WORK PROGRAM-PROPOSED MATOPENI SEWER REHABILITATION WORKS
ID Task Task Name Duration Start Finish Qtr 1, 2025 Qtr 2, 2025
Mode Nov Dec Jan Feb Mar Apr May
1 PROPOSED MATOPENI SEWER 150 days Mon 04/11/24 Fri 30/05/25
REHABILITATION WORKS
2 1.0 PRELIMINARIES AND GENERAL 150 days Mon 04/11/24 Fri 30/05/25
ITEMS
3 CONTRACTUAL 14 days Mon 04/11/24 Thu 21/11/24
REQUIREMENTS-Insurances,
Perrformance securities,permits(NCA,
KPLC, DOSH, NEMA, NCCG
4 Mobilization and Setting up of camp 10 days Mon 18/11/24 Fri 29/11/24
5 Setting out of the works 7 days Mon 02/12/24 Tue 10/12/24
6 Installation of project signboard 4 days Mon 25/11/24 Thu 28/11/24
7 Quality control and material testing 150 days Mon 04/11/24 Fri 30/05/25
8 2.0 MEASURED WORKS 140 days Mon 18/11/24 Fri 30/05/25
9 Testing of the works 14 days Mon 12/05/25 Thu 29/05/25
10 Class B Site Investigation 7 days Mon 25/11/24 Tue 03/12/24
11 Demolitions and site clearance 30 days Mon 18/11/24 Fri 27/12/24
12 CLASS I: PIPEWORKS 100 days Mon 18/11/24 Fri 04/04/25
13 Nominal Bore 300mm in Trenches 100 days Mon 18/11/24 Fri 04/04/25
14 Trenching/Excavation for precast 60 days Mon 18/11/24 Fri 07/02/25
concrete pipework
15 Laying and Joining the concrete 40 days Mon 16/12/24 Fri 07/02/25
pipes
16 Testing of installed pipeline 14 days Mon 10/02/25 Thu 27/02/25
17 Backfilling around pipes with 25 days Fri 28/02/25 Thu 03/04/25
compaction
18 CLASS K-PIPEWORK-MANHOLES AND 48 days Mon 20/01/25 Wed 26/03/25
PIPEWORK ANXILLARIES
19 Type B Manholes 48 days Mon 20/01/25 Wed 26/03/25
20 Excavation for manholes 20 days Mon 20/01/25 Fri 14/02/25
21 Mnahole concrete 14 days Sat 15/02/25 Wed 05/03/25
22 Backfilling around manholes with 15 days Wed 05/03/25 Tue 25/03/25
compaction
23 Manhole covers 15 days Wed 05/03/25 Tue 25/03/25
24 Installation of Ladder 14 days Sat 15/02/25 Wed 05/03/25
25 PIPEWORK AT CROSSINGS 30 days Mon 24/03/25 Fri 02/05/25
26 River , stream and vally crossings and 30 days Mon 24/03/25 Fri 02/05/25
existing sewers
Task Inactive Task Manual Summary Rollup External Milestone
Split Inactive Milestone Manual Summary Deadline
Project: MATOPENI SEWER POW
Milestone Inactive Summary Start-only Progress
Date: Wed 25/09/24
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks
WORK PROGRAM-PROPOSED MATOPENI SEWER REHABILITATION WORKS
ID Task Task Name Duration Start Finish Qtr 1, 2025 Qtr 2, 2025
Mode Nov Dec Jan Feb Mar Apr May
27 RE-INSTATEMENT 30 days Mon 31/03/25 Fri 09/05/25
28 Breaking up temporary and 30 days Mon 31/03/25 Fri 09/05/25
permanent reinstatement of concrete
paved roads and drainage
29 CUSTOMER CONNECTIONS 30 days Tue 01/04/25 Mon 12/05/25
30 CLASS L: SUPPORTS AND PROTECTION 42 days Mon 31/03/25 Tue 27/05/25
ANCILLARIES TO LAYING & EXCAVATION
31 Extras to excavation and backfilling 18 days Mon 31/03/25 Wed 23/04/25
32 Excavation in rock 42 days Mon 31/03/25 Tue 27/05/25
33 Bed haunching and Concrete 35 days Wed 09/04/25 Tue 27/05/25
surrounds
34 CLASS Y: SEWER AND WATER DRAIN 60 days Mon 30/12/24 Fri 21/03/25
RENOVATION & ANXILLARY WORKS
35 Clearance in preparation of existing 11 days Mon 30/12/24 Mon 13/01/25
sewers
36 Removal of intrusions 15 days Tue 14/01/25 Mon 03/02/25
37 Renovation of existing sewers by 33 days Tue 04/02/25 Thu 20/03/25
renovating damaged manholes
38 SITE RESTORATION, MEASUREMENTS 15 days Mon 12/05/25 Fri 30/05/25
AND HANDOVER
Task Inactive Task Manual Summary Rollup External Milestone
Split Inactive Milestone Manual Summary Deadline
Project: MATOPENI SEWER POW
Milestone Inactive Summary Start-only Progress
Date: Wed 25/09/24
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks