You are on page 1of 8

UPDATE LIST 7 July 2023

Original Physical %
Activity ID Activity Name Start Finish Phase Facilities
Duration Complete
SGAR-10014 Supervision for equipment manufacture 150 18-May-21 A 6-Nov-23 PROCUREMENT 2P01 77.46%
CHA-P10391Supervision for equipment manufacture 50 26-May-23 A 08-Jul-23 A PROCUREMENT 2P01 100%
CHA-P50001Bidding evaluation and declaring successful bidder 15 04-May-23 A 18-May-23 A PROCUREMENT 2P01 100%
CHA-P50011Signing contract 10 18-May-23 A 27-May-23 A PROCUREMENT 2P01 100%
CHA-P50021Document submission by manufacturer 4 27-May-23 A 30-May-23 A PROCUREMENT 2P01 100%
CHA-P50022Purchasing Material by subcontractor 5 30-May-23 A 03-Jun-23 A PROCUREMENT 2P01 100%
CHA-P50031Supervision for equipment manufacture 56 03-Jun-23 A 6-Nov-23 PROCUREMENT 2P01 20%
SGAR-10042 Supervision for equipment manufacture 110 08-Jan-23 A 1-Nov-23 PROCUREMENT 2P02 85.60%
CHA-P10871Unpacking and inspection 15 18-Jun-23 A 04-Jul-23 A PROCUREMENT 2P02 100%
PP57760 Excavation work and cut pile head construction 100% 14 29-Nov-22 A 01-Jul-23 A CONSTRUCTION 2P02 100%
SGAR-10074 Supervision for equipment manufacture 180 18-May-21 A 30-Aug-23 PROCUREMENT 2P03 77.27%
SGAR-10075 FOB at loading port 30 19-Mar-23 A 7-Oct-23 PROCUREMENT 2P03 74.69%
CHA-P12451Transportation and custom clearance 20 05-Jun-23 A 30-Jun-23 A PROCUREMENT 2P04(02 100%
CHA-P12461Arrived at site 10 19-Jun-23 A 01-Jul-23 A PROCUREMENT 2P04(02 100%
CHA-P12471Unpacking and inspection 15 23-Jun-23 A 07-Jul-23 A PROCUREMENT 2P04(02 100%
CHA-P50422Purchasing Material by subcontractor 30 14-Jun-23 A 5-Aug-23 PROCUREMENT 2P04(02 15%
CHA-P54951Supervision for equipment manufacture 88 19-Jun-23 A 10-Oct-23 PROCUREMENT 2P05(01 20%
PP173160 LC Pouring 6 13-May-23 A 02-Jul-23 A CONSTRUCTION 2P05(01 100%
PP173220 Rebar Installation 100% 14 18-Jun-23 A 07-Jul-23 A CONSTRUCTION 2P05(01 100.00%
PP173240 Concreted Pouring 50% 7 24-Jun-23 A 13-Jul-23 CONSTRUCTION 2P05(01 95.70%
SGAR-10144 FOB at loading port 30 09-Jun-23 A 05-Jul-23 A PROCUREMENT 2P05(02 100%
SGAR-10145 Transportation and custom clearance 30 06-Jul-23 A 5-Aug-23 PROCUREMENT 2P05(02 30%
CHA-P13941Transportation and custom clearance 20 02-Jul-23 A 26-Jul-23 PROCUREMENT 2P05(02 50%
SGAR-10174 Supervision for equipment manufacture 270 08-Feb-23 A 19-Jan-24 PROCUREMENT 2P06 66.67%
SGAR-10175 FOB at loading port 20 25-May-23 A 8-Feb-24 PROCUREMENT 2P06 66.67%
CHA-P14511Unpacking and inspection 15 28-Jun-23 A 4-Sep-23 PROCUREMENT 2P06 20%
CHA-P14381Transportation and custom clearance 30 11-Jun-23 A 5-Aug-23 PROCUREMENT 2P06 20%
CHA-P14572Purchasing Material by subcontractor 30 11-Nov-22 A 12-Jan-23 A PROCUREMENT 2P06 100%
CHA-P14641Preparing and issuing tendering document 13 02-Mar-23 A 19-Mar-23 A PROCUREMENT 2P06 100%
CHA-P14651Bidding 28 19-Mar-23 A 19-Apr-23 A PROCUREMENT 2P06 100%
CHA-P14661Bidding evaluation and declaring successful bidder 11 19-Apr-23 A 04-May-23 A PROCUREMENT 2P06 100%
CHA-P14671Signing contract 9 04-May-23 A 12-May-23 A PROCUREMENT 2P06 100%
CHA-P14681Document submission by manufacturer 9 12-May-23 A 20-May-23 A PROCUREMENT 2P06 100%
CHA-P14682Purchasing Material by subcontractor 30 20-May-23 A 18-Jun-23 A PROCUREMENT 2P06 100%
CHA-P50622Purchasing Material by subcontractor 30 13-Jun-23 A 05-Jul-23 A PROCUREMENT 2P06 100%
SGAR-10202 Supervision for equipment manufacture 120 18-May-21 A 10-Sep-23 PROCUREMENT 2P07 29.19%
SGAR-10203 FOB at loading port 15 10-Jun-23 A 25-Sep-23 PROCUREMENT 2P07 3.56%
SGAR-10204 Transportation and custom clearance 15 26-Jun-23 A 18-Oct-23 PROCUREMENT 2P07 2%
SGAR-10205 Arrival at site 7 19-Jun-23 A 25-Oct-23 PROCUREMENT 2P07 1.56%
SGAR-10206 Unpacking and Inspection 10 26-Jun-23 A 4-Nov-23 PROCUREMENT 2P07 1.56%
A53490 Excavation work and cut pile head construction 100% 14 02-Jun-23 A 13-Jul-23 CONSTRUCTION 2P07 70%
A53500 LC Pouring 3 04-Jun-23 A 16-Jul-23 CONSTRUCTION 2P07 85%
A53520 Rebar Fabrication 50% 7 20-Jun-23 A 13-Jul-23 CONSTRUCTION 2P07 60.80%
A53550 Rebar Installation 50% 14 01-Jun-23 A 21-Jul-23 CONSTRUCTION 2P07 55%
A53580 Concreted Pouring 50% 14 23-Jun-23 A 28-Jul-23 CONSTRUCTION 2P07 44.00%
SGAR-10235 Supervision for equipment manufacture 90 10-Feb-23 A 7-Sep-23 PROCUREMENT 2P08 92.20%
SGAR-10236 FOB at loading port 20 27-May-23 A 27-Sep-23 PROCUREMENT 2P08 92.20%
CHA-P50822Purchasing Material by subcontractor 23 06-Jun-23 A 29-Jun-23 A PROCUREMENT 2P08 100%
CHA-P50831Supervision for equipment manufacture 90 30-Jun-23 A 12-Oct-23 PROCUREMENT 2P08 20%
SGAR-10272 FOB at loading port 15 03-Jul-23 A 21-Jul-23 PROCUREMENT 2P09 99%
CHA-P16222Purchasing Material by subcontractor 30 03-Nov-22 A 02-Dec-22 A PROCUREMENT 2P09 100%
CHA-P16231Supervision for equipment manufacture 80 02-Dec-22 A 16-Nov-23 PROCUREMENT 2P09 50%
CHA-P50931Supervision for equipment manufacture 90 14-May-23 A 12-Oct-23 PROCUREMENT 2P09 20%
SGAR-10302 Supervision for equipment manufacture 112 18-Dec-22 A 1-Dec-23 PROCUREMENT 2P10 38.30%
CHA-P49931Supervision for equipment manufacture 56 15-May-23 A 31-Aug-23 PROCUREMENT 2P10 50%
CHA-P51022Purchasing Material by subcontractor 30 13-Jun-23 A 05-Jul-23 A PROCUREMENT 2P10 100%
CHA-P51031Supervision for equipment manufacture 55 05-Jul-23 A 30-Aug-23 PROCUREMENT 2P10 50%
CHA-P41591Preparing and issuing tendering document 13 07-May-23 A 19-May-23 A PROCUREMENT 2P11 100%
CHA-P41601Bidding 26 19-May-23 A 13-Jun-23 A PROCUREMENT 2P11 100%
CHA-P41611Bidding evaluation and declaring successful bidder 13 13-Jun-23 A 28-Jun-23 A PROCUREMENT 2P11 100%
CHA-P17301Bidding evaluation and declaring successful bidder 11 06-Apr-23 A 16-Apr-23 A PROCUREMENT 2P11 100%
CHA-P17311Signing contract 7 16-Apr-23 A 22-Apr-23 A PROCUREMENT 2P11 100%
CHA-P17321Document submission by manufacturer 10 22-Apr-23 A 06-May-23 A PROCUREMENT 2P11 100%
CHA-P17322Purchasing Material by subcontractor 30 06-May-23 A 04-Jun-23 A PROCUREMENT 2P11 100%
CHA-P17331Supervision for equipment manufacture 54 04-Jun-23 A 29-Aug-23 PROCUREMENT 2P11 50%
CHA-P51122Purchasing Material by subcontractor 30 04-Jun-23 A 05-Jul-23 A PROCUREMENT 2P11 100%
CHA-P51131Supervision for equipment manufacture 90 05-Jul-23 A 12-Oct-23 PROCUREMENT 2P11 20%
PP69400 Concreted Pouring 100% 7 02-Jun-23 A 28-Jul-23 CONSTRUCTION 2P11 68%
SGAR-10367 Supervision for equipment manufacture 150 09-Jan-23 A 9-Nov-23 PROCUREMENT 2P12 80%
SGAR-10368 FOB at loading port 20 17-Jun-23 A 29-Nov-23 PROCUREMENT 2P12 44%
CHA-P17881Supervision for equipment manufacture 90 08-Jan-23 A 14-Apr-23 A PROCUREMENT 2P12 100%
CHA-P17891FOB at loading port 30 14-Apr-23 A 18-May-23 A PROCUREMENT 2P12 100%
PP70762 Alumina storage body construction 40% 28 01-Apr-23 A 02-Jul-23 A CONSTRUCTION 2P12 100%
PP70763 Alumina storage body construction 60% 28 03-Jul-23 A 18-Aug-23 CONSTRUCTION 2P12 9%
SGAR-10387 Specification proposed by design 7 31-Oct-22 A 02-Jul-23 A PROCUREMENT 2P13 100%
SGAR-10388 Preparing and issuing tender document 10 09-Nov-22 A 02-Jul-23 A PROCUREMENT 2P13 100%
SGAR-10389 Bidding 42 19-Nov-22 A 05-Jul-23 A PROCUREMENT 2P13 100%
SGAR-10390 Bidding evaluation and declaring successful bidder 5 31-Dec-22 A 11-Apr-23 A PROCUREMENT 2P13 100%
SGAR-10391 Signing contract 9 08-Jan-23 A 20-May-23 A PROCUREMENT 2P13 100%
SGAR-10392 Document submission by manufacturer 9 08-Feb-23 A 20-Jun-23 A PROCUREMENT 2P13 100%
SGAR-10393 Supervision for equipment manufacture 100 22-Mar-23 A 07-Jul-23 A PROCUREMENT 2P13 100%
CHA-P18321Supervision for equipment manufacture 90 07-Mar-23 A 12-Jun-23 A PROCUREMENT 2P13 100%
CHA-P18422Purchasing Material by subcontractor 30 10-Apr-23 A 12-May-23 A PROCUREMENT 2P13 100%
CHA-P18431Supervision for equipment manufacture 60 12-May-23 A 14-Aug-23 PROCUREMENT 2P13 50%
CHA-P18972Purchasing Material by subcontractor 30 10-Apr-23 A 14-May-23 A PROCUREMENT 2P14 100%
CHA-P18981Supervision for equipment manufacture 90 14-May-23 A 12-Oct-23 PROCUREMENT 2P14 50%
CHA-P51431Supervision for equipment manufacture 52 10-Apr-23 A 27-Aug-23 PROCUREMENT 2P14 50%
CHA-P49521FOB at loading port 30 20-May-23 A 19-Jun-23 A PROCUREMENT 2P15(01 100%
CHA-P41701Preparing and issuing tendering document 12 23-Apr-23 A 10-May-23 A PROCUREMENT 2P15(01 100%
CHA-P41711Bidding 26 10-May-23 A 05-Jun-23 A PROCUREMENT 2P15(01 100%
CHA-P41721Bidding evaluation and declaring successful bidder 13 05-Jun-23 A 18-Jun-23 A PROCUREMENT 2P15(01 100%
CHA-P41731Signing contract 8 18-Jun-23 A 29-Jun-23 A PROCUREMENT 2P15(01 100%
CHA-P41741Document submission by manufacturer 10 29-Jun-23 A 07-Jul-23 A PROCUREMENT 2P15(01 100%
PP74700 Rebar Installation 100% 7 29-Jun-23 A 3-Sep-23 CONSTRUCTION 2P15(01 27%
CHA-P41811Preparing and issuing tendering document 11 24-Mar-23 A 18-Apr-23 A PROCUREMENT 2P15(04 100%
CHA-P41821Bidding 30 18-Apr-23 A 22-May-23 A PROCUREMENT 2P15(04 100%
CHA-P41831Bidding evaluation and declaring successful bidder 11 22-May-23 A 01-Jun-23 A PROCUREMENT 2P15(04 100%
CHA-P41841Signing contract 8 01-Jun-23 A 08-Jun-23 A PROCUREMENT 2P15(04 100%
CHA-P41851Document submission by manufacturer 8 08-Jun-23 A 15-Jun-23 A PROCUREMENT 2P15(04 100%
CHA-P41861Supervision for equipment manufacture 57 15-Jun-23 A 1-Sep-23 PROCUREMENT 2P15(04 10%
SGAR-10476 Specification proposed by design 7 07-May-23 A 13-May-23 A PROCUREMENT 2P16(01 100%
SGAR-10477 Preparing and issuing tender document 7 13-May-23 A 19-May-23 A PROCUREMENT 2P16(01 100%
SGAR-10478 Bidding 28 19-May-23 A 15-Jun-23 A PROCUREMENT 2P16(01 100%
SGAR-10479 Bidding evaluation and declaring successful bidder 2 15-Jun-23 A 16-Jun-23 A PROCUREMENT 2P16(01 100%
SGAR-10480 Signing contract 7 16-Jun-23 A 25-Jun-23 A PROCUREMENT 2P16(01 100%
SGAR-10481 Document submission by manufacturer 7 25-Jun-23 A 01-Jul-23 A PROCUREMENT 2P16(01 100%
PP77910 Pile Head Treatment 50% 9 02-Jul-23 A 03-Jul-23 A CONSTRUCTION 2P16(01 100%
PP77920 Pile Head Treatment 100% 10 03-Jul-23 A 04-Jul-23 A CONSTRUCTION 2P16(01 100%
PP77930 LC Pouring 6 04-Jul-23 A 05-Jul-23 A CONSTRUCTION 2P16(01 100%
PP77940 Rebar Fabrication 25% 9 03-Jul-23 A 19-Aug-23 CONSTRUCTION 2P16(01 22%
CHA-P47561Preparing and issuing tendering document 14 10-Apr-23 A 28-Apr-23 A PROCUREMENT 2P16-02 100%
CHA-P47571Bidding 22 28-Apr-23 A 24-May-23 A PROCUREMENT 2P16-02 100%
CHA-P47581Bidding evaluation and declaring successful bidder 15 24-May-23 A 07-Jun-23 A PROCUREMENT 2P16-02 100%
CHA-P47591Signing contract 10 07-Jun-23 A 16-Jun-23 A PROCUREMENT 2P16-02 100%
CHA-P47601Document submission by manufacturer 10 16-Jun-23 A 28-Jun-23 A PROCUREMENT 2P16-02 100%
CHA-P53861Supervision for equipment manufacture 108 10-Apr-23 A 29-Nov-23 PROCUREMENT 2P16-04 20%
CHA-P48051Supervision for equipment manufacture 116 06-Mar-23 A 07-Jul-23 A PROCUREMENT 2P16-05 100%
CHA-P49421Supervision for equipment manufacture 116 28-Feb-23 A 07-Jul-23 A PROCUREMENT 2P16-06 100%
CHA-P53951Supervision for equipment manufacture 75 21-Mar-23 A 10-Jun-23 A PROCUREMENT 2P16-08 100%
CHA-P48221Preparing and issuing tendering document 14 07-Apr-23 A 20-Apr-23 A PROCUREMENT 2P16-08 100%
CHA-P48231Bidding 22 20-Apr-23 A 16-May-23 A PROCUREMENT 2P16-08 100%
CHA-P48241Bidding evaluation and declaring successful bidder 15 16-May-23 A 30-May-23 A PROCUREMENT 2P16-08 100%
CHA-P48251Signing contract 10 30-May-23 A 08-Jun-23 A PROCUREMENT 2P16-08 100%
CHA-P48261Document submission by manufacturer 10 08-Jun-23 A 17-Jun-23 A PROCUREMENT 2P16-08 100%
SGAR-11634 Purchasing Material by subcontractor 30 10-Apr-23 A 14-May-23 A PROCUREMENT 2P17 100%
SGAR-11644 Supervision for equipment manufacture 88 14-May-23 A 24-Oct-23 PROCUREMENT 2P17 50%
SGAR-10514 Supervision for equipment manufacture 70 11-Feb-23 A 15-Jun-23 A PROCUREMENT 2U01 100%
SGAR-10515 FOB at loading port 20 16-Jun-23 A 3-Sep-23 PROCUREMENT 2U01 90%
CHA-P21072Purchasing Material by subcontractor 30 10-Apr-23 A 14-May-23 A PROCUREMENT 2U01 100%
CHA-P21081Supervision for equipment manufacture 90 14-May-23 A 12-Oct-23 PROCUREMENT 2U01 50%
CHA-P51722Purchasing Material by subcontractor 30 17-Jun-23 A 7-Jul-23 PROCUREMENT 2U01 90%
PP80570 Pile Head Treatment 100% 7 01-Jul-23 A 03-Jul-23 A CONSTRUCTION 2U01 100%
PP80610 Rebar Fabrication 75% 7 30-Jun-23 A 03-Jul-23 A CONSTRUCTION 2U01 100%
PP80620 Rebar Fabrication 100% 5 04-Jul-23 A 07-Jul-23 A CONSTRUCTION 2U01 100.00%
PP80630 Rebar Installation 50% 14 01-Jul-23 A 3-Aug-23 CONSTRUCTION 2U01 71%
CHA-P21622Purchasing Material by subcontractor 30 10-Apr-23 A 14-May-23 A PROCUREMENT 2U02 100%
CHA-P21631Supervision for equipment manufacture 112 14-May-23 A 11-Jan-24 PROCUREMENT 2U02 50%
SGAR-10570 Transportation and custom clearance 30 02-Jun-23 A 03-Jul-23 A PROCUREMENT 2U03 100%
SGAR-10571 Arrival at site 10 03-Jul-23 A 30-Aug-23 PROCUREMENT 2U03 20%
CHA-P21991Arrived at site 10 19-Apr-23 A 28-Apr-23 A PROCUREMENT 2U03 100%
CHA-P22001Unpacking and inspection 15 28-Apr-23 A 17-May-23 A PROCUREMENT 2U03 100%
CHA-P22172Purchasing Material by subcontractor 30 10-Apr-23 A 15-May-23 A PROCUREMENT 2U03 100%
CHA-P22181Supervision for equipment manufacture 90 15-May-23 A 12-Oct-23 PROCUREMENT 2U03 50%
CHA-P38731Preparing and issuing tendering document 13 16-Dec-22 A 19-Jan-23 A PROCUREMENT 2U03 100%
CHA-P38741Bidding 30 30-Dec-22 A 28-Feb-23 A PROCUREMENT 2U03 100%
CHA-P38751Bidding evaluation and declaring successful bidder 13 01-Mar-23 A 08-Mar-23 A PROCUREMENT 2U03 100%
CHA-P38761Signing contract 9 09-Mar-23 A 09-Mar-23 A PROCUREMENT 2U03 100%
CHA-P38791FOB at loading port 20 10-Jun-23 A 25-Nov-23 PROCUREMENT 2U03 6%
CHA-P51922Purchasing Material by subcontractor 30 18-Jun-23 A 5-Aug-23 PROCUREMENT 2U03 20%
CHA-P22731Supervision for equipment manufacture 114 10-Apr-23 A 7-Jul-23 PROCUREMENT 2U04 50%
CHA-P52022Purchasing Material by subcontractor 30 18-Jun-23 A 19-Sep-23 PROCUREMENT 2U04 20%
PP85080 Concreted Pouring 75% 8 26-May-23 A 03-Jul-23 A CONSTRUCTION 2U04 100%
PP85090 Concreted Pouring 100% 10 03-Jul-23 A 04-Jul-23 A CONSTRUCTION 2U04 100%
SGAR-10620 Supervision for equipment manufacture 112 19-Feb-23 A 01-Jul-23 A PROCUREMENT 2U05-01 100%
SGAR-10621 FOB at loading port 20 02-Jul-23 A 9-Sep-23 PROCUREMENT 2U05-01 50%
CHA-P54051Supervision for equipment manufacture 115 13-Feb-22 A 06-Jul-23 A PROCUREMENT 2U05-01 100%
CHA-P54142Purchasing Material by subcontractor 30 10-Apr-23 A 14-May-23 A PROCUREMENT 2U05-01 100%
CHA-P54151Supervision for equipment manufacture 116 14-May-23 A 22-Dec-23 PROCUREMENT 2U05-01 50%
CHA-P52122Purchasing Material by subcontractor 30 17-Jun-23 A 19-Sep-23 PROCUREMENT 2U05-01 90%
CHA-P55251Supervision for equipment manufacture 116 07-Jun-23 A 7-Nov-23 PROCUREMENT 2U05-02 50%
CHA-P55042Purchasing Material by subcontractor 30 17-Jun-23 A 5-Aug-23 PROCUREMENT 2U05-02 20%
SGAR-12214 FOB at loading port 20 11-Feb-23 A 14-Dec-23 PROCUREMENT 2U05-04 45.71%
CHA-P55651Supervision for equipment manufacture 90 10-Apr-23 A 26-Nov-23 PROCUREMENT 2U05-04 50%
CHA-P55442Purchasing Material by subcontractor 30 17-Jun-23 A 5-Aug-23 PROCUREMENT 2U05-04 60%
PP155000 Rebar Installation 100% 6 20-Jun-23 A 2-Oct-23 CONSTRUCTION 2U05-04 82%
CHA-P56042Purchasing Material by subcontractor 30 10-Apr-23 A 18-May-23 A PROCUREMENT 2U05-05 100%
CHA-P56051Supervision for equipment manufacture 90 18-May-23 A 17-Dec-23 PROCUREMENT 2U05-05 50%
CHA-P55851Supervision for equipment manufacture 55 17-Jun-23 A 4-Sep-23 PROCUREMENT 2U05-05 20%
SGAR-12321 Supervision for equipment manufacture 115 23-Aug-22 A 06-May-23 A PROCUREMENT 2U05-06 100%
SGAR-12322 FOB at loading port 30 06-May-23 A 06-Jul-23 A PROCUREMENT 2U05-06 100%
SGAR-12323 Transportation and custom clearance 30 06-Jul-23 A 5-Aug-23 PROCUREMENT 2U05-06 10%
CHA-P56451Supervision for equipment manufacture 116 14-May-23 A 7-Nov-23 PROCUREMENT 2U05-06 50%
CHA-P56501Preparing and issuing tendering document 7 07-Mar-23 A 13-Mar-23 A PROCUREMENT 2U05-06 100%
CHA-P56511Bidding 26 13-Mar-23 A 08-Apr-23 A PROCUREMENT 2U05-06 100%
CHA-P56521Bidding evaluation and declaring successful bidder 14 08-Apr-23 A 21-Apr-23 A PROCUREMENT 2U05-06 100%
CHA-P56531Signing contract 10 21-Apr-23 A 05-May-23 A PROCUREMENT 2U05-06 100%
CHA-P56541Document submission by manufacturer 9 05-May-23 A 13-May-23 A PROCUREMENT 2U05-06 100%
CHA-P56542Purchasing Material by subcontractor 30 13-May-23 A 11-Jun-23 A PROCUREMENT 2U05-06 100%
SGAR-12375 Supervision for equipment manufacture 115 23-Aug-22 A 06-Mar-23 A PROCUREMENT 2U05-07 100%
SGAR-12376 FOB at loading port 30 06-Mar-23 A 04-Apr-23 A PROCUREMENT 2U05-07 100%
SGAR-12377 Transportation and custom clearance 30 04-Apr-23 A 09-May-23 A PROCUREMENT 2U05-07 100%
SGAR-12378 Arrival at site 13 09-May-23 A 21-May-23 A PROCUREMENT 2U05-07 100%
CHA-P56761FOB at loading port 30 20-Jun-23 A 19-Aug-23 PROCUREMENT 2U05-07 50%
CHA-P56842Purchasing Material by subcontractor 30 10-Apr-23 A 20-May-23 A PROCUREMENT 2U05-07 100%
CHA-P56851Supervision for equipment manufacture 90 20-May-23 A 27-Nov-23 PROCUREMENT 2U05-07 50%
CHA-P56951Supervision for equipment manufacture 116 01-Apr-23 A 7-Jul-23 PROCUREMENT 2U05-07 80%
SGAR-12440 Unpacking and inspection 15 11-Jun-24 A 19-Jan-24 PROCUREMENT 2U05-08 27.18%
CHA-P57151Supervision for equipment manufacture 115 18-Oct-22 A 06-May-23 A PROCUREMENT 2U05-08 100%
CHA-P57161FOB at loading port 30 06-May-23 A 04-Jun-23 A PROCUREMENT 2U05-08 100%
CHA-P57251Supervision for equipment manufacture 116 14-Apr-23 A 4-Feb-24 PROCUREMENT 2U05-08 50%
CHA-P57042Purchasing Material by subcontractor 5 17-Jun-23 A 21-Jun-23 A PROCUREMENT 2U05-08 100%
CHA-P27131Supervision for equipment manufacture 60 10-May-23 A 18-Sep-23 PROCUREMENT 2U06 50%
PP89330 Rebar Fabrication 50% 9 25-May-23 A 04-Jul-23 A CONSTRUCTION 2U06 100.00%
PP89340 Rebar Fabrication 75% 10 05-Jul-23 A 30-Aug-23 CONSTRUCTION 2U06 13.70%
PP89360 Rebar Installation 50% 10 08-Jun-23 A 21-Aug-23 CONSTRUCTION 2U06 55%
SGAR-10672 Supervision for equipment manufacture 112 18-Aug-21 A 03-Jul-23 A PROCUREMENT 2U07 100%
CHA-P27461Supervision for equipment manufacture 118 13-Mar-23 A 07-Jul-23 A PROCUREMENT 2U07 100%
CHA-P39721Preparing and issuing tendering document 13 07-Apr-23 A 19-Apr-23 A PROCUREMENT 2U07 100%
CHA-P39731Bidding 28 19-Apr-23 A 21-May-23 A PROCUREMENT 2U07 100%
CHA-P39741Bidding evaluation and declaring successful bidder 13 21-May-23 A 02-Jun-23 A PROCUREMENT 2U07 100%
CHA-P39751Signing contract 9 02-Jun-23 A 10-Jun-23 A PROCUREMENT 2U07 100%
CHA-P39761Document submission by manufacturer 9 10-Jun-23 A 18-Jun-23 A PROCUREMENT 2U07 100%
CHA-P39771Supervision for equipment manufacture 118 18-Jun-23 A 9-Nov-23 PROCUREMENT 2U07 10%
CHA-P27681Supervision for equipment manufacture 118 18-Apr-23 A 19-Jan-24 PROCUREMENT 2U07 50%
CHA-P52331Supervision for equipment manufacture 120 22-May-23 A 25-Nov-23 PROCUREMENT 2U07 20%
PP90710 Rebar Fabrication 100% 7 23-Jun-23 A 27-Aug-23 CONSTRUCTION 2U07 41%
PP90720 Rebar Installation 50% 14 10-Jun-23 A 25-Sep-23 CONSTRUCTION 2U07 71%
PP90740 Concreted Pouring 25% 10 05-Jul-23 A 6-Oct-23 CONSTRUCTION 2U07 90%
SGAR-10706 FOB at loading port 30 20-May-23 A 03-Jul-23 A PROCUREMENT 2U08 100%
CHA-P28021FOB at loading port 30 05-Jun-23 A 12-Oct-23 PROCUREMENT 2U08 73%
CHA-P39881Supervision for equipment manufacture 90 10-Mar-23 A 12-Jun-23 A PROCUREMENT 2U08 100%
CHA-P52422Purchasing Material by subcontractor 30 18-Jun-23 A 5-Aug-23 PROCUREMENT 2U08 20%
CHA-P40101Supervision for equipment manufacture 90 06-Mar-23 A 26-Jun-23 A PROCUREMENT 2U09-02 100%
CHA-P29011FOB at loading port 20 30-Jun-23 A 9-Sep-23 PROCUREMENT 2U09-02 20%
CHA-P29221Supervision for equipment manufacture 115 10-Apr-23 A 7-Jul-23 PROCUREMENT 2U09-03 50%
CHA-P29331Supervision for equipment manufacture 90 19-Jun-23 A 12-Oct-23 PROCUREMENT 2U09-03 15%
SGAR-10751 Document submission by manufacturer 7 10-Mar-23 A 22-Jul-23 PROCUREMENT 2U10 16.67%
SGAR-10752 Supervision for equipment manufacture 90 02-May-23 A 21-Oct-23 PROCUREMENT 2U10 16.67%
SGAR-10753 FOB at loading port 30 22-Jun-23 A 20-Nov-23 PROCUREMENT 2U10 16.67%
SGAR-10754 Transportation and custom clearance 30 07-Jul-23 A 20-Dec-23 PROCUREMENT 2U10 17%
CHA-P52631Supervision for equipment manufacture 90 15-Jun-23 A 12-Oct-23 PROCUREMENT 2U10 20%
CHA-P43281Supervision for equipment manufacture 90 10-Apr-23 A 22-Oct-23 PROCUREMENT 2U11 50%
CHA-P43331Preparing and issuing tendering document 14 07-Apr-23 A 20-Apr-23 A PROCUREMENT 2U11 100%
CHA-P43341Bidding 29 20-Apr-23 A 23-May-23 A PROCUREMENT 2U11 100%
CHA-P43351Bidding evaluation and declaring successful bidder 11 23-May-23 A 02-Jun-23 A PROCUREMENT 2U11 100%
CHA-P43361Signing contract 9 02-Jun-23 A 10-Jun-23 A PROCUREMENT 2U11 100%
CHA-P43371Document submission by manufacturer 10 10-Jun-23 A 19-Jun-23 A PROCUREMENT 2U11 100%
CHA-P52731Supervision for equipment manufacture 58 18-Jun-23 A 2-Sep-23 PROCUREMENT 2U11 20%
SGAR-10818 Supervision for equipment manufacture 122 09-Jan-23 A 13-Nov-23 PROCUREMENT 2U14 33.89%
SGAR-10820 Transportation and custom clearance 30 14-Jun-23 A 13-Jan-24 PROCUREMENT 2U14 34%
CHA-P30101Supervision for equipment manufacture 90 10-Apr-23 A 12-Oct-23 PROCUREMENT 2U14 50%
CHA-P52831Supervision for equipment manufacture 90 13-Jun-23 A 26-Nov-23 PROCUREMENT 2U14 20%
SGAR-10841 Supervision for equipment manufacture 122 18-Feb-23 A 25-Jun-23 A PROCUREMENT 2U15 100%
SGAR-10842 FOB at loading port 30 25-Jun-23 A 7-Jul-23 PROCUREMENT 2U15 100%
SGAR-10843 Transportation and custom clearance 30 07-Jul-23 A 5-Aug-23 PROCUREMENT 2U15 98%
CHA-P30431Supervision for equipment manufacture 111 10-Apr-23 A 7-Jul-23 PROCUREMENT 2U15 100%
CHA-P52931Supervision for equipment manufacture 54 18-Jun-23 A 29-Aug-23 PROCUREMENT 2U15 20%
SGAR-10864 Supervision for equipment manufacture 116 20-Feb-23 A 8-Jan-24 PROCUREMENT 2U16 32.19%
CHA-P30761Supervision for equipment manufacture 112 10-Apr-23 A 06-Jul-23 A PROCUREMENT 2U16 100%
CHA-P30771FOB at loading port 30 06-Jul-23 A 5-Aug-23 PROCUREMENT 2U16 20%
CHA-P54351Supervision for equipment manufacture 113 10-Apr-23 A 7-Jul-23 PROCUREMENT 2G01 100%
CHA-P54551Supervision for equipment manufacture 90 14-Apr-23 A 07-Jul-23 A PROCUREMENT 2G01 100%
CHA-P53131Supervision for equipment manufacture 55 17-Jun-23 A 30-Aug-23 PROCUREMENT 2G01 20%
SGAR-10898aSteel structure and main equipment installation of each layer 28 14-Jun-23 A 27-Aug-23 CONSTRUCTION 2G01 95%
CHA-P31701Supervision for equipment manufacture 135 15-Mar-23 A 21-Jul-23 PROCUREMENT 2G01-01 100%
PP142970 Rebar Fabrication 100% 15 22-Jun-23 A 22-Jul-23 CONSTRUCTION 2G01-01 46%
PP142990 Rebar Installation 100% 15 31-May-23 A 4-Sep-23 CONSTRUCTION 2G01-01 73.20%
PP143000 Concreted Pouring 25% 15 20-Jun-23 A 02-Jul-23 A CONSTRUCTION 2G01-01 100.00%
PP143010 Concreted Pouring 50% 15 03-Jul-23 A 04-Jul-23 A CONSTRUCTION 2G01-01 100%
PP143020 Concreted Pouring 75% 15 05-Jul-23 A 19-Sep-23 CONSTRUCTION 2G01-01 74%
CHA-P32431FOB at loading port 20 09-Jun-23 A 07-Jul-23 A PROCUREMENT 2G01-02 100%
CHA-P32531Supervision for equipment manufacture 90 13-May-23 A 07-Jul-23 A PROCUREMENT 2G01-02 100%
CHA-P32751Supervision for equipment manufacture 118 10-Apr-23 A 07-Jul-23 A PROCUREMENT 2G01-02 100%
