0% found this document useful (0 votes)
30 views1 page

Nursing Staff Calculation for ED

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views1 page

Nursing Staff Calculation for ED

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

You are a head nurse in emergency department which consists of 20 beds, and there are 15 patients in this ED,

categories as the following: category one: 6 patients, category two: 4 patients, category three: 3 patients, category four 2,
otherwise the shift option in this department is 12 hours and the actual working days per month 13 shift.

Based on the previous data calculate how many nurses needed to cover the schedule of unit /month?

Total Nursing Care hr /day

• Category I 6 X 4.8 = 28.8 hr/day Category II 4 X 6.2 = 24.8 hr/day

• Category III 3 X 8.2 = 24.6 hr/day Category VI 2 X 10.8 = 21.6 hr/day

• Total nursing care hr/day = 28.8 + 24.8 + 24.6 + 21.6 = 99.8 hr/day

• Average of nursing care hr/day =

Total nursing care hours

____________________

Total number of patients

• Average of nursing care hr/day = 99.8 ÷ 15 = 6.7 nursing care hr/day

• Number of nurses needed/day =

Average of nursing care X Number of beds

_____________________

Shift option

• Number of nurses needed/day =

6.7 X20

_______

12 = 11 nurses/day

• Number of nurses needed/month =

Number of nurses/day X 30

__________________________________

Actual working days/month

• Number of nurses needed/month =

11 X 30

____________

13

• Number of nurses needed / month = 25 nurse/month