( DAY 1)
Name of Project Assignment: Orientation of BBBJR company and self-introduction with
the general manager AR. Bonifacio Barnachea Jr.
Location: Barangay Mabilbila, Santa, Ilocos Sur
Activity Assigned:
Site visit of the 3 ongoing project of the company with the general manager Ar.
Barnachea.
We’re divided into 3 groups and assigned for the project monitoring of 80 square meter 2-
storey residential house at barangay Manueva, Santa, Ilocos sur.
Lesson Learned:
The difference between theory and actual
Finishing materials used in construction
Workers in different sections
Elements in construction
Date: July 02, 2024 ( Tuesday)
Time: 6:30am - 4:30 pm
Documentations:
( DAY 2 )
Name of Project Assignment: Project Monitoring Of 2-Storey Resodential House
Location: Barangay Sacuyya, Santa, Ilocos Sur
Activity Assigned:
Site inspection
Reading and analyzing Structural Plans
Lesson Learned:
Process of making steel reinforcement and spacing of stirrups
Steel bar sizes and length
How footings and concrete hollow blocks made
Steel reinforcement installation
Date: July 03, 2024 ( Wednesday )
Time: 7:16am - 4:30 pm
Documentations:
( DAY 3 )
Name of Project Assignment: Project Monitoring of Pathway Concreting with one of the
companies foreman Catalino Vista
Location: Barangay Apatot, San Esteban, Ilocos Sur
Activity Assigned:
Project monitoring
Designing of multi-purpose hall fence
Designing and estimation of Tanod outpost project
Lesson Learned:
Concrete proportion used in road construction
Requirements needed in government construction
Importance of engagement with your workers
Installation of solar panel light
Date: July 4, 2024 ( Thursday )
Time: 7:10am - 5:00 pm
Documentations:
( DAY 4 )
Name of Project Assignment: Paper Works and Site Inspection of 2 Upcoming Proejects
Location: Barangay Mabilbila, Santa, Ilocos Sur / Apatot, San Esteban / Kilang, Galimuyod /
Mambug, Santiago, Ilocos Sur
Activity Assigned:
Paper works (cost estimates,IPW,breakdown of expenditures)
Site Inspection of Multi-purpose hall
Lesson Learned:
Estimation
Bidding
Design of bleachers and Tubular gate
Different construction materials
Date: July 05, 2024 ( Friday )
Time: 7:10am - 6:00 pm
Documentations:
( DAY 5 )
Name of Project Assignment: General Orientation with the Company Admin and Project
Monitoring of 2-storey Residential House
Location: Barangay Mabilbila / Manueva, Santa, Ilocos Sur
Activity Assigned:
Project monitoring
Communicating with the different workers
Lesson Learned:
Painting works and processes
Tile works and processes
Electrical works
Actual schedule of doors and windows
Measurement of ceiling, doors, and stairs
Date: July 06, 2024 ( Saturday )
Time: 7:15am - 4:30 pm
Documentations:
( DAY 6 )
Name of Project Assignment: Project Moniting of Pathway Concrete amd Ceiling works
Location: Barangay Sacuyya, Santa, Ilocos Sur and Apatot, San Esteban, Ilocos Sur
Activity Assigned:
Project moniting
Measuring of project dimensions
Lesson Learned:
Estimation of ceiling works
Estimation of tile works
Concrete proportion used in road constructions
Date: July 09, 2024 ( Tuesday )
Time: 7:00am - 5:30 pm
Documentations:
( DAY 7 )
Name of Project Assignment: Paper works, Site inspection and Estimaton of Upcoming and
Proposed Fence and Canal Concreting Projects
Location: Barangay Apatot, San Esteban / Gabao, Santiago, Ilocos Sur
Activity Assigned:
Project monitoring of pathway concreting, multi-purpose hall fence, estimation of canal
concreting and proposed fence project for 2025
Lesson Learned:
Design for canal concreting
Paper works and estimation
Date: July 11, 2024 ( Thursday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 8 )
Name of Project Assignment: Project Monitoring of Construction of 3- storey Legistative
Building
Location: Barangay Rizal, Cabugao , Ilocos Sur
Activity Assigned:
Site inspection
Reading and analyzing the project plans
Lesson Learned:
Design of circular stairs, conference room, and parking area
Materials used in finishing, electrical, and structural
Sizes of steel bars, columns,beams, and plumbing pipes
Date: July 15, 2024 ( Monday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 9 )
Name of Project Assignment: Project Monitoring of the start Construction of Tanod
Outpost Project
Location: Barangay Ampandula, Santa, Ilocos Sur
Activity Assigned:
Inspection of site preparation / demolition
Paper works ( excel, sketch-up, and CAD )
Lesson Learned:
New CAD design skills
Estimation
Construction phases
Date: July 16, 2024 ( Tuesday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 10 )
Name of Project Assignment: Project Monitoring of the Construction of Tanod
Outpost Project
Location: Barangay Ampandula, Santa, Ilocos Sur
Activity Assigned:
Estimation
CAD and sketch-up design
Project monitoring
Lesson Learned:
Estimation of materials
CAD and sketch-up designing
Date: July 17, 2024 ( Wednesday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 11 )
Name of Project Assignment: Project Monitoring of the Construction of Tanod Outpost
Project
Location: Barangay Ampandula, Santa, Ilocos Sur
Activity Assigned:
Site visit of the 3 ongoing project of the company with the general manager Ar.
Barnachea.
We’re divided into 3 groups and assigned for the project monitoring of 80 square meter 2-
storey residential house at barangay Manueva, Santa, Ilocos sur.
Lesson Learned:
Estimation
CAD and sketch-up design
Project monitoring
Date: July 18, 2024 ( Thursday )
Time: 7:00am - 4:30 pm
Documentations:
( DAY 12 )
Name of Project Assignment: Project Monitoring of the Construction of Tanod Outpost
Project, Estimation of Concrete Pathway, and Rehabilitation of Multi-purpose Hall
Location: Barangay Ampandula / Rizal / Nagpanaoan, Santa, Ilocos Sur
Activity Assigned:
Project monitoring
Estimation
Lesson Learned:
Estimation
Date: July 19, 2024 ( Friday )
Time: 7:00am - 4:00 pm
Documentations:
( DAY 13 )
Name of Project Assignment: Seminar / Training as Civil Engineer for Basic Stages of
Project Management Plan
Location: BBBJR Office ( AVR/Conference Room)
Activity Assigned:
Orientation Seminar
Simple activity about estimation
Assign for group project to be presented next meeting
Lesson Learned:
5 basic stages of construction plan
Detailed Architectural and Engineering Design Services
Estimations
Date: July 20, 2024
Time: 7:70am - 4:30 pm
Documentations:
( DAY 14 )
Name of Project Assignment: Construction of Farmers Trading Center Phase II
Location: Barangay Labut Norte, Santa, Ilocos Sur
Activity Assigned:
Site visit
Observation
Lesson Learned:
Safety precaution during rainy days
Move cautiously
Different construction materials
Date: July 22, 2024 ( Monday )
Time: 7:00am - 4:30 pm
Documentations:
( DAY 15 )
Name of Project Assignment: Group Project 2-storey Residential Building
Location: Home
Activity Assigned:
Due to inclement weather we are advise to stay at home and just work on the project
given by the company
Structural designs of the projects
Lesson Learned:
New CAD skills
Standard measurement used in structural designs
Date: July 23, 2024 ( Tuesday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 16 )
Name of Project Assignment: Group Project 2-storey Residential Building
Location: Home
Activity Assigned:
Due to inclement weather we are advise to stay at home and just work on the project
given by the company
Structural designs of the projects
Lesson Learned:
New CAD skills
Standard measurement used in structural designs
Date: July 24, 2024 ( Wednesday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 17 )
Name of Project Assignment: Seminar / Training on Disaster Risk Reduction Management
Location: BBBJR Office ( AV/Conference Room )
Activity Assigned:
Orientation Seminar
Overview of Risk Reduction Management
Group activity / sharing opinions
Lesson Learned:
4 Phases of DRRM
Foundation of Risk Reduction
Emergency Response Team
How to Avoid Risk and Reduce Disaster Risk
Date: July 25, 2024 ( Thursday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 18 )
Name of Project Assignment: Group Project 2-storey Residential Building
Location: Home
Activity Assigned:
Due to inclement weather we are advise to stay at home and just work on the project
given by the company
Structural designs of the projects
Lesson Learned:
New CAD skills
Standard measurement used in roofing and do designs
Date: July 26, 2024 ( Friday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 19 )
Name of Project Assignment: Group Project 2-storey Residential Building
Location: Home
Activity Assigned:
Due to inclement weather we are advise to stay at home and just work on the project
given by the company
Structural designs of the projects
Lesson Learned:
New CAD skills
Standard measurement used in structural designs
Date: July 27, 2024 ( Saturday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 20 )
Name of Project Assignment: Group Project 2-storey Residential Building
Location: Home
Activity Assigned:
Due to inclement weather we are advise to stay at home and just work on the project
given by the company
Structural designs of the projects
Schedule of doors and windows
Lesson Learned:
New CAD skills
Standard measurement used in doors and windows
Date: July 29, 2024 ( Monday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 21 )
Name of Project Assignment: Concreting of Canal
Location: Barangay Gabao, Santiago, Ilocos Sur
Activity Assigned:
Site visit
Installation of forms for canal
Observation
Lesson Learned:
Concrete proportion
Importance of clean sanitation
Date: July 30, 2024 ( Tuesday )
Time: 7:00am - 5:00 pm
Documentations:
( DAY 22 )
Name of Project Assignment: Project Presentation 2- storey Residential Building
Location: BBBJR Office
Activity Assigned:
Project presentation of 2-storey residential house
Lesson Learned:
Standard measurement for foundation plans
Steel reinforcement designs
Learn how to maximize space in desidning floorpan
Being confident
Date: July 31, 2024 ( Wednesday )
Time: 7:00am - 4:30 pm
Documentations:
( DAY 23 )
Name of Project Assignment: Rehabilitation of Health Center and Improvement of Post-
Harvest Facility
Location: Barangay Quirino, Santa, Ilocos Sur
Activity Assigned:
Project layout ( installation of fence)
Paper works
Lesson Learned:
Importance of communication
Designing and estimation
Having patience
Date: August 01, 2024 ( Tuesday )
Time: 7:00am - 10:00 pm
Documentations:
( DAY 24 )
Name of Project Assignment: Construction of Tanod Outpost
Location: Barangay Casiber, Santa, Ilocos Sur
Activity Assigned:
Electrical plan
Project Lay out
Paper works
Lesson Learned:
Teamwork is very importance
Electrical lay out
Date: August 02, 2024 ( Wednesday )
Time: 7:00am - 6:30 pm
Documentations:
( DAY 25 )
Name of Project Assignment: Finalizing Requirements
Location: Barangay Sucoc, Narvacan , Ilocos Sur
Activity Assigned:
Completing all requirements
Review for the BBBJR examination
Lesson Learned:
Experience is the best teacher
Always treasure every moment
Date: August 03, 2024 ( Thursday )
Time: 7:00am - 4:30 pm
Documentations:
( DAY 26 )
Name of Project Assignment: Seminar for 8-hour Safety and Health Mandatory Training
and Awarding of Certificates
Location: BBBJR Office
Activity Assigned:
Seminar for 8-hour Safety and Health Mandatory Training
Group activity and reporting
examination
Lesson Learned:
Integrity
Confidence
Humility
Date: August 08, 2024
Time: 6:30am - 7:30 pm
Documentations: