The document provides a detailed cost estimate for constructing a three-room residential house in Otuke Town Council for client Mr. Matana. The total estimated cost for the project is 10,123,000, broken down into categories such as foundation, ring beam, roof construction, doors and windows, and other expenses. Each category includes specific items, quantities, rates, and amounts to give a comprehensive overview of the financial requirements for the construction.

Uploaded by

awiciemmy85
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views2 pages

Estimate

The document provides a detailed cost estimate for constructing a three-room residential house in Otuke Town Council for client Mr. Matana. The total estimated cost for the project is 10,123,000, broken down into categories such as foundation, ring beam, roof construction, doors and windows, and other expenses. Each category includes specific items, quantities, rates, and amounts to give a comprehensive overview of the financial requirements for the construction.

Uploaded by

awiciemmy85
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

COST ESTIMATE FOR THE CONSTRUCTION OF A PROPOSED THREE ROOMS

RESIDENTIAL HOUSE IN OTUKE TOWN COUNCIL.


CLIENT: MR MATANA
S/NO ITEM UNIT QUANTITY RATE AMOUNT
FOUNDATION &
WALLING
01 Bricks pcs 8000 120 960000
02 Offloading bricks trip 8 7000 56000
03 Transporting bricks trip 8 40000 320000
04 Sand and transport trip 8 40000 320000
05 Red stone and trip 2 70000 140000
transport
06 Murram and transport trip 6 50000 300000
07 cement bags 30 21000 620000
08 Hoop iron rolls 5 40000 200000
09 dpc roll 3 10000 30000
10 Air bricks no 30 1000 30000
Sub total 2,976,000

RING BEAM
11 Iron bars 10mm pcs 10 26000 260000
12 Stirrups 6mm pcs 10 8000 80000
13 Binding wire roll 1 90000 90000
14 Nails 4” Kg 5 6000 30000
15 Nails 3” Kg 3 6000 18000
16 Nails 2” kg 2 6000 12000
17 Hacksaw blade no 2 4000 8000
18 Form work hire 20 3000 60000
18 Scaffolding hire 50000
Sub total 608,000

ROOF CONSTRUCTION
19 Iron sheet 30g no 20 35000 700000
20 Timber 4x3 No 7 15000 105000
21 Timber 6x2 No 8 15000 120000
22 Timber 4x2 No 20 10000 200000
23 Timber 3x2 no 20 8000 160000
24 Facia board 200x25 no 4 25000 100000
25 Wood preservative ltrs 20 1500 30000
26 Hoop iron roll 1 40000 40000
27 Bow saw blade no 2 14000 28000
28 Nails 6” kg 10 6000 60000
29 Nails 4” kg 8 6000 48000
30 Nails 3” kg 5 6000 30000
31 Nails 2” kg 3 6000 18000
Sub total 1,639,000

Doors and windows


32 Door 2.4x0.9 no 3 28000 560000
0
Door 2.1x0.9 no 2 20000 400000
0
Window1.1x0.9 no 3 23000 690000
0
Sub total 1,650,000

others
33 Water for works 1 lumpsum 300000
34 feeding 1 lumpsum 450000
35 labour 1 lumpsum 2,200,000
36 contigency 1 lumpsum 300000
Sub total 3,250,000

37 Grand total 10,123,000