Construction Project Schedule Overview

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views2 pages

Construction Project Schedule Overview

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Workshop.

02 Baseline Schedule

Activity ID Activity Name Original Start Finish Budgeted Total Total 2021 2022
Duration Cost Float
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Workshop.02 286 02-Jan-21 30-Nov-21 SAR852,403.85 0 30-Nov-21, Workshop.02

Milestones 286 02-Jan-21 30-Nov-21 SAR0.00 0 30-Nov-21, Milestones

Start Dates 0 02-Jan-21 02-Jan-21 SAR0.00 0 02-Jan-21, Start Dates


A1000 Project Start Date 0 02-Jan-21 SAR0.00 0 Project Start Date
Finish Dates 0 30-Nov-21 30-Nov-21 SAR0.00 0 30-Nov-21, Finish Dates
A1040 Project Finish Date 0 30-Nov-21 SAR0.00 0 Project Finish Date

Mobilization 37 02-Jan-21 13-Feb-21 SAR0.00 0 13-Feb-21, Mobilization


WS.MB.14100 Cleaning the Site 6 02-Jan-21 07-Jan-21 SAR0.00 0 Cleaning the Site
WS.MB.14200 Surveying Work 6 09-Jan-21 14-Jan-21 SAR0.00 0 Surveying Work
WS.MB.14300 Site Officess Erection 10 16-Jan-21 26-Jan-21 SAR0.00 0 Site Officess Erection
WS.MB.14400 Fixing the Fence 15 27-Jan-21 13-Feb-21 SAR0.00 0 Fixing the Fence
Construction 181 08-Feb-21 06-Sep-21 SAR852,403.85 0 06-Sep-21, Construction

Building A 5 08-Feb-21 13-Feb-21 SAR60,000.00 0 13-Feb-21, Building A


Sub-Structure 5 08-Feb-21 13-Feb-21 SAR60,000.00 0 13-Feb-21, Sub-Structure
Site Work 5 08-Feb-21 13-Feb-21 SAR60,000.00 0 13-Feb-21, Site Work
WS.CW.B Excavation 5 08-Feb-21 13-Feb-21 SAR60,000.00 0 Excavation
Building B 168 14-Feb-21 28-Aug-21 SAR781,903.85 0 28-Aug-21, Building B
Sub-Structure 34 14-Feb-21 24-Mar-21 SAR307,344.76 0 24-Mar-21, Sub-Structure
Site Work 34 14-Feb-21 24-Mar-21 SAR170,000.00 0 24-Mar-21, Site Work
WS.CW.B Excavation 7 14-Feb-21 21-Feb-21 SAR80,000.00 0 Excavation
WS.CW.B Backfilling Work 5 20-Mar-21 24-Mar-21 SAR90,000.00 0 Backfilling Work
Structure 14 22-Feb-21 09-Mar-21 SAR111,104.76 0 09-Mar-21, Structure
WS.CW.B Plain Concrete 6 22-Feb-21 28-Feb-21 SAR21,104.76 0 Plain Concrete
WS.CW.B Shuttering for Foundation 4 01-Mar-21 04-Mar-21 SAR22,500.00 0 Shuttering for Foundation
WS.CW.B Steelfixing for Foundation 6 01-Mar-21 07-Mar-21 SAR31,500.00 0 Steelfixing for Foundation
WS.CW.B Casting Concrete for Foundation 1 08-Mar-21 08-Mar-21 SAR31,500.00 0 Casting Concrete for Foundation
WS.CW.B Deshuttering for Foundation 1 09-Mar-21 09-Mar-21 SAR4,500.00 0 Deshuttering for Foundation
Waterproofing
Waterproofi 8 10-Mar-21 18-Mar-21 SAR26,240.00 0 18-Mar-21, Waterproofing
WS.CW.B Waterproofing for foundation 8 10-Mar-21 18-Mar-21 SAR26,240.00 0 Waterproofing for foundation
Super-Structure
Super-Structur 134 25-Mar-21 28-Aug-21 SAR474,559.09 0 28-Aug-21, Super-Structure
Structure 82 25-Mar-21 28-Jun-21 SAR154,812.73 0 28-Jun-21, Structure
Ground F
Floor 27 25-Mar-21 25-Apr-21 SAR51,000.01 0 25-Apr-21, Ground Floor
WS.CW Steelfixing for Columns & Walls 6 25-Mar-21 31-Mar-21 SAR5,795.56 0 Steelfixing for Columns & Walls
WS.CW Shuttering for Columns & Walls 6 01-Apr-21 07-Apr-21 SAR4,139.68 0 Shuttering for Columns & Walls
WS.CW Casting Concrete for Columns & Walls 1 08-Apr-21 08-Apr-21 SAR5,795.56 0 Casting Concrete for Columns & Walls
WS.CW Deshuttering for Columns & Walls 1 10-Apr-21 10-Apr-21 SAR827.94 0 Deshuttering for Columns & Walls
WS.CW Shuttering for Slabs & Stairs 6 11-Apr-21 17-Apr-21 SAR9,063.49 0 Shuttering for Slabs & Stairs
WS.CW Steelfixing for Slabs & Stairs 6 18-Apr-21 24-Apr-21 SAR12,688.89 0 Steelfixing for Slabs & Stairs
WS.CW Casting Concrete for Slabs & Stairs 1 25-Apr-21 25-Apr-21 SAR12,688.89 0 Casting Concrete for Slabs & Stairs
First Floor
Floo 27 26-Apr-21 26-May-21 SAR51,000.01 0 26-May-21, First Floor
WS.CW Steelfixing for Columns & Walls 6 26-Apr-21 02-May-21 SAR5,795.56 0 Steelfixing for Columns & Walls
WS.CW Shuttering for Columns & Walls 6 03-May-21 09-May-21 SAR4,139.68 0 Shuttering for Columns & Walls
WS.CW Casting Concrete for Columns & Walls 1 10-May-21 10-May-21 SAR5,795.56 0 Casting Concrete for Columns & Walls
WS.CW Deshuttering for Columns & Walls 1 11-May-21 11-May-21 SAR827.94 0 Deshuttering for Columns & Walls
WS.CW Shuttering for Slabs & Stairs 6 12-May-21 18-May-21 SAR9,063.49 0 Shuttering for Slabs & Stairs
WS.CW Steelfixing for Slabs & Stairs 6 19-May-21 25-May-21 SAR12,688.89 0 Steelfixing for Slabs & Stairs
WS.CW Casting Concrete for Slabs & Stairs 1 26-May-21 26-May-21 SAR12,688.89 0 Casting Concrete for Slabs & Stairs

Remaining Level of Effort Actual Work Critical Remaining ... Date Revision Checked Approved
Page 1 of 2
Actual Level of Effort Remaining Work Milestone
Workshop.02 Baseline Schedule

