Part.01 Scheduling Management Concepts
Part.01 Scheduling Management Concepts
01
What is the Project?
Project Properties
Operation Properties
Planning Force
Lecture 1.02
What is the Project Management?
to project activities
Project Start Organizing and Preparing Carrying out the work Ending the Project
Process Groups
Monitoring
Initiating Closing
Planning Executing and
Process Process
Controlling
• Collecting Data.
• Collect Work Performance Data.
• Creating Baseline Schedule:
• Apply Actuals in the Baseline (Updating).
• Engineering. • Tracking Testing and
• Work Performance Reports.
• Procurement. Commissioning Activities.
• Recovery Plan.
• Construction. • As Built Drawings.
• Revised Baseline.
• T & C & Closing. • Warranties.
• Issue Log.
• Staff Plan (Deployment • Snag list.
• Risk Register.
Schedule). • Closing Documents.
• Corrective and Preventive Actions.
• Equipment Plan. • Closeout Report
• Delay Analysis.
• EOT Claims.
Planning Force
Lecture 1.03
Project Management Plan
A - 4
B A 5
C A 4
D B 6
E C 3
F D,E 5
Planning Force
Lecture 1.04
Time Schedule Creation
General Conditions
Schedule Method Schedule Tool Procurement Schedule
Resource Resource
Sequence Engineering Procurement
Leveling Smoothing
Planning Force
Lecture 1.05
Time Schedule Approval
Logic Relationship
Total Float
Activity Duration
Dangling Activities
Resource Smoothing
Remaining Durations Schedule Performance Index Risk / Issue Log & Recommendations
Planning Force
Lecture 1.06
Schedule Methods & Techniques
Planning Force
Lecture 1.07
Critical Path Method
Activity Name
1 4 4 16 5 20
Start A F Finish
1 0 4 16 0 20
5 4 8 9 3 11
C E Backward Path
9 4 12 13 4 15
1 3 3 9 4 12
5
A C
1 0 3 9 0 12
13 3 15 14 2 15
-2
Start E F Finish
13 0 15 14 0 15
1 4 4 5 6 10
B D
3 2 6 7 2 12
Planning Force
Lecture 1.08
Resources
Scope
Cost Quality
Direct In Direct
Long Lead Items Normal Items
Planning Force
Lecture 1.09
Resource Leveling VS Smoothing
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
Planning Force
Lecture 1.10
Schedule Compressing
4 5 6 7
8 9 10 11 12
Fast Track 1 2 3
3 4 5 6
5 6 7 8 9 High Risk
Crashing 1 2 3
4 5
6 7 8 High Cost
Ali KATARY ECCDA, PMP®, PMI-SP®, PMI-RMP®, P3O®, SSYB, NCN-A
3
CONTACTS
Ali Katary
Planning Force
Lecture 1.11
Cost Allocation
Contract
Contractor Owner
Documents
1 2 3 4 5 6 7 8 9 10
PV
PV
PV
PV
PV
1 2 3 4 5 6 7 8 9 10
PV
PV
-ve Behind <1 Behind
PV
SV = EV - PV 0.00 ON SPI = EV / PV =1 ON
PV
EV +ve Ahead >1 Ahead
PV EV
EV
1 2 3 4 5 6 7 8 9 10
Planning Force
Lecture 1.12
Baseline VS Updated Schedule
Baselines are the frozen version of the project schedules. Before updating the project
schedule for the first time, the baseline schedule is retained as a target. This means the
baseline schedule is the same as the project schedule at the beginning.
A - 2
B A 3
C B 1
A - 2
Updated Finish
B A 3
Delay
Remaining
C B 1
Past
Forecasting
Actual
Planning Force
Lecture 1.13
EVM Planned Value
A 200 2
B 600 3
C 200 1
100%
80%
60%
40%
20%
10%
1 2 3 4 5 6
Planning Force
Lecture 1.14
EVM Earned Value
A 200 2
B 600 3
67 133
100%
80%
60%
40%
20%
10%
13%
7%
1 2 3 4 5 6
Planning Force
Lecture 1.15
EVM Key Performance Indicators
1000
800
600
400
PV 200
Schedule Variance (SV) = EV - PV = 133 – 200 = - 67
100
Schedule Performance Index (SPI) = EV / PV = 133 / 200 = 0.67
EV 133
67
1 2 3 4 5 6
PV EV
EV – PV = - VE EV – PV = ZERO EV – PV = + VE
PV EV
EV / PV < 1 EV / PV = 1 EV / PV > 1
Planning Force
Earned Schedule Management
BAC
100
TPI = ES ÷ AT
80
PV
60
40
20 EV
0
M.01 M.02 M.03 M.04 M.05 M.06 M.07 M.08 M.09 M.10
ES TV = ES - AT
AT
80
60
PV
40
20 EV
0
M.01 M.02 M.03 M.04 M.05 M.06 M.07 M.08 M.09 M.10 M.11 M.12 M.13
ES TV
60
PV
40
20 EV
0
M.01 M.02 M.03 M.04 M.05 M.06 M.07 M.08 M.09 M.10 M.11 M.12 M.13
ES TV
60
PV
40
20 EV
0
M.01 M.02 M.03 M.04 M.05 M.06 M.07 M.08 M.09 M.10 M.11 M.12 M.13
ES TV
40
20
0
M.01 M.02 M.03 M.04 M.05 M.06 M.07 M.08 M.09 M.10 M.11 M.12 M.13
AT = SAC TVAC
Earned Schedule (ES): This duration from the beginning of the project to the date on which the PV
should have been equal to the current value of EV.
Actual Time (AT): This is the duration from the beginning of the project to status date.
Planned Accomplishment Rate (PAR): The average PV per time period can be calculated by
dividing the BAC by SAC, and can be called the PV Rate.
The Expected Accomplishment Rate (EAR): the expected average accomplishment rate per time
period from the status date to the completion of the project or the work package.
The Time Variance at Completion (TVAC) gives an indication of the estimated amount of time that
the project will be completed ahead or behind schedule, TVAC = SAC − TEAC.
Planning Force