QUANTITY SHEET

Widht/ Height/
Sr. No. Item Description No. Length Breadth Depth Quantity
(m)
(m) (m)

1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 15 1.30 1.30 2.19 55.52 cu m

L \ W = 1 + 0.15 + 0.15 = 1.3


Depth From GL = 2.19 m

2 PCC in Foundation
L / W = 1.3 m H = 40 mm (0.040 m) 15 1.3 1.3 0.04 1.01 cu m

3 Footing
L / W = 1 m H = 150 mm (0.150 m) 15 1 1 0.15 2.25 cu m

4 RCC Column
Size = 230 mm x 230 mm 15 0.23 0.23 2.93 2.32 cu m

H = 2.93 m (up to Plinth)

5 RCC Beam at Ground Level


Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.23 0.83 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m

Total 3.82 cu.m

6 DPC at Plinth Level


Beam - 1 w = 0.23, L = 3.12 m 5 3.12 0.23 3.59 sq.m

Beam - 2 w = 0.23, L = 3.80 m 5 3.8 0.23 4.37 sq.m

Beam - 3 w = 0.23, L = 1.96 m 3 1.93 0.23 1.33 sq.m

Beam - 4 w = 0.23, L = 3.52 m 3 3.52 0.23 2.43 sq.m

Beam - 5 w = 0.23, L = 3.79 m 3 3.79 0.23 2.62 sq.m


Beam - 6 w = 0.23, L = 3.28 m 3 3.28 0.23 2.26 sq.m

Total 16.60 sq .m

7 RCC Column in Superstructure


Column (230 mm x 230 mm) 15 0.23 0.23 3.98 3.16 cu.m

H = 3.98

8 RCC Beam at Slab Level


Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.23 0.83 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.23 1.01 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.23 0.31 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.23 0.56 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.23 0.60 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.23 0.52 cu.m

Total 3.82 cu.m

9 RCC Slab (1:1.5:3)


L = 13.26 m, W = 7.16 m 1 13.26 7.16 0.125 11.87 cu.m

Thickness = 150 mm

Deduction
Column (230 mm x 230 mm) 3 0.23 0.23 0.125 0.02 cu.m

H= 0.125 m

Beam
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.15 0.32 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.15 0.39 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.15 0.07 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.15 0.12 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.15 0.13 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.15 0.11 cu.m

Total 1.15 cu.m

Total Deduction 1.17 cu.m

Slab Qty after Deduction = 10.70 cu.m


11.87 - 1.17 = 10.70 cu. m

10 Earthfilling up to plinth
L = 13.26 m W = 7.16 m 1 13.26 7.16 0.934 88.68 cu.m

Deduction:
Beam and Wall
Beam - 1 (230 x 230 mm) L = 3.12 m 3 3.12 0.23 0.984 2.12 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 3 3.8 0.23 0.984 2.58 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 1 1.93 0.23 0.984 0.44 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 1 3.52 0.23 0.984 0.80 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 1 3.79 0.23 0.984 0.86 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 1 3.28 0.23 0.984 0.74 cu.m

7.53 cu.m

Actal Earthwork =
88.68 - 7.53 = 81.14 m 81.14 cu.m

11 Brick Wall GL to PL
Beam - 1 (230 x 230 mm) L = 3.12 m 5 3.12 0.23 0.704 2.53 cu.m

Beam - 2 (230 x 230 mm) L = 3.80 m 5 3.8 0.23 0.704 3.08 cu.m

Beam - 3 (230 x 230 mm) L = 1.96 m 3 1.93 0.23 0.704 0.94 cu.m

Beam - 4 (230 x 230 mm) L = 3.52 m 3 3.52 0.23 0.704 1.71 cu.m

Beam - 5 (230 x 230 mm) L = 3.79 m 3 3.79 0.23 0.704 1.84 cu.m

Beam - 6 (230 x 230 mm) L = 3.28 m 3 3.28 0.23 0.704 1.59 cu.m

11.68 cu.m

11 Brick Work in Superstructure

Wall - 1 6 3.12 0.23 2.85 12.27 cu.m

L = 3.12 m, W = 0.23 m, H = 3m
Wall - 2
L = 3.80 m, W = 0.23 m, H = 3m 4 3.8 0.23 2.85 9.96 cu.m

Wall - 4
L = 1.96 m, W = 0.23 m, H = 3m 2 1.96 0.23 2.85 2.57 cu.m
Wall - 4
L = 3.52 m, W = 0.23 m, H = 3m 3 3.52 0.23 2.85 6.92 cu.m

Wall - 5
L = 3.79 m, W = 0.23 m, H = 3m 3 3.79 0.23 2.85 7.45 cu.m

Wall - 6
L = 3.28 m, W = 0.23 m, H = 3m 3 3.28 0.23 2.85 6.45 cu.m

Wall - 7
L = 3.12 m, W = 0.23 m, H = 3m 3 3.12 0.23 2.85 6.14 cu.m

Extra Wall
L = 2.29 m, W = 0.23 m, H = 3m 1 2.29 0.23 2.85 1.50 cu.m

53.27 cu.m

Deduction of Door & Window:


Door :
D = (1.2 x 2.1 m) 2 1.2 0.23 2.1 1.16 cu.m

L = 1.2 m,W = 0.23 m, H = 2.1 m


D2 = (1.0 x 2.1 m) 2 1 0.23 2.1 0.97 cu.m

L = 1.0 m,W = 0.23 m, H = 2.1 m


D3 = (0.82 x 2.1 m) 3 0.82 0.23 2.1 1.19 cu.m

L = 0.82 m,W = 0.23 m, H = 2.1 m

Window:
W1 = ( 1.5 x 1.05 m) 1 1.5 0.23 1.05 0.36 cu.m

L = 1.5 m, W = 0.23 m, H = 1.05 m

Ventilation 2 0.6 0.6 0.23 0.17 cu.m

L = 0.60 m, W = 0.23, H = 0.60

Parking Opening 1 3.17 0.23 2.85 2.08 cu.m

L = 3.17 W = 0.23 H= 3
Total 5.92 cu.m

Actual Qty= 52.27 - 5.92 = 49.87 cu. m 47.35 cu.m


13 Parapet Wall
Long wall, L = 13.72 m, W =0.15 2 13.72 0.15 0.98 4.03 cu.m

Height = 0.90 m

Short Wall, L = 7.62 m, W = 0.15 2 7.62 0.15 0.98 2.24 cu.m

Height = 0.90
Total 6.27 cu.m

Deduction:
Column:
L = 0.23 W= 0.15 m, H = 0.98 m 15 0.23 0.15 0.9 0.47 cu.m

Atual Brick work = 6.27 - 0.47 = 5.81m 5.81 cu.m


To unprotect sheet ang Get passwork , Please Pay 100 rs
to Mobile Number 8905904345 by google pay
any other app and Msg I have paid for password.
Building Estimation
QUANTITY SHEET
Widht/ Height/
Sr. No. Item Description No. Length Breadth Depth Quantity
(m) (m) (m)

1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 12 1.50 1.50 1.50 40.50 cu m

Depth From GL = 1.5 m


2
Footing (1m x 1m) 12 1.3 1.3 0.1 2.03 cu m
Thickness = 0.10

3 Column(300mm x 300mm)
Base(1m x 1m) 12 1.00 1.00 0.15 1.80 cu m
Thickness = 0.15
Stem(0.30 x0.30)
height= 1.25+0.55 = 1.80 m 12 0.30 0.30 1.80 1.94 cu m
Total 3.74 cu m

4 Plinth Beam
Beam (300 mm x 300 mm)
Beam - 1 (3m length) 4 3.00 0.30 0.30 1.08 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.30 2.52 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.30 0.92 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.30 0.62 cu m
Total 5.14 cu m

5 Earth Filling in Plinth


Bed Room (3m x 4m) 1 3.00 4.00 0.45 5.40 cu m
Kitchen + Dining (4m x 4m) 1 4.00 4.00 0.45 7.20 cu m
Drawing (4m x 6m) 1 4.00 6.00 0.45 10.80 cu m
Bath/ W.C. (3m x 2.3m) 1 3.00 2.30 0.45 3.11 cu m
Varandah (3m x 3.4m) 1 3.00 3.40 0.45 4.59 cu m
Total 31.10 cu m

6 Damp Proof Course(DPC)


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 17.01 sq. m
7 Brick Work in Super Structure
57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 3.00 51.03 cu m

Bath / WC Wall:
W1, L = 1.5 m , B= 0.10 m 1 1.50 0.10 3.00 0.45 cu m
W2, L=0.8 m, B= 0.10 m(2.3-1.5) 1 0.80 0.10 3.00 0.24 cu m
Total 51.72 cu m
Deduction:
Door:
D(1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
D1(1.00 X 2.10 m) 1 1.00 0.30 2.10 0.63 cu m
D2(0.75 X 2.10 m) 2 0.75 0.30 2.10 0.95 cu m
MS (1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
Windows:
W(2.00 X 1.20 m) 1 2.00 0.30 1.20 0.72 cu m
W1(1.50 X 1.20 m) 3 1.50 0.30 1.20 1.62 cu m
W2(1.20 X 1.00 m) 2 1.20 0.30 1.00 0.72 cu m
W3(1.20 X 1.20 m) 2 1.20 0.30 1.20 0.86 cu m
Ventilation:
V(0.90 x 0.60 m) 1 0.90 0.30 0.60 0.16 cu m
V1 (0.60 x 0.60 m) 1 0.60 0.30 0.60 0.11 cu m
Cupboard:
CB(1.50 x 1.80 m) 1 1.50 0.15 1.80 0.41 cu m
CB1 (1.20 x 1.80 m) 1 1.2 0.15 1.80 0.32 cu m
Open:
O (1.20 x 2.10) 2 1.20 0.30 2.10 1.51 cu m
Total 9.52 cu m
Lintel:
Door:
D(1.20 X 2.10 m)(L= 1.20+0.15+0.15) 1 1.50 0.30 0.15 0.07 cu m
D1(1.00 X 2.10 m) 1 1.30 0.30 0.15 0.06 cu m
D2(0.75 X 2.10 m) 2 1.05 0.30 0.15 0.09 cu m
MS (1.20 X 2.10 m) 1 1.50 0.30 0.15 0.07 cu m
Windows:
W(2.00 X 1.20 m) 1 2.30 0.30 0.15 0.10 cu m
W1(1.50 X 1.20 m) 3 1.80 0.30 0.15 0.24 cu m
W2(1.20 X 1.00 m) 2 1.50 0.30 0.15 0.14 cu m
W3(1.20 X 1.20 m) 2 1.50 0.30 0.15 0.14 cu m
Ventilation:
V(0.90 x 0.60 m) 1 1.20 0.30 0.15 0.05 cu m
V1 (0.60 x 0.60 m) 1 0.90 0.30 0.15 0.04 cu m
Open:
O (1.20 x 2.10) 2 1.50 0.30 0.15 0.14 cu m
Total 1.13 cu m

Total Brickwork after deduction Total 41.06 cu m

Beam (300 mm x 300 mm)


Beam - 1 (3m length) 4 3.00 0.30 0.23 0.83 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.23 1.93 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.23 0.70 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.23 0.48 cu m
Total 3.94 cu m

8 Slab
L = 7.9 m
B = 10.9 m
H = 0.10 1 7.90 10.90 0.10 8.61 cu m
150 mm
150 mm

Door Length Bearing


150 mm