BUILDING ESTIMATION
(FOR FIRST FLOOR)
QUANTITY SHEET
SL. NO. ITEM DESCRIPTION NOS LENGTH (M) WIDTH (M) HEIGHT (M) QUANTITY
1 COLUMN UPTO PARAPET WALL
(G+1) 20 0.83 0.83 11 152.66 CUM.FT
COLUMN (10"X10") 152.66 CUM.FT
COLUMN COST PER CUM.FT 1500 152.66 228990.00 RS
(INCLUDING MATERIAL,
SHUTTERING AND LABOUR
CHARGED) RS.1500/CUM.FT
2 SLAB BEAM
BEAM (10"X10") 4 48 0.83 0.83 132.27 CUM.FT
BEAM (10"X10") 6 13 0.83 0.83 53.73 CUM.FT
BEAM (10"X10") 5 13 0.83 0.83 44.78 CUM.FT
3 BEAM (10"X10") 6 12 0.83 0.83 49.60 CUM.FT
280.38 CUM.FT
SLAB BEAM COST PER CUM.FT
(INCLUDING MATERIAL, 1500 280.38 420570.00 RS.
SHUTTERING AND LABOUR
CHARGED) RS.1500/CUM.FT
5 BRICK WORK IN SUPERSTRUCTURE
LONG WALL (5") 4 48 0.41 11 865.92 CUM.FT
SHORT WALL (5") 6 13 0.41 11 351.78 CUM.FT
SHORT WALL (5") 3 13 0.41 11 175.89 CUM.FT
SHORT WALL (5") 6 12 0.41 11 324.72 CUM.FT
SHORT WALL (5") 2 5 0.41 11 45.1 CUM.FT
1763.41 CUM.FT
6 DEDUCTIN
DOOR (3'6"X7') 2 3.50 0.41 7 20.09 CUM.FT
DOOR (3'X7') 5 3 0.41 7 43.05 CUM.FT
DOOR (2'6"X7') 5 2.5 0.41 7 35.875 CUM.FT
WINDOW (6'X5') 5 6 0.41 5 61.5 CUM.FT
WINDOW (4'X5') 1 4 0.41 5 8.2 CUM.FT
VENTILATION (3'X1'6") 6 3 0.41 1.5 11.07 CUM.FT
179.78 CUM.FT
ACTUAL BRICK WORK 1 1763.41 MINUS 179.79 1583.62 CUM.FT
13.5 BRICK IN 1 CUM.FT 1 1583.63 @ 13.5 21379.01 NOS
COST OF 1 BRICK =14 RS 21379 14 299306 RS
7 SLAB CONCRETE 1 44 54 0.41 974.16 CUM.FT
STEEL IN SLAB @ 2.90/CUM.FT 1 974.16 @ 2.9 2825.06 KG
CEMENT (0.22 BAGS/CUM.FT) 1 974.16 @ 0.22 214.32 BAGS
SAND (0.414CUM.FT /CUM.FT) 1 974.16 @ 0.414 403.30 CUM.FT
AGGREGATE 1 974.16 @ 0.829 807.58 CUM.FT
(0.829 CUM.FT/1CUM.FT
COST OF STEEL 2825.06 65 183628.9 RS
COST OF CEMENT 214.32 480 102873.6 RS
COST OF SAND 403.3 250 100825 RS
COST OF AGGREGATE 807.58 450 363411 RS
750738.5 RS
ENGINEER SIGN