Kabe Hotel Construction Project Proposal
Kabe Hotel Construction Project Proposal
202
0
1. Executive summary
Page 1
Project Proposal for The Construction of Hotel service Building
202
0
It is obvious that the most of above services are available in almost all Ethiopian
hotels open without good business plan. Our intent is to set realistic business
expectations, and eliminate any question about the profitability of this business
venture.
This hotel business will have a plan to improve the life style of the members which
make them more independent with economic or self-sustaining behind to their
families, creating employment opportunities in all societies, developing the
professional career and skills through a continuous, ever evolving and ever
Page 2
Project Proposal for The Construction of Hotel service Building
202
0
In particular, we set, develop and execute goals and strategies to bring the best
level of high performance to full services at all levels for serving the customers.
We are confident that this hotel business can greatly enhance an impressive
performance by working as part of a team. So that the combined experience of the
principal owners and other staffs upper office management skills will bring high
levels of customers’ services.
The current fast and dynamic economic growth of Ethiopia especially in urban and
semi-urban areas necessitates equivalent growth of building and construction
sector as well as the hotel industry. The sector should expand rapidly to support the
overall economic development sustainable.
In the building sector of the economy, the multi- purpose in the one becoming
rapidly expanding in urban areas of the nation since dynamic economic
development of urban economy requires the construction of these buildings in
towns to support the growing of business service sectors like restaurant, bar,
Cafeterias, guest room, Gymnasium, game zone, offices, shopping malls, parking
and other activities.
Page 3
Project Proposal for The Construction of Hotel service Building
202
0
houses that can be used for hotels, cafeterias, Gymnasium, office space, shopping
malls and catering services in the Semi-urban areas like Gojo town is
disproportionately low to cope with the growing demand and population increase.
Following growing demand trends, and with the expectation of high return on their
investment capital, large number of land developers pooled their financial
resources and invested in the property market.
To this effect, the owner of the envisioned hotel Use Building Mr. Takele Chala
who has been living for long time in this town, planned to construct and make a
significant expansion on Kabe Hotel in Jeldu district, Gojo town and undertaken
this project study to check the market, technical and financial feasibility of this
project. The promoter is very ambitious and committed to realize the project.
Hence, he expects to get the necessary support from the city administration to
make the project to be operational.
Besides, the government policies and incentives for the private sector investment
are very promising that motivates the promoter to engaged in mixed use building
for hotel and other businesses.
Page 4
Project Proposal for The Construction of Hotel service Building
202
0
Page 5
Project Proposal for The Construction of Hotel service Building
202
0
2.2 Vision
To be the first choice of guests, local market, business partners and To grow
as a leader company in the hotel sector and to increase its presence at the
national level, which sustained on the commitment with the customer,
quality, austerity, professionalism and prudent management, and
establishing a large business group involving in variable economic sectors.
2.3 objectives
The objective of this firm is to provide good quality services for society,
government, for new comer from other place to Gojo.
Page 6
Project Proposal for The Construction of Hotel service Building
202
0
2.4 Goals
The goals of the business are:
To meet the projects’ goals as per the construction time limits, prearranged
costs and quality standards.
To provide a substantial income.
To establish and run a highly sustainable life style of the investor and the
employees
To create a business and working environment where both the customer and
employee are treated with dignity and respect.
Increase the hotel’s average occupancy level by 50% above the current.
2.5 Missions
We are committed to providing our customers with highest quality of services,
products and others such as:-
Delivering quality marketing structure serves to the public and resulting in the
reasonable profit to the owner
Page 7
Project Proposal for The Construction of Hotel service Building
202
0
Provide quality service to the society & ensuring continues improvement of the
company in all aspects
Respect the costumer interest and service quality with the costumer needing
time. Hard work is our behavior
Ever service as a business entity that is committed to the creation of the
excellent values that utility needs of customers.
to make good quality of guest coming too my Hotel for full service of the need
of costumer
Page 8
Project Proposal for The Construction of Hotel service Building
202
0
43’’N latitude and 380 3’ 52’’longitudes E. It also shares common boundary with
Edensa Galena peasant association to the north, Chilanko peasant association to the
south,Tullu Bultuma peasant association Easter Bicho peasant association to the
west.
In order to respond to the created environment the town is in need of major, basic
and feasible urban projects to be developed.
Therefore, the existing shortage or absence in the supply of these services, along
with its commercial and administrative access, better location and infrastructure
access, escalating trend of urbanization and business activities, thus it is with such
reason that this project is identified and proposed and assumed to be more
profitable.
Page 10
Project Proposal for The Construction of Hotel service Building
202
0
A. Source of Revenue
As public policy of any nation, the government collects different forms of taxes
from different business organizations and individuals. Among the different forms
of taxes, business income taxes, payroll income tax and VAT are collected from
undertaking business activities. Therefore, the building will serve as sources of
revenue for the town as well as for the region.
B. Employment opportunity
One of the problems that our country faced is unemployment. Therefore, the
current objective of the government is working on tackling the problem of
unemployment and fostering the development process either through creating self-
employment or employment in other organization. Hence, this project will hire 26
individuals and more than 80 individual during construction.
Page 11
Project Proposal for The Construction of Hotel service Building
202
0
It deemed to minimize the demand for bed room and other bundles of services
in the area.
Serve the silliness and good condition of the any assemble of any government
and non-government.
Furthermore, it serves as the pilot experience and ground for other investor to enter
in to such kinds of urban development. It also contributes on the efforts made on as
a character given building for physical development pattern of the townscape.
Page 12
Project Proposal for The Construction of Hotel service Building
202
0
Page 13
Project Proposal for The Construction of Hotel service Building
202
0
gap for such demand as many merchants, organizations are flouring to the town
every day. From prior business experiences, the demand of Hotel service building
in Gojo Town is very high and hence the demand and the supply gap is very wide.
Page 14
Project Proposal for The Construction of Hotel service Building
202
0
premises modified as show rooms and sailing posits. As a result there is a large gap
between the developed and that of the supply for modern bed rooms; Bank and
cafeteria accommodation hence this project would not face any problem of demand
scarcity for it business center and it would provide good service to customers.
4.2 Customers
The company wants to establish varies customers’ base and will therefore
concentrate its business and marketing on local market and nationwide which will
be the dominant target market.
The company works with the commitment to successfully attend the needs of
quality and compliance of the customers, establishing favorable and long term
relationships with them. Also, it promotes a work environment which encourages
personal and professional development of its employees.
4.3 Competitors
The size and complexity of a project determines if local contractors have the
capacity to execute the work. The larger and more intricate the proposed project is,
Page 15
Project Proposal for The Construction of Hotel service Building
202
0
the more it will potentially attract the attention of a broader number of prospective
Competitors. This is good for competition, but may increase service costs.
In the Hotel service there are price and non-price based competition that may faced
by the investors. Moreover, there are different competitors that will compete with
the project either directly or indirectly. But the hotel use building under discussion
has diversified marketing strategies that could enable it come up with the different
competitors in the market. Moreover it will frequently conduct competitors
research which focuses on, the strength and the weaknesses, the different
competitors’ strategies, the techniques they use in rendering the service, their
customer handling methods, food quality and asses ability, bed room quality and
facility and others. Generally the project has many other projects all over Ethiopia
which compete with it.
Classification of competition
Page 16
Project Proposal for The Construction of Hotel service Building
202
0
This level refers to those companies that offer products that provide the same
service or satisfy the same need. In this case we must convince the consumer that
our products and services are the best alternative in the market.
This competition is based on companies that offer products similar attributes but
with a different presence. In this case we must persuade the consumer that the
attributes offered by our products are the best in its category.
They belong at this level the companies with products fighting for the same
consumer budget. In hotel sector, in this case it would fight between getting their
customers, counting on specialized counseling in installation. Therefore, hotel
companies seeking to gain competitive advantages over other companies in the
sector in terms of quality, location, research, development and innovation, or
prices. Therefore, the possibility of threat of substitutes in the hotel industry is low.
Page 17
Project Proposal for The Construction of Hotel service Building
202
0
Following our survey of hotel service building users in Gojo Town are mainly
firms providing cafeteria and restaurants, bed room, supermarkets service,
computer Center Crevice. The different customers for commercial buildings also
include shops and offices that are currently renting out to provide their goods and
services.
Future demand for office space is actually driven from growth in number of offices
in the city which in turn is influenced by the macro-economic growth in the
country.
4.4 Pricing
Referring to the method of pricing, the company usually sets its prices by an
objective method based on cost.
I. Pricing through adding a percentage of profits to the unit cost of
production.
If the unit cost matches the total cost of production, then the margin will
target profit, and also cover these fixed costs, administrative expenses,
commercial, financial and industrial gain. The use of this procedure is
that all sector companies offer similar prices, and thus, avoid situations of
price competition.
II. Pricing through competition or tender.
This is where companies present their offers to a particular project where
its basic characteristics are specified, and the contract to the company
Page 18
Project Proposal for The Construction of Hotel service Building
202
0
that suits and meeting the requirements set wins. The company decides
the price without knowing the competitors.
Having many years of experience in the sector plays an important role. The
company can establish a probability of success of winning the contract associated
with each price, so knowing the difference between revenues and costs, can
calculate their expected benefit from the past experience.
After analyzing the general environment and specific environment, the situation in
the hotel sector in Ethiopia will be analyzed.
Page 19
Project Proposal for The Construction of Hotel service Building
202
0
Page 20
Project Proposal for The Construction of Hotel service Building
202
0
Focus on a service or project that your company does particularly well in your
advertising to bring customers on board in this area. This helps make your brand
memorable and sets you apart from the competition.
Social Media
Post photos of past sites for customers to peruse, and encourage users to post their
own pictures of your construction jobs. This helps to more and more people access
information about the company.
Page 21
Project Proposal for The Construction of Hotel service Building
202
0
Since the project will be engaged Hotel building the main sources of its annual
revenue would be from the hotel service and rental of building spaces such as bed
room, cinema, offices, and café & restaurant. Therefore, the sources of revenue
Page 22
Project Proposal for The Construction of Hotel service Building
202
0
have been classified in to one category namely the rental of cinema, offices,
assembly bedrooms restaurant and café based on these classifications. Based on the
market price of similar Hotel use building in the area, the envisioned buildings set
the following fair price (Before VAT) for its service, hence when the building
construction fully get operational it is assumed to generate a yearly income of ETB
380,000.
Page 23
Project Proposal for The Construction of Hotel service Building
202
0
SN Description Land M2
Ground 1st floor 2nd floor
1 Building (G+2)
1.1 Ground 400
1.2 First floor 400
1.3 Second Floor 400
Parking & Green area 200
Total 600
This date of completion is practical based on the time of year in which the building
will be completed. The team allowed a two week contingency for any setbacks.
Typically, winter construction tends to cause unforeseen delays that negatively
impact a construction project.
Page 25
Project Proposal for The Construction of Hotel service Building
202
0
dead load of 7.5 pounds per square foot was assumed for mechanical equipment,
floor coverings and ceilings.
Similarly, the design of the typical bay accounted for the use of different
commercial space, in which a live load of 125 pounds per square was assumed.
Loads were calculated based on the requirements of the minimum Design loads for
Buildings and other Structures.
Page 26
Project Proposal for The Construction of Hotel service Building
202
0
the lowest responsible bidder. This, is of course, presupposes that the favorable
proposal does not exceed the allocated budget.
The project team developed a coordinated project schedule and construction plans
that would reflect the expectations for an actual construction project. The project
schedule was developed using the preliminary designs given to the project team.
Additionally, the group considered typical construction activities and durations
taken from similar construction projects as well as realistic constraints on building
development. For instance, it is necessary for the structural frame to be completed
before concrete can be placed for the slab on deck. Hand drawn construction plans
detailing site entrances and storage areas were coordinated with the project
schedule to give the reader visualizations of the construction site set up through
various periods of the construction process.
