PGDISM Project Work.
PGDISM Project Work.
INDEX
S.NO ITEM DESCRIPTION
1 Index
2 L&T Ltd EOHS Policy
Golden Safety Rules.
3 Project Highlights
4 Organization Chart and Responsibilities/Authority
5 Responsibility matrix
6 EHS Objectives & Targets
7 Responsibilities of Project team
8 Environmental Management System
9 Improvement Measures
10 Welfare and First aid facility
11 Safety Management System
12 EOHS Competence.
13 EOHS Committee, Meeting & Communication
14 Operational Control Procedures
1 Excavation
2 Scaffold Formwork systems
3 Electrical
4 Earth Moving Equipment’s
5 Pneumatic Tools
Page 2 of 89
6 Hand Power Tools
7 Lock Out – Tag Pout
8 Concrete Work
9 Dust control
10 Handling and Storage of gas cylinders
11 Transportation
12 Waste Management System
13 Handling and Storage of Building materials
14 Stacking & Piling
15 Storage & handling
16 Housekeeping
17 Batching Plant
18 Welding and Gas cutting works
19 Height Work
20 Machine & Equipment’s
21 Confined Space
22 Demolition
23 DG Operation
24 Flammable Materials
25 Personnel Protective Equipment
15 Emergency Preparedness Procedure
16 Hazard Identification & Risk Assessment
17 Hierarchy of Controls
18 Work Permits & Check Lists
19 Recommendations
20 Observation Table
Page 3 of 89
21 Conclusions
20 Reference’s
Page 4 of 89
Page 5 of 89
Page 6 of 89
Page 7 of 89
Page 8 of 89
Page 9 of 89
Project Description
Delhi–Meerut Regional Rapid Transit System (Delhi–Meerut RRTS).
Salient Features of the Project: Construction of elevated viaduct from end of Shatabdi Nagar
Station to Brahmpuri DN ramp and from Begumpul UP Ramp to Modi Puram end including Modi
Puram Depot entry Ramp and 5 elevated stations of Delhi – Ghaziabad – Meerut RRTS Corridor.
Page 10 of 89
EOHS - Organization Chart for RRTS PACKAGE–07
I Responsibility & Accountability Matrix for EOHS function:
EOHS Activity
Responsibility
Identifying & Posting EOHS officer to the
Mr. Radha Kant Sharma
concerned site
Provide required EOHS resources to site as
per their requirement. Project Manager
Promotional programs like safety awards, Mr. Radha Kant Sharma. / Mr. Sanjay Singh
incentives etc. Gangwar
Organize training on EOHS for site staff. Head (T & D)/ Mr. Radha Kant Sharma
Note: Taking guidelines from above objectives, site specific objectives & Targets can be prepared.
Time duration, responsibilities & action plan will be defined by the project in charge.
EOHS OBJECTIVES & TARGETS -
1.1 Responsible for establishing and administrating EOHS function at Project Site.
1.2 Ensure that the EOHS objective & program become an integral part of project planning,
incorporated in all operations.
1.3 Responsible for providing necessary resources for implementing EOHS system.
1.4 Chair EOHS Committee meeting.
4. 0 EOHS Officer:
4.1 The EOHS Officer shall guide / assist the site in charge & support to execution team in
respect of prevention of personnel injuries, maintaining a safe working environment & in
discharge of statutory obligations. Followings are duties of EOHS Officer:
1. NOISE POLLUTION:
Noise Control:
a. The noise generation level shall not be allowed for more than prescribed limits.
b. Stationary equipment shall be located in such a way that noise levels generated have least or
nil impact on the community.
c. Necessary silencers / mufflers shall be provided on construction equipment, which shall be
properly fitted and maintained.
d. DG shall be enclosed by acoustics in order to reduce noise levels.
e. Noise and Air monitoring to be done once in a month
2 Allowable Noise Emission Levels:
The maximum allowable construction noise levels expose to public is 90 dB (A) or peak sound
pressure level is 140 dB (A) as per the standard. This requirement shall be taken care while
purchasing of such equipment and machineries.
Where there are no ambient noise measurements, construction activities shall be limited to levels
measured at a distance of 200 Feet or at the nearest affected building whichever is closer, as
given in table below.
3.1 Ensure that sufficient lighting of the right type and at the right place is provided at all
locations.
3.2 Selection of Luminaries shall be as per the area requirement indicated below:
3.3 Ensure that LED luminaries are placed properly so that no person is required to work in dark
areas. Clamps should be used for attaching luminaries to poles and other convenient
supports.
3.4 All LED luminaries should be robust, resistant to corrosion and rain proof especially at the
point of the cable entry. The correct type of lamp for each LED luminary should always be
used and when lamps need to be replaced it shall be in accordance with the supply voltage.
Employee welfare means “the efforts to make life worth living for workmen.” According to Todd
“employee welfare means anything done for the comfort and improvement, intellectual or social, of the
employees over and above the wages paid which is not a necessity of the industry.”
1.3 SANITARY CONVENIENCES
1.3.1 Adequately cleaned, ventilated and lighted.
1.3.2 Adequate provisions made for different sexes.
1.3.3 For each 200 workers one latrine & one urinal will be provided.
BOCW Rules: - To provide one latrine for every 20 workers up to 100 workers and thereafter one
for every additional 50 workers. In addition, one urinal to be provided for every 100 workers.
1.3.6 Water must be replenished from time to time in the water tank where latrines and urinals are
provided.
1.3.7 Ensure proper disposal system for the disposal of sewerages waste
1.3.8 Provide vent pipe of at least 3 mtr height for the septic tank wherever provided.
1.3.9 Log sheet must be posted near the latrines and toilets and ensure timely cleaning of the same
and ensure it is in usable condition at all times.
1.4.1 Conspicuously mark with appropriate signs “Drinking water” in local language near drinking
water facility.
1.4.2 Provision of drinking vessels or other suitable method of drinking.
1.4.3 Periodic checks shall be taken to ensure proper cleanliness during monsoon.
1.4.4 Proper drainage facility shall be provided for waste water.
1.4.5 Cleaning of drinking water tanks should be carried out at once in a week / as and when
required.
1.4.6 As per Section 32 of BOCWA to provide minimum quantity of 5 liters per workman per day.
1.4.7 Quality of the drinking water shall conform to the requirements of national standards on Public
Health.
1.4.8 While locating this drinking water facility care to be taken that these are easily accessible
within a distance of 200m from the place of work for all workers at all location
1.4.9 Drinking water points should not be situated within six meters of any washing places, urinals
or latrines.
1.5 MEDICAL FACILITIES.
1.5.1 A building worker who is employed for a work involving high risk or hazard inherent
activities such as every operator of crane; lifting appliances and transport equipment’s shall
be considered appropriate for the periodical medical checkup.
1.5.2 Facility of the periodical medical treatment shall be availed by the above identified worker at
free of cost.
1.5.3 The periodic medical treatment shall be availed once in a two year as per Schedule VII of
BOCWR Rule 233(A)
1.5.4 The medical examination shall include---(1) General Physique (2) Vision (3) Hearing (4)
General alertness.
1.5.5 Doctor visit will be once in a month for site / camp for pre medical / periodic medical checkup
Pre medical check up to be done for all the workers before engaged to work at site.
1.6.1 At the construction site, first-aid facilities shall be provided and maintained.
1.6.2 When a person is critically injured, he shall be taken to the designated hospital immediately
after emergency medical treatment. Other than EOHS staff supervisors should also be trained
for first aid treatment. EOHS Officer/ First Aider/Admin persons will deal the first aid
responsibility.
1.6.3 Stretcher must be made available in the site to shift the injured person from the incident
location to the first aid center / ambulance van.
1.6.4 The First Aid facilities shall be easily accessible and may consist of the following:
this list is not intended to be exhaustive or compulsory but as guidance:
1.6.4.5 The location of first aid station on site shall be clearly marked with appropriate
signs and their location indicated on the site emergency plan.
1.6.4.6 Male Nurse to be deployed
a. A sufficient number of eye wash bottles with distilled water clearly marked.
b. Boric acid eye drops, 4% xylocaine eye drops and soda bi carbonate eye drops.
c. Small sized sterilized dressing
d. Medium sized sterilized dressings
e. Large sized sterilized dressings
f. Large sized sterilized burn dressings
g. Packets of the sterilized cotton wool (15cm).
h. 200 ml bottle of Cetrimide (1%) solution or suitable antiseptic solution
i. One (200 ml) bottle of mercurochrome (2%) solution in water.
j. One (120ml) bottle of Salvolatile having the doses and mode of administration indicated
on the label.
k. One pair of scissors
l. One roll of adhesive plaster. (6cm X 1mtr) & two roll of adhesive plaster. (2cm X
1mtr)
m. Sterilized eye pads in separate seal packets.
n. A bottle containing 100 tablets (Each of 325 mg) of aspirin or any other analgesic
o. Roller bandages 10 cm wide & 5 cm wide.
p. One tourniquet
q. A supply of suitable splints
r. Packets of safety pins
s. Kidney tray
t. A snake bite lancet
u. A bottle containing potassium permanganate crystals.
v. One copy of first aid leaflet issued by the directorate general
w. Triangular bandages.
x. Pairs of suitable, sterilized, latex hand gloves.
Note: 1. Above contents shall be revised and maintained as per BOCWR of concern state, no
medicine should be kept in the first aid box; all general-purpose medicine should be kept with
administration staff only.
1.8 Record of First Aid treatment given to any worker shall be recorded in register.
First Aid injuries to be analyzed with root cause, corrective and preventive actions for reduction and
same to be communicate Brigade and JLL once in a month.
Regular spray of mosquito repellents & other pest control sprays to be done to prevent deceases.
Anti-venom Medicine to be made available at site
Carbolic acid or other relevant medicines to be sprayed at Bushes in sites and
worker’s colony to prevent snake bite.
Areas to be kept clean without bush / waste heap.
III SAFETY MANAGEMENT SYSTEM:
1.1 Work place rules are required to make sure that employees, contractor and sub-contractors know
exactly what is expected from them while carrying out work at Projects sites. Rules and
regulations are in place to protect the health and safety of every individual and to minimize
the potential damage or loss to equipment or to environment.
1.2 It is imperative that all workers understand that they must respect and follow all rules and
regulations while working at JMC Project sites.
1. All activities must be carried out in accordance with the approved EOHS Plan and
Approved Method statements and Hazard Identification and Risk Assessment (HIRA).
2. All Site-based personnel and visitors to Site must ensure that suitable PPE is worn at all
times while on the construction site. Additional PPE must be worn appropriate to the
location and task being performed.
3. Person / equipment / material shall enter & exit the site only through the gate designated.
Only license holder driver / operator are allowed to operate any vehicle /Machinery. All
vehicle /machinery shall be inspected by a competent person prior to use.
4. Smoking and eating is prohibited throughout the workplace except in designated areas.
5. Adequate internal and external lighting shall be provided by all Contractors for all
workspaces. All portable electrical equipment shall not exceed 220 volts with effective
Safety Trip system excluding portable welding sets.
6. Only qualified electrician is authorized for any electrical connection, disconnection and
maintenance work.
7. Instructions given on safety signs must be adhered to at all times.
8. Safety sign, Posters and barricades shall not be replacing or remove without permission
from the person responsible for EOHS.
9. Fire extinguishers must not be removed from their designated places except for
extinguishing ire.
10. Any person working on or near operational plant or equipment must be competent and
trained in such work.
11. Do not touch any hazardous chemicals or unknown item at site. For chemical handling
MSDS has to follow.
12. Color band to be imposed on the hard barricading pipes must be of “Red and White”
instead of “Yellow and Black”.
13. Work place shall be kept neat & clean. Wastage/Debris shall be collected at identified
areas after the completion of work on daily basis.
14. Waste collection bins such as Organic, recyclable, metal scarp, hazardous with proper
color code system shall be kept and maintained on daily / weekly / monthly as per the
generation of waste.
15. Access shall be free from any obstruction at site.
16. Only authorized person should sit along with driver on the machinery.
17. During heavy rain, improper lighting, heavy wind blowing at site, nobody should work at
height.
18. No children shall be permitted inside the working area. Crèche should be provided in
labour colony.
19. Horseplay, fighting, gambling and possession of firearms, ammunition, alcoholic
beverages and illegal drugs are strictly prohibited. Any person found in possession of or
under the influence of un-controlled substance or alcohol will be immediately removed
from site.
20. Report all injuries to Project in charge & other concerned immediately, no matter how
slight they may be.
21. Consumption of alcohol is strictly prohibited, any person found drunk shall be sent out of
the site instantly. Alcohol detector shall be kept at site, to check for the same.
EOHS Training
1.0 Introduction
Training is an essential part of any EOHS program. Management recognizes that imparting relevant
training is an absolute requirement for safe execution of project. Training includes induction,
necessary job-related safety procedure, statutory requirement, prevailing safe work practices, tool
box and mock drill etc. Hence it is important to impart training to all the personnel working in JMC
Project Sites.
Project EOHS in charge shall organize EOHS induction for all new personnel (JMC Employee, Sub-
contractors and (labours) on basic EOHS requirements of the Project site and significant feature of
the construction work. It is mandatory that all contractors and employees attend the EOHS induction
prior to starting their work. No employee shall be permitted to work on the construction site without
having attended the EOHS induction.
The elements that are common, but not limited to most EOHS induction programs are
a. EOHS Policy & Objectives
b. General Safety rules of L&T
c. Use & Importance of PPE
d. Major site Hazards and protective measures
e. Location of First aid medical facility
f. Location of welfare facilities like drinking water, toilets etc.
g. Details about Emergency response plan like emergency announcement system, evacuation
route and emergency assembly points
h. Introduction of L&T Key personal
i. Waste management practices
Separate Induction room to be available and Safety Induction for new workmen and other
Training Programs to be conducted there with Audio / Video facilities.
1.2 TOOLBOX TALK
a. It is mandatory for all Supervisors/ Foremen to conduct and deliver a toolbox talk at work
locations within their respective area prior to commencement of work assignments.
b. Supervisors/ Foremen shall ensure that the potential hazards of the task and specific safety
requirements while executing the tasks are clearly understood and briefed to all the personnel
involved and ensure that safe working procedures are strictly followed.
Topics to be discussed shall include but not restricted to the following as and when applicable.
Emergency Procedures Gas Cylinders
PPE Scaffolding
Site Safety Regulations Deep Excavations
Housekeeping Lifting
Fire Prevention Rigging
Safe Working Practices Manual Material Handling
Near Miss Electrical Safety
• Eye Protection Spill prevention
• Safety aspects of Tools & tackles Waste Management
EOHS Manager, in consultation with Project Manager will determine that a job holder is competent
to do his job safely and ensure that appropriate training is given. Trade and skill training that is
required in the project sites are for:
a. Lifting Supervisors
b. Crane Operator
c. Scaffold Supervisors
d. Excavation, Shoring and Piling Supervisors
e. Welder and Gas cutter
f. Batching plant & Concrete pump operator
g. Excavator/Dumper/Tipper Operator
h. DG Operator
i. Electrician
a. Every month one training on various aspects related to EOHS function must be conducted at
site by EOHS Officer for minimum one hour. Topics which can be covered for different target
groups.
b. All JMC employees performing high risk job such as a working on height, confined space
entry, hot work, heavy structure erection, handling of hazardous substance and electrical
installation & maintenance shall be given job specific training.
c. All training records should be sent to HO T&D Department as well as shall be maintained
properly at site.
d. Besides indoor training, demonstrations on various aspects like fire extinguisher, mock drill,
use of PPE, etc, also should be organized at site.
e. Mock drill shall be conducted once in a year for each emergency defined.
f. Mock drill to be conducted once in a month for each emergency defined
g. Training regarding use of first Aid items must be given to the selected staff for carrying out
first aid treatment at site.
h. EOHS training will be a continuous exercise and will be regularly imparted through refresher
course, seminars, talk, etc.
i. Supervisor shall identify competency required to carry out activity based on hazards and
significant aspects as per EOHS requirements.
j. EOHS officer shall devise training modules to fulfill above competency requirements.
2. EOHS COMPETENCE
2.1 Competence requirement and mapping shall be carried out for person involved in activity
having significant EOHS aspects.
2.2 Supervisor shall identify competency required to carry out activity based on hazards and
significant aspects as per EOHS requirements.
2.3 The competence of the candidate will be reviewed during the recruitment for the job he is
appointed, whenever required.
2.4 EOHS officer in consultation with the project manager will determine that the job holder is
competent to do his job safely.
2.5 EOHS officer will ensure that appropriate training is given if required to perform and complete
the job as per EOHS guidelines.
2.6 It will be ensured that respective HOD’s will give education to their employees and
contractor’s personnel to make them competent.
2.7 HOD will decide additional / special competence required for any specific job and select the
competent employee for the job.
2.8 Following table may be used as reference for verifying the competence:
Sr. Category Competence
No.
General Requirement
1 Physical fitness a) Worker should be having good physical health
b) Worker weight shall between ranges of 50-75 Kg.
c) Worker shall not suffer from any disease.
d) Worker shall have good vision and hearing capability.
e) Worker shall not have any bad past history.
2 EOHS a) Worker shall have knowledge of use of PPE for work carried out.
Requirement b) Worker shall have knowledge of general construction safe conditions.
c) Worker shall have knowledge of signage and posters displayed at site.
d) Worker shall have knowledge of emergency evacuation rout.
e) Worker shall have knowledge of work at height and scaffold work.
f) Worker shall have knowledge of proper stacking of material and housekeeping.
Trade Requirement
3 a) Worker shall be aware about use of safety tools while carrying out the job.
Concrete work b) Worker shall have knowledge of best practice in handling of the material.
4 Bar cutting and a) Worker shall use proper PPE’s
bending
5 work (Skilled & b) Worker shall be able to understand the measurements and alphabets
unskilled c) Worker should be able to understand the simple sketch showing the details of the
worker) reinforcement
d) Worker shall be well versed with the use of bar cutting/bending machine.
e) Worker shall be aware of proper methods for shifting cut bars.
6 Shuttering work a) Worker shall be able to understand the measurements and alphabets.
(Skilled and
b) Worker should have firsthand knowledge of the tools and tackles used for the job.
Unskilled)
c) Worker shall be able to carry out job in accurate line and level.
d) Worker shall be familiar with erection of staging with various materials such as H frames,
Steel pipes, Cup-locks, etc.
7 Masonry and a) Worker shall be familiar with various types of bricks /concrete blocks and their standard
Plaster work size available
b) Worker shall possess firsthand knowledge of the tools and tackles used brickwork and
plaster.
c) Worker should possess knowledge about various methods of Brickwork and plaster
d) Worker shall be having knowledge of cement, mortar proportion for brickwork & plaster.
e) Worker should be having 1st hand knowledge to prepare staging for their work in safe
manner.
8 Flooring work a) Worker shall possess knowledge of various tiles/stones used for the flooring.
b) Worker shall possess knowledge of the tools and tackles used for the job.
c) Worker shall be able to demonstrate show good workmanship i.e. fine joints line level etc.
d) Worker shall possess knowledge about cutting of stones/tiles to required size and shape
9 Rigger Work a) Worker shall possess knowledge of the tools and tackles used for the job.
b) Worker shall have knowledge of methodology of rigging work.
c) Worker shall be able to work at height
10 Electrician a) Worker shall have knowledge of basic electric work and wire work.
b) Worker shall have knowledge of electrical methodology work.
1 EOHS Committee, meeting & communication:
To facilitate participation and consultation on Environment, occupational health & safety related
matters, EOHS committee shall form at project sites. The EOHS committee should have formal
status and its members shall include;
The prime objective of EOHS committee is to promote co-operation between site team &
workers in order to investigate, develop and carryout measures to ensure that environment,
health and safety are adhered at site.
2 EOHS COMMUNICATION:
2.1 The EOHS information shall be communicated to employees by means of Monthly Safety
Meeting, Management Review Meeting and circulars.
2.2 The EOHS issues requiring large scale awareness shall be communicated through circulars /
emails / hold meetings.
2.3 Records of all such circulars / meetings / mails shall be maintained in communication
Register/File.
2.4 The Project site management shall take every effort to communicate the environment, health
and safety information through following procedure.
EOHS AWARENESS
The objective of EOHS promotional activity is to develop and maintain awareness about
environment, health and safety among all personnel of the project site.
The Project site management shall take every effort to communicate the environment, health and
safety measures through following procedure.
EOHS information boards will be provided at site to display information such as safe man hours,
incidents at site, important contact Nos etc.
Site EOHS officer will be responsible for updating the EOHS information board on daily basis.
i. Posters and signage will be adopted at site as visual aids for incident prevention, fire
prevention and EOHS promotion.
ii. Posters and signage will be related to safety, environment protection, Occupational health
etc.
iii. Posters shall be in Local Language-Kannada on top, National Language-Hindi in the center
and Global Language-English at the bottom has to be followed. (Will follow in future)
iv. Posters shall be displayed as per standard list.
v. A safety park to be set up at a prominent location of the site.
vi. All PPEs, safety devices, signboards, fire protection equipment, and safety models to be
displayed in the safety park.
vii. Safety award winners as well as violator of the month and their photo graph to be exhibited
there.
viii. The safety park to be maintained throughout the project duration.
1. EXCAVATION
1.1. Preparation
1.1.1. Study the soil characteristics such as its load bearing strength, type of soil, angle of repose for
soil require etc with help of QA/QC dept. or Client/consultant.
1.1.2. Collect information about underground services like pipelines, live electrical cable, drainage
line, base of nearby structure from relevant sources.
1.1.3. See that excavated area is not blocking the excess to the site for man and materials both or
otherwise necessary sign shall be displayed at appropriate locations.
1.1.4. Alternate route for traffic is provided in case of road blockage.
1.2.1. Experience and knowledgeable supervisor should supervise excavation work continuously.
1.2.2. Give the toolbox talk regarding safety measures to be observed to the workers involved
before starting the job.
1.2.3. Confirm methodology to be adopted, explain risk assessment and plan of action in case of
emergency & PPEs to be provided for use.
1.2.4. Minimum person shall be kept inside the pit. All idle workers should be removed from
excavation.
1.2.5. Each excavation shall be inspected daily by supervisor/Engineer or more often if conditions
change rapidly.
1.3.1. Safe access shall be provided to workers by means of ladder, stairs or ramps.
1.3.2. Depth more than 1.5 meter shall be barricaded
1.3.3. Ensure that proper passage over the excavation shall be provided for by passers with
minimum 600mm wide gratings with proper hand rail.
1.3.4. Excavated earth shall be placed at least 2 feet away from the edge of excavation.
1.3.5. Warning signs including light signal (if work is carried out on road or public area) shall be
provided.
1.3.6. Arrangement for the dewatering shall be made in case of presence of ground water.
2.4 Barricade
a. Barrier such as guardrails, hole cover, or any other guard must be provided with suitable
signage to protect building workers against fall.
b. A warning barricade shall be kept five (5) feet away from the edge of any excavation,
hole, platform or roof. A protective barricade may be placed closer Barricades shall be
erected before a hole is cut and extended as the excavation progresses.
c. Barricade signs shall be fully informative, legible and visibility displayed.
d. Hard barricading with safety net to be provide in staircase well
e. Where barricades cannot be installed, safety nets should be installed close to the level of
terrace at which danger of fall exists.
f. All work areas, walkways, platforms etc. elevated 1.5 meter or more, must be
encompassed by an approved guard rail or rope.
g. All cut outs or openings through floors shall be covered with stone, thick plywood, metal
plate or rebar gratings or rigid guard rail immediately.
h. Barricades shall be removed when no longer needed.
i. Where secured foot hold is impracticable, safety belt with secure anchorage arrangement
should be provided. A life line with sufficient strength should be provided all around the
building to which the workers exposed to the risk of falling for tying the hooks of their
safety belts.
j. Any opening, hole or gap on floors, grating or walking / working surface, where person,
tools or materials can subject to potential fall, to be appropriately covered and / or
guarded. Covers when applied shall be of substantial strength, capable to sustain at least
twice the weight of the person(s) or materials that can be imposed on the cover at any one
time.
k. Guard rails shall be made of solid materials (i.e. scaffold tubing) and shall be capable to
sustain without failure, a minimum of 100Kg‟s. Downward or outward force.
l. Lift shaft gate: At the openings of lift shaft in each floor, gate shall be provided to
prevent fall of people at lift shaft, for opening the lift shaft gate for working inside lift
shaft work permit shall be obtained from safety DEPT.
3.ELECTRICAL
3.1 Prior to any work being carried out on any electrical equipment an assessment must be
carried out of the risks involved and the safety measures necessary to eliminate or minimize
the risk.
3.2 All electrical systems, plant, equipment, apparatus, wires and cables must be presumed live
unless proved dead. Consideration must be given to stored energy that may be retained in
plant, equipment and apparatus after its disconnection/isolation from the system.
3.3 All electrical loads shall be studied properly and distributed as per requirement or standard.
3.4 All electrical equipment’s must be inspected and stick “safe-To Use” sticker on the
equipment with color code system, color code will vary month on month basis and the cycle
will be rotate once in every 4 months.
3.5 All electrical work including the repair and maintenance of electrical appliances must be
undertaken by qualified electricians/electrical engineers and with the exception of electrical
appliances disconnected from the supply, must be under a permit to work.
3.6 Rubber mat shall be provided at distribution board to serve insulation purpose.
3.7 Defective electrical equipment returned to the stores must be clearly and conspicuously
marked as “defective/faulty do not use” and separated from equipment that is in safe
condition and available for use.
3.8 Site electrical supply must be as low as is reasonably practicable but should not exceed 220v
except for the supply.
3.9 All electrical cables shall be properly insulated and shall be kept at minimum 2.0 mt height.
3.10 Distribution boards in offices, workshops, stores and in the construction, site must have the
means of electrical isolation on the outside of the cabinet, must be protected by fuses or
circuit breakers and an RCD, must have lockable doors and must be earthed/grounded.
3.11 All electrical equipment, except for double insulated power tools, must be effectively earthed.
3.12 All earthing pit shall be properly maintained with identification. Earthing measurement shall
be recorded on regular basis as per requirement.
3.13 Industrial plug tops shall be used for drawing power supply from the distribution boards, use
only male female sockets for jointing cables
3.14 Never allow the hand power tool to hung on the scaffold and never allow to carry the hand
power tool by means of electrical cord.
3.15 Resistance of the individual Earth Pits to be less than 2 Ohms.
3.16 Resistance of the earthing grid to be less than 1 Ohms.
3.17 Electrical equipment must be switched off and disconnected from the power supply before
any repair or maintenance is to be carried out on the equipment.
3.18 Earth leakage circuit breaker (ELCB)-30 mA shall be used on all extension cords and
portable tools. All 120-volt outlets and all extension cords shall have third wire grounding
conductor installed and intact.
3.19 GI wires shall not be used on temporary lighting circuits. Every temporary lamp holder shall
have a lamp installed and a lamp guard in place. Non-conductive materials shall be used for
securing lighting wires to supports.
Weather Protection
All DBs, panels, switches shall be housed properly.
All such establishment shall have sufficient space inside & should be provided with closing doors /
sides secured with cover. These protection enclosures shall be placed at a convenient height with
adequate supports to avoid tilting
Earth moving equipment should be provided with standard safety features such as lights, rear mirrors
& an audible reversing signal.
No earth moving equipment should be moved until all persons are cleared away.
Supervisors along with operators should survey route of the earth moving equipment for:
a. Electrical lines which may be an obstruction
b. Underground conduits containing service line
c. Slope gradients
d. Overhead obstructions
During the operation of equipment such as a back hoe or excavator and where workers are in its
proximity, a banks man (signal man) should be present to direct the operator.
5. PNEUMATIC TOOLS:
The following general precautions shall be adopted specifically whilst using pneumatic tools.
Obtain 3rd party test certificate for the compressor (air handling unit).
Suitable PPE shall be worn for ear and eye protection as a mandatory requirement;
Compressed air shall be relieved from the line before disconnection tools from the line; of hose/pipe.
Air hoses shall be pressure-rated by the manufacturer, and this pressure shall not be exceeded;
Defective hoses shall be removed from operation and replaced;
Hoses shall not be left on ladders, steps, scaffolds, or walkways;
The use of compressed air for blowing dirt from the hands, face, or clothing is prohibited.
6 HAND POWER TOOLS:
6.1 Hand tools used in elevated work areas shall have a strap/rope of approximately 1m in length
used to attach a hand tool to a person’s wrist, or in the case of heavy tools to some fixed point
such as a guard rail.
6.2 Hand tools shall be kept in serviceable condition and used only for the purpose for which
they are designed.
6.3 Power tools shall be regularly inspected and tested to ensure safe operating conditions.
6.4 When work is being carried out at an elevated position, tools not in use shall be secured or
placed in holders.
6.5 Hurling tools or materials from one location to another from one worker to another, or
dropping them to lower levels shall be prohibited.
6.6 Attention must be paid to not using tools which may cause sparks in locations where
hazardous gasses may exist.
6.7 Power tools shall be operated only by trained / Skilled / authorized by JMC / designated
personnel.
6.8 Flexible cable shall be used for all portable electric tools.
6.9 Waterproof connectors shall be used for cable connections; and Electric hand tools shall be
grounded (earthed).
6.10 All portable power tools to be used on site to be ISI marked, free from any defects
and properly grounded or double insulated and protected with Residual Current Circuit
Breaker (RCCB) or ELCB
6.11 All portable power tools will be equipped with properly functioning "Push button
Switch”.
6.12 No grinder will be used without its original guard properly in place. All grinders shall
be marked with the designated maximum running speed (RPM Rating) and must be ensured
that the maximum speed of the spindle does not (at any time) exceed the maximum periphery
speed (RPM Rating) marked on the grinding disc or wheel.
6.13 Repair of defective power tools will be performed only by the designated competent
maintenance / electrical personnel.
6.14 No electrical hand tools, power cords and outlets will be used in damp locations or in
wet conditions. This includes welding / cutting activities. Power tools and work location
must be kept dry to avoid potential electric shock / burns. Tools shall not be used unless
protected with RCCB or ELCB protection
6.15 Loose clothing / hand gloves not to be allowed on activities around rotating
equipment such as magnetic drills, table saw, bending machines, etc.
INSPECTION OF TOOLS
7.1 Before starting any maintenance or inspection work, Energies present in the machine shall be
identified which need to be isolated for safe Maintenance work.
7.2 Energies present in the machine may be: - a) Electrical b) Hydraulic C) Pneumatic D)
Kinetic.
7.3 For isolation of Kinetic energy i.e. the equipment or components which retain stored energy by
means of springs, flywheels or due to gravity are to be deactivated or mechanically restrained
with sufficient strength to prevent motion e.g. by means of tying by chain, jacks, or placing a
safety block or chock.
7.4 For isolation of pneumatic and hydraulic energies, valves shall be shut off and balance energy
shall be released and drained.
7.5 A "DANGER - DO NOT OPERATE" tag shall be placed at the Energy isolating points like
electrical breakers, panels, MCBs, switchboards, distribution boards, valves or other energy
isolating devices.
7.6 There may be more than one tag / lock required while carrying out the maintenance or inspection
of a particular machine.
7.7 The tag for isolating the energies shall be kept and removed after completion of job by the P& M
Department.
7.8 Locks should also be put on the places where these can be provided on the energy isolating
sources.
7.9 Tags and locks shall be remained in position until the Maintenance and inspection work is fully
completed. Even if the operator leaves the machine and attends to another machine, tag / lock
will remain in its place.
7.10 P&M department shall be informed immediately for the breakdown in any machine or
equipment.
7.11 Equipment under maintenance or inspection shall be recorded in a log book.
7.12 The name of the person who isolated the energy shall be mentioned. After the job is completed
a remark of "Job Completed" shall be written.
7.13 If the job continues beyond the shift there shall be a written communication to the operator of
another shift or his reliever in case of particular machine is under maintenance and should not
be energized.
7.14 The lock and tag shall be removed after the completion of job.
7.15 P & M Head shall be responsible for implementation of the system at the time of maintenance,
or inspection. It shall be ensured that concerned people are trained.
8 CONCRETE WORK
CONCRETING
Concrete footings
• Excavation permit is required before excavate for the footings.
• Hard barricading has to be obtained for the edges. Shoring is required if it is loose soil.
• Adequate PPE’s is required for the concrete workmen.
• Concrete miller should be away of 3m from the footing.
• Speed limit is restricted to 8 km/ hr for all concrete millers
• Check Safety Devices like Reverse horn, Horn, Mirror, etc are functioning.
• Equipment fitness & Operator fitness certification systems are to be implemented.
• Proper access to the work place provided
• All electrical cables have to be routed overhead (minimum 08 feet). Employees are
properly clothed to protect skin while concreting Is their sufficient light provided for night
concreting – (60 Lux)
• Housekeeping done in and around the concrete location.
CONCRETE COLUMNS
• Skilled Carpenter and adequate semi-skilled semi carpenter and trained helper are required.
• Ply cutting machine must be with fill guarded.
• Tools and tackles must to be in noble condition.
• Adequate scaffolding staging is required for the column shuttering.
• Adequate scaffolding staging is required for the column concreting with the platform of
600mm & supports.
• Proper access to the work place provided
• All electrical cables have to be routed overhead (minimum 08 feet).
• Employees are properly clothed to protect skin while concreting Is there sufficient light
provided for night concreting – (60 Lux) Housekeeping done in and around the concrete
location.
CONCRETE SLABS
• Skilled Carpenter and adequate semi-skilled semi carpenter and trained helper are required.
• Ply cutting machine must be fully guarded.
• Tools and tackles must to be in noble condition.
• Adequate scaffolding staging is required for the column shuttering.
• Adequate scaffolding staging is required for the column concreting with the platform of 600mm
& supports
• Temporary edge protections have to be provided. With life lines and with reinforcement tor rod.
• Proper access to the work place provided
• All electrical cables have to be routed overhead (minimum 08 feet).
• Employees are properly clothed to protect skin while concreting Is their sufficient light
provided for night concreting – (60 Lux) Housekeeping done in and around the concrete
location.
• Check concrete pipe line properly supported
• Barricading of Lift pits & other ducts
• Putting of M.S. Jallis in lift pit as platform to cover the opening of working floor.
• Fall Protection (life line, safety net etc.) are provided
• Concrete Pipe line erection
• Skilled team with supervision is required
• Piping should be laid on adequate supports and secured to prevent movement.
• Pipelines should not be attached to temporary structures such as scaffolds & form work supports
as the forces and movements may affect their stability.
• Pipe connectors particularly those installed at height should be secured against dislodgement.
Pipeline should be checked for leakages and the couplers should be properly tightened to avoid
spillage.
• While cleaning the pipeline using a ball always ensures that a ball catcher is provided to catch
the ball at end of pipe line. Ensure that persons are at safe distance while cleaning operation is
being carried out.
• Never allow any worker to insert his hand inside out let of concrete pump for cleaning.
Scrapper tools shall be kept with concrete pump for cleaning purpose.
• Lock out concrete pump engine while cleaning operation is going on.
CONCRETE MIXER:
• All gears, chains and rollers of concrete mixer should be adequately guarded to prevent
damage / danger to the operator.
• Concrete mixer hopper shall be protected by side railing and operators shall make sure before
lowering the skip that lower portion of skip is clear.
• Wire rope of Hopper should be checked for its condition periodically during its preventive
maintenance.
• Hopper hoist and anchoring brake should be checked \ adjusted.
• Nothing should be kept inside the motor enclosure.
• Be sure that motor fan guard is secured firmly.
• Be sure that wiring is properly connected installed and double ear thing is done for electric
mixers
TRANSIT MIXER:
• Operator should always carry valid driving license and the vehicle fitness certificate, road tax,
vehicle insurance and PUC certificate for the equipment he operates.
• The Driver / operator must have to follow the instructions given by traffic controller / banksman
(e.g. - Speed limit, Sharp turn etc.)
• Automatic reverse horn must be installed and frequently checked for its proper functioning.
• It shall also be equipped with first aid kit and a fire extinguisher.
• Before sending the workmen inside the drum for cleaning, the rotation of the drum shall be
arrested. Drum cleaning should be done under the supervision of the P&M Engineer.
• While moving in the public roads the driver shall comply with all local traffic regulations.
• No person shall be allowed to stand between the transit mixer and concrete pump.
• While working near excavated pits and trenches the transit mixer shall be stopped well ahead of
the edge of the trench / pit.
CONCRETE VIBRATORS:
• Vibrator unit shall be completely enclosed and running belt of the engine shall be adequately
guarded.
• Electrically operated compacting vibrators shall be totally enclosed and be protected against
over loads by suitable overload relays and shall be effectively earthed.
• Ensure that sufficient length of cable is provided to the vibrator.
• Ensure electric starters are fixed firmly on the stand.
• While needle is inserted in the vibrator, ensure needle rod is firmly locked.
• Ensure that proper lubrication of needle inner core is done
CONCRETE PUMP:
CONCRETE MI11ER
CONCRETE BREAKING
Before any demolition work is commenced and also during the progress of the work:
a. All roads and open area adjacent to the work site should be closed or suitably protected.
Along with that appropriate warning signs shall be displayed for cautioning approaching
persons.
b. Before demolition operations begin, the Contractor shall ensure that the power on all
electric service lines is shut off and the lines cut or disconnected at or outside the
demolition site. If it is necessary to maintain electric power during demolition operation,
the required service lines shall be adequately protected against damage.
c. No floor, roof or other part of the building shall be overloaded with debris or materials as
to render it unsafe.
d. Entries to the demolition area shall be restricted to authorized persons only.
e. Persons handling heavy materials/equipment’s shall wear safety shoes and safety helmets.
f. All practical steps shall be taken to prevent danger to persons employed, from risk of fire
or explosion or flooding.
g. No electric cable or apparatus which is liable to be a source of danger over a cable or
apparatus used by the operator shall remain electrically charged.
h. Debris will be shifted through designated shaft and will be used for land fill after
segregation.
9 DUST CONTROL
11 TRANSPORTATIONS
12 WASTE MANAGEMENT
12.1 Hazardous waste oil and oil-soaked cotton & sand must be disposed to KSPCB approved
vendor
12.2 Hazardous waste must be collected in a bin and regularly cleared from the bins and stored in
from time to time
12.3 Collection, transportation and disposal of all waste shall he strictly managed.
12.4 Construction waste shall be segregated as much as possible at site to increase the feasibility of
recycling.
12.5 Waste concrete and masonry shall be used for filling material/road restoration works.
12.6 Scrap collected shall be sent to scrap yard.
12.7 Construction waste shall be used in preparing site road construction work. It will be also, used
as backfilling material to level off the site.
12.8 Biodegradable wastes shall be collected at waste bins and disposed off at Authorized waste
dumping yards with their prier permission. Non-biodegradable wastes shall be dumped at the
designated place, shown by concerned officials
12.9 Oil traps shall be provided for minor leakages from mobile equipment’s and generators. Oil
separator/ interceptors shall be provided to prevent the release of oils and grease in to
drainage system. It shall be cleaned on regular basis.
Waste Storage, Handling and Disposal
a. JCB and tippers shall be deployed to transport the same to the client approved designated
place. For proper disposal handle the waste mud generated from the pile foundations
mechanically.
b. Any other wastes generated from our activities shall be collected properly in waste bins
kept at the designed places and to the possible extent shall be disposed by auction to the
waste buyers.
General Considerations
a. All materials in bags, containers, bundles of stored in tiers shall be stacked, blocked and
limited in height so that it is stable and secured against sliding or collapse.
b. Materials shall be stacked as low as possible and in no case higher than 6ft. unless there is a
specific requirement and adequate safety precautions are taken up.
c. Temporary and permanent storage of materials shall be secure, neat, and orderly to eliminate
hazards and conserve space. Materials piled haphazardly or strewn about increase the
possibility of accidents to employees and damage to materials.
d. Storage shall be planned to reduce the number of materials handling so as to reduce hazard
and injury to workmen.
i. All the exits and aisles shall be kept clear at all times. ii.
All the materials shall be labeled and stacked size wise.
iii. Bins and racks shall be used to facilitate storage and reduce hazards.
iv. Racks shall be secured to the floor, the wall, and to each other.
v. Racks, when damaged, shall be repaired immediately.
e. Workmen shall not be allowed to climb on racks; Self-supporting Stepladders of adequate
height shall be used to place or remove materials on racks.
f. Adequate number of fire extinguishers and fire buckets shall be kept inside store building.
g. Materials shall be stacked in such a way that they do not block fire protection equipment
mounted on the wall.
h. Storekeeper / assistants shall be trained on use of fire extinguisher.
a. Materials shall be segregated as to kind, size and length and placed in neat, orderly
b. piles that are safe against falling. If the piles are high, they shall be stepped back at
c. suitable intervals in height. Piles of materials shall be arranged so as to allow a passageway
of not less than 1 m width in between the piles or stacks for inspection and removal. All
passageways shall be kept clear of dry vegetation.
d. Materials shall be stacked on well drained, firm and unyielding surface. Material shall not
e. be stacked so as to impose any undue stresses on walls or other structures.
f. Materials shall be stacked in such a manner as not to constitute a hazard to passerby.
g. When the materials have to be handled manually, each workman shall be instructed by his
h. Foreman or supervisor in the proper method of lifting heavy objects.
i. Workmen shall be provided with suitable equipment for his personal safety as necessary.
Supervisors shall also take care to assign enough men to each lifting job; the weight carried
by each man shall be determined by the distance to be moved, difficulty of movement
presented, time required, etc.
j. Whenever any stack exceeds 1.5 m height, suitable and safe means of access shall be
k. provided for the use of workmen and such means of access shall not disturb the stability l. of
the stack.
m. Appropriate signs shall be placed at all storage locations where special conditions exist or
n. where special precautions are necessary.
The stacking, storage and handling of materials generally used in for construction works
shall conform to the following guidelines:
TIMBER
Timber shall be stacked on unyielding and level dunnage. Cross strips or cross piling shall be used
where the pile is more than 1m high.
The top of each pile shall be kept as level as possible when timber is being removed.
No nails shall be allowed to protrude so as to cause any injury.
At least two men shall carry long boards, and care shall be exercised at corners and cross walks.
CEMENT
Stacks shall not be higher than 10 bags. If the stack has to be more than 8 bags high, the bags shall
be arranged in header and stretcher fashion, that is, alternate layers lengthwise and crosswise, so as
to tie the piles together to lessen the danger of toppling over. Bags shall be removed uniformly from
the top of the piles to avoid tipping of the stack.
Bulk cement stored in silos or bins may fail to feed to the ejections system. When necessary to enter
a silo or bin for any purpose, the ejection system employed shall be shut down and locked out. When
necessary for a workman to enter such storage area, he shall wear a lifeline, with another workman
outside the silo or hopper attending the rope. Work permit system shall be implemented for carrying
out this work.
• Glass panels used in construction shall be stacked on edge with suitable supports.
• Glass edges shall be covered or otherwise protected to prevent injuries to workmen passing
by.
• Waste glass pieces shall be stored or disposed of in such a manner as to avoid injuries to
workmen.
• Workmen handling glass panes, waste glass pieces and fiberglass shall be provided with
suitable hand protection.
• Holding the glass sheet under arm pit shall be prohibited.
• Pipe shall be stacked on solid, level sills and contained in a manner to prevent spreading or
rolling of the pile. Where high quantity storage is necessary, suitable packing shall be placed
between succeeding layers to reduce the pressure and resulting spreading of the pile.
• Heavy-duty cantilever racks can be used to allow good visibility and easy access to materials.
• Orderly storage as to sizes and lengths enhances access and removal operations
• Removal of pipe from a pile shall be accomplished by working from the ends of the pipe.
• In loading pipe or transit, it shall be so secured as to insure against displacement.
• While handling piles or poles taglines shall be used to control movement of them. In
stacking and handling of pipes and other conducting materials the following minimum
Safety distances shall be ensured from the overhead power lines:
• 11 KV and below 1.40m
a. The motor vehicles shall be properly blocked while being loaded or unloaded; brakes alone
shall not be dependent upon to hold them.
b. Ladder shall be used to climb up/down the vehicle.
c. Load on the vehicle shall be secured adequately so that the load does not slide down. If
d. the width of the load exceeds that of the vehicle, red lights/flag shall be provided on all the
corners of the vehicle to caution other vehicles on the road.
e. Unloading shall be started from top.
f. When motor vehicles are being loaded or unloaded near passageways or walkways, adequate
warning signs shall be placed on each end of the Vehicle to warn pedestrians and the drivers of
the other vehicles.
a. Stockpiles of these materials shall be so located as to provide easy access for withdrawing.
b. Materials shall not be piled against walls that will be endangered by thrust, nor along the
sides of any excavation or on the top of an embankment so as to cause slips.
c. Employees required to enter hoppers shall be equipped with safety belts and lifelines,
attended by another person. Machine-driven hoppers, feeders, and loaders shall be locked in
the off position prior to entry.
a. Paints, varnishes, thinners and other flammable materials shall be kept in properly sealed or
closed containers. The containers shall be stored in a well-ventilated, free from excessive
heat, smoke, sparks or flame. A separate shelter shall be provided for storing these materials.
b. Paint materials in higher quantities other than required for daily use shall be kept stocked
under regular storage place.
c. Paint scrapings and paint-saturated rags and debris shall be removed daily from the premises
and, preferably, destroyed by burning at a safe place.
d. Ventilation adequate to prevent the accumulation of flammable vapours to hazardous levels
of concentration shall be provided in all areas where painting is done. When electric lights,
switches or electrical equipment are necessary; they shall be of explosion- proof design.
Fire Buckets and foam type shall be kept ready for use in case of fire.
e. No smoke or open fire, exposed heating elements, or other sources of ignition of any kind
shall be permitted in areas or rooms where spray painting is being done.
f. MSDS will be displayed near the storage area and communicate to all the workers engaged
and record to be maintained.
a. Housekeeping is the act of keeping the working environment cleared of all unnecessary
waste, thereby providing a first line of defense against incidents and injuries.
b. Contractors, Sub-contractors and employees shall understand and accept that improper
housekeeping is the primary hazard in construction sites and ensure that a high degree of
housekeeping is always maintained. Indeed "Cleanliness is next to Godliness".
c. Housekeeping is the responsibility of all the personnel, and line management commitment
shall be demonstrated by the continuous effort of supervising staff towards this activity.
d. All stairways, passageways and gangways shall be maintained without any blockages or
obstructions.
e. Wooden pieces with protruding nails shall be either bent or removed & properly stacked.
f. All surplus earth and debris are removed / disposed off from the working area to designated
dump sites. Truck carrying sand, earth and any pulverized materials etc. in order to avoid dust
or odor impact shall be covered while moving.
g. Throwing of Debris from upper floors are not allowed, need to incorporate the plan for
removal of debris from upper level
h. Approval from Local authority to be obtained to dump the Debris in designated yard as
per NGT norms
i. Proper and safe stacking of materials is of paramount importance at yards, stores and such
locations where material would be unloaded for future use. The storage area shall be well laid
out with easy access and material stored / stacked in an orderly and safe manner.
j. Unused / surplus cables, steel items and steel scrap laying scattered at different place within
the working areas shall be removed to identify location(s).
k. All wooden scrap, empty wooden cable drum and other combustible packing materials shall
be removed from work place to identified location(s).
l. Empty cement bags and other packing materials shall be properly stacked and removed.
m. Adequate lighting shall be provided in and around our site.
n. Periodical scrap removal shall be done from each section.
o. Proper storages of Reinforcements and shuttering shall be done.
p. Proper barricading and its cleanliness.
q. Removal of glue tins, glue hand-gloves from launching sections from time to time.
r. Removal of waste concrete, empty cement bags, plastic bottles, plastic tea cups, oily wastes,
cotton wastes, empty bentonite bags, empty chemical tins etc.
s. Empty oxygen cylinders and LPG cylinders be removed from site and sent back to store on
timely basis
t. Proper accesses shall be maintained with un-slippery floors.
u. Dangling wires, protruding nails and storage in front of accesses shall be prevented.
v. Proper storages of flammable materials shall be done.
w. Drain cleaning shall be done on periodical basis
SHUTTERING
• Skilled Carpenter and adequate semi-skilled semi carpenter and trained helper is required
Ply cutting machine must be fully guarded.
• Tools and tackles must be in good condition.
• Supervision is required
• Identify the purpose for which scaffold is required
• Erect the scaffolding by competent rigger / scaffolding worker under supervision of
experienced supervisor. Inspect all the pipes and accessories before erection.
• Display scaffolding status tags at prominent location all the time.
• Scaffold having more than 10 m height shall be secured with fixed structure first then at every
8 m. Provide base plant: size :6 x 6 inches , thickness:6 mm
• The footing of scaffold shall be placed on a leveled and sound ground capable to carrying
max. intended load without settlement or displacement.
• Don’t use concrete blocks, barrel, boxes or loose brick for support of scaffold. Provide
guard rail, mid-rail to all open sides of scaffold platform.
• Safe and convince means of access like portable ladder, fixed ladder, ramp etc shall be
provided to the scaffold.
• Always keep minimum 3 mtr. Distance from overhead high tension line.
• Scaffold shall be vertical & checked with plumb.
• Working platform of the scaffold shall be fully covered with Khapeda (Gratings) Scaffolding
erector shall not be allowed to work on scaffold without the use of full body harness, safety
lines and helmet
DE SHUTTERING
• Skilled Carpenter and adequate semi-skilled semi carpenter and trained helper is required
Ply cutting machine must be fully guarded.
• Tools and tackles must be in good condition.
• Supervision is required Scaffolding shall be dismantled by the scaffolder in presence of
competent / experience supervisor.
• Display scaffolding status board at prominent location.
• Scaffolding removal shall be done from top to bottom plane wise.
• Loose scaffolding member shall be lowered down by rope & not by using man chain or
throwing.
• The area of dismantling shall be barricaded & no movement of personnel underneath the
same.
• Loose member shall be segregated and stacked properly.
• While erecting or dismantling of scaffold the spanner shall be used with proper string in hand
so that it will not fell down.
a. All welding cables shall be of the completely insulated, flexible type, capable of handling
the maximum current, requirements of the work in progress, taking into account the duty
cycle under which the welder is working.
b. The cable shall be free from repair or splice up to a minimum distance of 3.0 m from the
electrode holder. When it becomes necessary to connect or splice lengths of the cable to
another, substantial insulated connectors of a capacity at least equivalent to that of the
cable, shall be use.
Ladders can be used for light jobs of low risk and short duration.
Only one person allows climbing the ladder at a time. Before
taking in use, inspect the ladder for the following a. Mud or
Grease on rungs (Slippery)
b. Warped, sagged or distorted.
Make sure that ladder set on a firm level base
Have man to hold the ladder or tie the ladder from top.
Make sure that ladder reaches at least 1m above landing platform.
