Bridge Plaza Restoration Project Classic Schedule Layout 15-Aug-25 13:46
Activity ID Activity Name Original Start Finish Total Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027
Duration Float
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
NEWPROJ Bridge Plaza Restoration Project 392 07-Aug-25 05-Feb-27 0 0
NEWPROJ.1 Milestones
NEWPROJ 392 07-Aug-25 05-Feb-27 0 0
A1180 Notice to Proceed 0 07-Aug-25 0 Notice to Proceed, 07-Aug-25
AB1210 Final Completion 0 05-Feb-27 0 F
NEWPROJ.2 Pre-Construction
NEWPROJ 28 07-Aug-25 15-Sep-25 0 15-Sep-25, NEWPROJ.2 Pre-Construction
NEWPROJ.2.1 Submittals
NEWPROJ 5 07-Aug-25 13-Aug-25 0 13-Aug-25, NEWPROJ.2.1 Submittals
A1000 Prep. & Sub. Site Safety Plan 5 07-Aug-25 13-Aug-25 0 Prep. & Sub. Site Safety Plan
NEWPROJ.2.2 Approvals
NEWPROJ 15 21-Aug-25 10-Sep-25 0 10-Sep-25, NEWPROJ.2.2 Approvals
A1060 Rev. & App. Site Safety Plan 15 21-Aug-25 10-Sep-25 0 Rev. & App. Site Safety Plan
NEWPROJ
NEWPROJ.2.3 Procurement 0 0
NEWPROJ.2.4 Permits
NEWPROJ 3 11-Sep-25 15-Sep-25 0 15-Sep-25, NEWPROJ.2.4 Permits
A1170 Obtain Work Permit 3 11-Sep-25 15-Sep-25 0 Obtain Work Permit
NEWPROJ.3 Construction
NEWPROJ 343 16-Sep-25 07-Jan-27 0 07-Jan-27, NEW
A1310 Installation of Temp. Fence 5 16-Sep-25 22-Sep-25 0 Installation of Temp. Fence
NEWPROJ.3.1 Phase 1
NEWPROJ 155 23-Sep-25 27-Apr-26 0 27-Apr-26, NEWPROJ.3.1 Phase 1
AB1220 Remove Existing Precast Concrete Planters for 1 23-Sep-25 23-Sep-25 0 Remove Existing Precast Concrete Planters for Reinstallation
AB1230 Remove existing Wooden Bench for Reinstallat 2 24-Sep-25 25-Sep-25 0 Remove existing Wooden Bench for Reinstallation
AB1240 Remove and Salvage Existing Bronze Plaques 2 26-Sep-25 29-Sep-25 0 Remove and Salvage Existing Bronze Plaques for Reinstallation
AB1250 Remove and Salvage Light Poles 2 30-Sep-25 01-Oct-25 0 Remove and Salvage Light Poles
AB1270 DEM03- Demolition of existing Pavers at South 15 02-Oct-25 22-Oct-25 0 DEM03- Demolition of existing Pavers at South Walkway
AB1280 DEM13- Demolition of existing Concrete Slab a 22 02-Oct-25 31-Oct-25 0 DEM13- Demolition of existing Concrete Slab at Concert Hall and library Plaza
AB1290 DEM01- Demolition of existing WPS and Toppin 25 23-Oct-25 26-Nov-25 0 DEM01- Demolition of existing WPS and Topping Material on Bridge
AB1380 WPF 02- Installation of WPS at South Plaza 17 27-Nov-25 19-Dec-25 0 WPF 02- Installation of WPS at South Plaza
AB1440 Provide Concrete Toping Slab at South Plaza 16 22-Dec-25 12-Jan-26 0 Provide Concrete Toping Slab at South Plaza
AB1450 Installation of Paving System at South Plaza 10 13-Jan-26 26-Jan-26 0 Installation of Paving System at South Plaza
AB1460 WPF 01 Installation of WPS on Bridge 16 27-Jan-26 17-Feb-26 0 WPF 01 Installation of WPS on Bridge
AB1470 Installation of Channel Drain 17 13-Feb-26 09-Mar-26 0 Installation of Channel Drain
AB1480 Provide Concrete Toping Slab on Bridge 16 05-Mar-26 26-Mar-26 0 Provide Concrete Toping Slab on Bridge
