Sub-Structure and Superstructure Works
Sub-Structure and Superstructure Works
Site exploration is the process of investigating the physical properties of the soil,
rock, groundwater, and other subsurface conditions at a construction site before
designing and building any structure. It is a crucial step in civil engineering and
geotechnical engineering to ensure the safety, stability, and suitability of the
proposed structure.
Objectives of Site Exploration:
1.Determine soil bearing capacity for foundation design.
2.Identify soil and rock strata and their properties.
3.Detect groundwater level and flow conditions.
4.Assess soil behavior under load (compressibility, shear strength, etc.).
5.Locate problematic soil layers, such as expansive clay or collapsible soils.
Soil Exploration or Site Investigation:
• The process of extracting the overall information of the soil by performing various
tests is called soil exploration.
• The main objective of soil exploration is to extract adequate info. about the type and
nature of soil at different depths for designing safe, sound and economical
foundation.
Procedure:
• Excavation depth >4bp
• Load is applied via hydraulic
jack
• Settlement are recorded from
a gauge attached
• Load increment= 1/5th bearing
capacity
• Settlements are observed for
each increment of load after an
interval of 1, 4, 10, 20, 40 & 60 min.
& hourly interval onward till settlement
rate is < 0.2mm/hr.
3.2 Foundation and its type:
• Lowest part of a structure that transmits load to the ground.
• Also called the sub-structure of a building.
Types:
1. Shallow Foundation
• Depth of foundation <= width
• Spread, Combined, Strap, Continuous and Mat foundation are types of shallow
foundation.
2. Deep Foundation
• Pile Foundation
• Pier Foundation Sandy soil/ soft soil
• Well Foundation Under water
Mat foundation
Combined footing
Well foundation
https://www.youtube.com/watch?v
=s6E2t_kW57M
Pile Foundation
2.3 Earthwork excavation of foundations (soft soil, hard
rock and wet excavation)
Site Clearance
• Process of clearing the site so that it does not obstruct in the future while
working.
• Includes removal of top soil, busters and trees and demolition of present
structure.
Kassi
Excavation in soft soil:
6. Freezing Process
• Suitable for excavation in water logged soils like sand gravel and silt.
• Not suitable for deep excavation.
• Freezing pipes are inserted around the excavated area.
• Freezing liquid is then supplied by refrigerator plant.
• Now, the ground around the pipes start to freeze forming a thick frozen
earth.
• The water around the frozen earth cannot penetrate inside.
• Finally, excavation is carried out.
7. Electro-osmosis
• Through this Method, the Earth is Stabilized by Passing a Direct Current Through
Electrodes Placed Inside the Ground to the Excavated Trenches.
• Two Electrodes are Driven into the Saturated Cohesive Soils.
• Anode and cathode are made into the ground.
• When direct current is passed, water shall start moving in the direction of current.
• Positive ions will move in the direction of current and free water being dragged
towards the negative electrodes where the water shall accumulate and finally flow
out.
2.4 Excavation of trenches for pipes, cables, etc. and refilling
works
• Width of trench not greater than 1.5m. or 10 sq. m. in plan and to any depth.
• Refilling with the same excavated material is done and the disposal of surplus soil is made
up to 50m.
• Depending upon the depth of excavation, no. of pipes and type of soil, the width of trench
varies.
1. Up to 1m depth, the authorized width of trench for excavation shall be taken as external
dia. plus 25cm. When a pipe is laid on concrete bed, the width shall be the external dia. of
pipe plus 25cm or the width of concrete bed, whichever is more.
2. For depth >1m, an allowance of 5cm/m of depth for each side of the trench shall be added
to the authorized width which is given throughout the depth.
3. In firm soils, the sides of the trenches shall be kept vertical up to the depth of 2m from the
bottom. For depth>2m, the excavation width is made broader with respect to the depth.
4. For loose, slushy and soft soil, the width shall be suitably increased and if necessary,
shoring is done.
2.5 Some common problems with existing foundation
1. Settlement
2. Bearing capacity failure
• Sub-soil characteristics
• Ground water condition
• Termite action
Stone masonry and its types
Built using two or more types of masonry units (e.g., brick + concrete
block).
Usually includes:
Hollow Block
Autoclaved Aerated Cement (AAC) Block Masonry:
Concrete 3D Printer
Plastering: Plastering is the process of covering rough surface of
walls, column, ceiling and other components of building with a thin
coat of mortar to get smooth durable surface. Plastering hide defective
workmanship.
Plaster is the finishing work that gives even, smooth, regular and
clean surface on wall, ceiling, floor, roof and other parts of the
building.
Often plastering is required to provide a satisfactory base for
decorating the surface by white-washing, color washing, painting,
etc.
57
Objective of plastering:
To protect the external surface against penetration of rain water.
To protect surface against atmospheric agents.
To conceal inferior materials and defective workmanship.
To develop decorative effect and improve appearance.
Requirements of good plaster:
It should attach to the background and remain during all
variation in seasons.
It should be hard and durable.
It should possess good workability.
It should be possible to apply in all weather conditions.
It should be cheap.
It should check moisture penetration.
58
Types of plasters
1. Lime plaster (lime, sand, water)
2. Cement plaster (cement, sand, water)
3. Mud plaster (earth, optional sand, straw
and water.)
4. Surkhi plaster (surkhi, sand, water)
5. Bajra plaster (dal, lime, earth, water)
59
Method of plastering
1. Preparation of surface background
2. Application of rendering coat
3. Application of final coat
Preparation of surface background
Before plastering, the mortar joints should be raked to a depth of 10-15mm so
that the plaster can easily catch to the wall.
All dust should be removed from wall by using stiff wire brush.
Any uneven should be removed for easy plastering.
The wall should be uniformly wet before plastering.
After that dots are placed of the interval of 2m×2m with the equal level or
thickness of about generally 12mm.
This type of dots are provided on the wall where plastering operation being
operating.
After that the whole wall is cover by plaster by the help of gauging
tool(trowel), float and floating rule.
60
Defects in plaster work:
1. Cracking
2. Efflorescence: whitish crystalline substance, presence of
salt in plaster making materials
3. Blistering: formation of small patches of plaster swelling
out beyond the plaster surface and making due to improper
slaking of lime particles in the plaster.
4. Falling out of plastering
5. Flaking- formation of very loose mass of plastered surface
due to poor bond between successive coat
61
62
Pointing
63
Pointing
64
Purpose of pointing
1. Protecting joints from adverse effect of atmosphere.
2. Give better appearance.
3. Economy to plaster.
4. Preventing entry of water in to wall through joints.
Pointing procedure
1. Joints are raked to 10 mm depth.
2. Raked joints are cleaned by using brushes.
3. Joints are kept wet for few hours.
4. Mortar is applied on the joints by means of small trowel.
5. Applied mortar is given the shape of desired type of pointing.
6. Curing is done for 3-10 days.
65
66
Old brickwork with broken and
missing mortar in joints
67
Rake out old joints to Raked joints are cleaned by
10mm minimum using brushes.
69
Types of pointing
70
Types of pointing
71
72
9.4 Paints and Painting works
73
9.4 Paints and Painting works
Paints
It is the liquid material applied on timber, metal or masonry surfaces.
It acts as protective or decorative on applied surface.
It is composed of two main components; pigment and organic binders.
Constituents of oil paint
Base - The base of a paint is a solid substance that forms the bulk of the paint and
gives it its character. Metallic oxide in the form of powder, chief ingredient of
paint, keep surface opaque (fine powder of white lead , red lead, zinc oxide
iron oxide etc.
Extender or inert filler - cheap pigment for volume. additives in paint that
modify its properties, such as texture, gloss, drying time, and opacity
Pigment for color - mixed to give desired color
74
9.4 Paints and Painting works
Vehicle - The vehicle in paint is a liquid that carries the pigment and binder in paint, and
holds the pigment particles together without dissolving them. The vehicle also acts as a
binder to adhere the pigments to the surface being painted
a. Water-based acrylic: The vehicle is water.
b. Oil paint: The vehicle is usually linseed oil.
c. Tempera: The vehicle is an emulsion, which is a mixture of an aqueous liquid with
an oil, fat, or resin.
d. Watercolor: The vehicle is water and gum arabic, a sticky plant substance that
acts as the binder.
e. Acrylic: The vehicle is synthetic plastic resin.
Thinner or solvent - liquid that makes the paint thin & evaporates after applying paint(
spirit, turpentine)
Drier - material containing metallic compound, accelerates the drying of paint(lead
acetate, manganese dioxide)
Anti Skinning and Plasticizer ( Prevent gelling and minimize cracking)
75
Characteristics of good paint
76
Types of paints
77
Types of paints
Importance of varnish
1. The varnish applied on the decorative surfaces
enhances the appearance of the paint.
2. Safeguards the wood work from atmospheric agents.
3. Increases the durability of paint.
79
Types of varnish
81
Painting on wood work
Painting process on new wood work
Painting process on old wood work
82
1. Preparation of surface
1. Wood work be properly seasoned.
2. The surface be clean, dry and free from dust.
3. The surface is made smooth by rubbing with
sand /glass paper.
83
2. Knotting : This is the process of sealing the knots (resin
flows from it & destroys paint).
Patent knotting
Applying of one or more coats of Shellac or aluminum
varnish on the knots
Size knotting
Applying of first coat of mixture of red lead in water with
glue and is hot on knots, Applying of second coat of mixture
of red lead in oil thinned with boiled oil & turpentine on
dried first coat
Lime knotting
The knot is covered by hot lime for 14 hours, the lime is
than scrapped off & knot be treated by size knotting
84
3. Priming
The surface is painted by first coat of primer before fixing wood work and
fills all pores on it.
4. Stopping
Nail holes, cracks and open joints are filled up with putty.
It is than rubbed by sand paper to make smooth surface.
The putty used is the chalk powder mixed to linseed oil.
5. Second and succeeding coats (under coats)
First coat of paint with desired color is applied on
priming coat.
If necessary, second coat of paint is than applied after
the first coat is dried.
6. Finishing coat
The last coat of desired colored paint is applied to give
smooth & good surface.
85
Painting on old wood work
1. Preparation of surface
Old painting if blistered & flaked should be completely removed.
Removing of old paint by blow lamp
The paint is softened by heat (from blow of lamp).
Thus softened paint is removed by stripping knife.
Removing of old paint by paint removers
Paint removers are available in the market and are applied on
the painted surface.
The old paint lifts up, wrinkles and can be easily removed by
sharp knife etc.
Caustic soda solution is also useful for removing old paint. The
solution of caustic soda and water is applied on the surface
and it is made wet for 48 hours.
Old paint is softens and can be easily scraped off.
86
2. Coating of paint
First coat of desired paint is applied on the clean and smooth surface of
woodwork. If necessary, second coat is also applied.
3. Finishing coat
Final coating is applied to give smooth, uniform and pleasing surface.
87
Painting on Metal works
This is the process of prevention of rust in metal works.
Procedure of painting on metal surfaces
1. The scale and rust if any are removed by scrapping or brushing.
2. Oil, grease and dust are removed by washing with petrol,
benzene or limewater.
3. The surface thus clean and dry is treated with phosphoric acid.
This protects the surface from rusting and provides adhesive
surface.
4. Now, the prime coating is done underneath which further 2-3
coats are laid.
5. After the under-coat is dried, final coat of desired type of paint
is applied giving uniform an pleasant surface.
88
Painting works on masonry(existing)
Step 1 - Clean the Surface
89
Step 2 - Make any Repairs
If there is any major defects in the surface to repair, use a
simple, ready-mix concrete patch to make those repairs after
you clean it.
Step 3 - Seal and Prime
The sealer is often clear, but keeps moisture from coming
through the concrete. This is especially true in basements,
which tend to hold moisture anyway.
90
If you are not sure whether your basement has been sealed or not, tape all
four sides of a square of plastic kitchen wrap onto the floor and leave it for
24 hours. If the floor hasn't been sealed, you will see condensed water
between the plastic wrap and the floor that has evaporated up through the
concrete.
Use the two step process of sealing and priming to build a strong, water resistant
foundation for your paint.
91
Painting on plastered surface
Preparation of surface.
Priming coat
First coat
Final coat
92
1) Preparation of surface
Allow freshly plastered surface to mature.
Repair and correct any water seepage problems. Avoid rusting and leakage from the water
pipe.
Any holes and cracks are repaired by plaster of paris or by wall putty.
In old surfaces previous coatings of lime wash/powder distemper/cement paint must be
thoroughly scraped off.
Fungus affected area must be given separate treatment i.e. 5-10% solution of bleach
powder and water should be applied and left to dry for 8-10 hours.
2) Priming coat of mixture of equal parts of white and red lead in boiled
linseed oil is applied on the surface. Drying time10-12 hours.
3) First coat of desired paint is applied on the surface.
4) Final coat of the desired paint is applied on the dried first coating.
93
94
Frame Structure : Reinforced Cement Concrete (RCC) Structure
1. Precast Construction:
Concrete elements are cast and cured in a controlled environment.
Advantages: Quality control, reduced construction time, and
minimal site disruption.
Common precast elements: Beams, slabs, columns, and wall
panels.
Frame Structure : Reinforced Cement Concrete (RCC) Structure
2. Cast-in-Situ Construction:
Concrete is poured and cured on-site within formwork.
Advantages: Flexibility in design and monolithic construction.
Commonly used for foundations, slabs, and structural frameworks.
Cast-in-situ
Formwork
Formwork or shuttering is a temporary construction used as a mould
for the structure, in which concrete is placed and in which it hardens
and matures.
Also, formwork is the arrangement of timber planks in the trenches
to prevent the collapsing of soil when the depth of trench is more.
This is also called as timbering.
The construction of formwork involves considerable expenditure of
time and cost in building work, and even higher in bridges.
Forms are classified as wooden, plywood, steel, combined wood-
steel, reinforced concrete and plain concrete.
Timber is the most common material used for formwork. The
disadvantage of wooden formwork is the possibility of warping,
swelling and shrinkage of the timber.
Use of Formworks
Formwork for excavations and trenches.
Formworks for reinforced concrete construction.
97
Formworks for excavation and trenches:
Timbering of trenches:
This is the arrangement of timber planks in the trenches to prevent
collapsing of sides.
When the depth of trench is large, or when the sub-soil is loose, the
sides of the trench may cave in. The problem can be solved by
adopting a suitable method of timbering.
Why timbering is needed?
To protect the worker working inside.
To protect the completed work from being ruined by the falling
debris.
Methods of Timbering
1. Stay bracing
2. Box sheeting
3. Vertical sheeting
4. Runners
5. Sheet piling
100
1. Stay Bracing:
• This method is used for supporting the
sides of a trench excavated in fairly
firm soil, when the depth of
excavation does not exceed about 2m.
• The method consists of placing Polling board
vertical sheets or polling boards
opposite each other against the two
walls of the trench and holding them
in position by one or two rows of
struts.
• The sheets are placed at an interval of Strut
102
2. Box sheeting:
• This method is adopted in loose soils, when the depth of
excavation does not exceed 4 m.
• The method consists of vertical sheets placed very near to each
other (sometimes touching each other) and keeping them in
position by longitudinal rows (usually two) of wales.
• Struts are then provided across the wales.
Wale
Vertical sheeting
Box sheeting
103
104
a) In water-logged area:
• Vertical sheeting is provided which are very close to each
other, binding them with horizontal boards called wales.
• Struts are then adjusted against the wales.
105
b) In loose dry soil:
Here, instead of vertical sheeting, horizontal sheeting is provided.
Those horizontal sheeting is supported by vertical wales.
Now, the vertical wales are supported by the struts.
Bracing is done incase the soil is too loose and if the depth of
excavation is more.
106
3. Vertical sheeting:
• This system is adopted for deep
trenches (up to 10 m depth) in soft
ground.
• The method is similar to the box
sheeting except that the excavation is
carried out in stages and at the end of
each stage, an offset is provided, so
that the width of the trench goes on
decreasing as the depth increases.
• Each stage is limited to about 3 m in
height and the offset may vary from
25 to 50 cm per stage.
• For each stage, separate vertical
sheeting, supported by horizontal
wailings and struts are provided.
107
4. Runners
• This system is used in extremely
loose and soft ground, which needs Wale
immediate support as excavation
progresses.
Runner
• The system is similar to vertical
sheeting of box system, except that
in the place of vertical sheeting,
runners (made of long thick wooden Strut
108
5. Sheet Piling:
This method is adopted when
(i) soil to be excavated is soft or loose
(ii) depth of excavation is large
(iii) width of trench is also large
(iv) there is sub-soil water.
Sheet piling
109
110
Precautions in timbering of trenches
Possibility of slip of earth
Testing of timbering elements
Safety of adjacent structure
Traffic in the surrounding
Provision of ladders
Safety helmet
Supervision
First aid box
Fencing and light
111
Formwork for RCC Construction:
The cost of the formwork used in RCC construction varies from 20-
25% of the cost of concrete work.
Type of formwork
Wooden and Steel
Formwork for:
Beam
Slab
Column
112
Characteristics of a good formwork:
1. Strong enough to withstand load, resist the impact due to
consolidation, and carry the load of the workmen etc.
2. Leakage proof.
3. Perfectly flat and smooth.
4. Cheap and easily available.
5. Reusable.
6. Light in weight.
7. They should be such that erection and dismantling is easily
accomplished.
8. The formwork should be watertight to prevent loss of fine
materials, especially cement slurry, through gaps, which, if
found, should be closed with clay/plaster of Paris, but which
in practice are simply covered by plastic/polythene sheets.
9. Braced rigidly to prevent slippage, sagging etc.
10. Formwork should be clean before pouring.
113
Principal requirements
A good formwork should satisfy the following requirements:
1. Cheap and easily available material
2. Sufficiently rigid
3. Strong enough to resist loads such a dead load of concrete
and live load during its pouring, compaction and curing
4. Easy to strip and erect
5. Strong base support
6. It should be suitable for re-use several times.
7. It should be practically water proof so that it does not absorb
water from concrete. Also, its shrinkage and swelling should
be minimum.
8. It should be as be light as possible.
9. The surface of the formwork should be smooth
10. All joints of the formwork should be stiff so that lateral
deformation under loads is minimum
115
Formworks for reinforced concrete construction
Terminology
• Sheathing: Vertical timber plank used on column.
• Yokes: Bracing members to tie up sheathing.
• Wedges: Wooden piece used to tighten various elements of
framework.
• Cleats: Wooden piece fixed to the sides of beam.
• Joists/battens: Wooden member supporting decking.
• Ledgers: Horizontal wooden piece nailed to cleats and form
bearing of joist.
• Bottom sheathing: Bottom plank of beam (thicker).
• Head tree: Horizontal beam connected at top of vertical
post (props) through inclined cleats or beams.
116
Batten
tree.
• Slab formwork rests on battens
and joists.
Post
• If the height of the post is more
than 8 feet, horizontal bracing
is needed.
Wedge
Sole plate
120
Side yoke
Wedge
End yoke
Bolt
Sheathing
121
122
Formwork for Staircase:
Consists of vertical and inclined posts, inclined members, wooden
planks, riser planks, etc.
123
Formwork for Wall:
124
Steel Construction
Krishna: Life feels heavy when you carry what’s not your-
Let go the weight and open new doors . Shed the burdens , the fear ,
when you release , you will find your flame.