Maintain 4:1 ratio of base and vertical distance.
Do not carry any material while climbing or descending the ladder.
Do not lean sideway from ladder- it is safer to move the ladder
Face the ladder when climbing or descending
Metal ladder should not be used near or adjacent to overhead power lines.
Do not use ladder or any other purpose than provide access.
Do not place the ladder in front of door or in path of moving object unless it is guarded.
Do not place ladder on support of fragile or movable object.
Portable ladder shall be provided with anti-skid base at bottom. Provide
solid footing if ladder is to be placed on loose soil.
While working inside the shaft proper life line to be ensured.
• The right plant and machinery should be used for the job.
• All moving parts should be guarded, e.g. exposed gears, chain drives, projecting engine
shafts.
• The machinery should be maintained in accordance with its maintenance period and all safety
devices are erected for their operation.
• All operators should be trained and competent.
• Lockout tag out procedure shall be followed for maintenance of any plant and machinery.
RE-BAR CUTTING / BENDING MACHINES
The equipment should be erected by a competent person. The operators should be trained and
competent.
Fixed equipment, e.g. mast climbers, should be rigidly connected to the structure against which it is
operating.
The working platform should have adequate guard rails and toe boards or other barriers to prevent
people and materials falling off.
Precautions should be taken to prevent people being struck by the moving platform, projections from
the building or falling materials, e.g. barrier or fence around the base.
The power supply should be isolated and the equipment should be secured at the end of the working
day.
Vehicles and mobile power equipment are not allowed on site without approval from the
Administrator, and they shall be driven by trained Authorized Operators only.
All equipment shall be inspected prior to use by P & M supervisor as per the operating manual.
The winch shall be installed securely on firm ground with a good view for the work;
The area where the winch is installed shall have ample space for inspection and maintenance and be
kept clean at all times.
Ensure proper communication (walkie talky or mobile phone) system for the lifting of materials from
ground floor to upper floors.
The winding drum diameter shall be 20 times the diameter of the wire rope;
The end of the wire shall be fixed securely to the winding drum;
Wire ropes shall be wound regularly on the winding drum;
Warning markers shall be attached to the wire rope to prevent over winding;
Foot brakes shall be provided with adequate spacing from the ground to permit the brakes to be
operated freely. Gears shall be provided with a cover. The operating winch shall be located properly
for convenient operation. Winch motors shall be grounded:
Winch work shall be performed under the signal of the signal man;
When winch work is finished or suspended for a while, the power shall be switched off; The
winch operator shall not leave his position during winch operations.
a. Obtain 3rd party test certificate for all the lifting equipment, lifting tools & tackles (D-
shackle, Web sling, steel wire rope etc.
b. The crane should be on a firm level base.
c. Automatic safe load indicator shall be installed to the crane. The same should be
maintained and inspected weekly.
d. All operators should be trained and competent.
e. The banks man/signal man should be trained to give signals and to attach loads correctly.
f. The operator and banks man should find out the weight and center of gravity of the load
before trying to lift it.
g. Wires, chains and ropes should be in good condition.
h. Cranes should be inspected and examined by a competent person as per provision made
under BOCW act. Valid test certificate should be required with crane.
i. The results of inspections and examinations should be recorded.
ERECTION BY CRANE:
Confined space has a limited or restricted means of entry or exit, is large enough for employee to
enter and perform assigned work, and is not design for continuous occupancy by the employee. This
space may include, but are not limited to, underground tank, deep pits, sewer man hole, duct / trench,
silos etc.
Confined space has characteristics like
a. Contains or has the potential to contain a hazardous atmosphere.
b. Contain materials that have the potential for engulfment an entrant
c. has an internal configuration that might cause an entrant to be trapped or asphyxiated
by inwardly covering wall or by a floor that slops downward and tapers to a smaller
cross section and /or
d. Contains any other recognized serious safety or health hazards.
22. DEMOLITION
a. All demolition works shall be carried in a controlled manner under the management of
experience and competent supervision.
b. Concern department of client / consultant be informed and permission obtained whenever
required.
c. All glass or similar material or articles in exterior opening and all water, steam, electric,
gas and other similar supply line are de-energized and remove carefully before
commencing any demolition work.
d. Examine the wall of all structure adjacent to the structure to be demolished to determine
thickness, method of support to such adjacent structures.
e. No demolition work be performed if the adjacent structure seems to be unsafe unless and
until remedial measures like sheet piling, shoring, bracing or similar means be ensured
for safety and stability of adjacent structure from collapsing.
f. Debris / bricks and other materials or articles shall be removed by means of a. chutes
b. buckets or hoists
c. through opening through floor or
d. Any safe means.
g. No person other than building workers or other persons essential for operation of
demolition work shall be permitted to enter a zone of demolition and the area be provided
with substantial barricades.
23. DG OPERATION
Do's
a. During running of DG set, check the Oil pressure, temperature below red limit & Voltage
around 440 volts; ensure optimum loading (80%) for efficient output.
b. Carry out pre-operation checks as prescribed by the Manufacturer before the DG Set is
operated; Check for fuel leakage, cooling system leakage, and lubrication seal leakage.
c. Check fuel level, oil level & battery (Green Indication) and availability of signage "High
Voltage"
d. Keep diesel storage drum at identified places; ensure that there is no leakage and spillage
from the diesel storage.
e. In case of any diesel spills/leaks, immediately clean the area with any suitable absorbent
media (cloth, jute, saw dust etc.) and put the same in designated waste bins.
f. Coolant should be added as per required ratio in the system.
g. In case of any abnormality press Emergency button.
h. Check for any red indication during DG set running
i. Use PPEs whenever required
j. Fire Extinguishers should be available in defined place.
k. Follow the instructions of Engineer, including for maintenance activities
l. In case, the acoustics door has to be opened for any inspection purposes, ensure that ear
plugs muffs are used.
m. Monitor fuel consumption as per manufacturer's recommendations and carry out periodic
maintenance.
Don'ts
a. Never open the door of the acoustic enclosure without reason
b. Do not throw oily clothes at any places except designated bins.
c. Do not waste Oil/Diesel/Grease & water
d. Does not throw oily water in soil.
e. Do not use any liquid or Aerosol cleaners
f. Do not wear loose clothes and sleepers
g. Do not smoke inside the premises.
h. Collect used / spent lubrication and engine oils in small leak-proof containers after
maintenance & servicing activities after every 250 hours or as required; while handling
ensure that there is no spillage.
i. Ensure that the used oil generated is stored in leak proof drums and the same is applied as
Antirust on steel structure.
g. Outdoor storage of drums requires some care to avoid contaminations. Moisture and dirt in
hydraulic brake and transmission fluid, gasoline, or lubricants may easily cause malfunction
or failure of equipment, with possible danger to personnel. The storage area should be free of
accumulations of spilled products, debris and other hazards.
h. Compressed gases and petroleum products shall not be stored same building or close to each
other.
i. For bulk storage of petroleum (petrol, diesel etc.) and the like, the storage shall comply
strictly with the specifications given in the Petroleum Rules (and with the relevant act).
All employees entering the site must be checked for mandatory PPE’s
Safety helmets shall be worn with chin straps in accordance with the following color code:
Sr. No Helmet Color Code Employee Category
1 White Officer / Jr. Engineer and Above.
2 Blue Sr. Supervisor and Below.
3 Red P&M Operator / Electrician & Sub-contractor.
4 Green EOHS Staff
5 Yellow Workers
All the PPEs to be conformance to the IS standards or shall have internationally recognized
certification such as CE, UL Mark.
Quality of PPEs and other safety devices to be approved by JLL / Brigade
Test Certificate for all the PPEs to be submitted.
Specification for PPEs and other safety devices needs to be incorporate
As per Brigade OCP the fall arrester rope should be polyimide for better gripping ability
Polypropylene rope will be allowed only for Horizontal Life Line
PPE Matrix
Safety harness
Dust Mask
Safety Shoes
Safety Helmet
Face Shield
Leather Gloves
Rubber Gloves
Cotton Cloves
Welding Helmet
Safety Goggles
Ear Plug
Activities▼
Jacket
Manual Excavation ● ● ●
Excavation-Wet soil ● ● ●
Bar Cutting ● ● ● ●
Bar Bending ● ● ●
Carpentry ● ● ● ●
Cement Handling ● ● ● ● ●
Concreting ● ● ● ●
Masonry ● ● ● ●
Gas Cutting ● ● ● ● ● ●
Welding ● ● ● ● ●
Grinding ● ● ● ● ●
Chipping ● ● ● ● ● ● ●
Spray Painting ● ● ● ● ● ●
Painting ● ● ● ●
Height work above 2.0 ●
● ● ●
m.
Climbing ● ● ● ●
Horizontal Movement ●
● ● ●
@ Height
Introduction: This procedure has been prepared to provide information and guidance for responses
to emergency situations. The procedures were developed to cover emergencies in general which may
occur during construction and commissioning phases of the Project. While all situations cannot be
covered, the procedures listed remain applicable and should serve as overall guidance for any given
emergency. This procedure is not intended to be a substitute for good common sense which
must prevail in any given emergency situation.
Every One is expected to contribute personnel, materials and resources, as appropriate, to ensure the
efficient and maximum response to any emergency situation which may occur.
Types of Emergencies
1.1 Medical:
Contact the site EOHS officer and if casualty is in at obscure location or is trapped, alert
emergency response team. Casualty must not be moved until examined by site EOHS officer
except where casualty is in further danger by not being moved e.g., likely collapse of nearby
structure etc. In case of multiple casualties summon Statutory Emergency Services and where
applicable notify the Regulatory Authority.
1.2 Fire:
Whosoever notices fire, should alarm other by shouting. In case of minor fire, try to
extinguish using fire extinguisher but ensure escape route away from the fire is available at
all times. In case of large fire or if unable to extinguish minor fire call the emergency
response team. Dial the nearest Police Control Room or Fire Station the moment fire breaks
out. Display these phone numbers at prominent places on site. Don’t run if your dress
catches fire. Roll on the floor and try to put out the fire. Cling to the floor to escape from
smoke and fire. Do not use elevators or escalators. Rescue team must know from where to
get buckets, water, sand, long bamboo, etc. to extinguish fire. Switch off the cylinder valve
when not in use and/or follow all instructions for using gas cylinder/stove.
1.4 Earthquake:
While working on site during such emergency, immediately move to a clear area, away from
trees, signage boards, electrical wires and poles. If inside a building stay inside, take cover
under a sturdy piece of furniture such as a table or desk or crouch up against an internal wall
and cover your head with your arms. Don't run in panic, act calmly and walk fast to the open
area. Do not use elevators or escalators. If you’re on a sidewalk near buildings/ other
structures, enter into a doorway to protect yourself from falling bricks, glass, plaster, and
other debris. If you’re driving, pull over to the side of the road and stop. Avoid power lines
and other hazards. Stay inside the vehicle until the shaking is over. Stay out of incomplete
and/or under construction structures there may be a danger of falling objects such as partially
secured secondary steel work, pipes, pipe supports, scaffolding, etc.
1.6 Landslides:
In case of landslide the EOHS officer should immediately inform to the Project Manager it.
Project Manager in turn should contact the local authority and policemen for the remedial
actions. The on-duty staff or staff designated in the EOHS committee should be immediately
called for the further actions. Emergency vehicles should be kept ready
2 Emergency Communications
2.1 The site should have the suitable arrangements to contact the Medical Hospital, Fire station
and Police station.
3 Evacuation Arrangements
3.1 The Site should have the following arrangements in case of evacuation:
a. Emergency evacuation announcement system shall be identified and properly
communicated to all the persons including visitors.
b. Evacuation rout layout and assembly points shall be identified and displayed at
conspicuous location.
c. Emergency announcement codification, Emergency rout and assembly points shall be
included in the induction training.
4 Mock Drill
4.1 Mock drill is an exercise /scenario organized to access the level of preparedness and check
the response procedure pertaining to any emergency situation is followed.
4.2 Main objective to conduct mock drill are
a. To test emergency preparedness level of the project sites
b. To avoid misunderstanding in roles and responsibilities
c. For better coordination among the emergency response coordination teams
d. To make it accustom so as to react instantly/correctly.
e. To check the proper functioning of instruments used by emergency response coordination
teams (ERCT) as per emergency preparedness plan.
f. To train workers, staff and sub-contractors on how to practice proper actions.
4.3 On hearing siren as per codification decided, stop the work / switch off the machine and walk
fast towards emergency assembly points by taking emergency evacuation route or as directed
by your supervisor.
4.4 All workers, staff and sub-contractors & visitors will assemble at pre-determine assembly
points.
4.5 After head counting is done different ERC team will be activated as per roll and
responsibility given to them. (First aid, Firefighting, Rescue etc.)
4.6 On getting all clear siren (Information), all the workers and staff will resume their work.
4.7 An evaluation of the drill must be conducted to identify problems encountered during the
drill and how this can be corrected in future emergency mock drills.
s
5 Emergency Control center
To coordinate with emergency situation at project site, EOHS office shall be operated as an
Emergency Control center. Chief controller of Emergency will coordinate from this control room.
The Emergency control room shall be equipped with necessary communication facilities; site lay out
indication hazardous area/location of various emergency equipment’s / evacuation rout etc.
Important site contact numbers including government agencies like Police, fire department, govt.
hospital etc must be displayed in all prominent places and in EOHS notice boards.
He is retain overall responsibility for the project site and its personnel. As soon as he is
informed of the emergency, he shall proceed to the control room and meet the P&A.
Manager.
His duties shall be:
a. Assess the magnitude of the situation and decide if staff needs to be evacuated from
their assembly points.
b. Exercise direct operational control over areas other than those affected.
c. Maintain a continuous review of possible development and assess in consultation with
Incident Controller and other Key personnel as to whether stoppage of the construction
activities of entire site or any section of the site and evacuation of persons is required.
d. Liaison with Senior Officials of Police, Fire Brigade, Directorate of Industrial Safety, &
other resourceful personnel.
e. Control rehabilitation of affected areas on discontinuation of emergency.
f. Issue authorized statements to news media, and ensures that evidence is preserved for
inquiries to be conducted by statutory authorities.
On hearing of an emergency siren, he will rush to the scene of the occurrence and take
overall charge and report to Chief Controller. On arrival he will assess the scale of
emergency and decide if major emergency exists or is likely and inform the
Communication Officer accordingly.
a. Direct all operations within the affected areas with the priorities for safety of personnel
minimize damage to the property and minimize loss of materials.
b. Pending arrival of Site Controller, assume the duties of his post and, in particular.
c. (a) Direct the shutting down and evacuation of site and areas likely to be adversely
affected by the emergency.
(b) Ensure that all Key personnel and outside help are called in.
d. Provide advice and information to the Fire squad & Security Officer and the local fire
service as and when they arrive.
e. Ensure that all non-essential workers/staff of the areas affected are evacuated to the
appropriate assembly points, and the areas are searched for casualties.
f. In the event of failure of electric supply and internal telephones, set up communication
point and establish contact with Emergency Control Centre.
g. Report on all significant developments to the P. & A manager.
h. Have regard to the need for preservation of evidence so as to facilitate any inquiry into
the causes and circumstances, which caused or escalated the emergency.
He will also work as liaison Officer and will be stationed at the Main Entrance (Security
Office near Main Gate) during the emergency. He will under the direction of the site
Controller handle police, press and other inquiries, receive reports from roll-call leaders from
assembly points and pass on the absentee information to the Incident Controller. His
responsibilities shall include -
a. To ensure that casualties receive adequate attention, to arrange additional help if
required and information relatives.
b. To control traffic movements into the site and ensuring that alternative transport is
available when need arises.
c. When emergency is prolonged, arrange for the relief of personnel and organize
refreshments / catering facility.
d. From information received, advise the Site Controller of the situation, recommending
(if necessary) evacuation of staff from assembly points.
e. Depute suitable staff to act as running messenger between the Incident Controller and
himself if the telephone and other system of communication fails due to whatsoever
reasons.
f. Maintain prior agreed inventory in the control center.
g. In case of prolonged emergency involving risk to outside areas by wind-blown
materials, contact local Meteorological Office to receive early notification of changes
in weather conditions
Security Officer
a. Instruct & deploy security personnel at security posts\ gates and around affected area.
b. Mobilized the fire squad (security) at emergency site.
c. Cordon off the affected area and guide traffic / emergency vehicles and control un
necessary gathering of persons around.
d. Ensure vigilance at security posts / gates and be in constant contact with construction
manager / area manager and other numbers connected with firefighting operation.
7.5 Team Leaders (All departmental Head)
The Departmental head wherein the incident has taken place will report to Incident Controller
and provide assistance as required. They will decide which members of their staff they
require at the scene
a. Respond to the emergency call with fire crew in first turn out. Report to incident
controller at site of emergency.
b. Decide line of control actions in consultation with incident controller for fire fighting
and other control including evacuation of trapped personnel.
c. Deploy auxiliary fire squad for assisting fire crew.
d. Ensure safety of the crew members.
e. Keep constant contact with incident controller and chief controller.
Fire Fighting Measures
Electrical shock, burnt, fire, explosion measures may be occurred at the hot work places.
Fire Protection Equipment’s:
Fire protection equipment’s shall be plainly marked and shall be kept clear of all obstructions.
Fire buckets should be provided at the nearest location.
Fire buckets should be filled with sand.
Fire buckets should be placed far from the flammable materials.
All extinguishers shall be recharged or replaced promptly after use.
1.1. Precautions
The following fire prevention and protection measures shall be incorporated on site:
Access ways to escape routes from hazardous areas shall be constructed in compliance with local
regulations. These routes shall be free of any obstructions at all times and clearly marked with signs
written in the local language and English.
Site accommodation facilities and other temporary buildings shall have adequate fire extinguishers
and fire exits.
The location of the fire extinguishers shall be shown on the building plans.
A sign “Highly Flammable Liquids”, “No Naked Lights” and “No Smoking” shall be boldly
displayed at the entrances to stores containing flammable materials.
Extinguishers, hydrants and other fire protection equipment shall be provided wherever required and
maintained and regularly inspected on a schedule to be established by responsible EOHS dept.
Smoking shall be allowed only in the designated area under controlled conditions.
No motor fuel may be stored on site except in approved containers. Containers will be removed from
the work place at the end of the work. If fuel containers are stored on site, on a daily basis, they shall
be stored in an enclosed cabinet. Hot work shall not be permitted near such areas without a permit.
No equipment shall be filled with fuel while the motor is running.
All waste, packing materials, wood, shaving and oily rags must be regularly removed to a specially
designated location from where it will be removed by an appropriate contractor. Unwanted material
from more open areas of the site must also be collected at regularly and carried to the designated
area. Separate metal bins, with close-fitting metal lids must be provided for oily rags and other
combustible waste. Rubbish shall not be burned on site.
Electrical equipment’s shall be selected with correct capacity rating. No overloaded shall be allowed.
EOHS MOTIVATION
EOHS Incentive program.
EOHS incentive procedure developed at site to recognize and acknowledge good EOHS performance
by individuals.
EOHS awards may be given for different categories of contractors and employees once in a
month.
Incident Reporting
All incidents shall immediately be informed to the Project & EOHS leads of JMC, Brigade and JLL.
Report of LWC and fatal incident shall also be sent to HO-EOHS department within 48 hours
All Reportable accidents to be reported within 24 Hours from the time of the accident to
Brigade and JLL through First Information Report Format
Any near misses, Injuries and Incidents investigation report to be submitted to Brigade and
through the systems & Procedures established
INCIDENT INVESTIGATION
Definition
Near Miss:
Any event which under slightly unfavorable circumstances, may have result in harm to people,
damage to property, damage to environment or a cause of business interruption.
Fatal:
Any work-related injury resulting in to death of person
Investigation Procedure:
Investigation should be conducted in an open and positive atmosphere that encourages the witness to
talk freely.
a. The primary objective is to ascertain the facts with a view to prevent future and possible
more serious occurrences.
b. Accidents which result in death must be investigated by the panel including Project
Manager, RO EOHS Coordinator and site EOHS in charge or person identified by the
Divisional head. A competent person like civil / electrical / mechanical engineer may be
included in the panel based on the type of accident. An external expert may also be
included if in-house competent person is not available.
c. Near misses and first aid accidents should also be investigated by the site EOHS in
charge as soon as possible as they are signals of inadequacies in the EOHS management
system.
d. It is important that information relating to the incident is gathered in an organized way.
e. The following steps should be followed;
f. Take photograph and make sketches.
g. Examine involved equipment, working area or material and environmental conditions.
h. Interview the injured (in case of non-fatal), eye-witness and other involved parties.
i. Consult expert wherever necessary.