SGAR-10922 Supervision for equipment manufacture 90 17-Jan-23 A 9-Nov-23 PROCUREMENT 2G02-01 85.56%
SGAR-10923 FOB at loading port 20 02-May-23 A 29-Nov-23 PROCUREMENT 2G02-01 50%
CHA-P54651Supervision for equipment manufacture 120 10-Apr-23 A 21-Aug-23 PROCUREMENT 2G02-01 50%
CHA-P54851Supervision for equipment manufacture 120 28-Jan-23 A 16-Jun-23 A PROCUREMENT 2G02-01 100%
CHA-P54751Supervision for equipment manufacture 117 21-Feb-23 A 20-Jun-23 A PROCUREMENT 2G02-01 100%
CHA-P53231Supervision for equipment manufacture 54 12-Apr-23 A 15-Jun-23 A PROCUREMENT 2G02-01 100%
CHA-P48791Supervision for equipment manufacture 90 27-Feb-23 A 12-Jun-23 A PROCUREMENT 2G02-02 100%
CHA-P53511Supervision for equipment manufacture 120 07-Mar-23 A 07-Jul-23 A PROCUREMENT 2G02-02 100%
CHA-P53521FOB at loading port 30 07-Jul-23 A 5-Aug-23 PROCUREMENT 2G02-02 5%
SGAR-10949 Supervision for equipment manufacture 100 02-Dec-22 A 18-Sep-23 PROCUREMENT 2G03 93.58%
CHA-P42201FOB at loading port 30 25-Apr-23 A 28-May-23 A PROCUREMENT 2G03 100%
CHA-P42211Transportation and custom clearance 30 28-May-23 A 29-Jun-23 A PROCUREMENT 2G03 100%
CHA-P42221Arrived at site 10 29-Jun-23 A 07-Jul-23 A PROCUREMENT 2G03 100%
CHA-P33851Supervision for equipment manufacture 55 10-Apr-23 A 13-Jun-23 A PROCUREMENT 2G03 100%
CHA-P33861FOB at loading port 30 13-Jun-23 A 19-Aug-23 PROCUREMENT 2G03 2%
CHA-P53331Supervision for equipment manufacture 54 14-Jun-23 A 4-Nov-23 PROCUREMENT 2G03 10%
SGAR-10980 Supervision for equipment manufacture 113 26-Feb-23 A 18-Nov-23 PROCUREMENT 2G04 70%
CHA-P34401Supervision for equipment manufacture 90 08-Jan-23 A 26-Jun-23 A PROCUREMENT 2G04 100%
CHA-P34411FOB at loading port 30 26-Jun-23 A 21-Jul-23 PROCUREMENT 2G04 100%
CHA-P53431Supervision for equipment manufacture 60 13-Jun-23 A 5-Nov-23 PROCUREMENT 2G04 20%
SGAR-11754 Supervision for equipment manufacture 90 10-Apr-23 A 07-Jul-23 A PROCUREMENT 2G07 100%
CHA-P36161Supervision for equipment manufacture 100 01-Mar-23 A 01-Jul-23 A PROCUREMENT 2G07 100%
CHA-P53731Supervision for equipment manufacture 54 14-Jun-23 A 12-Sep-23 PROCUREMENT 2G07 20%
SGAR-11037 Supervision for equipment manufacture 77 18-Mar-21 A 11-Dec-23 PROCUREMENT 2D01 99.79%
CHA-P44231Preparing and issuing tendering document 16 26-Apr-22 A 13-Jul-23 PROCUREMENT 2D01 93.40%
CHA-P44241Bidding 29 16-May-22 A 11-Aug-23 PROCUREMENT 2D01 93.40%
CHA-P44251Bidding evaluation and declaring successful bidder 12 05-Jun-22 A 18-Aug-23 PROCUREMENT 2D01 93.40%
CHA-P44271Supervision for equipment manufacture 106 11-Sep-22 A 24-Nov-23 PROCUREMENT 2D01 35%
SGAR-11101 Hoisting of steel structure of main plant building and construc 14 24-Jun-23 A 3-Aug-23 CONSTRUCTION 2D01 77%
SGAR-11136 Arrival at site 24 12-Jun-23 A 5-Jan-24 PROCUREMENT 2D02 24.00%
SGAR-11137 Unpacking and inspection 15 07-Jul-23 A 20-Jan-24 PROCUREMENT 2D02 24%
CHA-P44561Supervision for equipment manufacture 106 30-Jan-23 A 29-Dec-23 PROCUREMENT 2D02 26.19%
CHA-P44571FOB at loading port 30 30-Jun-23 A 29-Jan-24 PROCUREMENT 2D02 4%
PP111070 Rebar Fabrication 50% 14 28-May-23 A 19-Aug-23 CONSTRUCTION 2D02 75.70%
PP111110 Rebar Installation 50% 7 07-Jun-23 A 13-Sep-23 CONSTRUCTION 2D02 73.70%
CHA-P44721Preparing and issuing tendering document 12 27-Feb-23 A 4-Sep-23 PROCUREMENT 2D03 5%
CHA-P44731Bidding 22 14-Mar-23 A 19-Sep-23 PROCUREMENT 2D03 5%
CHA-P44741Bidding evaluation and declaring successful bidder 7 26-Apr-23 A 26-Sep-23 PROCUREMENT 2D03 5%
CHA-P44761Supervision for equipment manufacture 70 11-Jun-23 A 13-Dec-23 PROCUREMENT 2D03 5%
SGAR-11184 Supervision for equipment manufacture 131 21-Mar-23 A 07-Jul-23 A PROCUREMENT 2D04 100%
CHA-P44821Preparing and issuing tendering document 7 18-Jan-23 A 24-Jan-23 A PROCUREMENT 2D04 100%
CHA-P44831Bidding 25 24-Jan-23 A 18-Feb-23 A PROCUREMENT 2D04 100%
CHA-P44841Bidding evaluation and declaring successful bidder 7 18-Feb-23 A 24-Feb-23 A PROCUREMENT 2D04 100%
CHA-P44851Signing contract 9 24-Feb-23 A 07-Mar-23 A PROCUREMENT 2D04 100%
CHA-P44861Document submission by manufacturer 10 07-Mar-23 A 16-Mar-23 A PROCUREMENT 2D04 100%
CHA-P44871Supervision for equipment manufacture 82 16-Mar-23 A 09-Jun-23 A PROCUREMENT 2D04 100%
CHA-P44881FOB at loading port 10 09-Jun-23 A 18-Jun-23 A PROCUREMENT 2D04 100%
CHA-P44891Transportation and custom clearance 10 18-Jun-23 A 30-Jun-23 A PROCUREMENT 2D04 100%
CHA-P45031Preparing and issuing tendering document 10 27-Feb-23 A 11-Aug-23 PROCUREMENT 2D04 15.71%
CHA-P45041Bidding 28 14-Mar-23 A 1-Sep-23 PROCUREMENT 2D04 15.71%
CHA-P45051Bidding evaluation and declaring successful bidder 13 03-Apr-23 A 13-Sep-23 PROCUREMENT 2D04 15.71%
CHA-P45061Signing contract 6 21-May-23 A 19-Sep-23 PROCUREMENT 2D04 15.71%
CHA-P45071Supervision for equipment manufacture 74 27-Jun-23 A 10-Dec-23 PROCUREMENT 2D04 5%
PP152130 Calculation 30 19-Jun-23 A 07-Jul-23 A ENGINEERING 2D05 100%
CHA-P45211Arrived at site 10 10-Jun-23 A 20-Jun-23 A PROCUREMENT 2D05 100%
CHA-P45221Unpacking and inspection 15 20-Jun-23 A 07-Jul-23 A PROCUREMENT 2D05 100%
CHA-P45381Supervision for equipment manufacture 110 26-Apr-23 A 1-Nov-23 PROCUREMENT 2D05 50%
CHA-P42691Preparing and issuing tendering document 10 17-Apr-23 A 27-Apr-23 A PROCUREMENT 2D05 100%
CHA-P42701Bidding 22 27-Apr-23 A 24-May-23 A PROCUREMENT 2D05 100%
CHA-P42711Bidding evaluation and declaring successful bidder 7 24-May-23 A 31-May-23 A PROCUREMENT 2D05 100%
CHA-P42721Signing contract 10 31-May-23 A 10-Jun-23 A PROCUREMENT 2D05 100%
CHA-P42731Document submission by manufacturer 10 10-Jun-23 A 20-Jun-23 A PROCUREMENT 2D05 100%
CHA-P45431Preparing and issuing tendering document 14 01-Mar-23 A 27-Sep-23 PROCUREMENT 2D05 78.97%
CHA-P45441Bidding 20 15-Mar-23 A 25-Oct-23 PROCUREMENT 2D05 78.97%
CHA-P45451Bidding evaluation and declaring successful bidder 15 03-Apr-23 A 9-Nov-23 PROCUREMENT 2D05 78.97%
CHA-P45461Signing contract 10 15-Apr-23 A 19-Nov-23 PROCUREMENT 2D05 78.97%
CHA-P45471Supervision for equipment manufacture 54 27-Jun-23 A 13-Jan-24 PROCUREMENT 2D05 16.57%
CHA-P45481FOB at loading port 20 30-Jun-23 A 2-Feb-24 PROCUREMENT 2D05 16.57%
CHA-P41011Arrived at site 10 30-Jun-23 A 14-Sep-23 PROCUREMENT 2D07 97%
CHA-P41021Unpacking and inspection 15 02-Jul-23 A 7-Oct-23 PROCUREMENT 2D07 97%
CHA-P45801Transportation and custom clearance 30 03-Jun-23 A 05-Jul-23 A PROCUREMENT 2D07 100%
CHA-P42591Bidding 25 06-Jun-23 A 06-Jul-23 A PROCUREMENT 2D07 100%
CHA-P45931Bidding 27 03-Apr-23 A 14-Aug-23 PROCUREMENT 2D07 47.61%
CHA-P45941Bidding evaluation and declaring successful bidder 7 15-May-23 A 21-Aug-23 PROCUREMENT 2D07 47.61%
CHA-P45951Signing contract 9 22-Jun-23 A 30-Aug-23 PROCUREMENT 2D07 47.61%
CHA-P45961Supervision for equipment manufacture 80 07-Jul-23 A 26-Nov-23 PROCUREMENT 2D07 7%
PP113820 Calculation 28 17-Jun-23 A 07-Jul-23 A ENGINEERING 2D08 100%
SGAR-11263 Supervision for equipment manufacture 111 30-Nov-22 A 17-Oct-23 PROCUREMENT 2D08 99.46%
SGAR-11264 FOB at loading port 20 20-Mar-23 A 6-Nov-23 PROCUREMENT 2D08 98.92%
CHA-P46371Supervision for equipment manufacture 100 25-Apr-22 A 5-Nov-23 PROCUREMENT 2D08 50%
CHA-P42811Bidding 7 02-Jun-23 A 08-Jun-23 A PROCUREMENT 2D08 100%
CHA-P42821Bidding evaluation and declaring successful bidder 14 08-Jun-23 A 21-Jun-23 A PROCUREMENT 2D08 100%
CHA-P42831Signing contract 10 21-Jun-23 A 03-Jul-23 A PROCUREMENT 2D08 100%
CHA-P57541Supervision for equipment manufacture 108 25-Apr-22 A 12-Oct-23 PROCUREMENT 2D08 50%
PP115800 Rebar Fabrication 50% 3 29-Jun-23 A 04-Jul-23 A CONSTRUCTION 2D09 100.00%
PP115810 Rebar Fabrication 75% 7 05-Jul-23 A 13-Jul-23 CONSTRUCTION 2D09 8.50%
PP115830 Rebar Installation 50% 6 09-Jul-23 A 12-Jul-23 CONSTRUCTION 2D09 86%