Matopeni Sewer Rehabilitation Plan

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
79 views2 pages

Matopeni Sewer Rehabilitation Plan

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

WORK PROGRAM-PROPOSED MATOPENI SEWER REHABILITATION WORKS

ID Task Task Name Duration Start Finish Qtr 1, 2025 Qtr 2, 2025
Mode Nov Dec Jan Feb Mar Apr May
1 PROPOSED MATOPENI SEWER 150 days Mon 04/11/24 Fri 30/05/25
REHABILITATION WORKS
2 1.0 PRELIMINARIES AND GENERAL 150 days Mon 04/11/24 Fri 30/05/25
ITEMS
3 CONTRACTUAL 14 days Mon 04/11/24 Thu 21/11/24
REQUIREMENTS-Insurances,
Perrformance securities,permits(NCA,
KPLC, DOSH, NEMA, NCCG

4 Mobilization and Setting up of camp 10 days Mon 18/11/24 Fri 29/11/24

5 Setting out of the works 7 days Mon 02/12/24 Tue 10/12/24


6 Installation of project signboard 4 days Mon 25/11/24 Thu 28/11/24
7 Quality control and material testing 150 days Mon 04/11/24 Fri 30/05/25

8 2.0 MEASURED WORKS 140 days Mon 18/11/24 Fri 30/05/25


9 Testing of the works 14 days Mon 12/05/25 Thu 29/05/25
10 Class B Site Investigation 7 days Mon 25/11/24 Tue 03/12/24
11 Demolitions and site clearance 30 days Mon 18/11/24 Fri 27/12/24
12 CLASS I: PIPEWORKS 100 days Mon 18/11/24 Fri 04/04/25
13 Nominal Bore 300mm in Trenches 100 days Mon 18/11/24 Fri 04/04/25

14 Trenching/Excavation for precast 60 days Mon 18/11/24 Fri 07/02/25


concrete pipework
15 Laying and Joining the concrete 40 days Mon 16/12/24 Fri 07/02/25
pipes
16 Testing of installed pipeline 14 days Mon 10/02/25 Thu 27/02/25
17 Backfilling around pipes with 25 days Fri 28/02/25 Thu 03/04/25
compaction
18 CLASS K-PIPEWORK-MANHOLES AND 48 days Mon 20/01/25 Wed 26/03/25
PIPEWORK ANXILLARIES
19 Type B Manholes 48 days Mon 20/01/25 Wed 26/03/25
20 Excavation for manholes 20 days Mon 20/01/25 Fri 14/02/25
21 Mnahole concrete 14 days Sat 15/02/25 Wed 05/03/25
22 Backfilling around manholes with 15 days Wed 05/03/25 Tue 25/03/25
compaction
23 Manhole covers 15 days Wed 05/03/25 Tue 25/03/25
24 Installation of Ladder 14 days Sat 15/02/25 Wed 05/03/25
25 PIPEWORK AT CROSSINGS 30 days Mon 24/03/25 Fri 02/05/25

26 River , stream and vally crossings and 30 days Mon 24/03/25 Fri 02/05/25
existing sewers

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: MATOPENI SEWER POW
Milestone Inactive Summary Start-only Progress
Date: Wed 25/09/24
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks


WORK PROGRAM-PROPOSED MATOPENI SEWER REHABILITATION WORKS
ID Task Task Name Duration Start Finish Qtr 1, 2025 Qtr 2, 2025
Mode Nov Dec Jan Feb Mar Apr May
27 RE-INSTATEMENT 30 days Mon 31/03/25 Fri 09/05/25
28 Breaking up temporary and 30 days Mon 31/03/25 Fri 09/05/25
permanent reinstatement of concrete
paved roads and drainage
29 CUSTOMER CONNECTIONS 30 days Tue 01/04/25 Mon 12/05/25

30 CLASS L: SUPPORTS AND PROTECTION 42 days Mon 31/03/25 Tue 27/05/25


ANCILLARIES TO LAYING & EXCAVATION

31 Extras to excavation and backfilling 18 days Mon 31/03/25 Wed 23/04/25

32 Excavation in rock 42 days Mon 31/03/25 Tue 27/05/25


33 Bed haunching and Concrete 35 days Wed 09/04/25 Tue 27/05/25
surrounds
34 CLASS Y: SEWER AND WATER DRAIN 60 days Mon 30/12/24 Fri 21/03/25
RENOVATION & ANXILLARY WORKS
35 Clearance in preparation of existing 11 days Mon 30/12/24 Mon 13/01/25
sewers
36 Removal of intrusions 15 days Tue 14/01/25 Mon 03/02/25
37 Renovation of existing sewers by 33 days Tue 04/02/25 Thu 20/03/25
renovating damaged manholes
38 SITE RESTORATION, MEASUREMENTS 15 days Mon 12/05/25 Fri 30/05/25
AND HANDOVER

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: MATOPENI SEWER POW
Milestone Inactive Summary Start-only Progress
Date: Wed 25/09/24
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks