ID Task Name Duration Start Finish Cost Sep '24 Oct '24 Nov '24 Dec '24 Jan
'24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21
1 CONSTRUCTION OF 127 days 16 Oct 10 Apr ₱31,991,738.61
DRAINAGE SYSTEM IN
AMLAC VILLE PAYATAS
B QUEZON CITY
2 Permits 30 days 16 Oct 26 Nov ₱5,345.37
3 Permits and 30 days 16 Oct 26 Nov ₱5,345.37
Clearances
4 Temporary Facilities 12 days 27 Nov 12 Dec ₱16,416.39
5 Temfacil 12 days 27 Nov 12 Dec ₱16,416.39
6 FACILITIES FOR THE 30 days 13 Dec 23 Jan ₱155,037.87
ENGINEERS
7 Provision of Field 30 days 13 Dec 23 Jan ₱155,037.87
Office for the
Engineer (Rental
8 Basis)GENERAL
OTHER 30 days 13 Dec 23 Jan ₱228,700.31
REQUIREMENTS
9 Project Billboard / 5 days 13 Dec 19 Dec ₱6,948.78
Signboard
10 Site Preparation 6 days 13 Dec 20 Dec ₱27,360.56
11 Occupational 30 days 13 Dec 23 Jan ₱114,217.86
Safety and Health
12 Program
Traffic Management30 days 13 Dec 23 Jan ₱41,236.09
13 Mobilization and 30 days 13 Dec 23 Jan ₱38,937.02
Demobilization
14 EARTHWORKS 9 days 24 Jan 05 Feb ₱2,900,084.40
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Raw
Summary Manual Summary Rollup Progress
Date: 17 Oct
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
ID Task Name Duration Start Finish Cost Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21
15 Clearing and Grubbing 2 days 24 Jan 27 Jan ₱889,883.71
16 Structure 4 days 24 Jan 29 Jan ₱1,301,144.48
Excavation,
17 Common of
Removal Soil
Actual 5 days 24 Jan 30 Jan ₱8,097.04
Structures/Obstruction
0.15 m thick PCCP
(Unreinforced)
18 Removal of Actual 5 days 24 Jan 30 Jan ₱155,615.84
Structures/Obstruction
0.10 m thick,
19 Sidewalk
Removal of Actual 5 days 24 Jan 30 Jan ₱535,271.23
Structures/Obstruction,
610 mm dia. RCPC
20 Subgrade 4 days 31 Jan 05 Feb ₱10,072.10
Preparation,
21 Common
SUBBASE Material
AND BASE 2 days 31 Jan 03 Feb ₱14,859.96
COURSE
22 Aggregate Subbase 2 days 31 Jan 03 Feb ₱14,859.96
Course
23 INSTALLATION PHASE 44 days 04 Feb 04 Apr ₱9,717,633.83
24 Installing of Box 44 days 04 Feb 04 Apr ₱9,339,817.40
Culvert
25 Installing of Manholes2 days 04 Feb 05 Feb ₱32,508.54
26 Installing of Sidewalk3 days 04 Feb 06 Feb ₱278,105.56
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Raw
Summary Manual Summary Rollup Progress
Date: 17 Oct
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
ID Task Name Duration Start Finish Cost Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21
27 Curb and Gutter 3 days 04 Feb 06 Feb ₱67,202.33
28 SUBBASE COURSES 2 days 16 Oct 17 Oct ₱1,917.28
29 Portland Cement 2 days ₱1,917.28
Concrete
Pavement
30 (Unreinforced)
EARTHWORKS 5 days 24 Jan 30 Jan ₱2,354,741.07
31 Clearing and Grubbing
2 days 24 Jan 27 Jan ₱889,883.71
32 Structure 4 days 24 Jan 29 Jan ₱1,301,144.48
Excavation,
33 Common of
Removal Soil
Actual 5 days 24 Jan 30 Jan ₱8,097.04
Structures/Obstruction
0.15 m thick PCCP
(Unreinforced)
34 Removal of Actual 5 days 24 Jan 30 Jan ₱155,615.84
Structures/Obstruction
0.10 m thick,
35 Sidewalk
Removal of Actual 9 days 24 Jan 05 Feb ₱545,343.33
Structures/Obstruction,
610 mm dia. RCPC
36 Removal of Actual 5 days 24 Jan 30 Jan ₱535,271.23
Structures/Obstruction,
610 mm dia. RCPC
37 Subgrade 4 days 31 Jan 05 Feb ₱10,072.10
Preparation,
Common Material
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Raw
Summary Manual Summary Rollup Progress
Date: 17 Oct
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3
ID Task Name Duration Start Finish Cost Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21
38 SUBBASE AND BASE 2 days 06 Feb 07 Feb ₱14,859.96
COURSE
39 Aggregate Subbase Course
2 days 06 Feb 07 Feb ₱14,859.96
40 INSTALLATION PHASE 44 days 06 Feb 08 Apr ₱9,717,633.83
41 Installing of Box 44 days 06 Feb 08 Apr ₱9,339,817.40
Culvert
42 Installing of Manholes2 days 06 Feb 07 Feb ₱32,508.54
43 Installing of Sidewalk3 days 06 Feb 10 Feb ₱278,105.56
44 Curb and Gutter 3 days 06 Feb 10 Feb ₱67,202.33
45 SUBBASE COURSES 2 days 09 Apr 10 Apr ₱1,917.28
46 Portland Cement 2 days 09 Apr 10 Apr ₱1,917.28
Concrete
Pavement
(Unreinforced)
47 0.20 m thick
EARTHWORKS 5 days 24 Jan 30 Jan ₱1,450,042.20
48 Clearing and Grubbing 1 day 24 Jan 24 Jan ₱444,941.85
49 Structure 2 days 24 Jan 27 Jan ₱650,572.24
Excavation,
50 Common
Removal of Soil
Actual 3 days 24 Jan 28 Jan ₱4,048.52
Structures/Obstruction
0.15 m thick PCCP
(Unreinforced)
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Raw
Summary Manual Summary Rollup Progress
Date: 17 Oct
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 4
ID Task Name Duration Start Finish Cost Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21
51 Removal of Actual 3 days 24 Jan 28 Jan ₱77,807.92
Structures/Obstruction
0.10 m thick,
52 Sidewalk of Actual 3 days
Removal 24 Jan 28 Jan ₱267,635.62
Structures/Obstruction,
610 mm dia. RCPC
53 Subgrade 2 days 29 Jan 30 Jan ₱5,036.05
Preparation,
54 Common
SUBBASE Material
AND BASE 1 day 31 Jan 31 Jan ₱7,429.98
COURSE
55 Aggregate Subbase Course
1 day 31 Jan 31 Jan ₱7,429.98
56 INSTALLATION PHASE 22 days 31 Jan 03 Mar ₱4,858,816.91
57 Installing of Box Culvert
22 days 31 Jan 03 Mar ₱4,669,908.70
58 Installing of Manholes1 day 31 Jan 31 Jan ₱16,254.27
59 Installing of Sidewalk2 days 31 Jan 03 Feb ₱139,052.78
60 Curb and Gutter 2 days 31 Jan 03 Feb ₱33,601.16
61 SUBBASE COURSES 1 day 04 Mar 04 Mar ₱958.64
62 Portland Cement 1 day 04 Mar 04 Mar ₱958.64
Concrete
Pavement
(Unreinforced)
0.20 m thick
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Raw
Summary Manual Summary Rollup Progress
Date: 17 Oct
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 5