanitary
ware iceberg vanity basin 420 x 420mm (code
703400).
SAN23
Kiosk Sink - Small Gelato sink unit – 500 x 600 x 900h - Kiosk Sink
stainless steel counter with bowl in top bowl
size 400 x 350 x 200D and swing door below
includes all plumbing and fittings with
removable access panel.
Supplied as part of shopfitting
Tap
- Mixer tap: PMX 74 under basin mixer from
Kwikot
Fruit & Veg TDC Frame Track Spot B.Lee Black Oktalite B.Lee 3P LED4000‐BVC 05 special colour
General Food No Ceiling Track Spot B.Lee Black Oktalite B.Lee 3P LED4000‐830 05 3000K
Hot Deli Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐830 03 3000K
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Cold Deli TDC Frame Recessed Scenatic Point White Oktalite SncPoint 905 C02 BR‐FL LED1100‐830 01 3000K
No Ceiling Track Spot B.Lee Mini Black Oktalite B.LeeMini 3P LED4000‐830 05 3000K
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Wine Skimmed Ceiling Track Spot B.Lee Mini Black Oktalite B.LeeMini 3P LED4000‐830 05 3000K
Skimmed Ceiling Suspended Pendant Lights by Linear Pen 0441 Over tasting counter
Butchery + Fish Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED3000‐M+F 03 special colour 4000K
No Ceiling Track Spot Amatris B.Lee White Black Oktalite B.Lee 3P LED3000‐M+F 05 special colour
If service area have skimmed
Skimmed Ceiling Recessed Amatris White Oktalite Amatris G2 C04 WR LED2000‐840 01 4000K
ceiling and not drop in
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Bakery Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐BVC 03 special colour
Skimmed Ceiling Recessed Nimbus Silver Oktalite NimbusVP HRS‐WW LED4000‐BVC 03 special colour
Skimmed Ceiling Recessed Amatris White Oktalite Amatris G2 C04 WR LED2000‐830 01 3000k If service area have skimmed
ceiling and not drop in
No Ceiling Track Spot B.Lee Black Oktalite B.Lee 3P LED4000‐BVC 05 special colour
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Kitchen Shop TDC Frame Track Spot B.Lee Mini Black Oktalite B.LeeMini 3P LED4000‐840 05 4000K
Health & Beauty Skimmed Ceiling Recessed Agira Silver Oktalite Agira LED4000‐840 03 4000K
Dispensary Skimmed Ceiling Recessed Agira Silver Oktalite Agira LED4000‐840 03 4000K
Skimmed Ceiling Recessed Amatris White Oktalite Amatris G2 C04 WR LED2000‐840 01 4000K
Skimmed Ceiling Recessed Aegeon 195 White Province Lighting Aegeon 195/80/40 4000K
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Money Market Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐840 03 4000K
Kiosk Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐840 03 4000K
Manager offices Skimmed Ceiling Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐840 03 4000K
Entrance
Skimmed Recessed Agira Plus Silver Oktalite AgiraPl LED4000‐840 03 4000K
Bulkhead/Ceiling
Check outs TDC Frame Pendant Bali Black/Orange Oktalite OL Bali500 LED5000‐835 3500K Only in Fresh-X stores
No Ceiling/Ceiling Continuous Line C‐Line Black Oktalite 7640TB LED9000‐840 ET 05 4000K No TDC Frame
Signage above services
No Ceiling Track Spot B.Lee Black Oktalite B.Lee 3P LED4000‐835 05 3500K
departments
General trade floor No Ceiling/Ceiling Continuous Line C‐Line Black Oktalite 7640TB LED9000‐840 ET 05 4000K
Front line offices Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
BOH & Staff Room No Ceiling/Ceiling Surface Saxa White Province Lighting saxa/80/40/54w Triproof 4000k
Drop in Ceiling Recessed LED panel White Province Lighting Theia-R/6x6/80/40/36/Op 4000K
Bulk Store & Cold Room No Ceiling/Ceiling Surface Saxa White Province Lighting saxa/80/40/54w Triproof 4000k
No Ceiling/Ceiling Surface Metropolis White Province Lighting Metropolis/84/40/48 4000k Cold rooms
White Inside
And Outside
Tech X No Ceiling Suspended Pendant Lights by Linear PEN0441 4000K
With Black
Cable
White Inside
And Blue
No Ceiling Suspended Pendant Lights by Linear PEN0441 4000K
Outside With
Black Cable
With mounting bracket and
No Ceiling In Joinery LED Stip White LED SA CDE 4000K
drivers
With mounting bracket and
No Ceiling In Joinery LED Stip White LED SA Luminis E3 4000K
drivers
No Ceiling In Joinery LED Stip Black LED SA DAE 35 4000K With drivers
Installed In
No Ceiling LED Stip White LED SA CDE-S 23W 816mm 4000K
Gondola End
Café Skimmed Ceiling Suspended Pendant Illumina Royal super dome pendant Suspended in bulkhead
Skimmed Ceiling Suspended Pendant Province Lighting Type A: PPEN-DS-BW Banquet seating
Skimmed Ceiling Suspended Pendant Province Lighting Type B: PPEN-DS-CW Banquet seating
DET02 TYPICAL DETAILS FOR COLD ROOM AND FREEZER RECESSED IN NEW
CONCRETE SUSPENDED SLAB
WALL PANEL
10
100
*
DPC
CONCRETE FLOOR(25MPa)
DOOR
20
100
300
*
DPC
NOTE:
EXISTING CONCRETE
CONCRETE FLOOR(25MPa) SURFACE BED
WALL PANEL
10
100
50
*
DPC
75
SIKA CEMFLEX
WATER PROOFING
MEMBRANE
20
100
300
*
DPC
75
SIKA CEMFLEX
WATER PROOFING
MEMBRANE
NOTE:
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
NEW CONCRETE
CONCRETE FLOOR(30MPa) SUSPENDED SLAB
INSULATION BY OTHERS
WALL PANEL
10
100
50
*
DPC
75
SIKA CEMFLEX
WATER PROOFING
MEMBRANE
20
100
300
*
DPC
75
SIKA CEMFLEX
WATER PROOFING
MEMBRANE
NOTE:
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
DOOR
10 x 10mm POLYSULPHIDE
SEALANT JOINT AROUND THE detail 1
INTERNAL PERIMETER OF THE
COLD ROOM/FREEZER. PRIME
10
*= DIMENSION BY OTHERS
DETAIL 1
NOTE: SCALE 1:2
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
SKIRTING TILE
AT 45 DEGREES
SUSPENDED RC SLAB
50
WALL PANEL
REFRIGERANT SEALANT
CONCRETE BY BUILDER +/-200
150 MICRON MEMBRANE TO
RETAIN CONCRETE
INSULATION 100mm
POLYURETHANE
CONCRETE
NOTE:
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
CONCRETE
SURFACE BED OR
20
RC SLAB
TYPICAL PROOVER 5
100 100
406
FULL TILES
6
406
A A
50mm DIA STAINLESS
STEEL DRAIN
FULL TILES
6
25
5
NOTE:
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
4°
10
SCREED
20
CONCRETE
SURFACE BED OR RC SLAB
DETAIL 1
SCALE 1 : 10
STAINLESS STEEL
SIDE OF PROOVER
CONTINUOUS POLYSULPHIDE
SEALANT BEAD
TILES
5
2
TILE ADHESIVE
SCREED
CONCRETE
SURFACE BED OR RC SLAB
DETAIL 2
SCALE 1 : 2
NOTE:
1. POLYSCREED TO BE APPLIED IN STRICT ACCORDANCE WITH THE MANUFACTURER'S SPECIFICATIONS.
2. THE PREPARED SURFACE IS TO BE SATURATED WITH WATER 24 HOURS BEFORE THE POLYSCREED IS
APPLIED.
3. THE TEMPERATURE IN COLD ROOMS AND FREEZERS CAN ONLY BE DROPPED AFTER 5 DAYS AND
BELOW FREEZING POINT 7 DAYS AFTER THE POLYSCREED HAS BEEN LAID.
4. POLYSCREED AVAILABLE FROM "TECHNICAL FINISHES" (011) 8227242
DEVILS FORK
PALISADE FENCE
TO SCHEDULE
1850
SEE FULLBORE
DETAIL
WATERPROOFING
SCREED
SLAB BY 250
ENGINEER
screed to fall
torch-on waterproofing -
bituthene or similar
new suspended concrete slab
as per Structural Eng. details
DETAIL OF FULLBORE
EXIST. SCREED
CLOSE WATERPROOFING MEMBRANE
ARROUND PIPE WITH 2mm
BINDING WIRE
EXISTING CONCRETE
RC SLAB
TILES
CORE DRILLED
PENETRATION IN SLAB
EXISTING CONCRETE
RC SLAB
DIAMETER OF DIAMETER OF
PENETRATION STOP END
SECTION: REFRIGERATION DRAINAGE PIPE (mm) (mm)
PENETRATIONS ON SUSPENDED RC SLAB
100 160
SCALE 1:10
150 200
s.o.p.
A A
1,400
5 5
5,250
DETAIL
SCALE 1 : 2
NOTE:
2. STEEL TILES AVAILABLE FROM "BAKERITE INDUSTRIES" IN DURBAN. TEL: 031-700 5288
POLYSCREED
TOP OF EXISTING
60
CONCRETE SURFACE BED
EXISTING CONCRETE
SURFACE BED
RECESS
STRAIGHT CUT WITH CONCRETE
CUTTING EQUIPMENT TO FORM
RECESS IN EXISTING CONCRETE
SURFACE BED
NOTE:
8mm THK PORCELAIN TILES = "GENESIS" ESA 120 ALUMINIUM EDGE TRIM
12mm THK PORCELAIN TILES = "GENESIS" ESA 150 ALUMINIUM EDGE TRIM
COMPRIFIX 15 / 38 EXPANSION
JOINT COVER STRIP - TOP TO BE
FLUSH WITH TOP OF TILES
TILE ADHESIVE
RC SLAB
1,000
219x4,5mm
CIRCULAR HOLLOW
SECTION
1,200
600x600x1,3m DEEP
MASS CONCRETE
(15MPa) SURROUND
100
600
TYPICAL BOLLARD
SCALE 1:25
PORCELAIN TILES
50mm DEEP SAW-CUT JOINT
TO FORM STRAIGHT EDGE BEFORE
BREAKING OF EXISTING
SURFACE BED.3mm WIDE MOVEMENT JOINT
IN FINISHES. SEALED WITH FLEXIBLE
SEALANT. COLOUR TO MATCH GROUT
50
150
500 MAX.
WEAK FLOWABLE SAND/CEMENT
MIX (10:1) VIBRATED INTO PLACE
HALF BRICK
WALL
110 110
SEE REFRIDGERATION
ENGINEER'S DRAWING
(300 - 600mm WIDE)
TREAD: 250
162
65
75
250
275
25
GENERAL DETAILS
25
GRANO
75 mm REEDING IN
DETAILS - C
LOADING PLATFORM
STANDARD 2 RAIL 43mm DIA. 8
SCALE: 120
MACLOCK STEEL HOLLOW TUBE
BALUSTRADING 7
4
1300
REV DATE:
DETAIL OF STAIRS AT LOADING PLATFORM
75 mm REEDING IN GRANO
2
25 mm THICK UNTINTED 1
HARDENED GRANO
LOADING YARD 1,477
10.04.2019
REV -
DET15 21
A
WALL
50
NOTE:
A. HANDRAIL Ø42 X 2.5MM GALVANISED M/STEEL PIPE ENDS CLOSED WITH DISC PLATES FULLY
WELDED, NEATLY GROUND SMOOTH.
B. STIRRUP Ø12mm SOLID GMS ROD FED INFOR HOLE DRILLED IN BASE OF H.RAIL & WELDED. END
SPLIT & FLAIRED, AND EPOXY GROUTED INTO HOLE DRILLED IN WALL.
SYMMETRICALLY SPACED OVER HANDRAIL LENGTH & MAX. 1500mm APART, WITH STIRRUP
NOT MORE THAN 400mm FROM EACH END.
C. DISC PLATE 40 X 5mm WITH Ø13mm HOLE DRILLED IN CENTRE FOR STIRRUP TO PASS THROUGH,
SPOT-WELDED ON REVERSE SIDE TO STIRRUP.
FINISH: IF POSSIBLE LOCALLY. USE M/STEEL ELEMENTS AND HOT-DIP-GALVANISED EACH UNIT
OTHERWISE USE GMS ELEMENTS AS ABOVE AND APPLY COLD-GALV TO WELDS.
PALISADE FENCE
CONDENSOR REFRIGERATION
PALISADE FENCE
PLANTROOM - UNCOVERED
50 SQM
PALISADE FENCE
STANDARD MENTIS
HANDRAIL
190
STEEL STAIRCAASE TO
ENG. DETAILS 250
TREADS = 250mm
NGL RISERS = 190mm
90 x 90 x6mm M/STEEL
ANGLE IRON ATTACHED TO
WALL WITH 2 x M10 HILTY
HIT-HY 50 ANCHORS AS
PER ENG. DETAIL
TYPICAL DETAIL
MEZZANINE
TOP OF SLAB
SCALE 1:10
STD. CHECKERS
HANDRAIL
DETAIL
NGL
up
BACKUP GENERATOR
2500
00
50
200
2.500
NOTE:
1. 30 MPA CONCRETE
Head: 40 m
Power: 5 HP
Voltage:
BALL OR
GATE VALVE
UNION
(WITH
P PRESSURE
SWITCH)
750
750
5,590
TYPICAL PLAN OF MAIN DB ON PLINTH
SCALE 1:50
60 x 60 x 4mm ANGLE
CORNER PROTECTOR
FIXED ON EDGE
MAIN
DB BOARD
150
750
BRICK
WALL
150
SURFACEBED
NOTE:
1. DETAIL TO BE READ IN CONJUNCTION WITH ELECTRICAL CONSULTANTS DRAWING
LOADING
400
GROUND LEVEL
1,000 1,000
TRUCK
SCALE 1:20
3 x BUMPERS AS PER DETAIL
TRUCK
400
STRIP
BUMPER
TRUCK
SHEETING TO MATCH
BUILDING
SIDE CLADDING
VERTICAL FLASHING
500
1,500
EXTERIOR
BUTCHERY RECEIVING &
STAFF ENTRANCE
FLOOR
NOTE:
1. ROLLER SHUTTER AT BUTCHERY RECEIVING ONLY
100
115 x 95mm BUMPERS AS PER
UNI CAPE EQUIPMENT (PTY) LTD
TYPE M12/4 DB402D (OEA),
FIXED VERTICALLY TO
MANUFACTURER'S SPECIFICATIONS
IN FRONT OF LOADING DOCK @
CENTRES AS INDICATED ON GF
PLAN, C202
1,350 - HEIGHT TO BE CONFIRMED
900
FFL
SECTION:
SCALE 1:10
PLAN DETAIL
OF BUMPERS
SCALE 1:5
100
115 x 95mm BUMPERS AS PER
UNI CAPE EQUIPMENT (PTY) LTD
TYPE M12/4 DB402D (OEA),
FIXED VERTICALLY TO
MANUFACTURER'S SPECIFICATIONS
IN FRONT OF LOADING DOCK @
CENTRES AS INDICATED ON GF
PLAN, C202
FLASHING SIDE
CLADDING
CANOPY AT 3°
VERTICAL
FLASHING
TRUSS &
PURLINS TO
SCALE 1:10 ENG. DESIGN
RECEIVING AREA
RECEIVING YARD
3,450
2400
4,800
DETAIL
1.5° SLOPE
1500
1,350
NGL
FOUNDATION TO FOUNDATION TO
ENG. DETAIL ENG. DETAIL
NOTE:
1. STEEL STRUCTURE TO ENG. DRAWINGS;
2. CANOPY ROOF TO MATCH CENTRES COLOUR
750
MEZZANINE SLAB SLAB OPENING
255
1,1
00
STORAGE
GENERAL DETAILS
3150
GENERAL
25°
DETAILS - C
750
SCALE: 1:50
TYPICAL SECTION THROUGH
CONVEYOR
722
10.04.2019
1,500 7,656 1,500
TYPICAL PLAN OF CONVEYOR
REV -
SCALE 1:50
DET26 21
WATER METER
CWP RISER
1000
FFL
RECESSED WALL
ANGLE FIXED AS PER
MANUFACTURERS
INSTRUCTIONS
CHECKOUT ARCADE
FLOOR LINE
NOTE:
265
TILE SOFFIT LEVEL TO
CORNER PROTECTOR
2475
2210
2210
2100
FLOOR LINE
914
16mm MDF board fixed to wall
with split batons
250
TYPICAL PLAN OF FHR & NICHE BULKHEAD DETAIL FHR BACKING BOARD
SCALE 1:50
NEW CEILING
SOFT JOINT
FLOOR LINE
SOFT JOINT
C C
12.5
B B
50
75
12.5
C C
B C
63
3100
FLOOR
NOTE:
3200
NOTE:
M6
COLD ROOM OR
FREEZER
3,000
COLDROOM
PANEL
FLOOR LINE
+/-2000
DRY WALL CONSTRUCTION
WITH X-RATED BOARDS
TO ACT AS FIREWALL
SOFT JOINT
+/-2000
WITH X-RATED BOARDS
TO ACT AS FIREWALL
FLOOR LINE
SERVICE
4500
FLOOR LINE
horizontal bulkhead
ceiling line
support
WING WALLS
BULKHEAD LINE
5000 MAX
SLAB SOFFIT
WING WALLS
FLOOR LINE
NOTE:
· STRUCTURAL STEEL ELEMENTS TO BULKHEAD TO BE IN ACCORDANCE WITH ENG. DETAIL;
· TYPICAL DETAIL OF BULKHEAD SUPPORT TO TRUSS;
· VERTICAL SUPPORT TO BULKHEAD TO BE 5000mm(MAX) APART;
· STRUCTURAL SUPPORT ACCORDING TO STRUCT. ENG. DETAIL & SPECIFICATION;
· SUPPORT DETAIL TO BE APPROVED BY ARCHITECT;
· THE SUPPORT TO CEILING GRID MUST BE ACCORDING TO MANUFACTURERS SUPPORT DETAILS;
· THE CONTRACTOR NEEDS TO PROVIDE A REPORT FROM DONN ACCORDING TO THE STABILITY
OF THE CEILING GRID SUPPORT
25
23
DETAIL
20 8.5
250
TYPICAL STAIR SECTION
FRONT OF HOUSE & STAFF STAIRS
SCALE 1:5
110 150
1249 1247 1247 1247
ROUND
820
WALL LINE
50 110
945
2070
2200
945
110
80
110
1129 1129 1129 1129 1129 1129
150
6772
7,032
CHROMADEK FINISHED
STEEL FACIA
GALVANIZED CURVED
SQUARE TUBING BEAM
2.600
2,200
75 X 75MM GALVANIZED
SQUARE TUBING
BLOCK FOUNDATION
FRONT VIEW
5,000
75 X 75MM
GALVANIZED SQUARE
TUBING
5,000
150 X 300MM
PRECAST CURB
PLAN VIEW
NOTE:
- ROOF TO BE AS DRAWING OR DESIGN TO MATCH CENTRE ARCHITECTURE.
- DESIGN TO BE APPROVED BY SHOPRITE CHECKERS ARCHITECT.
- TAKES UP 2 PARKING BAYS.
30
400
1,400
1,370
400 x 700 BRICK WALL
COLUMN WITH CONCRETE
IN CENTRE. PLASTER AND
110 180 110 PAINT COLUMNS
220
700
260
220
FOUNDATION ACCORDING
COLUMN TO ENGINEERS DETAIL
PLAN COLUMN
SECTION
9,220
4,350 4,370
500 150 3,700 501 3,720 150 500
125 150 125 PURPOSE MADE STEEL SWIVEL RESTRICTION BOOM. PURPOSE MADE STEEL SWIVEL RESTRICTION BOOM.
GALVANISED & PAINT FINISH TO SPECIFICATION. GALVANISED & PAINT FINISH TO SPECIFICATION.
150
ENTRANCE EXIT
1,250
1,370
400 335
ROAD SURFACE
EXIT
735
7,000
400 335
400 X 700 COLUMN 735
OM.
TO DETAIL. ION BO 335 400
PLASTER & PAINT FINISH TO STRICTATION.
IVEL RE IFIC
SPECIFICATION. E STEEL SW TO SPEC 400 X 700 COLUMN
AD NISH
OSE M INT FI TO DETAIL.
PURP ISED & PA PLASTER & PAINT FINISH TO
GALVAN SPECIFICATION.
700
E M
PURPOSISED & PAIN
GALVAN 3,575 400 375
WALKWAY WALKWAY
SURFACE SURFACE
NOTE:
M6
CANOPY
M6
FLOOR LINE
NOTE:
1. ALL CANOPIES TO END 100mm ABOVE CEILING LINE & CEILING TO BE FLUSH AGAINST CANOPY.
FLOOR DRAIN
REPAIR SCREED
NEW TILES
RC SLAB
NOTE:
WATERPROOFING MEMBRANE(SIKA CEMFLEX) UNDER TILES TO EXTEND FOR FULL FLOOR IN ALL
FOOD PREP AREAS.
133
250
1. SECTION
scale 1:10 250
300
250
250
scale 1:10
AFRICA CC
IRIS DE WITT
TEL: 082 733 6858
Ø50mm INLET
254
50mmDIAM PVC
WASTE PIPE FROM Ø110mm OUTLET
500
GREASE TRAP
2. SECTION
scale 1:10 250
300
250
250
120
254
Ø50mm INLET
450
Ø110mm
500
OUTLET
TYPICAL COFFER
450 SLAB
3. SECTION
scale 1:10 250
Ø50mm INLET
TYPICAL 530 X 530 COFFER
90° BETWEEN
PIPES
Ø110mm
300
250
OUTLET
250
300
3. PLAN: KD/FT 3
scale 1:10
150
Ø50mm OUTLET
4. SECTION 5. SECTION
scale 1:10
Ø110mm OUTLET
scale 1:10
240
150
150
240
100
100
100
OVEN USE
1
1 /2" FEMALE GMS
OUTLET
6. PLAN: Ø50mm
COBRA BRASS
6. SECTION
scale 1:10 TRAP(GMS outlet
scale 1:10
4mm THICK GRADE 304 STAINLESS STEEL SUPPORT 6mm COUNTERSUNK STAINLESS
BRACKET WELDED TO FRAME STEEL SCREWS
50 200 50
6
60
NOTE:
IT IS THE RESPONSIBILITY OF THE MANUFACTURER
TO ALIGN ALL COVERS AND FRAMES PRIOR
TO DELIVERY ON SITE.
ACCESS COVER - 4mm GRADE 304 STAINLESS STEEL,
FIXED TO FRAME WITH 4 NO. COUNTERSUNK
STAINLESS STEEL SCREWS
4mm THICK GRADE 304 STAINLESS STEEL SUPPORT 6mm COUNTERSUNK STAINLESS STEEL SCREWS
BRACKET WELDED TO FRAME
PORCELAIN TILES
'Y'
5
CEMENT SCREED
PACKING UNDER FRAME AND CEMENT GROUTING FRAME - 6mm THICK GRADE 304
STAINLESS STEEL ANGLE.
8mm Ø STAINLESS STEEL RAWLBOLTS 'X'= 50mm AND 'Y'= THICKNESS OF
NUMBER OF PER FRAME: 4 SCREED AND FINISH - 5mm.
FRAME TO BE PACKED AND LEVELED TO
LINE UP WITH TOP OF FLOOR FINISH,
BOLTED TO CONCRETE AND GROUTED.
Cash drawer
Sensormatic
Slip printer
2,650
50mm Dia hole for cables 2No. 40 x 25mm removeable galvanised steel
cable trays fixed to underside of top, corners
Cut out for sensormatic to be rounded
2,650
485
494
564
1,077
1,007
910
513
150 x 150mm cut out for cables Hole for power pole cables
50mm Dia hole for cables
Plan of Checkout
Scale : 1:20
Power pole
by PG Bison
GENERAL DETAILS
Double power point fixed inside top
50mm space for cables Cut out for sensormatic Belt to manufacturers details
Top to be 12mm Chipboard with 1.2mm
GENERAL
125
nised mild steel to profile sensormatic CPU
SCALE: 1:20
d to match Spectrum Green 1x normal and 3 x Dedicated double plugs on
plate
Curved front to be galvanised mild steel to
nised mild steel to profile profile and powder coated grey
d grey
Udjustable feet
REV DATE:
Udjustable feet
10.04.2019
DETAIL : TYPICAL DETAILS FOR CHECKERS CHECKOUTS 3 OF 3
REV -
DET50 21
495
35
1,700
Plan of Checkout
Scale : 1:20
50mm Dia hole for 2No. 40 x 25mm removeable galvanised steel
cables cable trays fixed to underside of top, corners
Cut out for sensormatic to be rounded 5
12
R
35
565
495
35
1,700
12
5
Plan of Checkout
Scale : 1:20
by PG Bison
GENERAL DETAILS
65mm Dia hole, silcone in Top to be 12mm Chipboard with
plastic cable route ring with 1.2mm Stainless Steel to prevent Birch Grey ref. 741FH, powder coated steel
cover denting with rubber bump rails cover to match Spectrum Green by PG Bison
with rubber bump rails
GENERAL
SCALE: 1:20
Curved front to be galvanised mild steel to 65mm Dia hole, silcone in plastic cable route
profile and powder coated grey ring with cover
REV DATE:
Rear Section Front Section
Scale : 1:20 Scale : 1:20
10.04.2019
REV -
DETAIL : TYPICAL DETAILS FOR CHECKERS EXPRESS CHECKOUTS 3 OF 3
DET53 21
SPECIFICATION
Number & Type: Goods Lifts (non passenger carrying)
Capacity: 2500kg
Floor to floor: ±3600mm (to be advised at each project)
Pit void: 1600mm
Shaft Size: 1915mm wide x 3000mm deep (or as modified)
Determined by Manufacturer & Project specific
Head Room (less car): 4750mm
Car size (ID): 1800mm(wide) x 2700mm(deep) x 2100mm(high) TBA on
each project
Number of stops: TBA as per requirements (typical - 2)
Entrances: Same side - to be advised
Motor Room position: Top of shaft / To supplier
Motor Room floor: Created from top steel
Lifting mechanism: Geared double drum traction
Control: Relay logic call and send from both landings
Power needs: 380 x 400 v 3 phase 50Hz to be supplied by the
client
Car Doors: Bolton preferred, Cody accepted
Door Locks: Dupalocks LE2
Landing doors: Eurofold
Top Steel: Supplied for installation by the builder for masonry shaft
Finishes: General Hoist:
* car walls galvanised steel, stainless steel preferred
* Bumper Rails to the car wall - 3 sides, 3 heights,
butterfly raised s/steel bumber
Butchery Receiving Hoist:
* Car walls stainless steell
* Bumper Rails to the car wall - stainless steel bumper
butterfly raised
SPECIFICATION
Side guides: Attached to shaft diagonals / to supplier
Shaft Light: To be supplied by client in masonry shaft
Pit walls: Reinforced concrete or solid masonry (by builder)
Motor Room platform: Off the top steels - part of lift installation
Speed: 0.2 m/s (min)
Call & send buttons: Recessed in Wall
Maintenance: 12 months free first year
Motor, Control Speed, selection and make to be approved
& Gearbox:
30 tile 50
plaster
30
50
plaster space behind
filled solid with mortar
inner flange
plugged & screwer
STAINLESS STEEL TYPE 304 18/10 STAINLESS STEEL TYPE 304 18/10
2mm THICK HIGHLY POLISHED 2mm THICK HIGHLY POLISHED
FACING SURFACES TO FACING SURFACES TO
EXACT HEIGHT OF TILES EXACT HEIGHT OF TILES
TYPE A - LOCATION TYPE B - LOCATION
Bakery/Deli Columns
Butchery/Fish
tile
10
plaster
50 tile
plaster
varies according to wall thickness
inner flange
steel-nailed to wall
contractor to notify supplier
of exact dimensions required
for each situation
wall thickness varies
TYPE D - LOCATION
Bakery/Deli
Butchery/Fish finished face
check finishes schedule
76
920
920
20
chemical fixing
130
150
CORNER PROTECTOR
FIXED WITH CHEMICAL
ACHORS
150
CONER PROTECTOR
WELD IN
CORNER
FROM TOP
TO
ELEVATION
BOTTOM
R=
100
50 INTERMEDIATE SUPPORTS
90x90x6mm
THICK BASEPLATES
90
15 60 15
60
6mm PLATE
15
100 350
Bread crate
100
A.F.F.L
20
on tile adhesive
on tile adhesive
750
1050
1200
150
1800
BUMPER GUARD AT
150
15|
EDGE TRIM
TILES
LOW WALL TILES
1,600
BUTCHERY SERVING AREA
3,000
BUTCHERY
TILES
Notes:
SECTION · steel structure as per engineers details and specification.
· prime all steelworks with red oxide and 2 coats Plascon Velvaglo,
White.
· aluminium frame to be secured to wall and support structure as per
glazing supplier details and procedures.
· tiling set out to be aligned with the existing wall tiling.
· sufficient size movement joints to be allowed between glazing
panels.
· specification as per butchery finishes schedules, low level wall to be
tiled on both sides.
BUTCHERY
type 'B' corner protector to full length and TILES
height of wall
7,412 895
1,250 1,231 1,231 1,231 1,231 1,238 30 835 30
565
glazing secured inside frame
BUTCHERY SERVING AREA
TILES
PLAN
7,412 895
1,248 1,231 1,231 1,231 1,231 1,238 30 30
835
line indicates ceiling level
Butt-jointed
glazing secured
inside frame as
per glazing
supplier details
and procedures
2,082 to be checked on site
fixed
glazing
fixed
glazing
ELEVATION
JOINT OF CORNER
PROTECTORS TO BE
AT TILE JOINT
PAINT
UNDER-TILE
CNR PROTECTOR
ELEVATION COLUMNS
TILES LAID WITH CERAMIC TILES
VERTICALLY UNDERNEATH
1,500
CEILINGS/BULKHEADS
SCALE 1:25
JOINT OF CORNER
PROTECTORS TO BE 530
AT TILE JOINT
300 300 230
110mm BRICK-
WORK AROUND
WATER PIPE
COLUMN DETAILS
50x50 S/S CORNER 50x50 S/S CORNER
PROTECTOR DETAIL PROTECTOR DETAIL
DWG C600-1, TYPE A DWG C600-1, TYPE A
LOCATION:
FREE-STANDING COLUMNS: TYPICAL PLAN TYPICAL PLAN COLUMNS ON
TRADING FLOOR & SERVICE DEPTS OF COLUMNS GRIDS CD/03 & CD/05
SCALE 1:15 SCALE 1:15
silicone seal
11,720
1,863 1,863 2,590 1,620
C/L C/L 1,108 122 1,269 C/L
MEZZANINE SUPPORT 50x50x2.5 CROSS BEAM HEIGHT OF C/L
BEAMS SHS FRAME 90x90x4.0 SHS STILES MEZZANINE STRUCTURE
168 50 112
50
GENERAL DETAILS
60x60x2.5 60x60x2.5 60x60x2.5
SHS FRAME SHS FRAME SHS FRAME
GUIDE TRACK FOR GATE
GENERAL
SLIDING GATE
TYPE CD35
DETAILS - C
SCHEDULE
SCALE: NTS
C/L TO MATCH
50x50x4 50x50x4 50x50x4 GATE MIDRAIL
ANGLE ANGLE ANGLE
FFL
REV DATE:
GROUND FLOOR BULK STORE
60x60x2.5 90x90x4.0 90x90x4.0 90x90x4.0 90x90x4.0 CD35 90x90x4.0 60x60x2.5
SHS STILE SHS STILE SHS STILE SHS STILE SHS STILE SHS STILE SHS STILE
steel sliding gate
10.04.2019
1,863 1,863 1,863 1,863 2,590 1,620
REV -
PLAN: STEEL CAGE 1
DET64 21
50x50x2.5 SHS
FIXED TO WALLS
1,925
60x60x2.5 SHS
CROSS BRACING
OVER CAGES
1,925
GENERAL DETAILS
GENERAL
1,925
DETAILS - C
50x50x4 ANGLE
CROSS BRACING
OVER CAGES
SCALE: NTS
1,925
CAGE 10 CAGE 9 CAGE 8 CAGE 7 CAGE 6
REV DATE:
CD25/5 CD25/4 CD25/3 CD25/2 CD25/1
C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L
1,152 910 994 994 910 994 994 910 994 994 910 994 994 910 1,029
3,056 2,897 2,897 2,897 2,933
MAIN FRAME OVERALL 14,740
10.04.2019
PLAN: STEEL SCREENS 3 & 4 (CAGES 6-10) (SCALE: 1:100)
REV -
DET65 21
COLUMN
GENERAL DETAILS
50x50x2.5 50x50x2.5 50x50x2.5
SHS FRAME SHS FRAME SHS FRAME
FFL
GENERAL
SCALE: NTS
DETAIL : TYPICAL STEEL CAGES 3 OF 3
9,680 O/A DIMENSION OF CAGE
9,620 INTERNAL DIMENSION OF CAGE 60
1,925 1,925 1,925 1,925 1,920
REV DATE:
CROSS BRACINGS CROSS BRACINGS CROSS BRACINGS CROSS BRACINGS
60
60x60 50x50x4
x2.5 ANGLES
720
720
660 60
STILES
50
50
60x60 60x60
x2.5 x2.5
STILE 50x50x4 50x50x2.5 STILES
BOLTED ANGLE SHS FRAME
TO WALL
10.04.2019
2,160
2,160
2,280
2,280
ANGLES
FFL FFL
50
50
20
20
REV -
DET66 21
536
150
HINGE
100
NO. DISK
2,032
CL
KICK PLATE
1,050
FULL WIDTH
TO U/S OF
DOOR HANDLE
100
HINGE
150
FFL
EDGES.
KICKPLATE
• Kickplate full width to underside of door LOCK & FURNITURE
handle
• SS FLUSH RING
• SS ESCUTCHEON ON ROSE PROFILE
•
NUMBER
DISK
HANDLES
FFL
DOOR HINGES
• MUTUAL G1 ANTI-BANDIT PERSONNEL • HINGED ON ROTAN CONTINUOUS HEAVY
DOORS SUPPLIED BY MASS MUTUAL DUTY HINGES
AUSTEN - CONTACT (021 931 9404)
• COMPLETE WITH FRAME TO SUIT CLEAR
FINISHED OPENING OF 969x2100mm IN CLOSER
IRONMONGERY
DOOR FRAMES
• 100x50 M/STEEL FRAME SUPPLIED GENERAL
• FINISH PRIMER UNDERCOAT.
• SATIN PULL HANDLES,D TYPE
• FINAL COATS BY CONTRACTOR
• NUMBER DISK - 45dia. x 2mm THICK.
AFTER INSTALLATION
• ASSA 87001SS DOORSTOP.
KICKPLATES
· S/Steel 300mm Kick plates
VISION
2100 CLEAR FINISHED OPENING
NUMBER
DISK
HANDLES
FFL
DOOR HINGES
• MUTUAL G1 ANTI-BANDIT PERSONNEL • HINGED ON ROTAN CONTINUOUS HEAVY DUTY
DOORS SUPPLIED BY MASS MUTUAL HINGES
AUSTEN - CONTACT (021 931 9404)
• COMPLETE WITH FRAME TO SUIT CLEAR
FINISHED OPENING OF 969x2100mm IN CLOSER
IRONMONGERY
DOOR FRAMES
• 100x50 M/STEEL FRAME SUPPLIED GENERAL
• FINISH PRIMER UNDERCOAT.
• FINAL COATS BY CONTRACTOR • VISION PANEL 300w x 400h FITTED WITH 38mm
AFTER INSTALLATION BRG BULLET RESISTANT.
FIREPROOF VENT
86
HINGE
1,966
HANDLE
HINGE
FFL
DOOR HINGES
• STANDARD STRONGROOM DOOR TYPE DS • STANDARD BY SUPPLIER
50/2 CAT2 HEAVY DUTY - BY MUTUAL SAFE
& SECURITY (PTY) LTD
• WALL OPENING:1000w x 1920h
CLOSER
IRONMONGERY
• NIL
DOOR FINISHES
• 2cts PLASCON VELVAGLO ON SUPPLIED GREY • LOCK SUPPLIED WITH DOOR.
UNDERCOAT
•(CONTRACTOR NOT ALLOWED TO OPEN
DOOR WITH KEYS)
DOOR FRAMES
• STANDARD BY SUPPLIER
GENERAL
• 185 x 185mm DOUBLE ENDED STRONGROOM
VENTILATOR ABOVE DOOR CENTRE TO DOOR IN
BRICKWORK BY MUTUAL.
• UNIVERSAL DOORSTOP BY MUTUAL.
KICKPLATES
• NIL
BRUSH STRIP
HINGE HINGE
450x600 450x600
VISION VISION
PANEL PANEL
2100-2500
BRUSH STRIP
BUMPER BUMPER
HINGE HINGE
FFL
DOOR HINGES
• PURPOSE MADE INDUSTRIAL DOUBLE • 4 x CAST ALUMINIUM HINGES WITH CAM
CRASH-DOOR BY APEX (OR EQUAL OPERATION AND BEARINGS
APPROVED) - 1630x2036 (CONFIRM ON SITE)
- TO MANUFACTURER'S SPEC.
IRONMONGERY
DOOR FINISHES
• FOR APEX DOORS WITH BRUSH, COLOUR GENERAL
CHARCOAL (CHECKERS STD).
• 3mm POLYCARBONATE VISION PANELS.
• BUMPER RAIL ON TRADING FLOOR
DOOR FRAMES AND BOH. AS DOOR STOP
• 127x76x3mm GALVANIZED MS STEEL BOX • S/S BUMPER RAIL ON TRADING FLOOR
SECTION FRAME WITH 127x64mm HEAD SIDE AS DOOR STOP
CHANNEL SECTION
• BLACK POWDER COATING ON FRAME • BRUSH STRIPS BETWEEN DOOR LEAFS, AND LEAFS
AND TOP FRAME.
75 1,100 75
BRUSH STRIP
64
HINGE
450x600
VISION
PANEL
2,044
1,980
BUMPER
HINGE
FFL
DOOR FINISHES
• FOR APEX DOORS WITH BRUSH, COLOUR
CHARCOAL (CHECKERS STD).
100 150
GROOVE IN PLASTERED HINGE
100
WALLS WITH STEEL DOOR LEAF
DOWEL RODS
HINGE
100
NUMBER
DISK
FILL SOLID WITH
MORTAR BEHIND
STEEL FRAME FRAME WIDTH EQUAL TO
WALL THICKNESS + 30mm
2,032
2,064
BRICK WALLS
KICK PLATE
900
FLUSH DOOR
100
STEEL FRAME BEYOND
HINGE
200
150
FFL
2210 AFL
2,032
INDICATOR BOLT CL
TILED WALLS
1,032
FLUSH DOOR
100
FFL
• CORE 50% SOLID TIMBER PRIMER, 1ct UNIV UNDERCOAT, 2cts DULUX
SUBSTRATE
SILTHANE SILK
GENERAL
HINGES • AS COAT HOOK/DOOR STOP,RUBBER TIPPED
• 2x 100mm STEEL BUTT HINGES INTEGRAL FIXED WITH ONE-WAY ALUM. SCREWS
WITH FRAME - PAINTED & SPINDLE OILED
100 150
GMS SHEETING ON OUTER FACE
OF DOOR, WITH 20mm RETURN
DRIPBAR
FLANGES
ONTO SIDES & TOP EDGES
HINGE DOOR
100
HINGE GMS SHEETING ON OUTER FACE
OF DOOR, WITH 20mm RETURN
100
FLANGES
NO. DISK ONTO SIDES & TOP EDGES
DOOR 2032
DOOR 2032
LEVER HANDLE LEVER HANDLE
CL HINGE
100
1.093
KICK PLATE
1,150
1,150
1,050
100
HINGE
150
FFL FFL
FILL SOLID WITH FRAME WIDTH EQUAL TO
MORTAR BEHIND WALL THICKNESS + 30mm
WEATHER DRIP-BAR STEEL FRAME BUILT IN ON LOCK SIDE
SILTHANE SILK
• KNOB CYL LOCK.
OR
• FINISH 1ct PLASCON WOOD PRIMER, 1ct FROM:
PLASCON UNIVERSAL UNDERCOAT, 2cts • ASSA ABLOY
SUBSTRATE
100 150
HINGE
100
HINGE
1.093
100
NO. DISK
DOOR LEAF
DOOR 2032
DOOR 2032
CL HINGE
100
FILL SOLID WITH FRAME WIDTH EQUAL TO
MORTAR BEHIND WALL THICKNESS + 30mm
STEEL FRAME BUILT IN ON LOCK SIDE
KICK PLATE
1,150
1,150
100
HINGE
150
FFL FFL
WEATHER DRIP-BAR
DOOR DRIPBAR
DOOR
GMS SHEETING TAKEN OVER
TOP OF DOOR & 20mm RETURN INTERNAL FLOOR
AT BOTTOM & SIDES FINISH AS PER GMS SHEETING ON OUTER FACE
FIN. SCHEDULE OF DOOR, WITH 20mm RETURN
WEATHERBAR (WHERE APPL.) FLANGES
ONTO SIDES & TOP EDGES
25x75x25x6mm GALV. M.S. Z-PROFILE
WITH BUILDING-IN LUGS WELDED ON
BELOW AND BOLTTED TO SLAB -
FLOOR FINISH FLUSH WITH TOP OF LIP.
ON INNER FACE
• SINGLE P/BOLT P/BAR 1200mm
DOOR FINISHES
• FINISH 1ct DULUX PINK PRIMER, 1ct • EN2-4 DOOR CLOSER
UNIVERSAL UNDERCOAT, 2cts DULUX
SILTHANE SILK • TO BE APPROVED BY FIRE
OR
CONSULTANT AND CONFORM TO SANS
• FINISH 1ct PLASCON WOOD PRIMER, 1ct
10400
PLASCON UNIVERSAL UNDERCOAT, 2cts
PLASCON VELVAGLO FROM:
• ASSA ABLOY
HINGES • CISA
• 3x100 STEEL BUTTS INTEGRAL WITH FRAME • DORMA
• GEZE
METAL SHEET PROTECTION
• 0.8mm GMS SINGLE SHEET EPOXY GLUED GENERAL
ONTO OUTER FACE OF DOOR, WITH 20mm
RETURN FLANGES ONTO SIDE & BOTTOM • 1 x KEYBOX
EDGES; & FULL RETURN OVER TOP WITH
20mm FLANGE INSIDE - SCREWED AT EDGES • INSTALL DRIP BAR AT TOP OF DOOR ON OUTSIDE
(CONCEALED WHEN CLOSED). PAINTED AND WEATHER BAR AT BOTTOM
SAME COLOUR AS WALL. • NO SUNLIGHT TO BE VISIBLE FROM INSIDE ,BELOW
OR AROUND DOOR.
150
150
HINGE HINGE
100
100
PULL HANDLE
2,032
2,032
100
KICK PLATE FULL WIDTH KICK PLATE FULL WIDTH
1,000
900
900
100
100
HINGE HINGE
150
150
FFL FFL
OUTSIDE INSIDE
• CORE 50% SOLID TIMBER; WITH 1mm THICK PRIMER, 1ct UNIV UNDERCOAT, 2cts DULUX
POLISHED S/S KICKPLATE TO REQUIRED SIZE SILTHANE SILK ENAMEL
ON OUTER FACE,EPOXY GLUED & SCREWED
WITH COUNTERSUNK S/S SCREWS ON OUTER
EDGES.
GENERAL
LOCK & FURNITURE
• DOORSTOP SCREWED TO FLOOR IN SENSIBLE
• FACILITY INDICATOR BOLT. POSITION TO ALLOW MAXIMUM OPENING.
• SS TUBULAR PULL HANDLES • NATURAL ANODISED PARAPLEGIC SIGN PLATE
• DOOR CLOSER. • 45 D x 2mm THICK NUMBER DISK.
FROM:
• ASSA ABLOY
• CISA
• DORMA
• GEZE
DOOR
FFL
BELOW AND BOLTTED TO SLAB -
FLOOR FINISH FLUSH WITH TOP OF LIP.
