Kanpur Nagar Nigam
Detail of Measurements
Name of work :- Repairing and painting Work of Ramleela park in karrahi Ward-70 Zone -2
Sr
Item of work No. Length Breadth Height/Dep. Quantity Unit
no.
1 Dismantling of existing plaster
including disposal of refuse as directed
by engg. i/c. within a distance of 60mtr.
wall 2 x 1 52.80 1.50 158.40
1 x 1 52.80 1.50 79.20
1 x 2 29.30 1.50 87.90
1 x 2 65.20 1.50 195.60
1 x 2 10.00 0.80 16.00
1 x 180 0.92 0.60 99.36
- Total(A) 636.46 Sqm
Taken Qty=330.40x10% 63.65
Total 64.00 Sqm 37 2368
2 Scraping of old white or colour wash
including refusal of dismantled material
up to 60.0mtr distance as per direction by
engg-in-charge.
Area same as item no -1(A) 636.46
Total 636.46 Sqm
Taking 90% 572.81
Total 573.00 Sqm 12 6876
3 Class-150 brick work supper structure
above plinth lebel upto floor to lexle (upto
two story) including necessary cutting and
molding of brick work .
L/S 1.00
Total 1.00 Cum
Say 1.00 Cum 7218 7218
4 Steel work in built up tubular (round,
square or rectangular hollow tubes etc.)
trusses, including cutting, hoisting, fixing
in position and applying a prming coat of
approved steel primer, including welding
and bolted with special shaped washers
etc. complete.
L/s 100.00
Total 100.00 kg
say 100.00 kg 135.00 13500
5 12mm thick cement plaster in single coat on
fair side in 1:4 cement, fine sand etc all
complete.
same qty as item no.1 64.00
Total 64.00 Sqm
Say 64.00 Sqm 176 11264
6 Finishing walls with water proofing cement
paint in three coats of approved quality with
one priming coat in even shade including
labour T&P etc all complete.
same qty as item no.3 636.46
Total 636.46 Sqm
Say 637.00 Sqm 85 54145
7 Painting or varnishing on iron work in large
area with one priming coat and two coat of
1 x 2 1.90 - 1.50 5.70
1 x 1 1.00 1.00 1.00
1 x 180 1.80 0.80 259.20
Total 265.90 Sqm
Say 266.00 Sqm 71 18886
total 114257.00
gst 12% 20566.26
total 134823.26