Activity ID Activity Name Original Start Finish Budgeted Total Total 2021 2022
Duration Cost Float
c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Second F
Floor 28 27-May-21 28-Jun-21 SAR52,812.71 0 28-Jun-21, Second Floor
WS.CW Steelfixing for Columns & Walls 6 27-May-21 02-Jun-21 SAR5,795.56 0 Steelfixing for Columns & Walls
WS.CW Shuttering for Columns & Walls 6 03-Jun-21 09-Jun-21 SAR4,139.68 0 Shuttering for Columns & Walls
WS.CW Casting Concrete for Columns & Walls 1 10-Jun-21 10-Jun-21 SAR5,795.56 0 Casting Concrete for Columns & Walls
WS.CW Deshuttering for Columns & Walls 1 12-Jun-21 12-Jun-21 SAR827.94 0 Deshuttering for Columns & Walls
WS.CW Shuttering for Slabs & Stairs 6 13-Jun-21 19-Jun-21 SAR9,063.49 0 Shuttering for Slabs & Stairs
WS.CW Steelfixing for Slabs & Stairs 6 20-Jun-21 26-Jun-21 SAR12,688.89 0 Steelfixing for Slabs & Stairs
WS.CW Casting Concrete for Slabs & Stairs 1 27-Jun-21 27-Jun-21 SAR12,688.89 0 Casting Concrete for Slabs & Stairs
WS.CW Deshuttering for Slabs & Stairs 1 28-Jun-21 28-Jun-21 SAR1,812.70 0 Deshuttering for Slabs & Stairs
Finishing 52 29-Jun-21 28-Aug-21 SAR213,486.04 0 28-Aug-21, Finishing
Second F
Floor 39 29-Jun-21 12-Aug-21 SAR199,267.94 0 12-Aug-21, Second Floor
WS.CW External block work 6 29-Jun-21 05-Jul-21 SAR30,158.73 0 External block work
WS.CW Internal block works 7 06-Jul-21 13-Jul-21 SAR15,746.03 0 Internal block works
WS.CW Internal Plastering 5 14-Jul-21 19-Jul-21 SAR42,857.14 0 Internal Plastering
WS.CW Plaster Board for Ceiling 10 28-Jul-21 08-Aug-21 SAR47,238.10 0 Plaster Board for Ceiling
WS.CW First Layers for Internal Painting 6 02-Aug-21 08-Aug-21 SAR36,000.00 0 First Layers for Internal Painting
WS.CW Flooring (Porcelain) 4 09-Aug-21 12-Aug-21 SAR27,267.94 0 Flooring (Porcelain)
Stairs 13 14-Aug-21 28-Aug-21 SAR14,218.10 0 28-Aug-21, Stairs
WS.CW Stair Case Granite 5 14-Aug-21 18-Aug-21 SAR3,718.10 0 Stair Case Granite
WS.CW Steel Handrail 8 19-Aug-21 28-Aug-21 SAR10,500.00 0 Steel Handrail
Mechanical 7 20-Jul-21 27-Jul-21 SAR106,260.32 0 27-Jul-21, Mechanical
HVAC 7 20-Jul-21 27-Jul-21 SAR106,260.32 0 27-Jul-21, HVAC
Second Floor
Secon 7 20-Jul-21 27-Jul-21 SAR106,260.32 0 27-Jul-21, Second Floor
First Fix
Firs 7 20-Jul-21 27-Jul-21 SAR106,260.32 0 27-Jul-21, First Fix
W Ducts & Valves 7 20-Jul-21 27-Jul-21 SAR94,984.13 0 Ducts & Valves
W Fan Cool Units 4 24-Jul-21 27-Jul-21 SAR11,276.19 0 Fan Cool Units
Building C 8 29-Aug-21 06-Sep-21 SAR10,500.00 0 06-Sep-21, Building C
Super-Structure
Super-Structur 8 29-Aug-21 06-Sep-21 SAR10,500.00 0 06-Sep-21, Super-Structure
Finishing 8 29-Aug-21 06-Sep-21 SAR10,500.00 0 06-Sep-21, Finishing
Stairs 8 29-Aug-21 06-Sep-21 SAR10,500.00 0 06-Sep-21, Stairs
WS.CW Steel Handrail 8 29-Aug-21 06-Sep-21 SAR10,500.00 0 Steel Handrail
Closeout 73 07-Sep-21 30-Nov-21 SAR0.00 0 30-Nov-21, Closeout

As Built Drawings
Drawing 35 07-Sep-21 17-Oct-21 SAR0.00 0 17-Oct-21, As Built Drawings
WS.CL.15200 Arch. As Built Drawings 35 07-Sep-21 17-Oct-21 SAR0.00 0 Arch. As Built Drawings
Snaging & Desnaging
Desn 69 07-Sep-21 25-Nov-21 SAR0.00 0 25-Nov-21, Snaging & Desnaging
WS.CL.15900 Snag List 33 07-Sep-21 14-Oct-21 SAR0.00 0 Snag List
WS.CL.16000 De Snaging 36 16-Oct-21 25-Nov-21 SAR0.00 0 De Snaging
Closeout Documents
Docum 4 27-Nov-21 30-Nov-21 SAR0.00 0 30-Nov-21, Closeout Documents
WS.CL.16300 Taking over Certificate 4 27-Nov-21 30-Nov-21 SAR0.00 0 Taking over Certificate