AB1490 Installation of Paving System on Bridge 16 25-Mar-26 15-Apr-26 0 Installation of Paving System on Bridge
AB1510 Reinstallation of Precast Concrete Planters 2 16-Apr-26 17-Apr-26 0 Reinstallation of Precast Concrete Planters
AB1520 Reinstallation of Wooden Bench 2 20-Apr-26 21-Apr-26 0 Reinstallation of Wooden Bench
AB1530 Reinstallation of Bronze Planques 2 22-Apr-26 23-Apr-26 0 Reinstallation of Bronze Planques
AB1540 Reinstallation of Light Poles 2 24-Apr-26 27-Apr-26 0 Reinstallation of Light Poles
NEWPROJ.3.5 Phase 2
NEWPROJ 61 28-Apr-26 21-Jul-26 0 21-Jul-26, NEWPROJ.3.5 Phase 2
AB1060 Discard existing Concrete Piers and Wooden Pl 3 28-Apr-26 30-Apr-26 0 Discard existing Concrete Piers and Wooden Planks
AB1070 Remove existing Water Inle ts 2 01-May-26 04-May-26 0 Remove existing Water Inle ts
AB1080 DEM09- Demolition of existing Concrete Slab a 15 05-May-26 25-May-26 0 DEM09- Demolition of existing Concrete Slab at Walkway belo w Bridge
AB1100 CON11- Concrete Slab-On-Grade Walkway belo 16 26-May-26 16-Jun-26 0 CON11- Concrete Slab-On-Grade Walkway below Bridge
AB1130 Provide Concrete Topping Slab on Walkway Bel 23 12-Jun-26 14-Jul-26 0 Provide Concrete Topping Slab on Walkway Below Bridge
AB1590 Provide Expansion Joint Cover Assembly 5 15-Jul-26 21-Jul-26 0 Provide Expansion Joint Cover Assembly
NEWPROJ.3.3 Phase 3
NEWPROJ 122 22-Jul-26 07-Jan-27 0 07-Jan-27, NEW
AB1000 Remove existing Concrete Bench for Reinstalla 1 22-Jul-26 22-Jul-26 0 Remove existing Concrete Bench for Reinstallation
AB1010 Discard existing Concrete Piers 2 23-Jul-26 24-Jul-26 0 Discard existing Concrete Piers
AB1020 DEM09- Demolition of existing Concrete Slab b 16 27-Jul-26 17-Aug-26 0 DEM09- Demolition of existing Concrete Slab below Bridge
AB1030 DEM10- Demolition of existing Concrete Steps/ 11 31-Jul-26 14-Aug-26 0 DEM10- Demolition of existing Concrete Steps/Seats
AB1170 STR03- New Concrete Staircase at Concert Ha 29 17-Aug-26 24-Sep-26 0 STR03- New Concrete Staircase at Concert Hall
AB1180 PLT01- Construction of Concrete Planter Wall 31 15-Sep-26 27-Oct-26 0 PLT01- Construction of Concrete Planter Wall
AB1190 Provide Concrete Topping Slab 30 07-Oct-26 17-Nov-26 0 Provide Concrete Topping Slab
AB1550 RMP01- Concrete Ramp Reconstruction at Con 20 09-Nov-26 04-Dec-26 0 RMP01- Concrete Ramp Recon
AB1580 RAI02- Installation of Metal Railing 19 07-Dec-26 31-Dec-26 0 RAI02- Installation
AB1670 Reinstall existing Precast Concrete Bench 5 01-Jan-27 07-Jan-27 0 Reinstall existin
NEWPROJ.4 Post Construction
NEWPROJ 21 08-Jan-27 05-Feb-27 0 0
A1190 Removal of Temp. Fence 2 08-Jan-27 11-Jan-27 0 Removal of T
A1210 Final Inspection 4 12-Jan-27 15-Jan-27 0 Final Inspe
A1220 Prep. & Sub. As Built Drawings 9 18-Jan-27 28-Jan-27 0 Prep
A1250 Rev. & App. of As Built Drawings 6 29-Jan-27 05-Feb-27 0 R
Actual Level of Effort Remaining Work Page 1 of 1 TASK filter: Critical.
Actual Work Critical Remainin... © Oracle Corporation