Jointly (NCRTC and L&T) review the Incidence rate of First Aid Cases and set a target
for reduction.
EOHS INSPECTION: -
Risk Assessment
HIRA
a. For HIRA we need to identify OHS concern/ Hazard- physical, chemical, biological, ergonomic involved
in all the activities. It should be identified on their probability of the occurrence and impact of that
particular hazard of the activity.
b. The rating for the HIRA would be defined by the following criteria:
c. Impact Rating in the scale of Low-L, Medium-M & H-High.
d. Probability rating in the scale of Low-L, Medium-M & H-High.
e. In order to get the value of significant risk and the Risk Priority No; determine the value of RPN from the
risk matrix in the scale of 1-5. If the value of RPN or Risk Level is 3 or more than 3, then consider it as
significant
OHS - Risk Assessment Matrix
Risk
When it can lead to fatal When it occurs frequently Severity rating
Rating
incident or permanent or chances approx. more
High = H
disability or property loss than 50 %.
L M H
more than Rs.1, 00,000. Probabilit
When it can lead to When it occurs y H 3 4 5
temporary disability or occasionally or chances Rating M 2 3 4
doctor visit is required or between 10% to 50%. L 1 2 3
Medium = M
when property loss is more
than Rs.10, 000 to Rs.1, RR = Risk rating
00,000.
When it can lead to first When it has never 1= Trivial
aid facility or property loss occurred before or 2= Tolerable
less than Rs.10, 000. Low = L chances less than 3= Moderate
approximately 10 %. 4= Substantial
5= Intolerable
To carryout risk assessment for site specific activities following table may be referred. The rating given in the table are
hypothetical.
Sr. Activity Hazard, Severity Severity Probabilit Risk Level Risk Controls
No. Concern Explanation Rating y Rating 1/2/3/4/5
H/M/L M/L/H
Sr. Activity Hazard, Severity Severity Probability Risk Level Risk Controls
No. Concern Explanati Rating Rating 1/2/3/4/5
on H/M/L M/L/H
13 Working Failure/ Serious M M 3 Scaffolds should be tied or
at height toppling of injury base height ratio can be
scaffold, ensured
Toppling of Serious M L 2 Ladder should be place 1:4
ladder injury ratio or to be tied with
structure.
Fall from Serious H H 5 Fall protection / edge
cutouts and injury protection to be provided
open edge
Hierarchy of Controls
Controlling exposures to hazards in the workplace is vital to protecting workers. The hierarchy of controls
is a way of determining which actions will best control exposures. The hierarchy of controls has five levels
of actions to reduce or remove hazards. The preferred order of action based on general effectiveness is:
1. Elimination
2. Substitution
3. Engineering controls
4. Administrative controls
5. Personal protective equipment (PPE)
Using this hierarchy can lower worker exposures and reduce risk of illness or injury.
Elimination
Elimination removes the hazard at the source. This could include changing the work process to stop using a
toxic chemical, heavy object, or sharp tool. It is the preferred solution to protect workers because no
exposure can occur.
Substitution
Substitution is using a safer alternative to the source of the hazard. An example is using plant-based
printing inks as a substitute for solvent-based inks.
When considering a substitute, it’s important to compare the potential new risks of the substitute to the
original risks. This review should consider how the substitute will combine with other agents in the
workplace. Effective substitutes reduce the potential for harmful effects and do not create new risks.
Elimination and substitution can be the most difficult actions to adopt into an existing process. These
methods are best used at the design or development stage of a work process, place, or tool. At the
development stage, elimination and substitution may be the simplest and cheapest option. Another good
opportunity to use elimination and substitution is when selecting new equipment or procedures. Prevention
through Design is an approach to proactively include prevention when designing work equipment, tools,
operations, and spaces.
Engineering Controls
Engineering controls reduce or prevent hazards from coming into contact with workers. Engineering
controls can include modifying equipment or the workspace, using protective barriers, ventilation, and
more. The NIOSH Engineering Controls Database has examples of published engineering control research
findings.
The most effective engineering controls:
are part of the original equipment design
remove or block the hazard at the source before it comes into contact with the worker
prevent users from modifying or interfering with the control
need minimal user input for the controls to work
operate correctly without interfering with the work process or making the work process more difficult
Engineering controls can cost more upfront than administrative controls or PPE. However, long-term
operating costs tend to be lower, especially when protecting multiple workers. In addition, engineering
controls can save money in other areas of the work process or facility operation.
Administrative Controls
Administrative controls establish work practices that reduce the duration, frequency, or intensity of
exposure to hazards. This may include:
work process training
job rotation
ensuring adequate rest breaks
limiting access to hazardous areas or machinery
adjusting line speeds
PPE
PPE is equipment worn to minimize exposure to hazards. Examples of PPE include gloves, safety glasses,
hearing protection, hard hats, and respirators. When employees use PPE, employers should implement a
PPE program. While elements of the PPE program depend on the work process and the identified PPE, the
program should address:
workplace hazards assessment
PPE selection and use
inspection and replacement of damaged or worn-out PPE
employee training
program monitoring for continued effectiveness
Employers should not rely on PPE alone to control hazards when other effective control options are
available. PPE can be effective, but only when workers use it correctly and consistently. PPE might seem
to be less expensive than other controls, but can be costly over time. This is especially true when used for
multiple workers on a daily basis.
When other control methods are unable to reduce the hazardous exposure to safe levels, employers must
provide PPE. This includes:
while other controls are under development
when other controls cannot sufficiently reduce the hazardous exposure
when PPE is the only control option available
Administrative controls and PPE require significant and ongoing effort by workers and their supervisors.
They are useful when employers are in the process of implementing other control methods from the
hierarchy. Additionally, administrative controls and PPE are often applied to existing processes where
hazards are not well controlled.
Training and evaluation can help ensure selected controls are successful. Employers should correctly train
workers and supervisors on how to use controls. Workers and their supervisors should evaluate controls on
a regular basis. Regular evaluation can check whether controls are effective in reducing workers’ exposures
and identify potential improvements.
VII List of Checklists / Formats / Permits:
Work permits: - In the context of construction and industrial sites,
are documents that authorize specific work activities to take place,
ensuring that safety measures are in place and adhered to. These permits
help in the regulation and management of diverse tasks, from routine
maintenance to high-risk operations.
Page 85 of 89
23 Piling
24 Excavation
25 Concreting
26 Work on Roof
27 Wood Working
28 Road Works
29 Demolition
30 Gas cutting & welding
31 Grinding
32 Grinding
33 Radiography
34 Work over water
35 Occupational Health
36 Environment
Recommendations: -
In this very big project, All the workers, staff, Managers are required to
wear the necessary PPE’S while on the construction site to reduce the
accident. we are committed to achieve the zero hard vision at all our
operations so as to ensure that everyone goes home safely at the of every
working shift.
Conclusion’s: -
Page 86 of 89
References :-
Page 87 of 89
17. s^ "Alstom Will Deploy India's First ETCS L3 System, Bags 937
Cr Delhi-Meerut RRTS Signalling Contract". RailPost. 20
January 2021. Archived from the original on 3 May 2023.
Retrieved 3 May 2023.
18. ^ "Nokia tests mission-critical voice and data on 4.9G private
wireless network for NCRTC". ET Telecom. 4 August
2022. Archived from the original on 3 May 2023. Retrieved 3
ssMay 2023.
19. ^ "A transformational step for Alstom: completion of the
acquisition of Bombardier Transportation". Alstom Press
releases and news. 29 January 2021. Archived from the original
on 15 March 2023. Retrieved 29 April 2023.
20. ^ "Bombardier bags rolling stock deal for Delhi-Meerut RRTS
corridor". The Economic Times. 7 May 2020. Archived from the
original on 29 April 2023. Retrieved 29 April 2023.
21. ^ Agarwal, Kabir (6 May 2017). "Delhi-Meerut rapid rail priority for
govt: CM Yogi". The Times of India. Retrieved 8 July 2018.
22. ^ "Govt approves Rs 30,274 cr Delhi-Ghaziabad-Meerut Regional
Rapid Transport System". 19 February 2019.
23. ^ "PM Narendra Modi laid down the foundation stone for the
project". 8 March 2019. Retrieved 8 March 2019.
24. ^ "दिल्ली से मेरठ तक का सफर 60 मिनट में, रोजाना हजारों
यात्रियों को होगा फायदा". Dainik Jagran (in Hindi).
Retrieved 4 June 2019.
25. ^ Jha, Abhijay (8 July 2020). "Work on Delhi-Meerut RRTS
corridor gathers pace". The Times of India. Retrieved 15
October 2020.
26. Agarwal, Anshu (9 February 2021).
27. ^ Rai, Sandeep (18 March 2022). "Tunnelling Work For Delhi-
meerut Rrts Corridor Begins In Meerut | Meerut News - Times of
India". The Times of India. Retrieved 6 April 2022.
28. ^ "Paytm Awarded Delhi - Meerut RRTS' AFC Contract Package
26B". The Metro Rail Guy. 10 April 2022. Retrieved 10
April 2022.
29. ^ "Delhi-Meerut RRTS on track, 24.8% completed so far:
Ministry". The Hindu. 5 April 2022. ISSN 0971-751X.
Retrieved 6 April 2022.
30. ^ Livemint (8 May 2022). "Delhi-Meerut RRTS: Fastest trainset in
country built under 'Make in India'". mint. Retrieved 15
May 2022.
31. ^ "Delhi-Meerut Rapid Train Hits Track, Trial Btw Sahibabad-
Duhai Successful | Watch Video Here". India.com. 8 August
2022. Retrieved 26 February 2023.
32. ^ "RRTS trials to south Meerut by year-end". The Times of India.
4 February 2023. ISSN 0971-8257. Retrieved 26
February 2023.
33. ^ "NCRTC Conducts Successful Trial Run Of India's First High-
Speed RRTS Train From Duhai To Ghaziabad". India.com. 4
January 2023. Retrieved 26 February 2023.
Page 88 of 89
34. ^ "Ghaziabad: Four RRTS stations on 17km priority line to be
ready by mid-March". Hindustan Times. 25 February 2023.
Retrieved 26 February 2023.
Page 89 of 89