Workers Accommodation Compound (ph-1) Update 30-Sep-2023+Events Rev01 Classic Schedule Layout 31-Oct-23 12:42

Activity ID Activity Name Original Start Finish


Cost Actual Total Budgeted2023 2024 2025
% Cost Total Cost
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan
Duration Complete
SPARK.WAC.Ph.1-BL01-2 Workers Accommodation 185 01-Jul-23 A 01-Feb-24 100% $2,497,370.80
Compound (ph-1)AUpdate 30-Sep-2023+Events Rev01 $2,497,370.80 01-Feb-24 A, SPARK.WAC.Ph.1-BL01-2 Workers Accommodation Compound (ph-1) Update 30-Sep-2023+Events Re

SPARK.WAC.Ph.1-BL01-2.MS Key Milestones 167 01-Jul-23 A 31-Dec-23 A 0% $0.00 $0.00 31-Dec-23 A, SPARK.WAC.Ph.1-BL01-2.MS Key Milestones

SPARK.WAC.Ph.1-BL01-2.EN Engineering 12 01-Jul-23 A 11-Oct-23 A 100% $1,428.67 $1,428.67 11-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.EN Engineering

SPARK.WAC.Ph.1-BL01-2.PRO Procurement 170 18-Jul-23 A 01-Feb-24 A 100% $20,715.71 $20,715.71 01-Feb-24 A, SPARK.WAC.Ph.1-BL01-2.PRO Procurement

SPARK.WAC.Ph.1-BL01-2.CW Construction works 123 03-Jul-23 A 23-Nov-23 A 100% $2,475,226.41 $2,475,226.41 23-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW Construction works

SPARK.WAC.Ph.1-BL01-2.CW.MOB Mobilization works 5 03-Jul-23 A 08-Jul-23 A 100% $2,143.00 $2,143.00 08-Jul-23 A, SPARK.WAC.Ph.1-BL01-2.CW.MOB Mobilization works
SPARK.WAC.Ph.1-BL01-2.CW.Z2 ZONE 2 113 29-Jul-23 A 23-Nov-23 A 100% $1,106,987.61 $1,106,987.61 23-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2 ZONE 2
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A Junior building type-2 (A) 113 29-Jul-23 A 23-Nov-23 A 100% $350,860.83 $350,860.83 23-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A Junior building type-2 (A)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub Substructre 113 29-Jul-23 A 23-Nov-23 A 100% $350,860.83 $350,860.83 23-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub.E Earthworks 11 29-Jul-23 A 08-Aug-23 A 100% $65,619.50 $65,619.50 08-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub.E Earthworks
Excavate to formation level 6 29-Jul-23 A 03-Aug-23 A 100% $53,725.10 $53,725.10 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 5 03-Aug-23 A 08-Aug-23 A 100% $11,894.40 $11,894.40 Imported fill and compaction with 25 cm A-1-A layer under footing
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub.C Concrete Works 47 01-Oct-23 A 23-Nov-23 A 100% $285,241.33 $285,241.33 23-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub.C Concrete Works
Shutters + 50 mm thick PC Under Footings 5 01-Oct-23 A 05-Oct-23 A 100% $17,036.07 $17,036.07 Shutters + 50 mm thick PC Under Footings
RC For Footings + column neck 15 07-Nov-23 A 23-Nov-23 A 100% $268,205.26 $268,205.26 RC For Footings + column neck
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-A.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B Junior building type-2 (B) 93 03-Aug-23 A 07-Nov-23 A 100% $350,860.83 $350,860.83 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B Junior building type-2 (B)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub Substructre 93 03-Aug-23 A 07-Nov-23 A 100% $350,860.83 $350,860.83 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub.E Earthworks 11 03-Aug-23 A 15-Aug-23 A 100% $65,619.50 $65,619.50 15-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub.E Earthworks
Excavate to formation level 6 03-Aug-23 A 09-Aug-23 A 100% $53,725.10 $53,725.10 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 5 10-Aug-23 A 15-Aug-23 A 100% $11,894.40 $11,894.40 Imported fill and compaction with 25 cm A-1-A layer under footing
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub.C Concrete Works 33 01-Oct-23 A 07-Nov-23 A 100% $285,241.33 $285,241.33 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub.C Concrete Works
Shutters + 50 mm thick PC Under Footings 5 01-Oct-23 A 05-Oct-23 A 100% $17,036.07 $17,036.07 Shutters + 50 mm thick PC Under Footings
RC For Footings + column neck 18 18-Oct-23 A 07-Nov-23 A 100% $268,205.26 $268,205.26 RC For Footings + column neck
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.JB-B.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB isolated building 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1 Adminstration buildings 39 06-Aug-23 A 04-Oct-23 A 100% $45,050.05 $45,050.05 04-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1 Adminstration buildings
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub Substructre 39 06-Aug-23 A 04-Oct-23 A 100% $45,050.05 $45,050.05 04-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub.E Earthworks 8 06-Aug-23 A 15-Aug-23 A 100% $39,203.78 $39,203.78 15-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub.E Earthworks
Excavate to formation level 5 06-Aug-23 A 10-Aug-23 A 100% $32,687.31 $32,687.31 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 3 12-Aug-23 A 15-Aug-23 A 100% $6,516.47 $6,516.47 Imported fill and compaction with 25 cm A-1-A layer under footing
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub.C Concrete Works 4 01-Oct-23 A 04-Oct-23 A 100% $5,846.27 $5,846.27 04-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub.C Concrete Works
Shutters + 50 mm thick PC Under Footings 4 01-Oct-23 A 04-Oct-23 A 100% $5,846.27 $5,846.27 Shutters + 50 mm thick PC Under Footings
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.IB1.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M Service building (SUPER MARKET) 5 11-Aug-23 A 15-Aug-23 A 100% $66,993.73 $66,993.73 15-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M Service building (SUPER MARKET)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub Substructre 5 11-Aug-23 A 15-Aug-23 A 100% $66,993.73 $66,993.73 15-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub.E Earthworks 5 11-Aug-23 A 15-Aug-23 A 100% $66,993.73 $66,993.73 15-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub.E Earthworks
Excavate to formation level 5 11-Aug-23 A 15-Aug-23 A 100% $66,993.73 $66,993.73 Excavate to formation level
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub.C Concrete Works 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-M.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT Service building (KITCHEN&DINNING)5 16-Aug-23 A 20-Aug-23 A 100% $88,538.05 $88,538.05 20-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT Service building (KITCHEN&DINNING)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub Substructre 5 16-Aug-23 A 20-Aug-23 A 100% $88,538.05 $88,538.05 20-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub.E Earthworks 5 16-Aug-23 A 20-Aug-23 A 100% $88,538.05 $88,538.05 20-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub.E Earthworks
Excavate to formation level 5 16-Aug-23 A 20-Aug-23 A 100% $88,538.05 $88,538.05 Excavate to formation level
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub.C Concrete Works 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.sub.W Water proofing 0 0% $0.00 $0.00

Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: Completed.
Actual Work Critical Remaining Work summary © Oracle Corporation
Workers Accommodation Compound (ph-1) Update 30-Sep-2023+Events Rev01 Classic Schedule Layout 31-Oct-23 12:42
Activity ID Activity Name Original Start Finish Cost Actual Total Budgeted2023 2024 2025
% Cost Total Cost
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan
Duration Complete
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-KT.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO Service building (MOSQUE) 6 01-Nov-23 A 07-Nov-23 A 100% $109,090.41 $109,090.41 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO Service building (MOSQUE)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub Substructre 6 01-Nov-23 A 07-Nov-23 A 100% $109,090.41 $109,090.41 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub.E Earthworks 6 01-Nov-23 A 07-Nov-23 A 100% $109,090.41 $109,090.41 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub.E Earthworks
Excavate to formation level 6 01-Nov-23 A 07-Nov-23 A 100% $109,090.41 $109,090.41 Excavate to formation level
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub.C Concrete Works 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MO.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH Service building (MPH) 6 01-Nov-23 A 07-Nov-23 A 100% $95,593.71 $95,593.71 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH Service building (MPH)
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub Substructre 6 01-Nov-23 A 07-Nov-23 A 100% $95,593.71 $95,593.71 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub.E Earthworks 6 01-Nov-23 A 07-Nov-23 A 100% $95,593.71 $95,593.71 07-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub.E Earthworks
Excavate to formation level 6 01-Nov-23 A 07-Nov-23 A 100% $95,593.71 $95,593.71 Excavate to formation level
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub.C Concrete Works 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z2.SB-MPH.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3 ZONE 3 95 15-Jul-23 A 01-Nov-23 A 100% $1,366,095.80 $1,366,095.80 01-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3 ZONE 3
SPARK.WAC.Ph.1-BL01-2.CW.Z3.SB-A Supervisors Buildings (A) 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.SB-B Supervisors Buildings (B) 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.SB-C Supervisors Buildings (C) 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A Senior Building (A) 94 15-Jul-23 A 01-Nov-23 A 100% $403,964.47 $403,964.47 01-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A Senior Building (A)
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub Substructre 94 15-Jul-23 A 01-Nov-23 A 100% $403,964.47 $403,964.47 01-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.E Earthworks 79 15-Jul-23 A 15-Oct-23 A 100% $105,043.20 $105,043.20 15-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.E Earthworks
Excavate to formation level 4 15-Jul-23 A 18-Jul-23 A 100% $48,929.15 $48,929.15 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 3 01-Aug-23 A 06-Aug-23 A 100% $10,534.75 $10,534.75 Imported fill and compaction with 25 cm A-1-A layer under footing
Backfilling with excavated material and compaction 4 10-Oct-23 A 15-Oct-23 A 100% $45,579.30 $45,579.30 Backfilling with excavated material and compaction
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.C Concrete Works 28 23-Aug-23 A 10-Oct-23 A 100% $269,527.25 $269,527.25 10-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.C Concrete Works
Shutters + 50 mm thick PC Under Footings 3 14-Sep-23 A 17-Sep-23 A 100% $17,302.91 $17,302.91 Shutters + 50 mm thick PC Under Footings
RC For Footings + column neck 11 23-Aug-23 A 10-Oct-23 A 100% $252,224.34 $252,224.34 RC For Footings + column neck
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.W Water proofing 6 26-Oct-23 A 01-Nov-23 A 100% $29,394.02 $29,394.02 01-Nov-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.sub.W Water proofing
Dampproofing and Waterproofing for foundation 6 26-Oct-23 A 01-Nov-23 A 100% $29,394.02 $29,394.02 Dampproofing and Waterproofing for foundation
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-A.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B Senior Building (B) 76 18-Jul-23 A 15-Oct-23 A 100% $403,964.47 $403,964.47 15-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B Senior Building (B)
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub Substructre 76 18-Jul-23 A 15-Oct-23 A 100% $403,964.47 $403,964.47 15-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.E Earthworks 76 18-Jul-23 A 15-Oct-23 A 100% $105,043.20 $105,043.20 15-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.E Earthworks
Excavate to formation level 4 18-Jul-23 A 22-Jul-23 A 100% $48,929.15 $48,929.15 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 3 06-Aug-23 A 08-Aug-23 A 100% $10,534.75 $10,534.75 Imported fill and compaction with 25 cm A-1-A layer under footing
Backfilling with excavated material and compaction 4 10-Oct-23 A 15-Oct-23 A 100% $45,579.30 $45,579.30 Backfilling with excavated material and compaction
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.C Concrete Works 20 14-Sep-23 A 10-Oct-23 A 100% $269,527.25 $269,527.25 10-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.C Concrete Works
Shutters + 50 mm thick PC Under Footings 3 14-Sep-23 A 21-Sep-23 A 100% $17,302.91 $17,302.91 Shutters + 50 mm thick PC Under Footings
RC For Footings + column neck 11 23-Sep-23 A 10-Oct-23 A 100% $252,224.34 $252,224.34 RC For Footings + column neck
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.W Water proofing 6 01-Oct-23 A 07-Oct-23 A 100% $29,394.02 $29,394.02 07-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.sub.W Water proofing
Dampproofing and Waterproofing for foundation 6 01-Oct-23 A 07-Oct-23 A 100% $29,394.02 $29,394.02 Dampproofing and Waterproofing for foundation
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-B.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C Senior Building (C) 73 23-Jul-23 A 17-Oct-23 A 100% $403,964.47 $403,964.47 17-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C Senior Building (C)
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub Substructre 73 23-Jul-23 A 17-Oct-23 A 100% $403,964.47 $403,964.47 17-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.E Earthworks 73 23-Jul-23 A 17-Oct-23 A 100% $105,043.20 $105,043.20 17-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.E Earthworks
Excavate to formation level 4 23-Jul-23 A 26-Jul-23 A 100% $48,929.15 $48,929.15 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 3 10-Aug-23 A 13-Aug-23 A 100% $10,534.75 $10,534.75 Imported fill and compaction with 25 cm A-1-A layer under footing
Backfilling with excavated material and compaction 4 12-Oct-23 A 17-Oct-23 A 100% $45,579.30 $45,579.30 Backfilling with excavated material and compaction
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.C Concrete Works 22 14-Sep-23 A 12-Oct-23 A 100% $269,527.25 $269,527.25 12-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.C Concrete Works

Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: Completed.
Actual Work Critical Remaining Work summary © Oracle Corporation
Workers Accommodation Compound (ph-1) Update 30-Sep-2023+Events Rev01 Classic Schedule Layout 31-Oct-23 12:42
Activity ID Activity Name Original Start Finish Cost Actual Total Budgeted2023 2024 2025
% Cost Total Cost
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan
Duration Complete
Shutters + 50 mm thick PC Under Footings 3 14-Sep-23 A 21-Sep-23 A 100% $17,302.91 $17,302.91 Shutters + 50 mm thick PC Under Footings
RC For Footings + column neck 13 23-Sep-23 A 12-Oct-23 A 100% $252,224.34 $252,224.34 RC For Footings + column neck
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.W Water proofing 6 01-Oct-23 A 07-Oct-23 A 100% $29,394.02 $29,394.02 07-Oct-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.sub.W Water proofing
Dampproofing and Waterproofing for foundation 6 01-Oct-23 A 07-Oct-23 A 100% $29,394.02 $29,394.02 Dampproofing and Waterproofing for foundation
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.NB-C.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB Recreation Building 10 25-Jul-23 A 19-Aug-23 A 100% $154,202.39 $154,202.39 19-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB Recreation Building
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub Substructre 10 25-Jul-23 A 19-Aug-23 A 100% $154,202.39 $154,202.39 19-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub Substructre
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub.E Earthworks 10 25-Jul-23 A 19-Aug-23 A 100% $154,202.39 $154,202.39 19-Aug-23 A, SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub.E Earthworks
Excavate to formation level 6 25-Jul-23 A 29-Jul-23 A 100% $127,186.56 $127,186.56 Excavate to formation level
Imported fill and compaction with 25 cm A-1-A layer under footing 4 15-Aug-23 A 19-Aug-23 A 100% $27,015.83 $27,015.83 Imported fill and compaction with 25 cm A-1-A layer under footing
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub.C Concrete Works 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.sub.W Water proofing 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.SUP superstructre 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.CW.Z3.RB.I Interior parts and equipments 0 0% $0.00 $0.00
SPARK.WAC.Ph.1-BL01-2.com commissioning and Close 0
Out 0% $0.00 $0.00

Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: Completed.
Actual Work Critical Remaining Work summary © Oracle Corporation