Detailed Cost Estimation by Element
1. Floor System (Timber CLT) – 3,000 m²
Component Unit Qty Rate (£) Cost (£)
CLT Panels m² 3,000 100 300,000
(structural
floor panels)
Acoustic & m² 3,000 12 36,000
Thermal
Insulation
Screed / m² 3,000 10 30,000
Leveling Layer
Floor Finish m² 3,000 15 45,000
(tiles/carpet/w
ood)
Fire protection m² 3,000 3 9,000
coating
Fixings & m² 3,000 3 9,000
Connectors
Total Floor £429,000
System Cost
2. Column System – Approx. 200 steel columns
Component Unit Qty Rate (£) Cost (£)
Steel UC pcs 200 300 60,000
203x203x100
Fabrication & pcs 200 150 30,000
Welding
Base Plates & pcs 200 80 16,000
Anchors
Fire Protection pcs 200 25 5,000
Coating
Erection & pcs 200 120 24,000
Lifting
Total Column £135,000
Cost
3. Beam System – Approx. 250 beams
Component Unit Qty Rate (£) Cost (£)
Steel UB pcs 250 220 55,000
305x102x25
Fabrication & pcs 250 110 27,500
Cutting
Connections & pcs 250 45 11,250
Brackets
Fire Protection pcs 250 20 5,000
Coating
Erection & pcs 250 100 25,000
Lifting
Total Beam £123,750
Cost
4. Wall System – External and Internal
Component Unit Qty Rate (£) Cost (£)
External Walls m² 1,800 120 216,000
(Cladding +
Insulation)
Internal m² 2,500 45 112,500
Partitions
(drywall/gypsu
m)
Painting & m² 4,300 12 51,600
Finishing
Doors & pcs 100 250 25,000
Frames
Total Wall Cost £405,100
5. Roof System – 2,000 m²
Component Unit Qty Rate (£) Cost (£)
Structural m² 2,000 60 120,000
Frame (Purlins
& Rafters)
Roof Sheeting m² 2,000 70 140,000
(Waterproof +
Insulated)
Gutters & m 500 20 10,000
Drainage
Roof Access pcs 5 1,200 6,000
Hatch &
Skylights
Total Roof Cost £276,000