The construction process for this project is normally a disjointed three mages
development by which the conceptualized need of the promoter of this project is
translated into a functional facility that will meet their needs in terms of time, cost
and quality.
5.5 Utilities
A number of utilities world be put in place in order to ensure smooth functioning
of the project. These utilities include:
Water Supply,
Supplementary Electricity supply.
Telephone line Internet Broadband
Drainage Facility
Page 27
Project Proposal for The Construction of Hotel service Building
202
0
Page 28
Project Proposal for The Construction of Hotel service Building
202
0
SWOT analysis is useful to identify what the favorable factors and critical tool for
the business are. In addition, this study will help establish appropriate objectives
and strategies to be followed by the company. To do this, the strengths and
weaknesses regarding the internal characteristics, and the threats and opportunities
regarding the external characteristics are studied.
SWOT analysis implies internal possibilities (strength and weakness) of a project
and its external environment (opportunities and threats) that might be faced during
project management.
Strength
Relying on one type of client, therefore should expand your horizon and
work with varies types of clients
Inexperienced Workers, workers need to be trained at the beginning of the
project
Lack of coordination, to coordinating the workers within the organization
Has little experience in the sector.
It must also rely on third parties on certain works.
Page 29
Project Proposal for The Construction of Hotel service Building
202
0
Opportunities
Threats
Page 30
Project Proposal for The Construction of Hotel service Building
202
0
Environmental conditions
Bad planning
Organizational disturbances
Negligence in purchasing and supply of material
Negligence in communication
Payment not made on time
Non-fulfillment of other contract responsibilities by the client
Additional demands and project changes
Difficulty in evaluation of expenses
Fluctuation in the costs of construction materials and equipments
A. Organization
The company will be operated as a private limited company (PLC). The overall of
management will be the responsibility of the owner. Our company will be operated
as its profitability is getting 30% by annual.
The organizational structure should be in a way that the company able to achieve
its objectives as well as the satisfaction of standard requirement. In addition to this,
the structure should fit the dynamics of all customers in the building ranging from
small business to large tenants.
Owner
Page 32
Project Proposal for The Construction of Hotel service Building
202
0
General
Manager
Technical and
Building Admin maintenance
manager
Waiter
s
As clearly shown in the organizational structure, the center organization has one
general manager and two main sections. Under the general manager there are the
maintenance and building administration department. Under building admin dept.
there exist two sections i.e. reception & Hotel manager. Further sub sections are
also organized under technical and maintenance manager. The following section
deals with the duties and responsibilities of each department.
Page 33
Project Proposal for The Construction of Hotel service Building
202
0
He/she will plan, organize, direct and control the overall activities of the
building.
He/she will devise policies and strategies that will enable the center to be
profitable.
He/she will incorporate modern technological innovation that will facilitate the
service delivery of the building to increase customer’s satisfaction.
He/she will plan, organize, direct and control the human and non-human
resources of the building so as to achieve the short and long run objectives of
the organization.
Page 34
Project Proposal for The Construction of Hotel service Building
202
0
Will prepare the annual financial statements and prepare condensed reports
for both the General Manager and other concerned government body.
Follow the overall status of the business and provide maintenance and repair
services
C. Hotel manager
Will handle the overall hotel activities of the organization which include
planning, organizing, directing, and controlling.
Will develop the hotel strategies for future multipurpose building
development
Will develop effective customer handling strategies.
Execute the promotion methods.
D. Technical and maintenance manager
Will handle the overall physical maintenance and related issues
Will make sure electricity and back up is organized.
Follow up security issues and educate tenants
Works in collaboration with general service to make sure tenants are well
served
B. Management
Hire a work crew and direct the workers on each detail of the job.
Offer wages according to your budget and set salary pay scale of the
company.
Let the workers know what their duties and what the project time frame is.
Coordinate with other managers and make sure that everyone is sticking
with the budget and time frame.
Get all the paperwork in order. The manager is responsible for getting all the
proper licenses and knowing all the regulations and safety codes.
Budget carefully, and keep records of money spent on the project.