WEATHER DRIP-BAR - WHERE APPLICABLE
FROM:
• ASSA ABLOY
• CISA
DOOR FINISHES • DORMA
SUBSTRATE
IRONMONGERY
• GEZE
• FINISH INTERNALLY WITH 1ct DULUX PINK
PRIMER, 1ct DULUX UNIVERSAL UNDERCOAT,
2cts DULUX SILTHANE SILK ENAMEL
GENERAL
DOOR
FFL
BELOW AND BOLTTED TO SLAB -
FLOOR FINISH FLUSH WITH TOP OF LIP.
WEATHER DRIP-BAR - WHERE APPLICABLE
DOOR FINISHES
SUBSTRATE
FROM:
IRONMONGERY
GENERAL
HINGES
• 6 No. 100x76mm BRASS BUTT HINGES
INTEGRAL WITH FRAME, SPINDLE OILED
METAL SHEET PROTECTION
• 0.8mm GMS SINGLE SHEET EPOXY GLUED
ONTO OUTER FACE OF DOOR, WITH 20mm
RETURN FLANGES ONTO SIDE & BOTTOM
DOOR FRAMES EDGES; & FULL RETURN OVER TOP WITH
• STANDARD 1.2mm DOUBLE REBATED GALV. 20mm FLANGE INSIDE - SCREWED AT EDGES
STEEL FRAME (CONCEALED WHEN CLOSED). PAINTED
FOR 230mm WALL SAME COLOUR AS WALL.
HINGE HINGE
100
100
2400
100
HINGE HINGE
150
FFL
DOOR FINISHES
SUBSTRATE
FROM:
IRONMONGERY
GENERAL
HINGES
• 4x No. 100x76mm STEEL BUTT HINGES
INTEGRAL WITH FRAME, SPINDLE OILED
DOOR FRAMES
• STANDARD 1.6mm DOUBLE REBATED GALV.
STEEL FRAME
FOR 230mm WALL
100 150
100
COAT-HOOK
ON INSIDE
HINGE
CENTRED
100
900
PLASTER TO WALLS NO. DISK
DOOR LEAF
PULL HANDLES
2,032
FLUSH DOOR
KICK PLATE
STEEL FRAME BEYOND FULL WIDTH
FILL SOLID WITH FRAME WIDTH EQUAL TO ON OUTSIDE
MORTAR BEHIND WALL THICKNESS + 30mm TO U/S OF
STEEL FRAME BUILT IN ON LOCK SIDE DR HANDLE
CLOSE TO DIVISION WALL
100
HINGE
200
150
FFL
KICKPLATE HINGES
• Kickplate full width to underside of door • 3x 100mm STEEL BUTT HINGES INTEGRAL
handle WITH FRAME - PAINTED & SPINDLE OILED
DOOR FINISHES
GENERAL
• FINISH 1ct DULUX WOOD PRIMER, 1ct DULUX
UNIVERSAL UNDERCOAT, 2cts DULUX
SILTHANE SILK ENAMEL
FROM:
• ASSA ABLOY
• CISA
• DORMA
• GEZE
100 150
HINGE
100
HINGE
100
NUMBER
DISK
2,032
KICK PLATE
900
100
HINGE
150
FFL
PLATE.
• MORTICE SASHLOCK SS.
KICKPLATE • DOUBLE CYLINDER.
• Kickplate full width to underside of door
handle
FROM:
DOOR FINISHES • ASSA ABLOY
• CISA
• FINISH 1ct PLASCON WOOD PRIMER, 1ct
PLASCON UNIVERSAL UNDERCOAT, 2cts
• DORMA
PLASCON VELVAGLO WHITE • GEZE
GENERAL
• 1 no. SS DOORSTOP SCREWED TO FLOOR IN
SENSIBLE POSITION TO ALLOW MAXIMUM
HINGES OPENING.
• 45 D x 2mm THICK NUMBER DISK.
• 3x 100mm STEEL BUTT HINGES INTEGRAL
WITH FRAME - PAINTED & SPINDLE OILED
• KEY NR. DISK.
WALL OPENING
2000Highx800Wide
100
900
2032
RECESS
HANDLE
eq eq
900
Guide plate
HINGES
• HILLALDAM COSY DELUX DOOR SLIDING SET
DOOR FRAMES
• NIL
• WALL OPENING 2000 x 800
2.500
FFL
HINGES GENERAL
• NIL • NIL
2.500
FFL
HINGES GENERAL
• NIL • NIL
2.100
FFL
HINGES GENERAL
• NIL • NIL
2400-2800
FFL
HINGES GENERAL
• NIL • NIL
SHUTTER BOX
SHUTTER BOX
LINE OF
WALL BEYOND LINTEL SOFFIT
100
2,400 OR 2700 STRUCTURAL OPENINGCHECK ON SITE
75x25x3mm COLD
ROLLED STEEL
GUIDE CHANNELS
FFL FFL
DOOR HINGES
• Size: 2400 x 2700 mm • None
• STEEL ROLLER SHUTTER BY SERRANDA (or
equal approved)
IRONMONGERY
KICKPLATES
• None
SHUTTER BOX
SHUTTER BOX
LINE OF
WALL BEYOND LINTEL SOFFIT
100
2,400 OR 2700 STRUCTURAL OPENINGCHECK ON SITE
75x25x3mm COLD
ROLLED STEEL
GUIDE CHANNELS
FFL FFL
DOOR HINGES
• Size: 1800 x 2400 mm • None
• STEEL ROLLER SHUTTER BY SERRANDA (or
equal approved)
IRONMONGERY
• CHAIN OPERATED.
• None
KICKPLATES
• None
SHUTTER BOX
SHUTTER BOX
LINE OF
LINTEL SOFFIT
75x150x3mm STEEL
FIXING BRACKETS
WELDED TO STEEL
CHANNELS &
BOLTED TO WALL
(CHEMICAL FIXING)
75x25x3mm COLD
2,000
ROLLED STEEL
GUIDE CHANNELS
DOOR HINGES
• Size: 1200 x 2700 mm • None
IRONMONGERY
equal approved)
• SLATS TO BE MIN. 1.2mm THICK CLOSER
• MANUAL CHAIN OPERATION - LH OR RH,
WHICHEVER IS SUITABLE • None
DOOR FINISHES
• GALVANISED factory finish to all elements
• BUTCHERY-PAINT BOX AND GUIDES
GENERAL
• GUIDE TRACK EDGES TO BE FLUSH WITH
OPENING JAMB FINISH
DOOR FRAMES • DOOR TO RETRACT FULLY UP TO OPENING
• GUIDES SOFFIT & BOX TO BE ABOVE LINTEL
KICKPLATES
• None
CLEAR GLASS
IN ACCORDANCE
WITH SABS 0400
2,620
3000-4000
LOCK
LOCK LOCK
480
CLEAR GLASS
IN ACCORDANCE
WITH SABS 0400
2,620
3000-4000
LOCK
AT SHOPFRONT 1
LOCK
LOCK
150 480
INSIDE FIXING
NATURAL NATURAL
ANODISED ANODISED
480 150
480 150
LOCK 2 LOCK 2
1,030
1,030
fixed fixed fixed
pane pane pane
150
150
DOOR FRAMES
• NATURAL ANODISED ALUMINIUM
GENERAL
• CLEAR SAFETY GLASS & SEALS IN STRICT
ACCORDANCE WITH SANS 10400
HINGE
SMOKEY GREY
TINTED GLASS
SAME HEIGT AS SF1A/B
CL
150
SMOKEY GREY
TINTED GLASS
630
HINGE
FFL
NOTE:
• ALL ALUMINIUM WORKS TO BE DONE IN ACCORDANCE WITH AAAMSA STANDARDS.
• THIS DRAWING IS A DESIGN INTENT DRAWING. THE SUBCONTRACTOR IS RESPONSIBLE FOR THE DESIGN
& SUPPLY.
• MANUFACTURER'S SHOP DRAWINGS ARE TO BE FORWARDED TO THE ARCHITECT FOR APPROVAL
BEFORE INSTALLATION.
IRONMONGERY
• DORMA
• GEZE
GENERAL
• 6mm SAFETY GLASS WITH SMOKEY GREY TINT TO
BE EXECUTED STRICTLY IN ACCORDANCE WITH
THE GLASS MANUFACTURERS' SPECIFICATIONS
AND ALL IN ACCORDANCE WITH THE NATIONAL
BUILDING REGS, SABS D137, SABS 0400 & SABS
DOOR FINISHES 1263.
• SEALS: DESIGN & SUPPLY
• NATURAL ANODISED ALUMINIUM (SHOPRITE)
OR POWDER COATED MATT ANTHRACITE
GREY (CH & HYPER) ,WITH GLASS PANELS.
HINGES
• 1 1/2 prs 100mm ALUMINIUM SINKLESS
HINGES WITH DOUBLE NYLON WASHERS
HINGE
600
PLASTERED
SMOKEY GREY BRICK WALLS
TINTED GLASS
2,100
830
FRAME INSTALLED
CL 930 U/F WALL FLUSH WITH EXT
150
HINGE
WALL TILES
SMOKEY GREY
TINTED GLASS
630
HINGE
FFL
NOTE:
• ALL ALUMINIUM WORKS TO BE DONE IN ACCORDANCE WITH AAAMSA STANDARDS.
• THIS DRAWING IS A DESIGN INTENT DRAWING. THE SUBCONTRACTOR IS RESPONSIBLE FOR THE DESIGN
& SUPPLY.
• MANUFACTURER'S SHOP DRAWINGS ARE TO BE FORWARDED TO THE ARCHITECT FOR APPROVAL
BEFORE INSTALLATION.
IRONMONGERY
• DORMA
• GEZE
GENERAL
• 6mm SAFETY GLASS WITH SMOKEY GREY TINT TO
BE EXECUTED STRICTLY IN ACCORDANCE WITH
DOOR FINISHES THE GLASS MANUFACTURERS' SPECIFICATIONS
• NATURAL ANODISED ALUMINIUM (SHOPRITE) AND ALL IN ACCORDANCE WITH THE NATIONAL
OR POWDER COATED MATT ANTHRACITE BUILDING REGS, SABS D137, SABS 0400 & SABS
GREY (CH & HYPER) ,WITH GLASS PANELS. 1263.
• SEALS: DESIGN & SUPPLY
HINGES
• 1 1/2 prs 100mm ALUMINIUM SINKLESS
HINGES WITH DOUBLE NYLON WASHERS
HINGE
SMOKEY GREY
2100 OVERALL FINISHED OPENING
1,350
NUMBER
DISK
CL LEVER HANDLES
150
KNOB ON INSIDE HINGE
ALUMINIUM PANEL
480
750
HINGE
150
FFL
FROM:
• ASSA ABLOY
• CISA
• DORMA
• GEZE
HINGE
0.150
CLEAR GLAZING
2100 OVERALL FINISHED OPENING
1,350
NUMBER
DISK
CL LEVER HANDLES
150
ALUMINIUM LOUVRE
PANEL
480
750
HINGE
150
FFL
NOTE:
• ALL ALUMINIUM WORKS TO BE DONE IN ACCORDANCE WITH AAAMSA STANDARDS.
• THIS DRAWING IS A DESIGN INTENT DRAWING. THE SUBCONTRACTOR IS RESPONSIBLE FOR THE DESIGN
& SUPPLY.
• MANUFACTURER'S SHOP DRAWINGS ARE TO BE FORWARDED TO THE ARCHITECT FOR APPROVAL
BEFORE INSTALLATION.
IRONMONGERY
FROM:
• ASSA ABLOY
• CISA
• DORMA
• GEZE
WALL
PLATE PROTECTOR FIXED TO
BRICKWORK WITH M6 BOLTS
150
ROLLER
100
SHUTTER
SIDE
TYPE H
SCALE 1:5
DOOR LEAF
25x75x6mm GALV.
MILD STEEL ANGLE WITH
BUILDING-IN-LUGS WELDED UNDER
AND BOLTED TO CONC. SLAB
NOTE:
vision panels
dtl
1
glazing panel
12 x 12mm aluminium glazing
beading
natural anodised
aluminium frame
vision panels
dtl
1
glazing panel
12 x 12mm aluminium glazing
beading
natural anodised
aluminium frame
FIXED - 1.100
dtl
1
glazing panel
12 x 12mm aluminium glazing
beading
natural anodised
aluminium frame
38mm BRG
1,000
PT2
Ø50mm
150
Glazed formica
base with tray
680 dtl
50
2,200
6mm VERTICAL
STEEL SUPPORT
1,300
TRADING ENTRANCE
100
Section
scale 1:20 230
GEYSER
SOAP
SANITARY DETAILS
DISPENSER
ALLOW FOR
TRANSFORMER
250
250
2 115
DCBPS DOUBLE BOWL POT SINK 100
150
150
ELECTRICAL UNIT
SANITARY
CONNECTION 75
DISTANCE TO BE AS SHORT ° BELOW WHB
DETAILS - C
AS POSSIBLE REFER TO 90
DRAINAGE LAYOUT
1 060
TRAP CHROME BOTTLE
910
910
WALL
800
SCALE: 1:25
TRAP
HB GT 500 * SINK TO BE FIXED ON
KB/FT 2 GREASE TRAP FLOOR WITH PLUGS
FLOOR DRAIN AND SCREWS
AFFL AFFL
ELEVATION SCALE 1:20 POT SINK
SECTION 1:20
CONFIRM EXACT DIMENSIONS WITH SUPPLIER
1850 * WHITE SILICON
65 SEALANT TO BE
590 303 303 590 DONE BEFORE B.O.
75 75 75 75 50 25 25
50
385
150
WALL
75
115
CHROME BOTTLE
200
99 75
TRAP
420
800
200
650
551
AFFL
SA01
DISTANCE TO BE AS SHORT
AS POSSIBLE REFER TO WHB
DRAINAGE LAYOUT SECTION 1:20
REV -
PLAN SCALE 1:20
21
250
2 115
150
150
SANITARY DETAILS
75
SANITARY
1 160
BLACK PVC
1 060
1 060
910
910
TRAP
DETAILS - C
WALL
* SINK TO BE FIXED ON
SCALE: 1:25
ELEVATION POT SINK
SCALE 1:20 SECTION 1:20
CONFIRM EXACT DIMENSIONS WITH SUPPLIER
1650
491 75 75 302 302 75 75 490
65
WALL
75
100 75
320
NOTE:
- 1650 POT SINK
650
550
- TO BE PURPOSE MADE
REV -
21
SANITARY DETAILS
250
2 115
150
150
75
665
SANITARY
1 160
DETAILS - C
1 060
910
910
SCALE: 1:25
AFFL AFFL
ELEVATION
SCALE 1:20 740
POT SINK
1650 SECTION 1:20
824 824
7575
WALL
75
75
665
565
REV -
21
* WHITE SILICON
300
SEALANT TO BE
DONE BEFORE B.O.
600
122
AFFL
600
300
300
100100
WALL
WALL
600
500
247
AFFL
PLAN SECTION
SCALE 1:20 SCALE 1:20
WASHTROUGH
SANITARY DETAILS SCALE: 1:20 REV DATE: 10.04.2019 REV -
line indicates top fixing support:
50x50mm m/steel angle iron frame
fixed to wall with m10 frame fit inside
50
edge. weld cross section to frame
200
below vanity top.
10L ZIP instant quail underslung vanity basin
600
boiling water
dispensor product code: 7004
SINK IN CANTEEN
from vaal sanitaryware
SANITARY DETAILS
Rustenberg Grey granite top Sink Unit: Franke Curveline CVN621
UPPER SHELVING PLAN stainless steel satin sink.
Sink Mixer Spout: Hansgrohe - Décor E2 -
Mixer - Chrome - Single lever basin mixer
SANITARY
SCALE: NTS
135 200 with peened finish and
246 246 246 246 Isolator for hydroboil supawood core(suplam)
10l zip instant boiling
300
water dispensor 300
Waterpoint for hydroboil White silicone seal
1 232
* Rustenberg Grey granite top Rustenberg Grey granite top
844
300
644
644
2 115
Microwave Finish, single lever Sink Mixer Spout: Hansgrohe
140
32
1 704
2 brick courses over
1 400
1 350
510
900
white grout. use PVC edge trim
granite shelf
painted neutral
100mm high tiled plinth
100
100
3 778
ELEVATION SECTION A-A
REV -
21
163
secure and neat installation. Wipe of excess sealant
PRODUCT CODE: 31733000
300
and allow to dry. from HANSGROHE SANITARYWARE
275
QUAIL UNDERSLUNG VANITY BASIN
300
PRODUCT CODE: 7004
SANITARY DETAILS
163
FROM VAAL SANITARYWARE
120 110 110 121 TO DB
471 471 471
CEILING LINE
DETAILS - C
SCALE: 1:30
Ø25mm
FLUSH 30A PP
ISOLATOR
400
700
600
TAPS: SINGLE LEVER BASIN MIXER 70
357 580 580 357 200
PRODUCT CODE: 31733000
2700
TAPS: SINGLE LEVER BASIN MIXER 70 163 275 163 HAND
from HANSGROHE SANITARYWARE DRYER
PRODUCT CODE: 31733000
from HANSGROHE 215 HOSE TAP
300
VANITY TOP: 32mm RUSTENBERG GREY VANITY TOP: 32mm RUSTENBERG GREY
1900
GRANITE WITH BULLNOSE EDGE GRANITE WITH BULLNOSE EDGE
1 600
REV -
SECTION FRONT ELEVATION
21
650
SIDE VIEW: WALL HUNG PAN FRONT VIEW: WALL HUNG PAN
scale 1:25 scale 1:25
NOTE:
- THIS SHOULD BE READ IN CONJUCTION WITH SCHEDULE OF FINISHES
- PLEASE FOLLOW SUPPLIERS INSTALLATION INSTRUCTIONS
A
500
645
Toilet
Wheelchair
Toilet roll
Holder
295
1800
WHB
DISABLED W.C.
4 m2
B
B
VANITY SHELF
400
Mirror
770
380
Grab rail
300
1750
WHB
820
740
480
Toliet
Podium
600 347
DISABLED W.C 1 OF 3
SANITARY DETAILS SCALE: 1:25 REV DATE: 10.04.2019 REV -
SANITARY
DETAILS - C SA09 21
Grab rail
820
740
Space for
480
Wheelchair
300
300
Pull handle
1000
300
700
0,600
Inside Outside
ELEVATION
DISABLED W.C 2 OF 3
SANITARY DETAILS SCALE: 1:25 REV DATE: 10.04.2019 REV -
SANITARY
DETAILS - C SA10 21
Work top
1200
450
DISABLED W.C 3 OF 3
SANITARY DETAILS SCALE: 1:25 REV DATE: 10.04.2019 REV -
WIRE SCREEN
DETAILS - C INDEX 21
NUMBER LOCATION
WS01 RETURNS
100
100
CLEAR OPENING 1040
50
50
GATE 900
75 STRIKING PLATE
20 50
20mm GAP
SLOTTED HOLES
FOR PADLOCK
HINGE
75
50
35
2,400 CLEAR OPENING
PULL GRIP,
MESH SPOT-WELDED PULL GRIP
STRIKING PLATE
TO REAR FACE
OF GATE FRAMING & PADLOCK
75 x 50h x 5
STRIKING PLATE
2,330
BRACING TUBE
FLUSH WITH
MID-RAIL REAR FACE
GATE FRAME
CAGE POST
MESH
HINGE GATE
FFL
80
GATE FRAME
• 900x2330 HOT DIP GALV MILD • GALV MILD STEEL TUBING WITH
STEEL GATE WITH 50x50x2.5 MS COLD GALV APPLICATION TO
HOLLOW SECTION AND 25x25x2.5 WELDS
HOLLOW SECTION MIDRAIL FRAME • STRIKING PLATE 100x150h x5 GALV
TUBING MITRE CUT AT CORNERS & MS PLATE WITH HOLE FOR
FULLY WELDED & GROUND PADLOCK
SMOOTH MENTIS TYPE 304
EXPANDED METAL SHEETING SPOT
WELDED TO REAR FACE OF FRAME
75x100h x5mm STOP PLATE TO
REAR OF GATE & ROUNDED PULL
GRIP (TO DETAIL) WITH HOLE FOR
PADLOCK WELDED TO GATE STILE
38x38x2.5mm HOLLOW
20
75x150x5 ROUNDED
TUBULAR FRAME WITH GMS EAR-PLATE
CORNERS MITRED & 50
EXPANDED METAL WITH 50x30x5
150
HINGE FULLY WELDED ROUNDED EAR
500
75
1,030 EQUAL
AS REQD.
IN FRAMEWORK
EXPANDED METAL
50
WELDED TO FRAME
50
30
SLAM-PLATE, 115x150x5 ROUNDED
EAR-PLATE GMS SLAM-PLATE
& LOCK, CENTER EXPANDED METAL 115
ON MID-RAIL
STRUCTURAL OPENING
2,060
2,100
DIAMOND PRESSED
PANEL GMS PLATE PANEL 115
1,030 EQUAL
75x150x5 ROUNDED
HINGE GMS EAR-PLATE
BOLTED TO WALL
FFL FFL 75
20
FRAME FINISH
• 38x38x2.5 HOLLOW TUBING, WITH • MADE UP GATE TO BE HOT DIP
CORNERS MITRED & FULLY WELDED GALVANISED
38x38x2.5mm HOLLOW 30 38 20
EXPANDED METAL
150
35 6
WELDED TO FRAME
100
ON OUTSIDE
2,100 STRUCTURAL OPENING
DIAMOND PRESSED
60
HINGE
FFL 35
20
FRAME FINISH
• 38x38x2.5 HOLLOW TUBING, WITH • MADE UP GATE TO BE HOT DIP
CORNERS MITRED & FULLY WELDED GALVANISED
100
100
50
50
STRIKING PLATE 75
CL CL
900 SLOTTED HOLES
FOR PADLOCK
MESH SPOT-WELDED TO
CAGE RAIL CORRIDOR-FACE OF CAGE FRAME
C/L 20mm GAP
75
PULL GRIP, STRIKING
50
35
PLATE & PADLOCK
PULL GRIP
2,255
75 x 50h x 5
BRACING TUBING FLUSH STRIKING PLATE
MID-RAIL WITH REAR FACE
GATE FRAME
MESH
HINGE
FFL
GATE FRAME
• 810x2185 GALV MILD STEEL GATE WITH • GALV MILD STEEL TUBING WITH COLD
50x50x2.5 MS HOLLOW SECTION AND GALV APPLICATION TO WELDS
25x25x2.5 HOLLOW SECTION MIDRAIL • PULL GRIP 5mm GALV MS PLATE
• FRAME TUBING MITRE CUT AT CORNERS WELDED TO GATE STILE
& FULLY WELDED & GROUND SMOOTH • STRIKING PLATE 70x50x5 GALV MS
• MENTIS TYPE 304 EXPANDED METAL PLATE WITH HOLE FOR PADLOCK
SHEETING SPOT WELDED TO REAR FACE
OF FRAME
RECEIVING CAGE
CAGE FRAME FIXED
TO WALL WITH
SPACERS IF REQD.
FREE OF JAMB
CORNER PROTECTORS
TOP TRACK
LINE OF
STRUCTURAL
OPENING
HINGE HINGE HINGE HINGE
RS DOOR
25
HINGE HINGE HINGE HINGE
PULL GRIP,
BRACING TUBE FLUSH STRIKING
WITH INSIDE FACE PLATE &
PADLOCK
ANGLE BRACING
1,125
20mm GAP BETWEEN
CAGE FRAME &
GATE STILE
FFL
GATE FRAME
• 4no. GALV MILD STEEL GATES • 60x60x2.5 GALV MILD STEEL
WITH 50x50x2.5 HOLLOWSEC FRAME TUBING WITH COLD GALV
AND 25x25x2.5 HOLLOWSEC CROSS APPLICATION TO WELDS PULL GRIP
BRACING WITH 25x25x2.5 GALV MILD 150x40x5mm GALV MS PLATE
STEEL BRACING ANGLES FRAME WELDED TO GATE STILE HOLED FOR
TUBING MITRE CUT AT CORNERS & PADLOCK STRIKING PLATE
FULLY WELDED & GROUND SMOOTH 120x50x5mm GALV MILD STEEL
MENTIS TYPE 304 EXPANDED METAL WITH HOLES FOR BOLT BOTH SIDES
SHEETING SPOT WELDED TO INSIDE
FACE OF FRAME
100
60x2.5x DEPTH AS REQD. LINE OF SHUTTER BOX OVER
G.M.S. SPACER TUBES
(CONFIRM SIZE ON SITE)
- FIXED TO WALL FREE FROM
RS DOOR FIXING BRACKETS RECEIVING CAGE
SHUTTER BOX
EQUAL EQUAL +60 EQUAL +60 EQUAL
MESH SPOT-WELDED
TO INSIDE FACE OF
RECEIVING YARD
RECEIVING CAGE
INDIVIDUAL GATE
FRAMES
25
HINGE HINGE HINGE HINGE
PULL GRIP,
BRACING TUBE FLUSH STRIKING
WITH INSIDE FACE PLATE &
PADLOCK
ANGLE BRACING
1,125
20mm GAP BETWEEN
CAGE FRAME &
GATE STILE
FFL FFL
GATE FRAME
• 4no. GALV MILD STEEL GATES WITH • 60x60x2.5 G.M.S. TUBING WITH COLD
50x50x2.5 HOLLOWSEC FRAME AND GALV APPLICATION TO WELDS, SPACED
25x25x2.5 HOLLOWSEC CROSS BRACING AWAY FROM WALL WITH 60w x DEPTH
WITH 25x25x2.5 GALV MILD STEEL AS REQUIRED x2.5 G.M.S. TUBING TO
BRACING ANGLES ALLOW FLOOR TRACK POSITION FREE
• FRAME TUBING MITRE CUT AT CORNERS ON INSIDE.
& FULLY WELDED & GROUND SMOOTH • PULL GRIP 150x40x5mm GALV MS PLATE
• MENTIS TYPE 304 EXPANDED METAL WELDED TO GATE STILE HOLED FOR
SHEETING SPOT WELDED TO INSIDE FACE PADLOCK. STRIKING PLATE 120x50x5mm
OF FRAME GALV MILD STEEL WITH HOLES FOR
BOLT BOTH SIDES
GATE
2400 AFFL
NIGHT DROP RECEIVING
MESH SPOT-WELDED
TO REAR FACE
OF GATE FRAMING
GATE 2,430
2,500
BRACING TUBE
BRACING TUBING FLUSH
WITH REAR FACE
PULL GRIP,
STRIKING PLATE
& PADLOCK
1,105
GATE FRAME
• 2600w x2430mm GALV MILD STEEL GATE • GALV MILD STEEL TUBING WITH COLD
WITH 50x50x2.5 MS HOLLOW SECTION GALV APPLICATION TO WELDS
AND 25x25x2.5 HOLLOW SECTION CROSS • PULL GRIP 150x40x5mm GALV MS PLATE
BRACING WELDED TO GATE STILE HOLED FOR
• FRAME TUBING MITRE CUT AT CORNERS PADLOCK
& FULLY WELDED & GROUND SMOOTH • STRIKING PLATE 100x5 GALV MS PLATE
• MENTIS TYPE 304 EXPANDED METAL BOLTED TO WALL
SHEETING SPOT WELDED TO REAR FACE
OF FRAME
LOCK & FURNITURE
• PADLOCK: VIRO HEAVY DUTY PADLOCK
• HILLALDAM STRAIGHTAWAY 200
HINGES SLIDING GEAR
• 2 no. GMS HINGES
RECEIVING
SOFFIT OF
WALL
OPENING
MESH SPOT-WELDED
TO REAR FACE
OF GATE FRAMING
GATE 2430
2435
BRACING TUBE
BRACING TUBING FLUSH
WITH REAR FACE
PULL GRIP,
STRIKING PLATE
& PADLOCK
GATE FRAME
• 2500w x2185mm GALV MILD STEEL GATE • GALV MILD STEEL TUBING WITH COLD
WITH 50x50x2.5 MS HOLLOW SECTION GALV APPLICATION TO WELDS
AND 25x25x2.5 HOLLOW SECTION CROSS • PULL GRIP 150x40x5mm GALV MS PLATE
BRACING WELDED TO GATE STILE HOLED FOR
• FRAME TUBING MITRE CUT AT CORNERS PADLOCK
& FULLY WELDED & GROUND SMOOTH • STRIKING PLATE 100x5 GALV MS PLATE
• MENTIS TYPE 304 EXPANDED METAL BOLTED TO WALL
SHEETING SPOT WELDED TO REAR FACE
OF FRAME
LOCK & FURNITURE
• PADLOCK: VIRO HEAVY DUTY PADLOCK
• HILLALDAM STRAIGHTAWAY 200
HINGES SLIDING GEAR
150
100
MESH SPOT-WELDED
TO REAR FACE
OF GATE FRAMING SLOTTED
HOLES FOR
PADLOCK
GATE 2,185
BRACING TUBE 2,255
BRACING TUBING FLUSH
WITH REAR FACE
PULL GRIP,
STRIKING PLATE
& PADLOCK
GATE FRAME
• 2600w x 2185h GALV MILD STEEL GATE • GALV MILD STEEL TUBING WITH COLD
WITH 50x50x2.5 MS HOLLOW SECTION GALV APPLICATION TO WELDS
AND 25x25x2.5 HOLLOW SECTION CROSS • PULL GRIP 150x40x5mm GALV MS PLATE
BRACING WELDED TO GATE STILE HOLED FOR
• FRAME TUBING MITRE CUT AT CORNERS PADLOCK
& FULLY WELDED & GROUND SMOOTH • STRIKING PLATE 100hx5 GALV MS PLATE,
• MENTIS TYPE 304 EXPANDED METAL HOLED FOR PADLOCK, WELDED TO
SHEETING SPOT WELDED TO REAR FACE CAGE POST
OF FRAME
100
1,800 WALL OPENING
1,750
C/L 1,700 GATE OPENING C/L
50
50 20 820 20 820 50 20
50
20
50x50x2.5 SHS
CAGE POST 50x50x2.5
SHS CAGE
455
BOLTED TO WALL MESH 50x50x4 ANGLE
POST
BOLTED
TO WALL
50
50x50x2.5 SHS CAGE RAIL
20mm GAP C/L
BETWEEN
20
GATE FRAMES 35 50 35
50
& CAGE HINGE STOP PLATE HINGE
STLILES/RAIL PULL GRIP
(MAX. 25mm) WELDED TO
MESH MESH ACTIVE GATE
100
CAGE FRAME OVERALL 2,780
50
PULL GRIPS SLOTTED
BOTH SIDES HOLES
OF ACTIVE
GATE LEAF FOR 85
PADLOCK
GATE 2,185
2,085
BRACE TUBING
FLUSH WITH MID-RAIL MID-RAIL
OPENING FACE
GATE
120
FRAME
MESH OF GATES
35
MESH
SPOT-WELDED TO
OPENING FACE 50
OF GATE FRAMING 70 x 40h PULL GRIP
ROUNDED
HINGE HINGE STOP PLATE
AT TOP OF
50
FFL GATES
20
GATE FRAME
• GALV MILD STEEL SWING GATE WITH 2 • GALV MILD STEEL TUBING AS
LEAFS SIZE 820 (w) x 2185 (h), EACH WITH INDICATED WITH COLD GALV
50x50x2.5mm MS HOLLOW SECTION GATE APPLICATION TO WELDS. OUTER
FRAME AND 25x25x2.5mm HOLLOW STILES & TOP RAIL TO BE MITRE CUT
SECTION MID-RAIL; FRAME TUBING MITRE AT CORNERS, FULLY WELDED &
CUT AT CORNERS & FULLY WELDED & GROUND SMOOTH, WITH MENTIS TYPE
GROUND SMOOTH, WITH MENTIS TYPE 304 304 EXPANDED METAL SHEETING SPOT
EXPANDED METAL SHEETING SPOT WELDED WELDED TO EXTERNAL FACE OF CAGE
TO OPENING FACE OF EACH GATE FRAME. FRAME (ON AIRLOCK/PASSAGE SIDE).
PULL GRIPS 5mm GALV MS PLATE BOTH ROUNDED STOP PLATE 70x40x5
SIDES OF ACTIVE GATE. STRIKING PLATE WELDED TO CAGE RAIL AT TOP OF
85x50x5 GALV MS PLATE ON INACTIVE LEAF MEETING GATE STILES.
(CONFIRM PULL GRIPS/STRIKING PLATE ON
SITE).
100
40x40x5
50
50
STOP PLATE
75 STRIKING PLATE
75
SLOTTED HOLES 50
37
FOR PADLOCK PULL GRIP
OPENING 930 (C.O.S.)
20 75 x 50h x 5
50 GATE 790 (C.O.S.) 20 50
STRIKING PLATE
20 50
40x40x5mm
ROUNDED STOP
270
PLATE WELDED
TO FRAME
HINGE
800
PULL GRIP,
STRIKING PLATE
2,000 (C.O.S.)
& PADLOCK
GATE
FFL
20
100
100
1,500 WALL OPENING (C.O.S.)
225 990 225
50
275 275
50
50 175 20 GATE 900 20 175
50 50 50 SLOTTED HOLES 75
50x50x2.5 SHS TOP RAIL, 20mm STRIKING PLATE
BELOW SUSPENDED CEILING (2800 AFFL) FOR PADLOCK
50 20
50x50x2.5 SHS 50x50x2.5
CAGE STILE SHS CAGE
70 x 40h STOP
455
BOLTED TO WALL MESH 50x50x4 ANGLE STILE BOLTED
TO WALL PLATE AT TOP
OF CAGE FRAME
70x40hx5 ROUNDED
50x50x2.5 SHS CAGE RAIL
50
STOP PLATE ON
CLOSING FACE
20
120
20mm GAP BETWEEN HINGE
GATE FRAME & CAGE
STILES/RAIL (MAX 25mm)
50
35
MESH MESH MESH
CAGE FRAME OVERALL 2,780
PULL GRIP
MESH SPOT-WELDED 50x50x2.5
TO FRONT FACE SHS CAGE
OF CAGE FRAME 75 x 50h x 5
POST STRIKING PLATE
PULL GRIPS BOTH
SIDES OF GATE,
STRIKING PLATE 50x50x4
GATE 2,185
MID-RAIL
BRACE TUBING FLUSH
WITH OPENING FACE
MESH MESH MESH
GATE FRAME
TRADING AREA
2045 AFFL
GATE
G.F. BULK STORE SOFFIT OF
WALL
OPENING
MESH SPOT-WELDED
TO REAR FACE
OF GATE FRAMING
GATE 2,075 - CONFIRM ON SITE
2,145 - C.O.S.
BRACING TUBE
BRACING TUBING FLUSH
WITH REAR FACE
PULL GRIP,
STRIKING PLATE
& PADLOCK
1,105
GATE FRAME
• 2080w x 2075h GALV MILD STEEL GATE • GALV MILD STEEL TUBING WITH COLD
WITH 50x50x2.5 MS HOLLOW SECTION GALV APPLICATION TO WELDS
AND 25x25x2.5 HOLLOW SECTION CROSS • PULL GRIP 150x40x5mm GALV MS PLATE
BRACING WELDED TO GATE STILE HOLED FOR
• FRAME TUBING MITRE CUT AT CORNERS PADLOCK
& FULLY WELDED & GROUND SMOOTH • STRIKING PLATE 100hx5 GALV MS PLATE,
• MENTIS TYPE 304 EXPANDED METAL HOLED FOR PADLOCK, WELDED TO
SHEETING SPOT WELDED TO REAR FACE CAGE POST
OF FRAME
11,720
1,863 1,863 1,863 1,863 2,590 1,620
C/L C/L CROSS FLOOR BEAM C/L C/L C/L 1,108 122 1,269 C/L
50x50x2.5 OF MEZZANINE MEZZANINE SUPPORT 50x50x2.5 CROSS BEAM HEIGHT OF C/L
122 50 SHS FRAMES BEAMS 168 50 SHS FRAME 90x90x4.0 SHS STILES MEZZANINE STRUCTURE
848 122 814 50 112
10
355 50
50
50x50x4 50x50x4 50x50x4 50x50x4 50x50x4 50x50x4
ANGLES ANGLES ANGLES ANGLES ANGLES ANGLES
2,340
2,280
W.SCREEN DETAILS
60x60x2.5 60x60x2.5 60x60x2.5
SHS FRAME SHS FRAME SHS FRAME
DETAILS - C
60
4,165
SLIDING GATE
50x50x4 50x50x4 50x50x4 TYPE WS10 50x50x4
ANGLE ANGLE ANGLE AS PER DOOR ANGLE
4,630 - CONFIRM ON SITE
SCHEDULE
C/L TO MATCH
50x50x4 50x50x4 50x50x4 GATE MIDRAIL
ANGLE ANGLE ANGLE
50
FFL
20
LOCATION: BULK STORE STEEL CAGE - PLAN & ELEVATION
60x60x2.5 SHS 90x90x4.0 MESH WELDED TO 90x90x4.0 50x50x2.5 SHS 90x90x4.0 GATE MESH WELDED TO 60x60x2.5 STILE
FIXED TO WALL SHS STILE OUTSIDE OF CAGE FRAMES SHS STILE SHS STILE INSIDE OF GATE FRAME FIXED TO COLUMN
C09
REV DATE:
EXTERNAL ELEVATION: STEEL CAGE 1
10.04.2019
1,863 1,863 1,863 1,863 2,590 1,620
O/A 11,720
REV -
PLAN: STEEL CAGE 1
WS14 21
W.SCREEN DETAILS
DETAILS - C
2C
WIRE SCREEN
50
CAGE O/A 4,632
LOCATION: BATTERY CAGE & STORE - PLAN
REV DATE:
60
10.04.2019
2A 2B
WS15
REV -
21
50 10
50x50x
2.5 STILE
50x50x4 50x50x4
W.SCREEN DETAILS
ANGLES ANGLES
1,120
50x50x GUIDE TRACK
1,060
DETAILS - C
50
GATE SLIDING GATE
TYPE WS06 TYPE WS09
50x50x2.5 50x50x4
SHS FRAME ANGLES
2,160
2,280
3,400 - CONFIRM ON SITE
C/L TO
50x50x4 MATCH
ANGLES
REV DATE:
50
FFL
20
50x50x2.5 SHS MESH WELDED 50x50x2.5 STILES MESH WELDED GATE MESH WELDED TO 60x60x2.5 STILE
TO OUTSIDE FIXED TO COLUMN TO OUTSIDE INSIDE OF GATE FRAME FIXED TO COLUMN
OF CAGE FRAME OF CAGE FRAME
10.04.2019
CAGE 2A CAGE 2B
EXTERNAL ELEVATION: STEEL CAGES 2A & 2B
REV -
WS16 21
10
50
W.SCREEN DETAILS
50x50x4 50x50x 50x50x4
ANGLE 2.5 SHS ANGLE
DETAILS - C
1,120
1,060
WIRE SCREEN
50
SCALE: NTS
ANGLES SHS FRAME ANGLES
LOCATION: BATTERY CAGE & STORE - ELEVATION 2
2,160
2,280
3,400 - CONFIRM ON SITE
50x50x4 50x50x4
ANGLE ANGLE
REV DATE:
FFL
20 50
50x50x2.5 SHS MESH WELDED
TO BATTERY CAGE SIDE
10.04.2019
ELEVATION STEEL CAGE 2C
WS17
REV -
21
50x50x2.5 SHS
FIXED TO WALLS
1,925
60x60x2.5 SHS
CROSS BRACING
W.SCREEN DETAILS
1,925
OVER CAGES
DETAILS - C
WIRE SCREEN
1,925
4A 4B 4C 4D
50x50x4 ANGLE
CROSS BRACING
OVER CAGES
1,925
CAGE 10 CAGE 9 CAGE 8 CAGE 7 CAGE 6
REV DATE:
60
WS06 WS06 WS06 WS06 WS06
C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L C/L
1,152 910 994 994 910 994 994 910 994 994 910 994 994 910 1,029
3,056 2,897 2,897 2,897 2,933
10.04.2019
MAIN FRAME OVERALL 14,740
REV -
PLAN: STEEL SCREENS 3 & 4 (CAGES 6-10) (SCALE: 1:100)
WS18 21
720
660 60
STILES SHS FRAME STILES STILES
50
GATE GATE GATE GATE
TYPE WS06 TYPE WS06 TYPE WS06 TYPE WS06
50x50x4 50x50x2.5 50x50x4 50x50x2.5 50x50x2.5 50x50x4
ANGLE SHS FRAME ANGLE SHS FRAME SHS FRAME ANGLE
2,160
2,280
COLUMN
50x50x2.5 50x50x2.5 50x50x2.5
SHS FRAME SHS FRAME SHS FRAME
W.SCREEN DETAILS
3,000 OVERALL HEIGHT OF CAGES
FFL
DETAILS - C
50
20
SCALE: NTS
9,620 INTERNAL DIMENSION OF CAGE 60
1,925 1,925 1,925 1,925 1,920
60x60 50x50x4
LOCATION: MEZZANINE CAGES AT B.O.H STORE - ELEVATION
x2.5 ANGLES
720
720
660 60
STILES
50
50
REV DATE:
60x60 60x60
x2.5 x2.5
STILE 50x50x4 50x50x2.5 STILES
BOLTED ANGLE SHS FRAME
TO WALL
2,160
2,160
2,280
2,280
ANGLES
10.04.2019
50
FFL FFL
50
20
20
REV -
TYPICAL SIDE ELEVATION: STEEL SCREENS 4A-4D (CAGES 6-10)
WS19 21
45° JOINT
CEILING
PANELS REBATED AND STEEL SKINS CUT 50 x 50 x 2L ALUMINUM ANGLE FIXED WITH
BACK TO PROVIDE THERMAL BLIND RIVETS AT 200 CENTERS SEALED WITH
DISCONTINUITY SILICONE SEALANT
WALL
EXTERNAL INTERNAL
INSULATED WALL TO
INSULATED CEILING JOINT
45° JOINT
SILICONE SEALANT
WALL WALL
FREEZER ROOM TO
UCOLD ROOM WALL JOINT
INSULATION
SILICONE SEALANT
EXTERNAL
R22) SEALED TOP & BOTTOM WITH ALUMINIUM COVING (AS PER DETAIL R22) SEALED
GREY SILICONE SEALANT TOP & BOTTOM WITH GREY SILICONE SEALANT
0,8mm BENT WHITE CHROMADEK CHANNEL
10 mm THICK POLYSCREED BY FFL TILE FLOOR OR 6mm THICK EXISTING FFL
BUILDER WALL POLYSCREED BY BUILDER
CONCRETE BY OTHERS
190
INTERNAL EXTERNAL
CLEAR INTERNAL HEIGHT
VAPOUR SEAL TO BE CUT-OFF FLUSH WITH TOP OF POURING CONCRETE AND SEAL WITH
CONCRETE POLYSULPHIDE SEALANT ALL ROUND
ALUMINIUM COVING (AS PER DETAIL ALUMINIUM CHECKER PLATE
R22) SEALED TOP & BOTTOM WITH SILICONE SEALANT
GREY SILICONE SEALANT
0,8mm BENT WHITE CHROMODEK CHANNEL
ALUMINIUM COVING (AS PER DETAIL R22)
6mm THICK POLYSCREED BY BUILDER SEALED TOP & BOTTOM WITH GREY
SILICONE SEALANT
CONCRETE BY BUILDER
TILE FLOOR OR 6mm THICK POLYSCREED BY
190
INTERNAL EXTERNAL
CLEAR INTERNAL HEIGHT
EXTERNAL
INTERNAL TAPE MEMBRANE TO WALL FOR POURING
CONCRETE. TRIM MEMBRANE FLUSH AFTER
VAPOUR SEAL TO BE CUT-OFF FLUSH WITH POURING CONCRETE AND SEAL WITH
TOP OF CONCRETE POLYSULPHIDE SEALANT ALL ROUND
3000
ALUMINIUM COVING (AS PER DETAIL R22) SEALED ALUMINIUM CHECKER PLATE
TOP & BOTTOM WITH GREY SILICONE SEALANT
SILICONE SEALANT
ALUMINIUM COVING (AS PER DETAIL R22)
6mm THICK POLYSCREED BY BUILDER SEALED TOP & BOTTOM WITH GREY
THICKNESS AND SILICONE SEALANT
SPECIFICATION OF 0,8mm BENT WHITE CHROMADEK CHANNEL
CONCRETE LAYER TO CONCRETE BY OTHERS
170
150 MICRON
CONCRETE
VAPOUR
MEMBRANE
EXTERNAL
INTERNAL TAPE MEMBRANE TO WALL FOR POURING
CONCRETE. TRIM MEMBRANE FLUSH AFTER
VAPOUR SEAL TO BE CUT-OFF FLUSH WITH POURING CONCRETE AND SEAL WITH
TOP OF CONCRETE POLYSULPHIDE SEALANT ALL ROUND
3000
ALUMINIUM COVING (AS PER DETAIL R22) SEALED ALUMINIUM CHECKER PLATE
TOP & BOTTOM WITH GREY SILICONE SEALANT
SILICONE SEALANT
ALUMINIUM COVING (AS PER DETAIL R22)
6mm THICK POLYSCREED BY BUILDER SEALED TOP & BOTTOM WITH GREY
THICKNESS AND SILICONE SEALANT
SPECIFICATION OF 0,8mm BENT WHITE CHROMADEK CHANNEL
CONCRETE LAYER TO CONCRETE BY OTHERS
170
150 MICRON
CONCRETE
VAPOUR
MEMBRANE
ALUMINIUM
CHECKER PLATE
1200
RISING HINGE
NOTE:
1. NETT DOOR OPENING SIZE AS PER SCHEDULE
2. FREEZER DOOR ONLY TO HAVE HEATER TAPE INSTALLED ALL
ELEVATION ROUND TO THE DOOR FRAME. REFER INSULATION DETAIL R10.
3. FREEZER & COLD ROOM TO HAVE EMERGENCY EXIT HANDLE
4. DOOR FURNITURE TO BE FERMOD OR APPROVED ALTERNATIVE.
INSIDE EMERGENCY EXIT HANDLE 5. OPERATING TEMPERATURE, THICKNESS & USAGE SAME AS
INSULATED WALL PANELS
6. FREEZER ROOM TO HAVE AIR PRESSURE RELIEF VALVE &
HEATER TERMINAL BOX
OUTSIDE
±60
1,8mm CHROMADEK
AROUND PERIMETER OF
THE DOOR OPENING
REFRIGERANT SEALANT
1,5mm ALUMINIUM CHECKER PLATE
END CAP
REMOVABLE COVER
INSULATION
DOORSTOP DOORSTOP
OPENING DOOR
DIRECTION OF SLIDE
GROUNDSTOP
DOOR GUIDE
A
ELEVATION
NOTE:
1. NETT DOOR OPENING SIZE AS PER SCHEDULE
2. FREEZER DOOR ONLY TO HAVE HEATER TAPE INSTALLED ALL ROUND TO THE DOOR FRAME.
REFER INSULATION DETAIL R10.
3. FREEZER & COLD ROOM TO HAVE EMERGENCY EXIT HANDLE
4. DOOR FURNITURE TO BE FERMOD OR APPROVED ALTERNATIVE.
5. OPERATING TEMPERATURE, THICKNESS & USAGE SAME AS INSULATED WALL PANELS
TOP VIEW 6. FREEZER ROOM TO HAVE AIR PRESSURE RELIEF VALVE & HEATER TERMINAL BOX
INSIDE
REFRIG. DETAILS
BLACK POWDERCOATED KICKPLATE THRESHOLD
BLACK POWDERCOATED STRIP
KICKPLATE STRIP
SEE DETAIL 5 FOR JOINT OF INSULATED WALL TO BLACK D-SHAPED BOTTOM WALK IN
SECTION A - A UNINSULATED FLOOR OR DETAIL 7 FOR JOINT OF HANDLE
DOOR FRAME
DETAILS - C
DOOR ANODIZED BLACK DOOR FRAME ALUMINIUM COVING WITH 38mm ALUMINIUM
SCALE: NTS
CHECKER PLATE 150 ANGLE SEALED TOP & BOTTOM BOTH ANGLE & DOOR IN OPEN
RAMP 40x70mm WOODEN BLOCK
FOAMED IN PLACE & ANCHORED COVING WITH SILICONE SEALANT (COLOUR TO POSITION
WALK IN DOOR FRAME TO @ 600mm CENTRES MATCH FLOOR) & REFRIGERANT SEALANT (NON- INSIDE OUTSIDE
BE FLUSH WITH FINISHED ANODIZED BLACK AMUMINIUM HARDENING MASTIC)
FLOOR 40x40mm ANGLE BLACK
DETAIL 1 OF WALK IN DOOR DETAIL 2 OF REACH IN DOOR
SECTION B - B POWDERCOATED
SCALE 1:50 KICKPLATE STRIP
scale: NTS scale: NTS
38
REV DATE:
WALK-IN COLD BOTTOM REACH IN
WALK-IN COLD ROOM
ROOM
DOOR FRAME
SHELVES SHELVES SCALE 1:10
SHELVES SHELVES
800
2 LOOPS OF UNDER FLOOR ELECTRIC
HEATER ELEMENTS 10w/m TO BE REACH-IN SWING DOORS (OPENING DOOR SCHEDULE:
REACH-IN SWING INSTALLED BEFORE CONCRETE OUTWARDS RIGHT TO LEFT)
OPENING
10.04.2019
SIZE W x H
DOORS (OPENING
OUTWARDS RIGHT WALK-IN SWING DOORS (OPENING WALK-IN SWING DOORS (OPENING OUTWARDS AWAY A 2 OFF DOUBLE THERMOPANE WALK-IN DOOR (2045x800) SWING DOOR
TO LEFT) OUTWARDS AWAY FROM EACH OTHER FOR FROM EACH OTHER FOR DOUBLE DOORS OUTWARDS
B 6 OFF DOUBLE THERMOPANE REACH-IN DOORS (1935x760) SWING DOOR
DOUBLE DOORS OUTWARDS RIGHT TO LEFT RIGHT TO LEFT FOR SINGLE DOORS)
PLAN LAYOUT ON RAISED FLOOR FOR SINGLE DOORS) PLAN LAYOUT ON SOLID FILL
R12
REV -
TYPICAL CROSS-SECTION OF PANELS FOR COLD/FREEZER ROOMS
21
190-FREEZER
FF L
FFL
INSULATION POLYURETHANE 28 kg/m2
THICKNESS AND
SPECIFICATION OF 80mm - COLD ROOM REFRIGERANT SEALANT CONCRETE RAMP BY OTHERS
CONCRETE LAYER TO BE
CONFIRMED BY 100mm - FREEZER ROOM 150 MICRON MEMBRANE TO RETAIN CONCRETE
STRUCTURAL ENGINEER
150 MICRON MEMBRANE VAPOUR
NOTE:
1. NETT DOOR OPENING SIZE AS PER SCHEDULE
2. FREEZER DOOR ONLY TO HAVE HEATER TAPE INSTALLED ALL ROUND TO THE DOOR FRAME. REFER
INSULATION DETAIL R10 FREEZER & COLD ROOM TO HAVE EMERGENCY EXIT HANDLE
3. DOOR FURNITURE TO BE FERMOD OR APPROVED ALTERNATIVE.
4. OPERATING TEMPERATURE, THICKNESS & USAGE SAME AS INSULATED WALL PANELS
5. FREEZER ROOM TO HAVE AIR PRESSURE RELIEF VALVE & HEATER TERMINAL BOX
FREEZER
OUTSIDE INSIDE
HEATER TAPE
TILE/POLYSCREED
30 SIZE TO BE DETERMINED(130) 25 50
60
10 x 10mm FLAT PLATE C/O +
COUNTER SUNK INTO TOP PLATE TO BE LARGE 150mm EACH ENDS OFF DOOR
M6 x 25 HEX. HEADBOLT TAP INTO ENOUGH TO TAKE SOCKET FOR M6 BOLTS.
BOTTOM ANGLE CENTERS INTO OPENINGS
TOP PLATE.
M6 x 35mm COUNTER SUNK BOLTS AND
NUTS M6 WASHER ON UNDERSIDE
REFRIG. DETAILS
M30 x 10 FLAT WELDED OF 75 x 50 x FITTED INTO M8 SLOT PUNCHED IN 50 x
6mm ANGLE HEATER TAPE 50mm ANGLE
DETAILS - C
OUTSIDE
INSIDE
50 x 6mm FLAT WELDED ONTO 10mm
75 x 50 x 6mm ANGLE C/O OFF DOOR PLUS FLAT TO T-SECTION
REFRIGERATION
100
M6 x 75mm BOLTS AND NUTS AT 450mm SPLIT AND FLANGED RAGS
SCALE: NTS
CENTERS WELDED ON AT 450mm
CENTERS
POSITION OF
DOOR FRAME
SPLIT AND FLANGED RAGS WELDED ON AT 450mm
CENTERS.
50 x 50 x 100mm LONG BLOCK OF POLYURETHANE - TO
REV DATE:
SPACE THE FRAME M10 x 90 BOLTS ARE USED TO BOLT
PIPE SPACERS M8 I/D x M120 1/D x 50mm LONG AT FRAME TO SILL
450mm CENTERS
10.04.2019
DOOR OPENING. PLUS 10mm EACH SIDE WRAPPED IN 375
MICRON VAPOUR BARRIER CL
R15
REV -
STILL/THRESHOLD DETAIL FOR FREEZER ROOMS (PART 2 OF 2)
21
±3400
CEILING
REFRIGERAN
3000
T SEALANT WALL
SILICONE
SEALANT
EXTERNAL 50 x 50 x 2L ALUMINIUM ANGLE FIXED WITH
BLIND RIVETS AT 200 CENTRES SEALED WITH
SILICONE SEALANT
INTERNAL
FFL
PANEL THICKNESS TO
BE INCREASED TO ENSURE
SUFFICIENT THERMAL BREAK
SUPPORT BRACKET
GALVANISED STEEL
SECTION LAMINATED INTO
3000
PANEL WALL
2100
FFL
SUPPORT BEAM
FULL HEIGHT
HANGING RAIL
3000
50 X 100 CHANNEL
1 x MID HEIGHT
2100
HANGING RAIL
MIN. 150 1000mm AFFL
FEET ANCHORED
TO FLOOR FFL
DIRECTION OF TRAFFIC
INTERNAL INTERNAL
PLAN VIEW
FRONT POST
REACH-IN DOOR FRAME HEIGHT
ALUMINIUM
SUPPORT
BRACKET
A A
FLAT SHELF
ALUMINIUM
50
SUPPORT
BRACKET
OVERLAPPING
CONFIGURATION
STRIP CURTAINS
REFRIG. DETAILS SCALE: NTS REV DATE: 10.04.2019 REV -
REFRIGERATION
DETAILS - C R22 21
REFRIG. DETAILS
SHOPRITE CHECKERS PROFESSIONAL TEAM ELECTRICAL CONTRACTOR
16A DOUBLE PLUG POINT BY
ELECTRICAL CONTRACTOR
FLOOR TO BE PAINTED
DETAILS - C
SCALE: NTS
TO PLANT ROOM
ACCORDING TO THE
STANDARD DETAIL IN THE
DOOR SCHEDULE
CHECKERS
PENETRATION THROUGH
WALL AT HIGH LEVEL BY
REV DATE:
BUILDER
SIMPLEX
10.04.2019
SCHEDULE)
R23
REV -
21
COMPRESSOR AREA
THE BUILDER. AT LEAST TWO ADJACENT
SIDES ARE TO ALLOW UNIMPEDED FLOW OF
AIR TO THE CONDENSERS. THE SHOPRITE
CHECKERS PROFESSIONAL TEAM TO ADVISE
REFRIG. DETAILS
ON FINAL REQUIREMENTS
DETAILS - C
SCALE: NTS
60m²
WATER TAP ACCORDING TO THE
SHOPRITE CHECKERS STANDARD
DETAIL FOR SERVICING OF
CONDENSERS
CHECKERS
REV DATE:
DN
10.04.2019
THE SHOPRITE CHECKERS
STANDARD STAIRCASE DETAIL
R24
REV -
21
2,100
2,100
- 11
475
1,922 60 218 cut outs and power points
11. Freestanding cellphone display unit and cellphone lockable
975
08 -
1,000
10 01 -
3,200
cupboard
500
07 10 -
- 12 I 12. Bumper rail
2,200
13. Signage on frame
14. Frame
09
1,200
1,100
12
850 100
- 06 I Please refer to all relevant drawings for manufacturing details,
01 07 -
TYPICAL LAYOUTS
I Back wall FFL equipment, cable managements cut outs and power points
SCALE: NTS
150
Plan Side Elevation
6,700
3,100 3,100
Bulkhead line
14 - - 13 14 -
- 06
MONEY MARKET 05 - - 04
6,200
1,700
300 300 02
1,200 1,200 1,200 1,200 500 682 218
02 03
3,200
07 01 09 - 08 - 10 07
10 I I
1,100
12 12
I I
FFL FFL
REV A
22
650
06
I
06. Counter with till and stepped sweet display
07. Bumper rail
08. Frame
500
800
300
Front Elevation
3,350
3,350 2,553
Bulkhead line Bulkhead line
KIOSK
I
01 - 08 08
- 02
04 05 - 03
3,200
06 -
06 -
Printer
CPU
07 - FFL FFL
3,200
1,140
17 05. Front and side walls painted and tiled to spec
05 I
2,400
2,100
07. Alarm keypad if entrance doors used as primary entrance &
exit by manager
1,100
08. Provisional AC control switch
1,000
FFL 09. Provisional Refrigeration monitoring system
340
170
10. Fire Alarm box
11. Admin desk to seat 2 people
Managers Office - Front Elevation Admin Office - Front Elevation 12. Admin PC
13. On request Admin PC
6,380
14. Shelves for file storage
220 3,355 110 2,500
15. Aluminium and glass panel
150 770 16. Raised platform, steps and treads all tiled to match service
SITE SPECIFIC 754 department tile spec
04 05 - 23
I I 17. Managers office counter
16
18. Signage on frame
16
300 66
19. Line of Ceiling height inside Office
TYPICAL LAYOUTS
- 03 - 12 11 14 -
SCALE: NTS
880
- 17 20. Camera system
01 - 21. AC
- 06 15 - 22. 100mm High floor tile to form tile skirting
02
2,200
2,200
- 07 23. Frame
Client
- 08 Chair
1,270
- 09 - 05 Please refer to all relevant drawings for manufacturing details,
Client equipment, cable managements cut outs and power points
01 05 Chair
- 10 I 13 - I Entrance into manager's office is always on the same side as the
Kiosk due to different counter heights.