Communicate with construction supervisors, owners, architects, other
managers and the working crew on a regular basis to determine what has
already been done and what needs to get done.
Page 36
Project Proposal for The Construction of Hotel service Building
202
0
Page 37
Project Proposal for The Construction of Hotel service Building
202
0
C. Vehicle
SN Description UOM Qty Unit Cost Total cost in Remark
in Fr. Birr
1 truck Unit 1 450,000 450,000 Duty Free
Total 450,000
D. Office Equipment’s
SN Description Measurement Qty Unit cost Total cost
in birr in Birr
1 Managerial tables Unit 3.00 3000.00 9,000.00
2 Managerial chairs Unit 3.00 2000.00 6000.00
3 Office table with chair Unit 6.00 1,500.00 9,000.00
4 Secretarial table with Unit 1.00 1,500.00 1,500.00
chairs
5 Computer with chairs Unit 2.00 10,000.00 30,000.00
6 Shelf Unit 1.00 4,300.00 4,300.00
7 Filing cabinets Unit 1.00 1,500.00 1,500.00
8 Guest chairs Unit 6.00 1000.00 6,000.00
9 Fax & Telephone machine Unit 2.00 1,800.00 3,600.00
10 Carpet and Curtain LS 1.00 18,000.00
Total 88,900.00
Page 38
Project Proposal for The Construction of Hotel service Building
202
0
Working Capital
Page 39
Project Proposal for The Construction of Hotel service Building
202
0
Page 40
Project Proposal for The Construction of Hotel service Building
202
0
I. Underlying Assumption
The financial analysis of the mixed use building is based on the data provided in
the preceding sections and the following assumptions.
Page 41
Project Proposal for The Construction of Hotel service Building
202
0
B. Depreciation
Building 10%
Building machinery and equipment 10%
Office Equipment’s 10%
Page 42
Project Proposal for The Construction of Hotel service Building
202
0
2. Depreciation Schedule
SN Description Original Value in Depreciation Depreciation per
Birr rate in % year in Birr
1 Construction and 4,964,788.75 10 296,478.87
Building
2 Bldg. machines 224,600.00 10 22,460.00
&Equipment’s
3 Vehicle 450,000.00 10 45,000.00
4 Office Equipment 88,900.00 10 8,890.00
Page 43
Project Proposal for The Construction of Hotel service Building
202
0
Expenses
Salary Expense 405,360 526,968.00 606,013.00
Operating Expenses 327,479.25 409,349.01 450,283.96
Deprecation Building 296,478.87 296,478.87 296,478.87
Deprecation Bld. 22,460.00 22,460.00 22,460.00
Page 44
Project Proposal for The Construction of Hotel service Building
202
0
6.6.1 Profitability
According to the projected income statement, the building will start generating
profit in the 2nd year of operation. Important ration such as profit to total sales, net
profit to equity (Return on equity) and net profit plus interest on total investment
(return on total investment) show as increasing trend during the lifetime of the
project. The income statement and the other indicators of profitability show that
the project is viable.
Page 46
Project Proposal for The Construction of Hotel service Building
202
0
Page 47
Project Proposal for The Construction of Hotel service Building
202
0
Conclusion
The construction of hotel use Building serve are one of the core to development
and the growth of one town B/C construction industry are back bone of the town.
Surrounding according construction of hotel use Building service is used to the rest
of guest coming to the Gojo pass this town. B/c of it unique to reducing
transporting cost the Gojo and neighbor town people who need to recreation rest
day and weeding day.
The feasibility study the company of market serves show that construction of hotel
use Building economical feasible necessity of the business company will necessary
to sport the market center of town.
Page 48
Project Proposal for The Construction of Hotel service Building
202
0
Recommendation
The Gojo Town is lake of infrastructure city like electricity, telle phone; road and
water supply are more danger to do some investment and the Gojo town
administration also not facilitate to the investor due to the land transfer to investor.
The construction project also not much acquired and used to local material such
mud housing. Other issue on the behavior of attraction of investor in the Gojo or
Jeldu Woreda duty facilitated the need investor
Page 49