2,200 21 2,200
Ceiling line Ceiling line A B 23 Ceiling line
I
I I I
21 21 21
- 04 04 -
1,700
08 07 06 14
I I I
3,200
17 01 -
C/L
I
2,700
2,700
2,700
180
11 - 12 11 05 - - 12 11
I 01 - - 05 I I
1,800
750
1,000
1,000
T03
- 01
750
22 22 22
I I I
FFL FFL FFL
340
REV A
Admin Office - Side Elevation A Admin Office - Rear Elevation Managers Office - Rear Elevation Admin Office - Side Elevation B
22
Bulkhead line
INFO - 02
- 09
3,200
01 04
I
1,500
1,100
06 FFL
I
I
05
Front Elevation CHECKERS HYPER ONLY
01. Back wall painted and tiled to spec
2,346
02. Signage on frame
600 SITE SPECIFIC 03. Aluminium and glass panel
04. Customer service counter
05. Bumper rail
I
01
06. Floor to match FOH general floor finish
07. AC
08 - 08. Site determined, aluminium and glass panel or side wall
1,320
04
I
- 03
Please refer to all relevant drawings for manufacturing
details, equipment, cable managements cut outs and power
581
points
300
07
09
- 08 03 -
3,200
04
I
1,100
930
06 FFL
I
Rear Elevation
- 12
03 -
- 03
03 19 03 01. Office external walls painted and tiled to spec
02. Aluminium windows finished anthracite grey with smokey
grey glazing
20 03. Office internal walls painted full height to match FOH
2.700
13 general wall colour
16 15 11
21 18 04. Floor to match service department tile spec
I
05. 100mm High floor tile to form tile skirting
22
06. Internal door with air grill
05 05
0.750
I I 07. High level AC
FFL
08. AC
Scanning Office - Elevation A Dark Room - Elevation A 09. UPS 200mm from wall
10. Main DB
6.440
11. Communication cabinet - data
2.631 0.220 3.149
12. Server cupboard shelves on sliding mechanism
0.200 13. Label printer
18 14. Zebra printer
I
I I 15. MFS 1 (2x for all Hyper stores)
I
03 14 0.900 03 16. Workforce management PC / Kronos PC
16 15 18
11 17. Scanning office desk
900
TYPICAL LAYOUTS
SCALE: NTS
13 - 12 18. Power Trunking
17 19. Amp / Ref. server
- 03 10 - A
20. Screen / Label server
1.980
2.200
04 - 07 04 21. OBS server
03 - B 22. Retail Radio server
- 02 09
03 - 06 03
I I
Please refer to all relevant drawings for manufacturing details,
I
equipment, cable managements cut outs and power points
0.220
01 D C
Scanning Office - Plan Dark Room - Plan
6.440
1.980 0.220 0.220 3.149 0.220 2.631 0.220 0.220 2.200
Ceiling line Ceiling line Ceiling line
I
- 07 07 - 08
- 03 03 - 03 -
2.700
2.700
2.700
13 15 13
2.100
2.100
2.100
- 16
I I
09
17 17
I I I I
05 18 18 05 18 05 18 05
0.750
0.750
I I I I
FFL FFL FFL
T05
Dark Room - Elevation C Dark Room - Elevation B Scanning Office - Elevation B Scanning Office - Elevation D
REV A
22
Please refer to all relevant drawings for manufacturing details, equipment, cable managements cut outs and
power points
17,005
9,315 110 6,010 110 1,000 230
1,215 3,000 3,000
- 01
TYPICAL LAYOUTS
SCALE: NTS
- 05
07 - 09
07 06
750
04
I
08 03 -
2,200
- 02
04 04
- 01
- 01
03 03
I I
REV A
22
115
345
115
115
3,450
2,760
2,760
115 115 115
345
Plan
Notes:
Save to receive 115mm 30MPA concrete fill between 115mm skin
walls and reinforced with 12Y reinforcing bars on 200 x 200mm
grid to eng details
Concrete ceiling over entire cash office
Please refer to all relevant drawings for manufacturing details,
equipment, cable managements cut outs and power points
11 -
09
I
I
I
05 07 06 -
08
02
10 - 04 - 03
01
12 13
PLAN
01 06 07 08
I
12
09
WHB
6,036
UB
I
14
13
05 10
12 12
I I
03 02
01 11
I
15 I
02
Plan Entrance facing
- 27
25
16
25 - 15
RAMP
21 20 24
04
28 -
04. Scale
05. AMB corner
23 06. Hot buffet 1875
07. ref bm 1875
Cheese - Plan 14 08. Canopy
15
I
09. Convec oven
10. Pizza oven
18 - 11. Deep fryer
I 12. Chicken grill
*
15 - 08 13. Stove
09 14. Ice machine
13 15. Flycatcher
07 I
15 16. Cold room ideal min size 5sqm
17. Freezer room ideal min size 5sqm
10
11 18. Lollipop sign for Deli and Cheese
DB
06 05
clean
cab. 04
I
- 07 Entrance from
trading floor
E 01
01 I
I
4X
1X 01. Floor drain
- 07 02. Pot deep sink
03. Fat trap
04. Clean cab
02 05. Cold room ideal min size 5sqm
03 I 06. Freezer room ideal min size 5sqm
C H I
01 07. Flycatcher
I
C
C
Plan
09
10
|
- 08
11
8,715
8,310
8,310
10
|
WINE
route I
01
Bulkhead line
4,150
4,000
3,200
2,400
FFL
Front Elevation
- 17
- 13 12 -
- 16
18 26
DB
I
01. 8ft Cake ref.
07 02. Cake ref 2500
WHB 12 03. Dry cake 2500
04. Pies 1250
05. Bakery line-up
06 - 06. Scale
22 - 07. Bakery line-up
08. Bakery back wall
10 - 09. Pie unit
- 08 10. Pot sink
05 11. Power pole
12. Flycatcher
- 09 13. Canopy
14. MC Slimline
23 - 15. MC Proover
16. Deep fryer
17. Hotplate
- 15 18. Flour store
04 19. Freezer room ideal min size 5sqm
20. Cold room ideal min size 5sqm
21. Bakery freestanding unit
11 21 - 22. Panini Stand
I 23. Bulkhead line
24. Frame and department signage
25. Lollipop sign
- 13 03 26. Wineshop
- 14
Please refer to all relevant drawings for manufacturing
details, equipment, power and finishes
06 -
- 11
- 14
02
- 24
11
I
12 - - 25 21 -
01
Plan
MACHINE
ICE
11 -
14 13
10 -
Plan
18
I
13 13 - 04
17
23
- 15
12 12
- 09 - 09 03
05
I
11 11
1830
S/S TABLE
14
02
10 10 01. 12ft Chicken
- 21 02. 12ft Gourmet
03. 12ft High-low
04. Biltong display
I - 09 I - 09 05. Scale
30 22 - 27 05 05 06. Flycatcher
28 - 07. Vacuum machine
08. S/S Table
06 - 25 09. Power pole
07 08 I 24 -
29 29 - 10. Wrap
- 26 11. S/S table
12. Saw
A
LOCATION: FRESH X CHECKERS AND HYPER BUTCHERY AREA AND OFFICE / STORE
SCALE: NTS REV DATE: JAN 2019 REV A
TYPICAL LAYOUTS T16 22
02 - 03
04
I 05
- 12
08 -
I I
06 07
08 -
09 -
09 -
09 -
- 13
09 -
- 14
09 -
Plan
01 03 -
I
02 -
I
01
01
I
02 -
I
01
05 - 01
04 I
I
07 -
I
04
D/B
06 -
HWB
04
I
I
04
04
I
I
04
04
I
I
04
04
I
Plan
0.220
03. Bench
D/B 04. Pegboard
- 16 17 - 05. Focus wall with glasses display in
alcove, "Cross" signage
- 14 13 06. Counter with equipment, shelves and
2.180
privacy screens
2.210
12 -
07. ID tiled and painted to spec,
aluminium door finished anthracite grey
- 11 with smokey grey glazing
- 08 15 08. Dispensary shelves with pelmet to
4.240
4.350
09 follow shelf layout
09. Kitchen / Compound / Office
0.800
tiled and painted to spec
1.370
6.170
10. Fridge
Bulkhead line 11. Compounding area
06 07
FE I 12. Lockable pedestal for S6 drugs
10
I
1.339
13. WC
18 14. Hand dryer plug @ 1300mm AFFL
0.800
15. Consultation area tiled and painted to spec
16. Shelving above
0.110
05 -
17. Fold down bed
TYPICAL LAYOUTS
0.400
SCALE: NTS
18. Private area tiled and painted to spec
03 - 19. Department signage
1.221
1.380
1.600
- 02 01 Please refer to all relevant drawings for
manufacturing details,equipment, cable
0.220
0.379
Plan
14.160
0.355 0.300 1.870 0.300 0.355 6.839 1.140 0.120 2.880
0.300
3.200
3.000
04
06
I
2.400
2.100
2.100
- 02
T18
FFL
I
REV A
01
0.300
Front Elevation
22
04. WHB
- 05 A 05. Mirror
06. Grab rail
- 04 07. WC
08. Flush
- 02 09. Space for wheelchair
- 03
Please refer to all relevant drawings for manufacturing
details,equipment, power and plumbing
01 -
Plan
1,800 1,800
500
CEILING 450 494 115 CEILING
- 05 02 05
2,700
770
I
- 06 - 06
1,750
- 08
I
04 04
160
03
1,000
820
09
740
740
820
07 07
480
480
FFL FFL
Elevation A Elevation B
04 02
03
550 230 900
I I
230
01 01
I
06
700
05 -
03
700
03
5,585
1,130
04
- 20 19
02
900
1,245
03 20
I
Male WC & Lockers - Plan
I
230
16
15
I
1,500
1,800
1,600
13
I 600 300
17
12 - 11 08
4,730
I
- 14
09 -
03
3,000
I
10
18
Canteen - Plan
230
10
LOCKERS
1,264
11
01 - 01. Walls painted to spec
600
02
05. Lesson desk TV box fixed to the wall using a wall mounting bracket
1,000
06. 16A double dedicated plug socket & network point behind TV
07. Chase in 25mm Upvc conduit for power
08. Chase in 50mm Upvc conduit for data and VGA
09. Storage cupboard 1200 L x 450 D x 750mm H
600
10. Lockers
- 03 09 11. Table and chairs
I
A 12. White board
886
05 - 12
- 04 03 I
I
Please refer to all relevant drawings for manufacturing
06 details, equipment and power
B
Plan
07 - 01 01
- 05
- 06 - 05
793
793
2,700
2,700
- 12 04 -
2,100
- 04
1,850
09 - - 09
1,307
1,307
03
I
FFL - 03 02 FFL
I
Elevation A Elevation B
I
04 06
03 -
01
05
05 - 02
3,000
08 -
06 08 -
07
Plan
06 05
2,440
07
02
01 03
I
Plan
Ceiling line
I
07 08
I
09
01
2,700
10 10
400
06 11
200
I
750
I
04
05 I
FFL
Elevation
01. Office internal walls painted full height to match FOH general wall colour
02. Floor to match service department tile spec
03. Aluminium door finished anthracite grey with smokey grey glazing
04. 100mm High floor tile to form tile skirting
05. Power trunking
06. Work top
07. Wallbands with steel adjustable shelving
08. LED light
09. 9U Swinframe network box
10. 32" Wall mounted LED monitor
11. 19" Desktop LED monitor
01 02
I I
3,500
02 -
2,100
- 08
- 01
I
I
12
13
FFL
7,170
I
10 -
230
I
12 I
07 04
11
I
13
- 01 06 - 01 A
S/S TABLE
2,650
2,190
1830
09 02 - - 03 02 -
- 08
05 07
I
I
01
230
I
03
Sorting Room - Plan Holding Room - Plan
01. Strip curtain 08. Stainless steel sorting and packing table
02. Lockable expanded metal sliding gate 09. Floor tiled to spec and sloped as shown
03. Refer to detail 12 in specifications for transition 10. Gully drain "Pollution Solution"
between typical porcelain tiles and concrete floors 11. 150mm Floor gully laid to falls
04. All 4 walls painted to spec 12. Tap point
05. All 4 walls tiled to spec 13. Single drip sink
06. No floor tiles in holding area 14. Gypsum Rhinoboard ceiling
07. Wallband racking
Please refer to all relevant drawings for manufacturing details, equipment, power and
plumbing
- 10
470
01
2,700
11
I
1,900
I
05
750
06 I
FFL
Elevation A
4,372
230 750 3,162 230
12 01. Office internal walls painted full height to match FOH general wall colour
02. Floor to match service department tile spec
10 - 03. Aluminium doors finished anthracite grey with smokey grey glazing
04. Aluminium windows finished anthracite grey with smokey grey glazing
750 230
3,960
230 750 2,000 750 230 - 04 05. 100mm High floor tile to form tile skirting
Ceiling line 06. Power trunking
07. Photocopier
TYPICAL LAYOUTS
SCALE: NTS
08. High level steel adjustable shelving
- 08 10 - 09. High level AC
470
- 03
01 02
3,960
2,000
10. Communication cabinet for data
11. Receiving clerk admin desk with drawers and lockable cupboards
12. Charging area for scanners plug points, to be above worktop level for ease
2,700
11 of connecting charger
I - 04
11 A
2,157
I
1,900
- 07
750
I
B - 06 Please refer to all relevant drawings for manufacturing details,
05 I
750
06 I - 08 equipment, cable managements cut outs and power points
FFL 09
Please note this is a generic drawing and must be adapted to site
230
C D
Elevation C Plan
3,960
230 400 900 900 900 400 230 4,372
750 2,000 750 230 1,866 1,296 750 230
Ceiling line Ceiling line
08 - - 08
03
01
04 04
2,700
2,700
12 11
2,157
2,157
2,100
I I
1,900
11 -
- 06
I
05 05
750
750
T25
I 06 I
FFL FFL
REV A
Elevation D Elevation B
22
10
11
I
1,200
3,310
09 04 -
9,893
02
I
230
1,500
04 - 01. Sliding door
02. Strip curtain
01 - 03. Refer to Detail 12 in specification regarding the transition
07 between typical porcelain tiles and concrete floors.
04. Walls tiled full height to match floor tile spec
1,500
Plan
- 02
700
950
- 01
7,800
- 03
5,690
- 01
230
Plan
01. Gate
02. Roller shutter 1200mm w x 2400mm h
03. Floor drain
Please refer to all relevant documents for finishes specs
16
10
I
18
15 13
17
14
12 12
- 09
11
07
I
08
I
19
05 06
I I
11 01 02 02 02 02
1,200
I I I I I I
I - 03 I - 03 I - 03 I - 03
04 04 04 04
Plan
01. Roller shutter 1200mm w x 2700mm h 07. Line of canopy over 13. Trolley storage
02. Roller shutter 2400mm w x 2700mm h 08. Stairs 14. Trolley wash
03. Sliding / folding gate 09. Ramp 15. Wet refuse
04. Air curtain 10. Steel sliding gate 16. Staff entrance
05. Loading dock 11. Generator room 17. Security booth
06. Bumper railings fixed vertically in front of loading dock 12. Staff parking 18. WC
Please refer to all relevant drawings for manufacturing details and equipment 19. Crate store
01
- 03
04 -
05
01. Security booth
02. Security ledge and cupboards to be confirmed
03. WC
04. WHB, with 600mm high splashback tiles
05. Shower
- 04
- 03
- 01
2,000
- 02
- 04
Plan
05
06 -
02 -
03
01
Plan
If generators are not containerised units, generators should sit in fully closed off rooms with a roof and
four brick walls.
Please refer to all relevant drawings for manufacturing details and equipment.